SlideShare a Scribd company logo
1 of 20
Simple example of EVM in action
© 2014 Planisware
The plan
• Our team has been tasked with planting the trees on
the plot of land behind our company’s new factory
• The plan:
– 30 batches of 20 trees (600 trees)
– 5 batches per day (100 trees)
– budgeted cost per tree 2.90$ (2.5$ per baby tree / 0.40$
for the slow release fertiliser)
→ total budget 1,740$
© 2014 Planisware 2
After the first day…
• 70 trees were planted (the team hit a patch with
stones that had to be removed before the trees
could be planted)
• Total cost was 350 $ (we had to rent a special
machine to help remove the stones which cost 147$
for the day)
• Simple EVM calculation:
– Earned Value = 70 trees planted  2.90$ = 203$
– Budgeted Cost = 100 trees planned per day  2.90$ = 290$
– Actual Cost = 70 trees planted  2.90$ + 147$ for the machine = 350$
© 2014 Planisware 3
Visually…
0
50
100
150
200
250
300
350
400
Start 1st day
Actual cost = 350$
Budgeted cost = 290$
Earned Value = 203$
© 2014 Planisware 4
Regarding cost…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 5
We are here
Regarding cost…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 6
We are here
We should have been here
Regarding cost…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 7
Cost variance = EV – AC
= 203$ – 350$ = -147$ < 0
Regarding cost…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 8
Cost variance = EV – AC
We’re over budget,
and have spent
203  350 = 58%
more budget than
anticipated (our cost
performance index)
= 203$ – 350$ = -147$ < 0
Regarding schedule…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 9
We are here
Regarding schedule…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 10
We are here
Which is where we
should have been then
Regarding schedule…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 11
Schedule variance
in hours
Regarding schedule…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 12
Schedule variance
in hours
= 203$ – 290$ = = -87$ < 0
Schedule variance
in dollars = EV – BC
Regarding schedule…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 13
Schedule variance
in hours
We’re late and
have only performed
203/290 = 70% of
the work planned
(our schedule
performance index)
= 203$ – 290$ = = -87$ < 0
Schedule variance
in dollars = EV – BC
The consequences
0
500
1000
1500
2000
2500
3000
Start 1st 2nd 3rd 4th 5th 6th 7th 8th 9th
© 2014 Planisware 14
Earned Value
today
Estimate at Completion
EAC = 3,000$
Budget at Completion
BAC = 1,740$
Extending the
Actual Cost
into the future
gives us the end
result if we do
not modify the
performance of
the project
The consequences
0
500
1000
1500
2000
2500
3000
Start 1st 2nd 3rd 4th 5th 6th 7th 8th 9th
© 2014 Planisware 15
Earned Value
today
Estimate at Completion
EAC = 3,000$
Budget at Completion
BAC = 1,740$
Cost Overrun
The consequences
0
500
1000
1500
2000
2500
3000
Start 1st 2nd 3rd 4th 5th 6th 7th 8th 9th
© 2014 Planisware 16
Earned Value
today
Planned end date
= 6 days
Estimate at completion
= 8.57 days
Project Slip
Estimate at Completion
EAC = 3,000$
Budget at Completion
BAC = 1,740$
Cost Overrun
The consequences
→ If we continue at this rate, we will need: 1,740$  58% = 3,000 $
(cost estimate at completion)
and 6 days  70% = 8.57 days (schedule estimate at completion)
to finish the work.
→ If we want to finish on budget, we need to work at
(planned remaining budget)  (actual remaining budget)
(1,740 – 290)  (1740 – 350) = 104.3% of the originally planned
performance
→ If we want to finish on time, we need to work at
(actual remaining work)  (planned remaining work)
(600 – 70)  (600 – 100) = 106% of the originally planned
performance
© 2014 Planisware 17
In technical terms…
In real life, the elements we calculated have slightly
different names:
• The Actual Cost is usually referred to as the Actual
Cost of Works Performed (ACWP)
• The Planned Cost = Budgeted Cost for Work
Scheduled (BCWS)
• The Earned Value = Budgeted Cost for Work
Performed (BCWP)
© 2014 Planisware 18
Summary
© 2014 Planisware 19
today
time
cost
ACWP
(Actual Cost of
Work Performed)
BCWS
(Budgeted Cost of
Work Scheduled)
BCWP
(Budgeted Cost of
Work Performed)
completion
date
Budget at
Completion (BAC)
Estimate at
Completion (EAC)
Schedule variance in $
SV = BCWS - BCWP
Cost variance in $
CV = ACWP - BCWP
Cost Overrun
Project SlipSchedule variance
in hours
To learn more about EVM and tools to
help manage it, visit our glossary:
www.planisware.com/glossary/earned-
value-management
© 2014 Planisware 20

More Related Content

What's hot

Earned value analysis
Earned value analysisEarned value analysis
Earned value analysisNikhil Raj
 
Work breakdown structures
Work breakdown structures Work breakdown structures
Work breakdown structures Ian Cammack
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project PresentationKhem Singh
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMansoor Shoaib
 
Fast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.pptFast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.pptJo Balucanag - Bitonio
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value AnalysisSaqib Raza
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIDavidMcLachlan1
 
Project crashing and job sequencing
Project crashing and job sequencingProject crashing and job sequencing
Project crashing and job sequencingBuha Payal
 
Earned value management
Earned value managementEarned value management
Earned value managementAshif AR
 
7.4 Earned Value Analysis
7.4 Earned Value Analysis7.4 Earned Value Analysis
7.4 Earned Value AnalysisDavidMcLachlan1
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost ManagementBhuWan Khadka
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 waleed hamdy
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Pathdmdk12
 
Project controls
Project controlsProject controls
Project controlsAshok Kumar
 

What's hot (20)

Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
Work breakdown structures
Work breakdown structures Work breakdown structures
Work breakdown structures
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Fast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.pptFast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.ppt
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
7.2 Estimate Cost
7.2 Estimate Cost7.2 Estimate Cost
7.2 Estimate Cost
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
 
Project crashing and job sequencing
Project crashing and job sequencingProject crashing and job sequencing
Project crashing and job sequencing
 
Earned value management
Earned value managementEarned value management
Earned value management
 
7.4 Earned Value Analysis
7.4 Earned Value Analysis7.4 Earned Value Analysis
7.4 Earned Value Analysis
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Path
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
Project controls
Project controlsProject controls
Project controls
 
Cost management
Cost managementCost management
Cost management
 

Similar to A simple example of Earned Value Management (EVM) in action

Homework chapter 7
Homework chapter 7Homework chapter 7
Homework chapter 7Miles Nowak
 
Culture Check on using Earned Value in Organization
Culture Check on using Earned Value in OrganizationCulture Check on using Earned Value in Organization
Culture Check on using Earned Value in OrganizationGhassan Kabbara
 
Earned value management
Earned value managementEarned value management
Earned value managementwhizkris
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Vivek Prakash
 
Earnvalue analysis in Software engineering
Earnvalue analysis in Software engineeringEarnvalue analysis in Software engineering
Earnvalue analysis in Software engineeringNitish Kumar
 
How Celoxis Helps in Budgeting & Costing
How Celoxis Helps in Budgeting & Costing How Celoxis Helps in Budgeting & Costing
How Celoxis Helps in Budgeting & Costing Nikhil Daddikar
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfNabeel Ahmad
 
Time value of money- TVM ( Discouting and Compounding)
Time value of money- TVM ( Discouting and Compounding)Time value of money- TVM ( Discouting and Compounding)
Time value of money- TVM ( Discouting and Compounding)Sweetp999
 
Earned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptxEarned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptxssuser5fc1e7
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
Padgett.sam
Padgett.samPadgett.sam
Padgett.samNASAPMC
 
7.4 Forecasting Techniques
7.4 Forecasting Techniques7.4 Forecasting Techniques
7.4 Forecasting TechniquesDavidMcLachlan1
 
Robert Corp. sponsors a defined benefit pension plan for its employe.pdf
Robert Corp. sponsors a defined benefit pension plan for its employe.pdfRobert Corp. sponsors a defined benefit pension plan for its employe.pdf
Robert Corp. sponsors a defined benefit pension plan for its employe.pdfALASEEMKOTA
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMatt Stehling
 
Introduction to Financial Accounting Solutions
Introduction to Financial Accounting SolutionsIntroduction to Financial Accounting Solutions
Introduction to Financial Accounting SolutionsMonique Anderson
 

Similar to A simple example of Earned Value Management (EVM) in action (20)

Homework chapter 7
Homework chapter 7Homework chapter 7
Homework chapter 7
 
Culture Check on using Earned Value in Organization
Culture Check on using Earned Value in OrganizationCulture Check on using Earned Value in Organization
Culture Check on using Earned Value in Organization
 
Chapter 9 q&p
Chapter 9 q&pChapter 9 q&p
Chapter 9 q&p
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares
 
Earnvalue analysis in Software engineering
Earnvalue analysis in Software engineeringEarnvalue analysis in Software engineering
Earnvalue analysis in Software engineering
 
How Celoxis Helps in Budgeting & Costing
How Celoxis Helps in Budgeting & Costing How Celoxis Helps in Budgeting & Costing
How Celoxis Helps in Budgeting & Costing
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 
Time value of money- TVM ( Discouting and Compounding)
Time value of money- TVM ( Discouting and Compounding)Time value of money- TVM ( Discouting and Compounding)
Time value of money- TVM ( Discouting and Compounding)
 
Earned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptxEarned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptx
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Padgett.sam
Padgett.samPadgett.sam
Padgett.sam
 
7.4 Forecasting Techniques
7.4 Forecasting Techniques7.4 Forecasting Techniques
7.4 Forecasting Techniques
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Project Control Process
Project Control ProcessProject Control Process
Project Control Process
 
Robert Corp. sponsors a defined benefit pension plan for its employe.pdf
Robert Corp. sponsors a defined benefit pension plan for its employe.pdfRobert Corp. sponsors a defined benefit pension plan for its employe.pdf
Robert Corp. sponsors a defined benefit pension plan for its employe.pdf
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Introduction to Financial Accounting Solutions
Introduction to Financial Accounting SolutionsIntroduction to Financial Accounting Solutions
Introduction to Financial Accounting Solutions
 

Recently uploaded

8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadAyesha Khan
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncrdollysharma2066
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 

Recently uploaded (20)

8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 

A simple example of Earned Value Management (EVM) in action

  • 1. Simple example of EVM in action © 2014 Planisware
  • 2. The plan • Our team has been tasked with planting the trees on the plot of land behind our company’s new factory • The plan: – 30 batches of 20 trees (600 trees) – 5 batches per day (100 trees) – budgeted cost per tree 2.90$ (2.5$ per baby tree / 0.40$ for the slow release fertiliser) → total budget 1,740$ © 2014 Planisware 2
  • 3. After the first day… • 70 trees were planted (the team hit a patch with stones that had to be removed before the trees could be planted) • Total cost was 350 $ (we had to rent a special machine to help remove the stones which cost 147$ for the day) • Simple EVM calculation: – Earned Value = 70 trees planted  2.90$ = 203$ – Budgeted Cost = 100 trees planned per day  2.90$ = 290$ – Actual Cost = 70 trees planted  2.90$ + 147$ for the machine = 350$ © 2014 Planisware 3
  • 4. Visually… 0 50 100 150 200 250 300 350 400 Start 1st day Actual cost = 350$ Budgeted cost = 290$ Earned Value = 203$ © 2014 Planisware 4
  • 5. Regarding cost… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 5 We are here
  • 6. Regarding cost… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 6 We are here We should have been here
  • 7. Regarding cost… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 7 Cost variance = EV – AC = 203$ – 350$ = -147$ < 0
  • 8. Regarding cost… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 8 Cost variance = EV – AC We’re over budget, and have spent 203  350 = 58% more budget than anticipated (our cost performance index) = 203$ – 350$ = -147$ < 0
  • 9. Regarding schedule… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 9 We are here
  • 10. Regarding schedule… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 10 We are here Which is where we should have been then
  • 11. Regarding schedule… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 11 Schedule variance in hours
  • 12. Regarding schedule… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 12 Schedule variance in hours = 203$ – 290$ = = -87$ < 0 Schedule variance in dollars = EV – BC
  • 13. Regarding schedule… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 13 Schedule variance in hours We’re late and have only performed 203/290 = 70% of the work planned (our schedule performance index) = 203$ – 290$ = = -87$ < 0 Schedule variance in dollars = EV – BC
  • 14. The consequences 0 500 1000 1500 2000 2500 3000 Start 1st 2nd 3rd 4th 5th 6th 7th 8th 9th © 2014 Planisware 14 Earned Value today Estimate at Completion EAC = 3,000$ Budget at Completion BAC = 1,740$ Extending the Actual Cost into the future gives us the end result if we do not modify the performance of the project
  • 15. The consequences 0 500 1000 1500 2000 2500 3000 Start 1st 2nd 3rd 4th 5th 6th 7th 8th 9th © 2014 Planisware 15 Earned Value today Estimate at Completion EAC = 3,000$ Budget at Completion BAC = 1,740$ Cost Overrun
  • 16. The consequences 0 500 1000 1500 2000 2500 3000 Start 1st 2nd 3rd 4th 5th 6th 7th 8th 9th © 2014 Planisware 16 Earned Value today Planned end date = 6 days Estimate at completion = 8.57 days Project Slip Estimate at Completion EAC = 3,000$ Budget at Completion BAC = 1,740$ Cost Overrun
  • 17. The consequences → If we continue at this rate, we will need: 1,740$  58% = 3,000 $ (cost estimate at completion) and 6 days  70% = 8.57 days (schedule estimate at completion) to finish the work. → If we want to finish on budget, we need to work at (planned remaining budget)  (actual remaining budget) (1,740 – 290)  (1740 – 350) = 104.3% of the originally planned performance → If we want to finish on time, we need to work at (actual remaining work)  (planned remaining work) (600 – 70)  (600 – 100) = 106% of the originally planned performance © 2014 Planisware 17
  • 18. In technical terms… In real life, the elements we calculated have slightly different names: • The Actual Cost is usually referred to as the Actual Cost of Works Performed (ACWP) • The Planned Cost = Budgeted Cost for Work Scheduled (BCWS) • The Earned Value = Budgeted Cost for Work Performed (BCWP) © 2014 Planisware 18
  • 19. Summary © 2014 Planisware 19 today time cost ACWP (Actual Cost of Work Performed) BCWS (Budgeted Cost of Work Scheduled) BCWP (Budgeted Cost of Work Performed) completion date Budget at Completion (BAC) Estimate at Completion (EAC) Schedule variance in $ SV = BCWS - BCWP Cost variance in $ CV = ACWP - BCWP Cost Overrun Project SlipSchedule variance in hours
  • 20. To learn more about EVM and tools to help manage it, visit our glossary: www.planisware.com/glossary/earned- value-management © 2014 Planisware 20