SlideShare a Scribd company logo
1 of 180
Workshop on “Plant Commissioning and
       Start-Up Procedures”
               Dr. Himadri Banerji
          MD EcoUrja Ex Reliance and Tata
                                            Organized By :
Standard Implementation Path is show here
The Commissioning Process Key State

                  Preparation and
                  planning

                  Mechanical Completion
                  and Integrity checking


                  Pre-commissioning &
                  Operational Testing

                    Start Up & Initial
                         Operation

                  Performance and
                  Acceptance testing

                  Post Commissioning
The Commissioning Process Detail - 1
      Preparation and       • Appointment of Commissioning
         planning             Manager or Lead Commissioning
                              Engineer
        Mechanical          • Appointment of Commissioning Team
        Completion            Members and Support Staff
   and Integrity checking   • Training
   Pre-commissioning &      • Information Compilation
    Operational Testing     • Safety and Risk Assessment
     Start Up & Initial     • Commissioning Strategy
          Operation           Development;
                            • Procedures and Checklist
     Performance and          Development
    Acceptance testing
                            • Post Commissioning
    Post Commissioning
                            • Detailed Plan and Budget Preparation;
The Commissioning Process Details – 1
Facility Commissioning Issues


      Time phasing construction and commissioning activities
      Time phasing the commissioning of the various parts of the plant relative
      to each other
      Relationships and timings determining when various systems need to be
      available:
      Electrical, Steam, Water, Instrumentation
      Sequencing of the overall plant startup and shutdown to ensure we do
      not create unsafe conditions
      Initial start up
      Process Control and Shutdown
      Performance testing
Developing Startup Procedures
   Engineering and construction companies generally follow a
   systematic procedure where by their startup engineers
   review the process design several times as it is developed
   After the first review, a preliminary start-up and operations
   procedure is written
   Decide what must be added to the design to make the
   process capable of being started up and operated;
   By the time the final engineering flow-sheets have been
   released a complete startup and operating instructions
   manual should have been completed.
Issues Considered

   Are various part of the process too depend on one another

   Is there enough surge capacity

   Are there provisions to prevent abnormal pressures, temperatures
   and rates of reaction

   Where are additional valves and bypass lines needed

   Special lines to allow equipment to be started up

   and rerun product/raw materials.
System Level Activities

    Utilities systems - steam, instrument air, process water, fire
    water, drainage, condensate return

    Electrical systems

     Instrumentation and instrumentation systems;

     Cleaning and flushing

     Purging

     Initial start up and shutdowns

     Performance testing
Equipment Level Activities

   Pressure testing & mechanical integrity testing of vessel,
   columns and pipe work.

   Heat Echanger, condensers, coolers etc.

   Mechanical equipment and machinery.

   Control Systems and Instrumentation.

   Operational testing.

   Proof testing and acceptance.
What can be done before mechanical
completion

  Utilities commissioning

  Lube and Seal-Oil Systems Cleaned

  Instrumentation and Control Loops Proven

  Piping, Towers and Vessels Cleaned

  Boil-Out, Dry-Out and Acid Cleaning

  Turbine, Motor and Pump Run-Ins

  Nitrogen Purge and Tightness Testing
Building Organisational Learning



                      Best Practice
                      Benchmarking                          Improvement
    Industry                                                 Processes
   Standards
                       Corporate           Procedures and
                     Knowledge Base         Check sheets
  Legislation
                                                            Experience

                Process Design          Specific
                                       Machinery
                                      &Equipment
Procedures

   Procedures are written routines/instructions that describe the logical
   sequence of activities required to perform a work process and the
   specific actions required to perform each activity.

  If there are no written procedures, there is no basis for
  monitoring performance, focus for improvement or
  mechanism by which to capture learning.

   The establishment of procedures and routines allow more time and
   mental energy to deal with the unexpected, which always happen
   during commissioning.
Commissioning / Startup Logic


    A Critical Path Network (Plan) with written procedures
    with related documents are required. These should
    define for the facility, each plant system:
    • The order in which the systems will be started up.
    • Individual activities at each stage.
    • Operation testing requirements.
    • Durations, waiting times, cooling times.
    • Total duration for starting up each system.
    • Resources required - labour, materials, equipment services
    • Temperatures, pressures, fluid flows used.
BY DR.HIMADRI BANERJI MD ECOURJA
EX. RELIANCE AND TATA Copyright www.ecouja.com   15
Commissioning / Startup and Shutdown Issues

   At the facility, system and equipment level, we want to avoid:
   • Creation/existence of explosive mixtures, usually because of
     the presence of air.
   • Water hammer and water based explosion effects, due to
     contact between water and hot substances (steam, oil, etc.)
   In particular, during commissioning hot fluids and gases will be
   coming into contact with cold surfaces in places that would be
   hot under normal operations.
Mechanical Completion and Integrity Checking
Mechanical Completion and Integrity Inspection

      Preparation and
         planning
                            •   Inspection
   Mechanical Completion    •   Pressure testing
   and Integrity checking   •   Cleaning and Flushing
                            •   Machinery checkout
    Pre-commissioning &
     Operational Testing

     Start Up & Initial
          Operation

     Performance and
    Acceptance testing

    Post Commissioning
Categories of Process Equipment

   Distillation Towers / Fractionation Towers
   Re-boilers & Other Shell & Tube Heat Exchangers
   Boilers and Fired Heaters
    Pressure Vessels and Pipe-work
   Fin-Fan Coolers
   Condensers
   Machinery/Rotating Equipment
   Valves
   Instrumentation
   Electrical Equipment
Machinery / Rotating Equipment

    Pumps

    Steam Turbines

    Gas Turbines

    Compressors

    Gas Engines

    Electric Motors
Mechanical Completion and Integrity
Inspection

    Involves checking that everything has been built and it there
    as per specification. Refer:
    • Piping Plan Drawings
    • Layout and construction drawings
    • P & ID’s

    Electrical systems, Instrumentation and control systems
    checkout done by appropriately qualified personnel
    (Electricians and Instrumentation technicians).

    General commissioning engineers generally do not get
    involved in this in a hands-on manner.
Mechanical Completion and Integrity
Inspection Procedure
   Divide plant into manageable areas;

   In a large plant, assign individuals or teams to specific areas;

   Establish a master set of piping plan drawings and P&ID’s,
   mark up areas:

   Individual commissioning engineers or teams walk every line
   and mark up every item that can be confirmed as present on
   master set of drawings.

   Use different colored “highlighter” pens to indicate different
   services.
Mechanical Completion and Integrity Inspection
Every line must be walked! Physically see every
Mechanical Completion and Integrity
Inspection Procedure Hints / Tips

    Ensure pipes, vessels, valves etc. are all in the right place.
    Valves are correct type - globe, gate, control;
    Vents, drains, steam traps etc.
    Flanges, bolts, types of bolts.
    Blind flanges and swing able blinds in place,
    correct rating.
    Check all tag numbers.
    Punch list any non-conformances.
Pipe Stressing

   Piping should provide adequately for expansion and
   contraction due to temperature changes, without placing
   excessive stresses on equipment;

   Misalignment between matching flanges on pipe work
   particular where there are changes indirection (elbows) can
   cause stressing;

   Misalignments where pipe-work connects to machinery,
   vessels and other process equipment;

   Can often be seen visually, or checked with gauges using the
   same procedures we use to align rotating equipment.
Piping and Equipment Supports
Piping and equipment support

   Mobile supports permit and guide the thermal growth of
   equipment undergoing temperature change;

   If they do not function correctly, vessels, equipment, pipe work,
   nozzles heat exchangers etc. may be damaged.
Typical Piping Support Methods
Piping and Equipment Supports


   Inspection prior to start up:
    • Check that installed according to specification and not
       jammed;

   Inspection during warm up:
    • Check thermal growth is occurring and supports are
       responding as per design;
    • Check that there is no surface buckling or crimping - this
       needs to be corrected;
    • Check expansion joints;
    • Check long straight runs of piping for bowing or support
       shoe that may have slipped;
    • Rule of thumb - bowing is excessive if you can see it.
Piping and Equipment Supports

    Inspection after cool-down:

    • Check that sliding supports have returned to original
      positions;

    • Establish that equipment can expand and contract as
      required.
Inspection of Spring Supports

   Before hydro-testing:
   • Check that spring stops are installed. (If not, the weight of
     water in pipe will deform the spring).

   After hydro-testing but before heating:
   • Check that stops are removed;
   • Check that spring pointer is positioned to cold setting;
Inspection of Spring Supports

    During and at end of heating:
    • Check pointer has not exceeded hot setting;

    After cool down:

    • check to establish piping can expand and

    • establish that springs can absorb loads.
Vessels and Columns
Inspection of Vessels and Columns

   The inspection of vessels, columns and reactors should be
   scheduled to be completed before construction has closed
   them up;

   Other inspections - e.g. for completeness or piping, insulation,
   safety etc. can be scheduled later;

   If a vessel has been sealed up by construction, it is your duty to
   inspect it, even it construction resist.
Inspection of Vessels and Columns

   Check that distributors have been installed correctly;

   De-misters installed correctly and of correct materials, design,
   type;

   Vortex breakers in place;

   Trays - packed or “bubble-cap” are correct:
   • Bubble caps not jammed or damaged, down comers clear,
     supports all OK.
Pressure Testing
Pressure Testing - Objectives

    The objective of pressure testing is to confirm the mechanical
    integrity of the plant;

    Verifying capability of containing the pressures it has been
    designed to hold;

    Ensure there are no leaks and verify that the plant can be
    reliably made leak free;

    Identify any vulnerabilities well before the plant is placed into
    service;

    Meet the requirements of legislation, local, international and
    industry standards.
Pressure Testing – Responsibilities

    Pressure tests of tanks, reactors and piping for mechanical
    strength and tightness of joints is usually done by the
    construction team;

    Commissioning team representatives should witness and
    certify the tests;

    Need to verify that all necessary safety precautions have
    been taken;
Pressure Testing - Procedures

    Water for testing and flushing should contain a rust inhibitor -
    one low in chloride content for stainless steel lines;

    After testing, water should be drained completely from all
    lines that do not normally carry water, steam or steam
    condensate;

    All low points should be checked for presence of water;

    Lines should be dried by blowing hot air, dry inert gas or
    instrument air.
Pressure Testing – Vacuum Systems

   Final checks of vacuum systems are best performed by
   pulling a vacuum and observing the rate of pressure rise in
   the blocked in system;

   Excessive leaks can then be located by applying a mild
   positive pressure and testing each flange with bubble
   solution.
Pressure Testing – Procedures 2


     Isometric drawings of all systems to be tested should be
     displayed on a board and marked up as each section is
     tested;

     Hydro testing of piping and equipment according to code
     requirements to confirm mechanical strength should be
     carried out on groups of equipment naturally suggested by
     design pressure and function;

     All water, steam, condensate, oil, gas and process steam
     piping should be hydro tested;

     Major equipment that has already been tested as part of
     manufacturing may be isolated by blanks.
Cleaning and Flushing
Cleaning and Flushing

   Need to ensure no construction debris is left in pipes of
   vessels - welding rods, bolts, gloves, rags etc.

   Large debris (lumber, cable, packaging) should have been
   removed during mechanical integrity inspections;

   Small debris (rags, nuts, dirt) must be flushed out of all pipe
   and vessels;

   Where oil coatings must be removed, chemical cleaning is
   necessary.
Cleaning and Flushing

   Before flushing is started, check the process
    thoroughly to ensure:

   • Screens have been installed in front of pump suctions.

   • Blinds in front of equipment such as compressors and
     turbines;

    • “Jumper” spool pieces to allow for continuity of flow.
Flushing

    Can be handled by geographic plant area;

    Sections too large for water flushing:
    • Pipes greater than 30 in diameter (0.75 m), or
    • Pipes that should not be touched with water;

    Should all be blown out with air or inert gas.
Flushing

   Regardless of whether pipes are cleaned with water, steam, air
   or nitrogen, flow velocities should be high enough to ensure
   that pipes will be suitably scoured;

   Need to ensure that the debris from one piece of equipment will
   not simply be flushed into another;

   Water velocities should be at least 12 ft/sec (approx. 3.75
   m/sec);

   Air velocities a minimum of 200 ft/sec (approx.65 m/sec).
Pre-Commissioning and Operational Testing
The Commissioning Process Detail - 3

      Preparation and
         planning

        Mechanical           • Steam and other utilities
        Completion             commissioned and introduced;
   and Integrity checking    • Dry running trials;
                             • Hot running trials;
   Pre-commissioning &       • Safe-fluid dynamic testing;
    Operational Testing      • Solvent dynamic testing;
                             • Process fluid tests.
     Start Up & Initial
          Operation

     Performance and
    Acceptance testing

    Post Commissioning
Commissioning Utilities
Commissioning Utilities

   Utilities commissioning usually represents the first phase of
   commissioning, as these usually need to operational first,
   before the rest of the plant can be commissioned;

   The steps for commissioning each utility should be planned in
   detail;

   Provides planning practice for planning the startup of the
   main plant.
Commissioning Utilities – Broad Guidelines

   Check supply pressures of all services - steam, cooling water,
   instrument air, nitrogen etc.
   At the most distant points, open drains, vent valves or pipe
   flanges and purge until fluids come out clean and rust free;
   Purge/blow out lines to each piece of equipment;
   Check that instrument air is clean and dry, and at correct
   pressure;
   Circulate water to waste water system until water lines clear
   and clean;
   Flush waste water and drain systems to ensure no blockages;
   Check operation of steam traps;
   Drain condensate to waste water until is clean.
Commissioning Utilities
Introducing Steam

    Steam usually represents the first “hazardous” fluid
     introduced into the “new” system;

    Admit steam slowly into the distribution system with
    atmospheric bleeds open:
    • Cold pipes will condense steam in places where it would
      not under normal operation;
    • Can lead to “water hammer”- can distort and rupture lines;

    After system has been warmed, slowly raise pressure and
    blow down the system with traps bypassed, until clean;

    Then place steam traps into service and check operation.
High Pressure Steam Systems
Specific Issues
   The cleanliness and purity of high pressure steam systems -
   particularly where the steam is used to drive a steam turbine
   should be checked by use of a “target”;

   For new boilers, or new sections added to steam system -
   blow down at full pressure;

   When steam appears clean, fit a target with a “mirrored”
   surface (ie. Small steel plate which has been polished, so that
   it is in the steam blow down stream;

   Blow down the boiler or system so that the target is impinged
   upon for a few minutes;

   Check target - ensure there are no small “pock marks” left on
   the target. If pock marked - repeat process.
Electrical Systems
Machinery and System Check-Out


   Check-out
   A crew of specialized individuals need to be mobilized to do the check-out
   and pre-commissioning in a plant:

   • All control loops, settings of PID loops, stroking of valves, transmitter
     calibration, etc…

   • P&ID conformity; is the plant built according the P&ID, is all instrumentation
     correctly installed, are they connected, are all valves correctly installed, etc…

   • Mechanical installation of all (major) equipment; levelling correct, alignments done,
     oil flushing satisfactory, etc…

   • Analyzer calibration, checking of tubing, problem assessment and
     identification.

   • Control systems functional check, communications check, integrity check, safety
     features checking, emergency stops check, critical operating parameters checking,
     etc…

   • Electrical check-out; check-out of MCC’s, switchgears, selectivity studies,
     protection systems, functional checks, etc…
Commissioning Electrical Systems
The following checks are typical of what is required

    Open circuit breakers and switches;

    Check that all bus-bars are free of dirt and foreign matter;

    Check grounding systems for continuity and resistance. Make
    sure all electrical equipment, vessels, structures are
    connected to the grounding system in accordance with
    drawings and specifications;

    Check that all sealed fittings are filled with proper sealants, all
    explosion proof, vapour-tight, dust-tight and weather tight
    enclosures are properly closed and secured;

    Check motor control and power circuitry for correct hookup.
Commissioning Electrical Systems – 2
The Following checks are typical of what is required
    Check all nameplates and panel directories to ensure that each
    circuit breaker and switch does control the proper circuit. Label all
    switches even though their application may seem obvious;

    Close main transformer primary disconnect switch and switch-gear
    main circuit breaker;

    Check voltmeter at switch-gear for proper voltage;

    Close first switch-gear circuit breaker, second, third etc.

    Close first motor control centre main circuit breaker, then
    each motor starter circuit breaker. Repeat for each MCC.

    Check overload breakers and heaters to ensure that the correct
    capacity units have been installed.
Commissioning Electrical Systems – 3
The following checks are typical of what is required

    Check that all lighting and power circuits are functioning
    correctly;

    Check motor bearings for proper lubrication;

    Remove motor power fuses and check main contractor,
    interlock and sequencing devices;

    Uncouple each motor, replace fuses and check direction of
    rotation by momentarily pressing the start button, then stop;

    Check manual, then automatic operation.

    Replace all couplings, check drive belts and make sure
    guards are installed.
Electric Motor Driven Pumps
Operational Testing
Operational Testing

    Progresses through several stages;

    Dry runs of individual items of equipment

    Hot testing of individual items of equipment and systems;

    Several stages of Dynamic Testing of:
    • Individual items of equipment;
    • Individual Systems/processes in isolation;
    • The whole new process plant installation.
Dry Runs and Hot Tests

    Check that motors are connected correctly and turn in the
    right direction;

    Shafts and impellers move freely;

    Equipment that is to be operated at temperature, raise to
    temperature and check;

    These tests should be performed by the manufacturer’s
    representative but witnessed by members of the client’s
    operating/commissioning personnel.
Hot Testing Equipment
   Applies to equipment whose leak-tightness must be tested at
   operating temperatures and after temperature reversals;

   Fixed-bed catalytic reactors that in normal conditions are
   heated by heat transfer fluids where leakage would
   contaminate the catalyst;

   Critical exchangers whose steam or cooling water is at a high
   pressure than the process fluid;

   Any equipment having complicated seals through which
   leakage could occur;

   Rotating machinery which must be able to rotate freely at
   temperature eg. Steam turbines, etc.
Hot Testing Procedures

    The thermal shock tolerance of equipment must be
    determined beforehand;

    To avoid thermal shock, the temperature of the heating
    medium may have to be raised gradually;

    Time required for a hot test must be established in advance;

    Establish a uniform temperature in all parts of equipment
    that are supposed to be uniformly hot during operation to
    avoid setting up stresses;
Dynamic Testing
Dynamic Testing

    Involves operating the equipment, before introducing “live”
    process fluid;

    During dynamic testing, we progress through:
    • Safe-fluid dynamic testing;
    • Dynamic testing with solvent;
    • Closed loop testing with process fluid.

    Once process fluid is introduced, normal plant safety procedures
    must come into effect as if it were a live operating plant.
Safe-Fluid Dynamic Testing


    Closed loop dynamic testing with safe fluids consists of
    operating equipment systems with air, water, inert gases etc.

    This permits flow testing of equipment;

    Gives first indication of how control loops work;

    Establishes performance while there is still time to modify the
    plant;

    Familiarizes operators with the operation of the equipment
    before hazardous materials are introduced;

    Gets rid of a lot of dirt which would be more difficult to

    Clear once the process fluid has been introduced.
General Principles for Testing


    For most plants, a period of 2-3 weeks is usually sufficient for
    operational testing, after the mechanical dry running of individual
    pieces of equipment and hot testing complete;

    Air and water tests should be set up in a closed loop with     fluids
    continuously recycled, with loops as large as possible;

    The loop should ideally be the same loop that will be subject to
    solvent testing;

    Tests should continue for several days in order to give all shifts a
    chance to conduct the same tests;

    All shifts should be given the opportunity to start up and
    shutdown each closed loop test.
General Principles for Testing

   A rough flow-sheet should be developed for air and water
   tests, predicting all information that normally appears on a
   process flow sheet - flow, temperature, pressure, heat
   transfer, power etc.

   will assist in alerting commissioning team for risks from over-
   pressuring, over loading temperature-shocking and stressing
   equipment;
Cautions During Testing

    Dynamic testing may lead to:
    • Unusual or unforeseen differential expansions;
    • Corrosion
    • Excessive weight of liquid into parts of the system;

    Care must be taken not to collapse or burst pressure
    vessels and tanks:
    • ensure there is always adequate venting;
    • avoid pulling a vacuum.
Dynamic Testing – Simulated Operations
Safe Fluid Testing
   Auxiliary services must be brought into operation
   first:
   • water cooling, inert gas generators, boiler feed water,
     firewater, steam production, etc.

   Water is pumped through the process (except where special
   conditions do not permit it) and boiled up in columns;

   Compressors and blowers should be operated on air or inert
   gas.
The Value of Dynamic Testing –
Simulated Operations

    Value of simulated operations will be to allow operator to
    become familiar with the operation of the process, before
    hazardous fluids are introduced;

    Equipment deficiencies can become apparent during dynamic
    testing;

    Failures and problems more easily corrected with safe fluids
    present

    Leaks should be found and tightened;

    Instruments can be placed into service - although selection of
    set-points will have to be deferred;

    Inspect the plant for evidence of design and construction
    errors.
Dynamic Testing – Simulated Operations
Dynamic Testing with a Solvent

    After safe fluid testing and subsequent repairs and
    modifications, we are ready for dynamic closed loop testing
    with a solvent;

    The “solvent” is a relatively safe fluid whose properties are
    close to that of the process fluid, or the process fluid itself;

    In order to allow for continuous re-circulation of the solvent
    and the use of different solvents in different parts of the plant,
    temporary lines will need to be installed.
Dynamic Testing with Process Solvent

   Introduce the process solvent. (if there is more than one,
   introduce only one at this stage);

   The dynamic testing procedure used for the safe fluid test is
   repeated for the process solvent dynamic testing;

   After operations with the first solvent have been brought
   completely under control, should the second solvent be
   introduced (if there is one).
Dynamic Testing with a Solvent

    The purpose of dynamic testing with a solvent is to check out
    equipment and instrument loops at, or near design conditions
    prior to the introduction of more hazardous process fluid;

    No reactions should be allowed to occur during these tests,
    so as to ensure that test fluids remain predictable in
    composition and properties;

    Guidelines used for safe-testing apply;

    Need to plan how solvent will be fed into the system and later
    removed.
Stages of Dynamic Testing with a “Solvent”


    Drain safe fluid and purge air used in the previous test from
    the system;

    Dry out equipment where safe fluid was water. Check flow
    sheets for where water is likely to accumulate.

    Fill systems with the solvent. Ensure provisions made for
    venting and drains closed;

    When adequate levels established, place pumps and
    compressors online to complete filling;

    Start closed loop circulation;

    Heat up the systems to simulate operating conditions by
    placing reflux, re-boiler and condensation systems into
    operation
Stages of Dynamic Testing with a “Solvent”

    Systematically check out instrumentation and control loops;

    After instruments have checked out, place as many as
    possible on automatic control;

    All shifts should go through starting and stopping equipment,
    heating and cooling closed loop systems;

    Dynamic “solvent "testing offers the best opportunity for
    operator training before the “real thing”;

    Operate equipment as near as possible to design capacities;

    Reliability of emergency shutdown systems and alarms must
    be proven;
    Critical instruments must be calibrated over their full range.
Stages of Dynamic Testing with a “Solvent”

    Deliberately operate equipment near its limits:

    Flood columns;

    Ease compressors into mild surges and plot surge curves;

    Overload condensers;

    Do not fear blowing a relief valve or two!

    After tests have been completed, plant should be ready for
    initial operation.
Closed Loop Dynamic Testing with Process Fluid

   Finally, introduce process fluid;

   During this step, instruments should be calibrated to cover
   their full range of flow, temperature and pressure;

   Ensure that instruments, process analysers and safety
   devices are kept work properly during these processes;

   After operations with process fluid are brought completely
   under control should the final stage of start-up be
   attempted.
Preparing to Introduce Process Fluid


    Before introducing hazardous liquids into the plant, we
    complete additional pressure testing and purging;

    Need to check that the stresses and strains of dynamic
    testing has not caused any leaks – these must be found and
    fixed;
Pressure Testing and Purging

   Consists of pressuring and de-pressuring with nitrogen
   several times, until at least <3% oxygen is reached;

   Vacuum systems should be evacuated and then re-pressured
   with nitrogen;

   Long runs of piping are swept with nitrogen;

   While under pressure, rate of pressure loss of the “blocked in
   "system is monitored as a check for leaks and that no vents
   or drains have been left open.
Dehydrating by Circulation


    It is usually not possible to water-free equipment simply by
    draining;

    Only positive method to water-free process equipment is oil
    circulation followed by repeated draining of low points;

    Ensure sufficient low point drains are provided on piping,
    control valve loops, vessels and process machinery;

    Startup lines - deliver oil to upper part (trays) of distillation
    towers (size for 20% of net distillate product rate);
Start Up and Initial Operation
Preparation and
      planning

Mechanical Completion
and Integrity checking

 Pre-commissioning &
  Operational Testing    • Introduction of process fluid
                         • Start-up and initial operation
                         • Trouble-shooting and
  Start Up & Initial
       Operation
                            problem correction.
                         • Plant taken to full operations.

  Performance and
 Acceptance testing

Post Commissioning
Most plants in petrochemical/chemical industry
  have the following “general ”form.


 Feed                   Reaction           Recovery   Product
 Preparation                                          refining




Start Up from the End of the Process and Work back
Start Up Logic

    It is common practice to buy in product and start up the
    last past of the process first and work backwards to the
    front. E.g.

    • Start up refining, get this working and in control;

    • Then possibly start up reaction and recovery;

    • Finally, feed preparation.
Into the Initial Operation

    Once raw materials are fed into the plant – usually at reduced
    rate until reaction conditions have been established;

    As each section is started up, establish as quickly as possible
    that process conditions are as expected;

    If potentially serious problems develop, there should be no
    hesitation on going into an emergency shutdown.
Ramping up the Plant

    Plant is brought slowly to design feed-rates and operating
    conditions;

    Usually done in steps with operating data evaluated and
    verified as OK at each step;

    Plant and laboratory data are now being collected and should
    be being evaluated promptly;
Coordination and Supervision
During Start Up
    Additional personnel, both supervisory and “on the- ground”
    are required at this stage;

    Cooperation between startup personnel and plant supervisory
    personnel is critical at this stage:

    • Need a daily meeting at least;

    • Often, a briefing each shift.
Trouble Shooting

   At this stage, many problem with equipment of the process
   itself may become apparent;

   The commissioning process goes through what is often an
   intense (and hopefully short) period of problem trouble
   shooting, problem solving, engineering correction and plant
   modification;
Performance and Acceptance Trails
Preparation and
      planning

     Mechanical
     Completion
and Integrity checking

Pre-commissioning &
 Operational Testing

  Start Up & Initial
       Operation

  Performance and        • Performance trails;
 Acceptance testing      • Formal Acceptance test

Post Commissioning
The Performance Trials

   Once the plant is fully operational, the final “proving trial” or
   performance run is performed in order to prove the plant can
   do what it is supposed to do;

   The values or range of values for each independent variable -
   flow, temperature, pressure, level, concentrations, etc. to
   which the plant must be operated to are determined;

   The plant is brought up to those conditions and the pre-
   agreed trial period begins.
Before the Trails of Performance Run
Need to Ensure that…

    Control of plant operating conditions has been achieved. I.e.
    temperature, pressures, levels and analyses are reasonably
    constant or in the case of a batch process, there is
    repeatability;

    Daily material and energy balanced can be performed and
    that these agree with “official” production figures;

    Product specifications are being achieved consistently.
Need to Verify …

   Physical operation, capability and capacity of plant and
   equipment;

   Energy and mass balance;

   Process chemistry;

   Efficiencies, yields and quality;

   All to specification.
Acceptance

   When the plant has met the Performance and Acceptance
   test requirements designed by the commissioning team there
   is usually a formal acceptance process involving signing of
   acceptance certificates;

   Once the plant is accepted it is officially part of the normal
   operations - the responsibility of operations and maintenance;

   Commissioning is officially over;

   The may still be outstanding punchlist items
Acceptance Testing

   It is common practice to prove performance repeatability
   and plant integrity as part of the performance test. That
   is:

    • Shutdown and Start Up the plant on several occasions and
      bring it up to test conditions to prove repeatability. Also
      ramp down and ramp up while online;

    • Re-inspection of critical process equipment - particularly
      columns to ensure they have not been damaged by the
      performance run.
Commercial Significant of Acceptance

    Formal Acceptance represents formal acknowledgment
    that the:

    • Contractor has full-filled their contractual obligations;
    • Commissioning team have full-filled their obligations;

    Completion of the Capital Project and transfer to Operations;

    Expenses and costs from acceptance onwards are now
    operating expenses not capital project costs;

    All subject to agreed punch-list items.
Post-Commissioning
Preparation and
      planning

     Mechanical
     Completion
and Integrity checking

Pre-commissioning &
 Operational Testing

  Start Up & Initial
                         • From plant on-stream to settled down
       Operation
                           and in regular production;
  Performance and        • Adjustments, modifications and fault
 Acceptance testing        correction;
                         • Completion of outstanding punch list
Post Commissioning         items
Post Commissioning

   Covers the period immediately after Acceptance;

   Outstanding punch-list items are completed;

   The first routine maintenance checks are performed, findings
   evaluated and reported;

   Process equipment and items covered by warranty are
   scrutinized for signs of premature wear-out or problems;

   Operating data is collected and evaluated to ensure
   consistent plant operations are maintained and sustainable.
BY DR.HIMADRI BANERJI MD ECOURJA
EX. RELIANCE AND TATA Copyright www.ecouja.com   103
WORKSHOP ON PLANT START UP AND
              COMMISSIONING




SEQUENTIAL START UP
AUTOMATION IN PLANT START UP AND COMISSIONING



BY DR. HIMADRI BANERJI
(EX RELIANCE AND TATA)
www.ecourja.com




                                 BY DR.HIMADRI BANERJI MD ECOURJA
                                 EX. RELIANCE AND TATA Copyright www.ecouja.com   104
Automation for Controlled Start Up

   To advocate the usage of process integration in industrial
   practice, it is important to be able to

   guarantee not only robust control during near steady state
   operation, but also to provide

   procedures for generating fast and reliable start-up
   sequences.




                                     BY DR.HIMADRI BANERJI MD ECOURJA
                                     EX. RELIANCE AND TATA Copyright www.ecouja.com   105
Sequential Start Up and Shutdown Using
Automation in Plant…Burner Management System
1. Burner Management System in Power Plants
 General

 The Burner Management System must be designed to ensure a safe, orderly
 operating sequence in the start-up and shutdown of fuel firing equipment and
 to reduce possible errors by following the operating procedure.

 The system is intended to protect against malfunction of fuel firing equipment
 and associated systems. The safety features of the system shall be designed
 to provide protection in most common emergency situations, however, the
 system cannot replace an intelligent operators reasonable judgment in all
 situations.

 In some phases of operation, the BMS shall provide permissive interlocks only
 to insure safe start-up of equipment. Once the equipment is in service, the
 operator must follow acceptable safe operating practices.

                                             BY DR.HIMADRI BANERJI MD ECOURJA
                                             EX. RELIANCE AND TATA Copyright www.ecouja.com   106
Sequential Start Up…BMS Functions
The BMS shall be designed to perform the following functions:
1.Prevent firing unless a satisfactory furnace purge has first been completed.
2. Prohibit start-up of the equipment unless certain permissive interlocks have first
   been completed.
3. Monitor and control the correct component sequencing during start-up and shut-
   down of the equipment.
4. Conditionally allow the continued operation of the equipment only while certain
   safety interlocks remaining satisfied.
5. Provide component condition feedback to the operator and, if so equipped, to
   the plant control systems and/or data loggers.
6. Provide automatic supervision when the equipment is in service and provide
   means to make a Master Fuel Trip (MFT) should certain unacceptable firing
   conditions occur.
7. Execute a MFT upon certain adverse unit operating conditions.

                                                BY DR.HIMADRI BANERJI MD ECOURJA
                                                EX. RELIANCE AND TATA Copyright www.ecouja.com   107
Furnace Explosions

    A common cause of furnace explosions is

   “Fuel leakage into an idle furnace and the ignition of the
    accumulation by a spark or other source of ignition”.

    Proper attention to the design of the interlocks and trip
    system to provide a safe light up of the boiler furnace is
    required.




                                      BY DR.HIMADRI BANERJI MD ECOURJA
                                      EX. RELIANCE AND TATA Copyright www.ecouja.com   108
Furnace Purge…Permissives


   Before any fuel firing is permitted, either initially or after a boiler
   trip, a satisfactory furnace purge cycle must be completed.

   Prior to starting a furnace purge cycle, the operator must
   ensure that the following purge requirements are satisfied[i]:

   1. Drum level within operating range (not high, not low)

   2. Instrument air header pressure within operating range

   3. Fan is in service

   4. Purge airflow capable of a minimum of 70% of the full load
   airflow established through the unit[ii].

                                          BY DR.HIMADRI BANERJI MD ECOURJA
                                          EX. RELIANCE AND TATA Copyright www.ecouja.com   109
Furnace Purge…Permissives


  5. All flame scanners reading "No Flame“
  6. Natural gas block valves are proven closed
  7. Fuel oil block valves are proven closed
  8. Air dampers are in the fully open position
  9. Natural gas, or fuel oil, header pressure upstream of block
     valve is satisfactory
  10. Pilot gas header pressure is satisfactory
  11. Burner Control System is energized
  12. A "No Master Fuel Trip condition" condition is established
                                      BY DR.HIMADRI BANERJI MD ECOURJA
                                      EX. RELIANCE AND TATA Copyright www.ecouja.com   110
Pre Purge Permissives
 Pre purge permissive condition checks and furnace purge are to be
 initiated by the operator from the local BMS panel (you may see detailed
 guidelines on cold starting using fuel oil, cold starting using natural gas
 from operating manuals).

 Purge air flow: The total furnace airflow shall not be reduced below the
 purge rate airflow (70% of the maximum continuous airflow capacity).

 Reducing airflow below these limits will lead to a MFT, and a new furnace
 purge will be required.

                                                         Suggested color design:
                                                        Purge Permissives indicating lights:   white

                                                        Purge Available indicating light:      green

                                                        Purge in progress indicating light:    amber

                                                        Purge complete indicating light:       white

                                                        MFT reset indicating light:            red


                                                  BY DR.HIMADRI BANERJI MD ECOURJA
                                                  EX. RELIANCE AND TATA Copyright www.ecouja.com       111
Main Flame Start-Up Sequence


    The main flame start-up sequence, from the lighting the of
    the pilot flame through main flame light-off, is an automated
    sequence.

    Once the start-up sequence has begun, only the “BOILER
    STOP” switch and the “EMERGENCY STOP” will interrupt
    the start-up sequence.

    Any interruption of the start-up sequence requires a post-fire
    purge prior to attempting to start the boiler again.

      To initiate the start-up sequence, the operator activates the
      “START BOILER” switch.



                                     BY DR.HIMADRI BANERJI MD ECOURJA
                                     EX. RELIANCE AND TATA Copyright www.ecouja.com   112
Pilot Flame Light-Off

    Before the burner can be started, satisfactory light-off
    conditions for the pilot and main burners must be met. This is
    accomplished when the following conditions are satisfied:

     For the pilot igniter:
  1. MFT relay reset
  2. Pilot gas header pressure normal

     For natural gas:
  1. All of the above mentioned for the pilot igniter
  2. Natural gas pressure normal
  3. Natural gas control valve is in light-off position



                                         BY DR.HIMADRI BANERJI MD ECOURJA
                                         EX. RELIANCE AND TATA Copyright www.ecouja.com   113
Pilot Flame Light-Off


  For fuel oil:
  1. All of the above mentioned for the pilot igniter
  2. Oil gun is in place in the burner
  3. Oil pressure is normal
  4. Fuel oil atomizing interlocks are satisfied
  5. Fuel oil atomizing medium is provided to the burner
  6. Oil control valve is in light-off position

  Other Conditions:
  1. No MFT condition after purge
  2. All flame scanners report no flame
  3. All natural gas, or all fuel oil, block valves shown closed
  4. All air dampers are in light-off position



                                       BY DR.HIMADRI BANERJI MD ECOURJA
                                       EX. RELIANCE AND TATA Copyright www.ecouja.com   114
Pilot Flame Light-Off

    Failure to meet any of these conditions shall prevent the
    burner light-off operation.

    To light the pilot flame, the pilot header vent valve, and, for
    natural gas fuel, the natural gas vent valve shall be closed by
    the boiler control system. Then, sequentially, the igniter
    transformer is energized, the pilot gas block valves are open
    and a 10 second pilot ignition timer starts counting down.
    When ignition timer cycle is completed, the igniter
    transformer is de-energized and the pilot flame scanner is
    checked by the control system. If the pilot flame is present,
    the main flame light-off sequence continues.



                                      BY DR.HIMADRI BANERJI MD ECOURJA
                                      EX. RELIANCE AND TATA Copyright www.ecouja.com   115
Pilot Flame Light-Off

    If the pilot flame fails, the boiler control system initiates a pilot
    flame failure shutdown. Additional attempts of pilot light-off
    are permissible provided a successful pilot light-off is made
    within 10 minutes after the furnace purge.

    Note that if the pilot flame continues to fail after several
    attempts, the boiler should be inspected to determine the
    fault and the condition corrected.




                                         BY DR.HIMADRI BANERJI MD ECOURJA
                                         EX. RELIANCE AND TATA Copyright www.ecouja.com   116
Main Flame Light-Off


    Once the pilot flame is made, the boiler control system opens the
    header block valves for the selected fuel.
    A main flame light-off timer begins a 15 second countdown for
    natural gas, or 20 seconds for fuel oil, to establish and stabilize the
    main flame.
    At 5 seconds before time out, the boiler control system closes the
    pilot block valves and opens the pilot vent valve.
    The remaining 5 seconds are used to detect the main flame. For
    the typical dual flame scanner design, a main flame failure
    shutdown is initiated if both flame scanners return a “no flame”
    signal to the burner control system.
    This will generate a boiler trip, and another furnace purge will be
    required.
    Once the burner is lit, the system is in the NORMAL RUN
    CONDITION and combustion controls should be released to
    modulation control


                                          BY DR.HIMADRI BANERJI MD ECOURJA
                                          EX. RELIANCE AND TATA Copyright www.ecouja.com   117
Shutdown


  Shutdown
  Per NFPA 8501, section 6-2.4.5, “The normal shutdown cycle for the boiler
  shall accomplish the following in the order listed:
     (a) Shut off fuel supply to the main burner.
     (b) Interrupt spark and shut off fuel supply to igniters, if in operation.
     (c) For oil:
     1. Where used, open the recirculating valve.
     2. Shut off atomizing medium, if desired.
     (d) For gas, vent piping between safety shutoff valves to atmosphere.
     (e) Perform a post purge of the boiler furnace enclosure.
     (f) Shut down fan, if desired.”
  For a safety shutdown, a manual reset is also required.
  Normal Boiler Shutdown
     A normal shutdown is initiated by operating BOILER SHUTDOWN switch. This
     will initiate the shut down sequence listed above.



                                                   BY DR.HIMADRI BANERJI MD ECOURJA
                                                   EX. RELIANCE AND TATA Copyright www.ecouja.com   118
Boiler Master Fuel Trip


    Any of the following conditions shall cause a boiler trip to
    occur. This results in the shutdown of all fuel and requires
    another furnace purge cycle before any attempt at re-lighting.
  For fuel oil:
  1. Excessive steam pressure.
  2. Low water level.
  3. Low fuel pressure.
  4. Low oil temperature.
  5. Loss of combustion air supply.
  6. Loss of flame.
  7. Loss of control system power.
  8. Loss of atomizing medium, if used.




                                     BY DR.HIMADRI BANERJI MD ECOURJA
                                     EX. RELIANCE AND TATA Copyright www.ecouja.com   119
Boiler Master Fuel Trip

  For natural gas:

  1. Excessive steam pressure or water temperature.
  2. Low water level.
  3. High or low gas pressure.
  4. Loss of combustion air supply.
  5. Loss of flame.
  6. Loss of control system power.




                                    BY DR.HIMADRI BANERJI MD ECOURJA
                                    EX. RELIANCE AND TATA Copyright www.ecouja.com   120
Boiler Master Fuel Trip


 In the event of an MFT, the control system shall initiate the
 following:

 1. Execute a shut down as listed above.
 2. Illuminate the appropriate indicator lights and alarms.
 3. Return the system to the pre-purge state

  Boiler restart will be inhibited until all pre-purge requirements
 are satisfied.




                                       BY DR.HIMADRI BANERJI MD ECOURJA
                                       EX. RELIANCE AND TATA Copyright www.ecouja.com   121
Alarms

 The following is a list of recommended alarm conditions:

 1. Any boiler or burner trip signal
 2. High or low water level
 3. High furnace pressure
 4. Partial Loss of flame (For the typical two scanner system,
    one indicates “no flame”)
 5. Main fuel shutoff valves closed
 6. Loss of control system power
 7. Unsuccessful burner shutdown




                                     BY DR.HIMADRI BANERJI MD ECOURJA
                                     EX. RELIANCE AND TATA Copyright www.ecouja.com   122
Interface with the Combustion
Control System (CCS)

  The following list, at a minimum, of signals should be sent
  to the Combustion Control System:
  1. Controls to purge position
  2. Controls to light-off position
  3. Normal run condition: release controls to modulation
  4. Main natural gas block valve open: permissive to place gas
  control valve in automatic.
  5. Master fuel trip: run boiler load to zero and place combustion
  controls in manual.
  6. Oil recirculation signal
  Under the provisions of NFPA 8501, section 6-5.2.3, for a single
  burner boiler, the BMS and CCS may reside in the same
  processor. This option can reduce the integration complexity
  and increase the BMS to CCS interface reliability.

                                      BY DR.HIMADRI BANERJI MD ECOURJA
                                      EX. RELIANCE AND TATA Copyright www.ecouja.com   123
Operator Interface

    The above describes a traditional operator interface using
    discrete switches and indicator lights. The control designer is
    encouraged to incorporate a graphical user interface or
    similar options in order to enhance the ease of use and
    readability of the boiler control system operator interface




                                      Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                             MD EcoUrja, Ex Reliance and Tata www.ecourja.com
SEQUENTIAL START UP AUTOMATION
  DESIGN PRINCIPLES OF BURNER
      MANAGEMENT SYSTEM




                 Workshop on Start Up and Commissioning Dr. Himadri Banerji
                        MD EcoUrja, Ex Reliance and Tata www.ecourja.com
Design Principles of Sequential Start-Up…
Case Study in Burner Management System Design
    Introduction
    Burner Management System Objectives
    BMS Design Standards and Definitions
    BMS Logic
    BMS Strategies and Hardware
    ◦ Types of Burner Management Systems
    BMS Interface to SCADA Systems
    Summary




                                 Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                        MD EcoUrja, Ex Reliance and Tata www.ecourja.com
Introduction


Burner
Management
Systems..




..a starting point.

                      Workshop on Start Up and Commissioning Dr. Himadri Banerji
                             MD EcoUrja, Ex Reliance and Tata www.ecourja.com
Introduction

   What is a BMS?
    A Burner Management System is defined as the following:
    ◦ A Control System that is dedicated to boiler safety,
      operator assistance in the sequential safe starting and
      stopping of fuel preparation and burning equipment, and
      the prevention of mis-operation of and damage to fuel
      preparation and fuel burning equipment. 1

     1. From NFPA 8501 “Standard for Single Burner Boiler
       Operation”




                                    Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                           MD EcoUrja, Ex Reliance and Tata www.ecourja.com
Burner Management Objective

    Sequence burner through safe start-up

    Insure a complete pre-purge of boiler

    Supervise safety limits during operation

    Supervise the flame presence during operation

    Sequence a safe shutdown at end of cycle

    Integrate with combustion control system for proper fuel
    and air flows


                                    Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                           MD EcoUrja, Ex Reliance and Tata www.ecourja.com
BMS Design Standards

       Each Burner Management System should be designed in
       accordance with the below listed guidelines to control and
       monitor all sequences of the start-up and shutdown of the
       burner
        ◦ National Fire Protection Association (NFPA 8501 /8502
          or others)
        ◦ Industrial Risk Insurers (IRI)
        ◦ Factory Mutual loss prevention guidelines
   o   Each burner management system should be designed to
       accomplish a safety shutdown in the event of an unsafe
       condition. (FAIL SAFE)




                                       Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                              MD EcoUrja, Ex Reliance and Tata www.ecourja.com
BMS Design Standards

    U.S. National Fire Protection Association (NFPA)
    ◦ Governs safety system design on virtually all boilers
      (regardless of the process to be used to combust the
      fuel)
    ◦ Requires the separation of the Burner Management
      System from any other control system
    ◦ Requires the use of a hardwired backup tripping scheme
      for microprocessor based systems
    ◦ Requires that a single failure NOT prevent an
      appropriate shutdown
    ◦ Factory Mutual loss prevention guidelines.




                                  Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                         MD EcoUrja, Ex Reliance and Tata www.ecourja.com
NFPA 8501

  NFPA 8501 Standard for Single Burner Boiler
  Operation

   ◦ Single Burner Boilers with fuel input greater than 12.5
     mBTU/Hr (Approx. 250 BHP)

   ◦ Single Fuel or Combination of Fuels (Common being
     Natural Gas / No.2 Oil / No. 6 Oil)

   ◦ Simultaneous Firing




                                      Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                             MD EcoUrja, Ex Reliance and Tata www.ecourja.com
NFPA 8502

  NFPA 8502 Standard for Prevention of Furnace Explosions /
  Implosions in Multiple Burner Boilers

   ◦ Multiple Burner Boilers with fuel input greater than 12.5
     mBTU/Hr

   ◦ Single Fuel or Combination of Fuels including Pulverized Coal

   ◦ Emphasis on implosion protection (larger boilers with induced
     draft systems)




                                        Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                               MD EcoUrja, Ex Reliance and Tata www.ecourja.com
BMS Definitions

   Furnace Explosions
   ◦ “Ignition of accumulated combustible mixture within the
     confined space of a furnace or associated boiler passes,
     ducts, and fans that convey gases of combustion to the
     stack”1
   ◦ Magnitude and intensity of explosion depends on
     relative quantity of combustibles and the proportion of air
     at the time of ignition

   1. From NFPA 8502 “Prevention of Furnace Explosions /
     Implosions in Multiple Burner Boilers”




                                      Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                             MD EcoUrja, Ex Reliance and Tata www.ecourja.com
BMS Definitions

   Furnace Explosions can occur with any or a combination
   of the following:1
   ◦ Momentary loss of flame followed by delayed re-ignition
   ◦ Fuel leakage into an idle furnace ignited by source of
     ignition (such as a welding spark)
   ◦ Repeated Light-off attempts without proper purging
   ◦ Loss of Flame on one Burner while others are in operation
   ◦ Complete Furnace Flame-out followed by an attempt to light
     a burner

   1. From NFPA 8502 “Prevention of Furnace Explosions /
     Implosions in Multiple Burner Boilers”



                                   Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                          MD EcoUrja, Ex Reliance and Tata www.ecourja.com
BMS Definitions

     Furnace Implosions
     ◦ More common in large Utility Boilers
     ◦ Caused by any of the following:
        Malfunction of equipment regulating boiler gas flow
        resulting in furnace exposure to excessive induced
        draft fan head capability
        Rapid decay for furnace gas temperature and pressure
        due to furnace trip

     1. From NFPA 8502 “Prevention of Furnace Explosions /
       Implosions in Multiple Burner Boilers”




                                   Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                          MD EcoUrja, Ex Reliance and Tata www.ecourja.com
BMS Basic Definitions

     Common Terminology
     ◦ Supervised Manual
        Manual Burner Light-off with Interlocks

     ◦ Automatic Recycling (Single Burner Only)
        Automatic Burner Start and Stop based on preset
        operating range (ie.. Drum pressure)

     ◦ Automatic Non Recycling (Single Burner Only)
        Automatic Burner Start and Stop based on Manual
        command to start.




                                    Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                           MD EcoUrja, Ex Reliance and Tata www.ecourja.com
Types of Flame Scanners

     Infrared (IR) Detectors
     ◦ Single Burner Applications
     ◦ More Suitable with Oil Burning Flames
     Ultra-Violet (UV) Detectors
     ◦ Multiple Burner Applications
     ◦ More Suitable for Gas Burners and Combination Gas /
       Oil Burners
     Self Check Scanners
     ◦ Flame Signal is interrupted at set intervals to verify
       proper operation of scanner




                                     Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                            MD EcoUrja, Ex Reliance and Tata www.ecourja.com
Single Burner BMS Inputs
                                                                                                                                                   Low Low Drum Level (D)
                                                                                                                                                   High Steam Pressure (D)
                                                                                                                                                                               (D)
                                                                                                                                                     Purge Purge Air Flow
                                                                                                                                                     Minimum Air Flow (D)




                                                                                                                                           (D)
                                                                             Limits Made
                                                                                                                     Flame / No Flame
                                                                            Hold to Purge

                                                                            SCRL   RESET     MO DE




                                                        BURNER                FUEL SELECT                FD FAN
                                                  OFF            ON           GAS      OIL           HAND OFF AUTO



                                                                                                                                            (D)
                                                                                                                     Fuel Oil Temp Low
                                                                                                                     Fuel Oil Temp High (D)
                                                                                                                                            (D)
                                                                                                                     Fuel Oil Press Low
                                                                                                                     Fuel Oil Flow (A)
                                                                                                                                                      (D)
                                                                                                                     Atomizing Medium Flow > Min
                                                                                                                     Atomizing                                                                                                              AE        TE
                                       (D)                                                                           Medium
                 Common Alarm Output
                                                                                                                     Press Low (D)


 Remote Annunciator
    (By Others)                                                                                                                                                                                                                                                           FEEDWATER
                                                                                                                                                                                                                                      PSH


                                                                                                                                                                                                                                      PSL                                 STEAM
                                                                                                                                                                                                                                                           PT   PSH
                                                                                                                                                                                                                                      FT


                                                                                                                                                                                                       IGNITER
                                                                                                                                                                                                               Safety Shut Off
                                                                                                                                                                                                       GAS                                                                        LSLL
                                                                                                                                                                                                               & Vent Valves

                                                                                                                                                                                                                                                                                  LSLL


                                                          Fuel                                       Fuel
                                                           Gas                                        Gas                                                           FT   PSL         TSH   TSL                                   FS
                                                          Press                                      Press
                                                           Low                                       High
                                                                      (D)                               (D)                          PSL                     PSL
                                                                                                                                                                   OIL                           Safety Shut Off   Control
                                                                                                                                                                                                     Valves         Valve

                                                                                                                        ATOMIZING          Control Valve &
                                                                                                                        MEDIUM             Shut Off Valve                                                                                    (D) - Descrete Signal Used By Flame Safeguard System


                                             FT                   PSL                                                PSH




                                         GAS                                       Safety Shut Off &                                                                                                           Control
                                                                                     Vent Valves                                                                                                                Valve

                                                                                                                                                                                                       Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                                                                                                                                                                                              MD EcoUrja, Ex Reliance and Tata www.ecourja.com
BMS Logic

    Burner Management Systems can be broken down
    into “Interlock Groups”

    Typical BMS Interlock Groups:
    ◦ Boiler Purge
    ◦ Igniter Header Valve Management
    ◦ Main Fuel Header Valve Management
    ◦ MFT (Master Fuel Trip) Logic




                                Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                       MD EcoUrja, Ex Reliance and Tata www.ecourja.com
Purge Interlocks
                                                   BOILER TRIPPED




                                                        AND                  PURGE / RESET PB

                                                                                  START-UP
                                                                                   TIMER


                                                    START FD FAN


              PERMISSIVES SATISFIED:
               - MAIN FUEL VALVES CLOSED
               - NO FLAME PRESENT
               - FD FAN RUNNING                         AND
               - MINIMUM AIR FLOW SWITCH MADE
               - WATER LEVEL SATISFACTORY
               - ATOMIZING MEDIUM ON
               - FUEL SUPPLY PRESSURE NOT LOW


                                                ENERGIZE FUEL RELAY


                                                                      NOT              AND

                                                PURGE SIGNAL TO CCS




                        PURGE AIR                                       FD DAMPER IN
                       FLOW SWITCH                      AND              FULL OPEN
                          MADE                                            POSITION



                                                   PURGE TIMER SET



                                                  PURGE COMPLETE
                                                                        NO
                                                      YES


                                                REMOVE PURGE TO CCS               SYSTEM TRIP


                                                                   Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                                                          MD EcoUrja, Ex Reliance and Tata www.ecourja.com
Igniter Interlocks
                                           PURGE COMPLETE




            AIR DAMPER IN LOW FIRE                                 FUEL VALVE IN LOW FIRE
                                                  AND
                   POSITION                                              POSITION



                                                                  ENERGIZE IGNITER AND
                                                                 IGNITER HEADER VALVES



                                           10 SECOND DELAY



                                           10 SEC PILOT TRIAL
                                              FOR IGNITION




                                           TIMER COMPLETE
                   FLAME
                  PROVEN             NOT



                                                  AND



                                                                            SYSTEM TRIP
                                           PERMIT FOR MAIN
                                               FLAME

                                                           Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                                                  MD EcoUrja, Ex Reliance and Tata www.ecourja.com
Main Flame Interlocks

                                   IGNITER TIMER
                                     COMPLETE




                   FLAME
                                       AND
                  PROVEN
                                                             ENERGIZE MAIN
                                                              FUEL VALVES

                                 10 SEC MAIN FLAME
                                       TRIAL




                                 TIMER COMPLETE

                           NOT



                                       AND



                                                      DE-ENERGIZE
                                                        IGNITION
                                                      COMPONENTS



                                   RELEASE TO
                                 MODULATE TO CCS                 SYSTEM TRIP




                                                     Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                                            MD EcoUrja, Ex Reliance and Tata www.ecourja.com
Single Burner Main Fuel Trip
       FOR OIL:                                           FOR GAS:
       - LOWFUEL PRESSURE                                  - LOWFUEL GAS PRESSURE
       - LOWTEM   PERATURE (HEATED OILS)                   - HIGH GAS PRESSURE
       - LOSS OF COM BUSTION AIR                           - LOSS OF COM BUSTION AIR
       - LOSS OF FLAM OR FAIL TO ESTABLISH
                      E                                    - LOSS OF FLAM OR FAIL TO ESTABLISH
                                                                         E
       - LOSS OF CONTROL SYSTEMENERGY                      - LOSS OF CONTROL SYSTEMENERGY
       - POWER FAILURE                                     - POWER FAILURE
       - LOWWATER LEVEL (AUXLEVEL CONTACT)                 - LOWWATER LEVEL (AUXLEVEL CONTACT)
       - LOSS OF ATOM IZING MEDIUM                         - EXCESSIVE STEAMDRUMPRESSURE
       - EXCESSIVE STEAMDRUMPRESSURE
       - HIGH OIL TEMPERATURE (HEATED OILS)
                                                                                  OR

                             OR




                                                   TRIP BOILER




         TRIP IGNITER,            TRIP MAIN FUEL             FUEL CONTROL
       IGNITER VALVES,            VALVES, OPEN                 VALVE TO
                                                                                       TRIP MFT RELAY
         OPEN IGNITER              VENT VALVE                   CLOSED
             VENT                   (GAS ONLY)                 POSITION


                                                                 Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                                                        MD EcoUrja, Ex Reliance and Tata www.ecourja.com
BMS System Types

   Early Burner Management Systems
   ◦ Hardwired Systems
   ◦ Solid State Systems

   Microprocessor Based Systems
   ◦ Honeywell 7800 series with fixed Logic.

   PLC Based Systems
   ◦ Programmable Logic Controller (PLC) Based
   ◦ Powerful, versatile, expandable, more reliable.




                                     Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                            MD EcoUrja, Ex Reliance and Tata www.ecourja.com
Early Burner Management Systems

   Hardwired Systems
   ◦ Relay and Timer Driven. Found on older installations
   ◦ Typical of Late 50’s, 60’s

   Solid State Systems
   ◦ Solid State Processors and Relays
   ◦ Found on Systems provided in the 70’s and 80’s
   ◦ Proprietary Hardware (ie.. Forney and Peabody)
   ◦ Spare Parts are extremely hard to find.




                                   Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                          MD EcoUrja, Ex Reliance and Tata www.ecourja.com
MicroProcessor Based Systems

   Microprocessor Based System providing:
   ◦ Burner Sequencing
   ◦ Ignition
   ◦ Flame Monitoring

   Fixed Program with Limited Configuration Changes

   Components Selected Based on Requirements
   ◦ Programmers, Flame Amplifiers, Message Displays




                                   Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                          MD EcoUrja, Ex Reliance and Tata www.ecourja.com
Typical BMS Layout




                          AMPLIFIER
                      EP PROGRAMMER




                AUTOMATIC PRIMARY SAFETY CONTROL




                                                                                          FIELD WIRING
                                            FIELD WIRING



                          FLAME
                         SCANNER




                                                       Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                                              MD EcoUrja, Ex Reliance and Tata www.ecourja.com
Micro Processor Capabilities

    Simple, Cost Effective

    Features
    ◦ Selectable Flame Amplifiers / Scanners
    ◦ Remote Display
    ◦ Remote Data Communications via Modbus Port
    ◦ Modernization kits are available to integrate with older
      systems
    ◦ Spare Parts Normally Readily Available




                                      Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                             MD EcoUrja, Ex Reliance and Tata www.ecourja.com
When These Systems are Used

   “Simple” Boiler Installations
   ◦ Packaged Fire tube / Water tube Boilers (Steam / Hot Water)
   ◦ Single Burner
   ◦ One Fuel at a Time
   ◦ No Flue Gas Re-Circulation
   ◦ Upgrades from Previous MicroProcessor Based Systems




                                    Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                           MD EcoUrja, Ex Reliance and Tata www.ecourja.com
PLC Based Burner Management Systems

   PLC Based Features
   ◦ NFPA 8501, 8502
   ◦ Watchdog timer
   ◦ UL 508 Certification

   Redundant Scanners

   Logic+ Message Center
   ◦ Shows program status
   ◦ Displays alarms
   ◦ Prompts operator



                            Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                   MD EcoUrja, Ex Reliance and Tata www.ecourja.com
PLC System Basic Design Features

    Each PLC based burner management system should
    incorporate a number of design techniques which help
    detect and act upon unsafe failure modes which can
    occur in any microprocessor based system. These
    design features include the following:

    ◦ Critical Input Checking
    ◦ Critical output channel monitoring
    ◦ Electro-mechanical Master Fuel Trip (MFT) Relay
    ◦ Redundant Watchdog Timers
    ◦ Low Water Cut-out Monitoring During Blow Down


                                     Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                            MD EcoUrja, Ex Reliance and Tata www.ecourja.com
PLC Based System Capabilities

    Provision for Multiple Fuel Firing
    ◦ Capped gas input during curtailment
    ◦ Changeover from gas to oil at any load
    ◦ Simultaneous firing of waste and fossil fuels

    Redundant Scanners, change scanner with fuel

    Single or Multiple Burner Applications

    Integration of BMS with SCADA




                                     Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                            MD EcoUrja, Ex Reliance and Tata www.ecourja.com
PLC Based Operator Interfaces

   Features
   ◦ Clear Written Messages to indicate status, required
     operator interaction, trip/alarm indication
   ◦ High Visibility through two lines of display
   ◦ Messages reduce time consuming troubleshooting
   ◦ Prioritizes Messages
       First Out Alarms
       Warning / Alarm Messages
       Status Messages / Prompts Operator




                                    Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                           MD EcoUrja, Ex Reliance and Tata www.ecourja.com
PLC System Layout

                                                                         Door Mounted Lights / Pushbuttons

          Logic+ Message
                                                                            SWITCH      SILENCE    LIGHT




              Display



                           PLC CPU         I/O   I/O   I/O   I/O

      COMBUSTION
    CONTROL SYSTEM

                                                                            FLAME AMPLIFIER
                                                                               (SINGLE /
                                                                              REDUNDANT)

                           I/O EXPANSION   I/O




                                                                                     FIELD DEVICES




                                                       Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                                              MD EcoUrja, Ex Reliance and Tata www.ecourja.com
Benefits of PLC Based Systems

    Flexibility / Reliability
    ◦ Programming Software allows changes to system

    Choice of PLCs
    ◦ GE / Modicon / Allen Bradley / Koyo

    Choice of Flame Scanners
    ◦ PPC / Fireye / Honeywell / Iris / Coen

    Application Specific

    Quantity of Burners / Fuels is not restricted


                                      Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                             MD EcoUrja, Ex Reliance and Tata www.ecourja.com
When to Use PLC Based Systems
    “Complex” Boiler Installations
    ◦ Larger Packaged Units / Field Erected Units

    ◦ Multiple Burners

    ◦ Multiple Fuels, On-line Fuel Changeovers

    ◦ Flue Gas Re-Circulation

    ◦ Replace Existing Relay Logic Systems

    ◦ Requirement to maintain consistent control platform (spare
      parts, etc..)

                                    Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                           MD EcoUrja, Ex Reliance and Tata www.ecourja.com
BMS SCADA Interface

   BMS Systems can be integrated into a SCADA System

   ◦ Allows Remote Monitoring of Flame Status

   ◦ Allows Remote Control of BMS

   ◦ Events (ie.. Burner trip) can be routed to Historical Portion
     of SCADA for fault evaluation

   ◦ Burner Operation can be trended over time




                                      Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                             MD EcoUrja, Ex Reliance and Tata www.ecourja.com
BMS SCADA Interface

   Interface Methods:
                                                                             SCADA PC




                      MODBUS
                   COMMUNICATION
                     PROTOCOL



                                                                                   MODBUS
                                                                                COMMUNICATION
                     Communication
                                                                                  PROTOCOL
                          Interface
                      (If Necessary)




                PLC CPU        I/O   I/O   I/O   I/O




                    BMS LOGIC+ SYSTEM
                                                                                 FIREYE E110 SYSTEM




                                                       Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                                              MD EcoUrja, Ex Reliance and Tata www.ecourja.com
BMS SCADA Interface




                      Workshop on Start Up and Commissioning Dr. Himadri Banerji
                             MD EcoUrja, Ex Reliance and Tata www.ecourja.com
Summary


Benefits Associated with Sequential Start Up Automation
and Burner Management Systems



    ◦ Help Improve plant safety
    ◦ Help qualify for reduced insurance cost
    ◦ Reduce Startup and Down Time with comprehensive
      alarming and diagnostics




                                   Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                          MD EcoUrja, Ex Reliance and Tata www.ecourja.com
Summary

 Review of Topics Discussed

   ◦ Sequential Start Up Automation,

   ◦ Objectives of Burner Management Systems

   ◦ BMS Design Considerations

   ◦ Basic BMS Logic

   ◦ Types of Burner Management Systems

   ◦ How BMS Systems can be integrated with Plant Wide
     SCADA Systems


                                   Workshop on Start Up and Commissioning Dr. Himadri Banerji
                                          MD EcoUrja, Ex Reliance and Tata www.ecourja.com
SAFETY ISSUES



         THE WORK PERMIT SYSTEM

                                            (Reference Document : <<AIGA 011/04 >>)



Presented by Dr Himadri Banerji EcoUrja www.ecourja.com
Summary



                                               Acknowledgement

      This document is adopted from the European Industrial
      Gases Association document TP 10/04 – The Work Permit
      System, and acknowledgement and thanks are hereby given
      to EIGA for permission granted for the use of their document




Presented by Dr Himadri Banerji EcoUrja www/ecourja.com
The Work Permit System. What is it?
  A work permit system consists primarily of a standard procedure
  designed to ensure that potentially hazardous routine and non routine
  work on industrial installations can be carried out safely. The procedure
  should define the need for the following essential steps:
      Details of the necessary preparatory work
      Clear definition of responsibilities
      Appropriate training of the work force
      Provision of adequate safety equipment
      A formal work permit with or without attached specific checklists.

  This work permit:
      specifies the work to be accomplished and authorizes it to be
      started under the strict observance of consigned work and safety
      procedures
      After information and agreement of all other concerned parties
      (process, safety, customers, suppliers,…)
The Work Permit System :
When?

    For all non-routine works,

    For hazardous routine works not covered by procedures,

    When work is performed:
       by your employees
       and/or third parties
The Work Permit System (1/2):
For what kind of work?
   A work permit is required in case of:
      Potential oxygen deficiency or enrichment
      Potential flammable/explosive atmosphere
      Potential high temperature/pressure
      Potential hazardous chemicals, e.g.: toxic substances
      Confined space entry, e.g.: tanks, cold box, pit, normally
      closed vessels
      Bypassing or removing/altering safety devices or equipment
      Elevated works
      Introduction of ignited sources where not permanently
      allowed (fire permit), e.g.: open flame, welding, grinding,
      Electrical troubleshooting or repair on live circuits
      Maintenance or repairs in areas or to equipment or lines,
      containing or supposed to contain hazardous materials or
      conditions,
The Work Permit System (2/2):
For what kind of work?
   Or also in case of:
         Manual or powered excavations
         Use of mobile cranes
         Insulation or catalysts handling
         Use of adapters
         Product conversion of stationary or mobile or portable
         vessels and containers
         Temporary or permanent changes, alterations, modification of
         equipment or processes,
         Exposure to traffic,
         Exposure to moving/rotating machinery
         In proximity of vents, liquid of gas
         On process lines with gas release
         Etc..
The Work Permit System : Why?

1. Because:
     In charge of the work, you don’t know everything
             about the site and the process around
             about the work

      Safety measures have to be prepared
      You cannot start the work without the OK of the production
      personnel or the customer or the supplier
      The production needs your OK in order to re-start the plant
      after your work is achieved

2. To obtain a safe as well as a quick and cost effective work
The Work Permit System : Why?

   In order to define the scope of work for everyone
   concerned/involved by and during the work, the Work Permit
   must be prepared with:

   The person responsible for the work
   The person(s) in charge of the production, the customer or
   supplier, who will release the process before the work starts
   The other work bodies
   The person in charge of HSE measures
The Work Permit System : How?

  Before issuing the Work Permit, you must:

      Describe the work to be done
      List all the specifications and drawings which are required
      Issue detailed planning with all involved entities
      Determine the logging and tagging procedures

  Fill-in together the work permit and sign,

  The start of the work must be authorized by production and/or
  user,

  The re-start of the process must take place after the work is
  finished.
The Work Permit System :
Review of Flowsheets, Drawings and
Specification

   Purpose of the review is to ensure all key persons involved in job
planning have a thorough understanding of the job. It should
include:
      Process fluids and materials involved,
      Degree of isolation,
      Effect of other processes,
      Power supply isolation,
      Specialist advice,
      Location of underground services and pipes,
      Location of elevated power cables,
      Location of elevated pipelines and walkways,
      Purging and lock-out requirements,
      Pressure, Temperature,
      Valve identification,
      Equipment specification,
      Operating and maintenance instructions,
      Materials of construction and compatibilities
The Work Permit System :
Work site inspection
          Anyone involved and signing the Safe Work Permit must
 visit the work place in order:

  •To inspect the work area
     Neighbouring activities, site rules, overhead, underground,
    access, natural hazards (flood, rain, snow…), etc,..

  •To identify potential hazards
      Flammable, oxygen, toxic substances, confined spaces,
    electricity, pressure, temperature, moving objects, traffic,
    falls/trips/slips, etc,..
The Work Permit System :
Development of Work Procedures
Preparation of a detailed work procedure is essential to ensure the work will
proceed safely in a planned and logical manner:

 Following requirements to be considered:
      Reference drawings, Timing of various operations, Details of any special
    equipment, Needs to inform local authorities, safety precautions and
    equipment, Emergency procedures, etc,..

 The procedure should include:
      Logging and tagging procedures: Electricity, process fluids Instrumentation,
    utilities (water, air, oil,…)

      Depressurising, Draining, Venting, Purging, Flushing, Isolating, Atmosphere
    checking, Disassembly of equipment, Method of repair, Reassembly and
    installation, Quality control, Pressure and leak testing, Reinstatement of
    equipment, Hand-back procedure, etc..
The Work Permit System : Example form
  Appendix 1         EIGA/IGC                              WORK PERMIT                                                             n° ……..

  Any attached document or log sheet ?        YES  NO HOW MANY ………..
  List of attached documents ……………….……………………….…………..……………...………………………………………………..

  1. WORK ACTIVITY

  Plant / Unit :………………...……………….…………………………………………………………………………………………………………..………...…
  Description of work to be done………………....……..….………….…………….……………………………………………………………………….......…
  Permit valid from :…………………………………………………………                Hours/date      To :…………………………………………………………………….
                                                                                                     Hours/date
  Have all relevant departments/personnel been consulted ?       YES  NOT APPLICABLE


  2. POTENTIAL HAZARDS & HAZARDOUS JOBS
                                                            YES   NO                                                                        YES NO
  . Jobs performed by contractors or temporary workers                 . Maintenance or repairs in areas, or to equipment or lines,
  . Potential oxygen deficiency or enrichment                            containing or supposed to contain hazardous materials or conditions
  . Potential flammable / explosive atmosphere                         . Manual or powered excavations
  . Potential high temperature / pressure                              . Use of mobile cranes
  . Potential exposure to hazardous chemicals (toxic, reactive,        . Insulation or catalyst handling
    acid, caustic….)                                                   . Use of adapters
  . Confined space entry                                               . Product conversion of stationary or mobile or portable vessels
  . Bypassing or removing/altering safety devices and equipment           and containers
  . Elevated work                                                      . Temporary or permanent changes, alterations, modifications of
  . Introduction of ignition sources where not permanently               equipment or processes
    allowed (fire permit)                                              . Exposure to traffic (road, mail)
  . Electrical troubleshooting or repair on live circuits              . Exposure to moving / rotating machinery

  Others (state) ……………………..……...…………………………………………………………………………

  3. SAFETY PRECAUTIONS
                                     YES NO                                                    YES NO                                       YES NO
  . Draining                                               . Remove hazardous materials                      . Standby man
  . Depressurising                                         . Fresh air ventilation                           . Elevated work
  . Physical Isolation                                     . Atmosphere analysis :                           . Contractors trained
  . Electrical Isolation                                                . Oxygen                             . Eliminate ignition sources
Plant Commissioning and Start-Up Procedures Workshop
Plant Commissioning and Start-Up Procedures Workshop
Plant Commissioning and Start-Up Procedures Workshop
Plant Commissioning and Start-Up Procedures Workshop
Plant Commissioning and Start-Up Procedures Workshop

More Related Content

What's hot

Mechanical Completions
Mechanical CompletionsMechanical Completions
Mechanical CompletionsAndy Lang
 
How to read a P&ID for Risk Analysis
How to read a P&ID for Risk AnalysisHow to read a P&ID for Risk Analysis
How to read a P&ID for Risk Analysisrisk_inspired
 
Process engineering of chemical plant
Process engineering of chemical plantProcess engineering of chemical plant
Process engineering of chemical plantPankaj Khandelwal
 
Process Plant Start Up and Commissioning
Process Plant Start Up and CommissioningProcess Plant Start Up and Commissioning
Process Plant Start Up and CommissioningpetroEDGE
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completionRonie Chu
 
Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trialNagesh H
 
PetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync
 
Process design for chemical engineers
Process design for chemical engineersProcess design for chemical engineers
Process design for chemical engineersAmanda Ribeiro
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installationslaithu2908
 
SPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT SlidesSPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT Slidesidell bryan
 
Commissioning of Offshore Installations
Commissioning of Offshore InstallationsCommissioning of Offshore Installations
Commissioning of Offshore Installationswan saiful arini
 
Interested party matrix - ISO 14001:2015
Interested party matrix - ISO 14001:2015Interested party matrix - ISO 14001:2015
Interested party matrix - ISO 14001:2015James Charles, PE, CPG
 
Process safety ADNOC STANDARD
Process safety ADNOC STANDARDProcess safety ADNOC STANDARD
Process safety ADNOC STANDARDPersonal Secret
 
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure  What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure Varun Patel
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docxSharad Naik
 

What's hot (20)

Mechanical Completions
Mechanical CompletionsMechanical Completions
Mechanical Completions
 
How to read a P&ID for Risk Analysis
How to read a P&ID for Risk AnalysisHow to read a P&ID for Risk Analysis
How to read a P&ID for Risk Analysis
 
Process Plant design fundementals
Process Plant design fundementalsProcess Plant design fundementals
Process Plant design fundementals
 
management of change
management of changemanagement of change
management of change
 
Process engineering of chemical plant
Process engineering of chemical plantProcess engineering of chemical plant
Process engineering of chemical plant
 
Process Plant Start Up and Commissioning
Process Plant Start Up and CommissioningProcess Plant Start Up and Commissioning
Process Plant Start Up and Commissioning
 
Ghulam Farid cv
Ghulam Farid cvGhulam Farid cv
Ghulam Farid cv
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completion
 
Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trial
 
Boiler explosion at exxon mobil singapore
Boiler explosion at exxon mobil singaporeBoiler explosion at exxon mobil singapore
Boiler explosion at exxon mobil singapore
 
PetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-Up
 
Process design for chemical engineers
Process design for chemical engineersProcess design for chemical engineers
Process design for chemical engineers
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installations
 
Process safety managment
Process safety managmentProcess safety managment
Process safety managment
 
SPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT SlidesSPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT Slides
 
Commissioning of Offshore Installations
Commissioning of Offshore InstallationsCommissioning of Offshore Installations
Commissioning of Offshore Installations
 
Interested party matrix - ISO 14001:2015
Interested party matrix - ISO 14001:2015Interested party matrix - ISO 14001:2015
Interested party matrix - ISO 14001:2015
 
Process safety ADNOC STANDARD
Process safety ADNOC STANDARDProcess safety ADNOC STANDARD
Process safety ADNOC STANDARD
 
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure  What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx
 

Viewers also liked

The commissioning process
The commissioning processThe commissioning process
The commissioning processtreshammedia
 
Boiler commissioning procedure
Boiler commissioning procedureBoiler commissioning procedure
Boiler commissioning procedureABVSAI
 
Cold hot working_annealing
Cold hot working_annealingCold hot working_annealing
Cold hot working_annealingPradeep I
 
Commissioning Plan Robert Thelander, Svenska kraftnät
Commissioning Plan Robert Thelander, Svenska kraftnät Commissioning Plan Robert Thelander, Svenska kraftnät
Commissioning Plan Robert Thelander, Svenska kraftnät Fingrid Oyj
 
Hp 2011 Rph Refining Hydrocarbon Technologies Profiles
Hp 2011 Rph Refining Hydrocarbon Technologies ProfilesHp 2011 Rph Refining Hydrocarbon Technologies Profiles
Hp 2011 Rph Refining Hydrocarbon Technologies Profilesabakshi2011
 
Power Point On Hydrocarbon
Power Point On HydrocarbonPower Point On Hydrocarbon
Power Point On HydrocarbonSamiran Ghosh
 
Hydrocarbon preeti bhatt
Hydrocarbon preeti bhattHydrocarbon preeti bhatt
Hydrocarbon preeti bhattkapde1970
 
Petrolium and gas processing
Petrolium and gas processingPetrolium and gas processing
Petrolium and gas processingwaseemakhtar120
 
Oil And Gas Processing
Oil And Gas ProcessingOil And Gas Processing
Oil And Gas Processingmubarak2009
 
E nodeb commissioning guide(v100r005c00 04)(pdf)-en
E nodeb commissioning guide(v100r005c00 04)(pdf)-enE nodeb commissioning guide(v100r005c00 04)(pdf)-en
E nodeb commissioning guide(v100r005c00 04)(pdf)-enVugar Ali
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process
 

Viewers also liked (14)

The commissioning process
The commissioning processThe commissioning process
The commissioning process
 
Boiler commissioning procedure
Boiler commissioning procedureBoiler commissioning procedure
Boiler commissioning procedure
 
Cold hot working_annealing
Cold hot working_annealingCold hot working_annealing
Cold hot working_annealing
 
Commissioning Plan Robert Thelander, Svenska kraftnät
Commissioning Plan Robert Thelander, Svenska kraftnät Commissioning Plan Robert Thelander, Svenska kraftnät
Commissioning Plan Robert Thelander, Svenska kraftnät
 
Hydrocarbons
HydrocarbonsHydrocarbons
Hydrocarbons
 
Hp 2011 Rph Refining Hydrocarbon Technologies Profiles
Hp 2011 Rph Refining Hydrocarbon Technologies ProfilesHp 2011 Rph Refining Hydrocarbon Technologies Profiles
Hp 2011 Rph Refining Hydrocarbon Technologies Profiles
 
Power Point On Hydrocarbon
Power Point On HydrocarbonPower Point On Hydrocarbon
Power Point On Hydrocarbon
 
Hydrocarbon preeti bhatt
Hydrocarbon preeti bhattHydrocarbon preeti bhatt
Hydrocarbon preeti bhatt
 
Hydrocarbons
HydrocarbonsHydrocarbons
Hydrocarbons
 
Petrolium and gas processing
Petrolium and gas processingPetrolium and gas processing
Petrolium and gas processing
 
Oil And Gas Processing
Oil And Gas ProcessingOil And Gas Processing
Oil And Gas Processing
 
The Future of Leadership Development
The Future of Leadership DevelopmentThe Future of Leadership Development
The Future of Leadership Development
 
E nodeb commissioning guide(v100r005c00 04)(pdf)-en
E nodeb commissioning guide(v100r005c00 04)(pdf)-enE nodeb commissioning guide(v100r005c00 04)(pdf)-en
E nodeb commissioning guide(v100r005c00 04)(pdf)-en
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement Guide
 

Similar to Plant Commissioning and Start-Up Procedures Workshop

General guidelines for building commissioning ppt
General guidelines  for building  commissioning pptGeneral guidelines  for building  commissioning ppt
General guidelines for building commissioning pptDayasagar Govidaraju
 
General guidelines for building commissioning ppt.pptx
General guidelines  for building  commissioning ppt.pptxGeneral guidelines  for building  commissioning ppt.pptx
General guidelines for building commissioning ppt.pptxDayasagar Govidaraju
 
E&I QC INSPECTOR RESUM AND documents.pdf
E&I QC INSPECTOR RESUM AND  documents.pdfE&I QC INSPECTOR RESUM AND  documents.pdf
E&I QC INSPECTOR RESUM AND documents.pdfIrfan786pak
 
ICH guidelines for validation Of Equipments by Nikita Sahu[1].pptx
ICH guidelines for validation Of Equipments by Nikita Sahu[1].pptxICH guidelines for validation Of Equipments by Nikita Sahu[1].pptx
ICH guidelines for validation Of Equipments by Nikita Sahu[1].pptxNikitaSahu39
 
EQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptxEQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptxRamkumar906213
 
EQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptxEQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptxRamkumar906213
 
Equipment Qualification
Equipment QualificationEquipment Qualification
Equipment QualificationCMiller669
 
Module_4_GCLP_LABORATORY_EQUIPMENT.ppt
Module_4_GCLP_LABORATORY_EQUIPMENT.pptModule_4_GCLP_LABORATORY_EQUIPMENT.ppt
Module_4_GCLP_LABORATORY_EQUIPMENT.pptssuserbf5fe71
 
Bioprocess Validation
Bioprocess Validation Bioprocess Validation
Bioprocess Validation Pramod Pal
 
Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...
Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...
Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...Kevin Perry
 
Facility & Equipment Quality System Outline
Facility & Equipment Quality System OutlineFacility & Equipment Quality System Outline
Facility & Equipment Quality System OutlineJoseph Busfield
 
Validation of equipments
Validation of equipmentsValidation of equipments
Validation of equipmentssuhasini
 
Seminar- Process Safety Management_.pptx
Seminar- Process Safety Management_.pptxSeminar- Process Safety Management_.pptx
Seminar- Process Safety Management_.pptxMoonJ3
 
Cleanroom Qualification
Cleanroom QualificationCleanroom Qualification
Cleanroom QualificationAnwar Munjewar
 

Similar to Plant Commissioning and Start-Up Procedures Workshop (20)

General guidelines for building commissioning ppt
General guidelines  for building  commissioning pptGeneral guidelines  for building  commissioning ppt
General guidelines for building commissioning ppt
 
General guidelines for building commissioning ppt.pptx
General guidelines  for building  commissioning ppt.pptxGeneral guidelines  for building  commissioning ppt.pptx
General guidelines for building commissioning ppt.pptx
 
Validation
ValidationValidation
Validation
 
E&I QC INSPECTOR RESUM AND documents.pdf
E&I QC INSPECTOR RESUM AND  documents.pdfE&I QC INSPECTOR RESUM AND  documents.pdf
E&I QC INSPECTOR RESUM AND documents.pdf
 
Commissioning Planning Meeting
Commissioning Planning MeetingCommissioning Planning Meeting
Commissioning Planning Meeting
 
ICH guidelines for validation Of Equipments by Nikita Sahu[1].pptx
ICH guidelines for validation Of Equipments by Nikita Sahu[1].pptxICH guidelines for validation Of Equipments by Nikita Sahu[1].pptx
ICH guidelines for validation Of Equipments by Nikita Sahu[1].pptx
 
Presentation1
Presentation1Presentation1
Presentation1
 
EQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptxEQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptx
 
EQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptxEQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptx
 
Equipment Qualification
Equipment QualificationEquipment Qualification
Equipment Qualification
 
Dr. ajmal nasir
Dr. ajmal nasirDr. ajmal nasir
Dr. ajmal nasir
 
Zaheer-CV- 2015
Zaheer-CV- 2015Zaheer-CV- 2015
Zaheer-CV- 2015
 
Module_4_GCLP_LABORATORY_EQUIPMENT.ppt
Module_4_GCLP_LABORATORY_EQUIPMENT.pptModule_4_GCLP_LABORATORY_EQUIPMENT.ppt
Module_4_GCLP_LABORATORY_EQUIPMENT.ppt
 
Bioprocess Validation
Bioprocess Validation Bioprocess Validation
Bioprocess Validation
 
Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...
Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...
Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...
 
4 validation jntu pharmacy
4 validation jntu pharmacy4 validation jntu pharmacy
4 validation jntu pharmacy
 
Facility & Equipment Quality System Outline
Facility & Equipment Quality System OutlineFacility & Equipment Quality System Outline
Facility & Equipment Quality System Outline
 
Validation of equipments
Validation of equipmentsValidation of equipments
Validation of equipments
 
Seminar- Process Safety Management_.pptx
Seminar- Process Safety Management_.pptxSeminar- Process Safety Management_.pptx
Seminar- Process Safety Management_.pptx
 
Cleanroom Qualification
Cleanroom QualificationCleanroom Qualification
Cleanroom Qualification
 

More from HIMADRI BANERJI

Workshop on Plant Commissioning and Seamless Startup final.pdf
Workshop on Plant Commissioning and Seamless Startup final.pdfWorkshop on Plant Commissioning and Seamless Startup final.pdf
Workshop on Plant Commissioning and Seamless Startup final.pdfHIMADRI BANERJI
 
Brochure on Two Day Workshop on Plant Commissioning and Seamless Start Up By ...
Brochure on Two Day Workshop on Plant Commissioning and Seamless Start Up By ...Brochure on Two Day Workshop on Plant Commissioning and Seamless Start Up By ...
Brochure on Two Day Workshop on Plant Commissioning and Seamless Start Up By ...HIMADRI BANERJI
 
Gas Turbines Failures Applications & Root Cause Analysis.pptx
Gas Turbines Failures Applications & Root Cause Analysis.pptxGas Turbines Failures Applications & Root Cause Analysis.pptx
Gas Turbines Failures Applications & Root Cause Analysis.pptxHIMADRI BANERJI
 
Gas Turbines O&M-Trainer Rev 01.pdf
Gas Turbines O&M-Trainer Rev 01.pdfGas Turbines O&M-Trainer Rev 01.pdf
Gas Turbines O&M-Trainer Rev 01.pdfHIMADRI BANERJI
 
Making Artificial Intelligence Work in Managing Change
Making Artificial Intelligence Work in Managing ChangeMaking Artificial Intelligence Work in Managing Change
Making Artificial Intelligence Work in Managing ChangeHIMADRI BANERJI
 
Case Studies IN Machine Learning
Case Studies IN Machine Learning Case Studies IN Machine Learning
Case Studies IN Machine Learning HIMADRI BANERJI
 
Program Link to Workshop AI.pdf
Program Link to Workshop AI.pdfProgram Link to Workshop AI.pdf
Program Link to Workshop AI.pdfHIMADRI BANERJI
 
Brochure for 2022 Webinar Dr.Himadri AI.pdf
Brochure for 2022 Webinar Dr.Himadri AI.pdfBrochure for 2022 Webinar Dr.Himadri AI.pdf
Brochure for 2022 Webinar Dr.Himadri AI.pdfHIMADRI BANERJI
 
Risk management in nuclear projects and strategy of small reactors [compatibi...
Risk management in nuclear projects and strategy of small reactors [compatibi...Risk management in nuclear projects and strategy of small reactors [compatibi...
Risk management in nuclear projects and strategy of small reactors [compatibi...HIMADRI BANERJI
 
Lng project risk and appraisal 2012 final 03092012
Lng project risk and appraisal 2012 final 03092012Lng project risk and appraisal 2012 final 03092012
Lng project risk and appraisal 2012 final 03092012HIMADRI BANERJI
 
Risk management FSRU himadri banerji
Risk management FSRU himadri banerjiRisk management FSRU himadri banerji
Risk management FSRU himadri banerjiHIMADRI BANERJI
 
Risk management during start up and commissioning of super critical once thro...
Risk management during start up and commissioning of super critical once thro...Risk management during start up and commissioning of super critical once thro...
Risk management during start up and commissioning of super critical once thro...HIMADRI BANERJI
 
FSRU RISK MANAGEMENT AND CONTROL
FSRU RISK MANAGEMENT AND CONTROLFSRU RISK MANAGEMENT AND CONTROL
FSRU RISK MANAGEMENT AND CONTROLHIMADRI BANERJI
 
Managing Smart Grids, Power System Networks with Analytics
Managing Smart Grids, Power System Networks with Analytics Managing Smart Grids, Power System Networks with Analytics
Managing Smart Grids, Power System Networks with Analytics HIMADRI BANERJI
 
Liquefied Natural Gas project risk and appraisal
Liquefied Natural Gas project risk and appraisal Liquefied Natural Gas project risk and appraisal
Liquefied Natural Gas project risk and appraisal HIMADRI BANERJI
 
Challenges in building the 21st century energy infrastructure
Challenges in building the 21st century energy infrastructureChallenges in building the 21st century energy infrastructure
Challenges in building the 21st century energy infrastructureHIMADRI BANERJI
 
Thermal coal upgradation and conversion in india ibc asia, jakarta april 25, ...
Thermal coal upgradation and conversion in india ibc asia, jakarta april 25, ...Thermal coal upgradation and conversion in india ibc asia, jakarta april 25, ...
Thermal coal upgradation and conversion in india ibc asia, jakarta april 25, ...HIMADRI BANERJI
 
Clean Coal Technology:Indian Perspective by Himadri Banerji
Clean Coal Technology:Indian Perspective by Himadri Banerji Clean Coal Technology:Indian Perspective by Himadri Banerji
Clean Coal Technology:Indian Perspective by Himadri Banerji HIMADRI BANERJI
 
Permananece of Nuclear Power: Strategies for Managing Safety Risks Post Fukus...
Permananece of Nuclear Power: Strategies for Managing Safety Risks Post Fukus...Permananece of Nuclear Power: Strategies for Managing Safety Risks Post Fukus...
Permananece of Nuclear Power: Strategies for Managing Safety Risks Post Fukus...HIMADRI BANERJI
 
Start Up and Commissioning of Supercritical Power Stations: Risk Management P...
Start Up and Commissioning of Supercritical Power Stations: Risk Management P...Start Up and Commissioning of Supercritical Power Stations: Risk Management P...
Start Up and Commissioning of Supercritical Power Stations: Risk Management P...HIMADRI BANERJI
 

More from HIMADRI BANERJI (20)

Workshop on Plant Commissioning and Seamless Startup final.pdf
Workshop on Plant Commissioning and Seamless Startup final.pdfWorkshop on Plant Commissioning and Seamless Startup final.pdf
Workshop on Plant Commissioning and Seamless Startup final.pdf
 
Brochure on Two Day Workshop on Plant Commissioning and Seamless Start Up By ...
Brochure on Two Day Workshop on Plant Commissioning and Seamless Start Up By ...Brochure on Two Day Workshop on Plant Commissioning and Seamless Start Up By ...
Brochure on Two Day Workshop on Plant Commissioning and Seamless Start Up By ...
 
Gas Turbines Failures Applications & Root Cause Analysis.pptx
Gas Turbines Failures Applications & Root Cause Analysis.pptxGas Turbines Failures Applications & Root Cause Analysis.pptx
Gas Turbines Failures Applications & Root Cause Analysis.pptx
 
Gas Turbines O&M-Trainer Rev 01.pdf
Gas Turbines O&M-Trainer Rev 01.pdfGas Turbines O&M-Trainer Rev 01.pdf
Gas Turbines O&M-Trainer Rev 01.pdf
 
Making Artificial Intelligence Work in Managing Change
Making Artificial Intelligence Work in Managing ChangeMaking Artificial Intelligence Work in Managing Change
Making Artificial Intelligence Work in Managing Change
 
Case Studies IN Machine Learning
Case Studies IN Machine Learning Case Studies IN Machine Learning
Case Studies IN Machine Learning
 
Program Link to Workshop AI.pdf
Program Link to Workshop AI.pdfProgram Link to Workshop AI.pdf
Program Link to Workshop AI.pdf
 
Brochure for 2022 Webinar Dr.Himadri AI.pdf
Brochure for 2022 Webinar Dr.Himadri AI.pdfBrochure for 2022 Webinar Dr.Himadri AI.pdf
Brochure for 2022 Webinar Dr.Himadri AI.pdf
 
Risk management in nuclear projects and strategy of small reactors [compatibi...
Risk management in nuclear projects and strategy of small reactors [compatibi...Risk management in nuclear projects and strategy of small reactors [compatibi...
Risk management in nuclear projects and strategy of small reactors [compatibi...
 
Lng project risk and appraisal 2012 final 03092012
Lng project risk and appraisal 2012 final 03092012Lng project risk and appraisal 2012 final 03092012
Lng project risk and appraisal 2012 final 03092012
 
Risk management FSRU himadri banerji
Risk management FSRU himadri banerjiRisk management FSRU himadri banerji
Risk management FSRU himadri banerji
 
Risk management during start up and commissioning of super critical once thro...
Risk management during start up and commissioning of super critical once thro...Risk management during start up and commissioning of super critical once thro...
Risk management during start up and commissioning of super critical once thro...
 
FSRU RISK MANAGEMENT AND CONTROL
FSRU RISK MANAGEMENT AND CONTROLFSRU RISK MANAGEMENT AND CONTROL
FSRU RISK MANAGEMENT AND CONTROL
 
Managing Smart Grids, Power System Networks with Analytics
Managing Smart Grids, Power System Networks with Analytics Managing Smart Grids, Power System Networks with Analytics
Managing Smart Grids, Power System Networks with Analytics
 
Liquefied Natural Gas project risk and appraisal
Liquefied Natural Gas project risk and appraisal Liquefied Natural Gas project risk and appraisal
Liquefied Natural Gas project risk and appraisal
 
Challenges in building the 21st century energy infrastructure
Challenges in building the 21st century energy infrastructureChallenges in building the 21st century energy infrastructure
Challenges in building the 21st century energy infrastructure
 
Thermal coal upgradation and conversion in india ibc asia, jakarta april 25, ...
Thermal coal upgradation and conversion in india ibc asia, jakarta april 25, ...Thermal coal upgradation and conversion in india ibc asia, jakarta april 25, ...
Thermal coal upgradation and conversion in india ibc asia, jakarta april 25, ...
 
Clean Coal Technology:Indian Perspective by Himadri Banerji
Clean Coal Technology:Indian Perspective by Himadri Banerji Clean Coal Technology:Indian Perspective by Himadri Banerji
Clean Coal Technology:Indian Perspective by Himadri Banerji
 
Permananece of Nuclear Power: Strategies for Managing Safety Risks Post Fukus...
Permananece of Nuclear Power: Strategies for Managing Safety Risks Post Fukus...Permananece of Nuclear Power: Strategies for Managing Safety Risks Post Fukus...
Permananece of Nuclear Power: Strategies for Managing Safety Risks Post Fukus...
 
Start Up and Commissioning of Supercritical Power Stations: Risk Management P...
Start Up and Commissioning of Supercritical Power Stations: Risk Management P...Start Up and Commissioning of Supercritical Power Stations: Risk Management P...
Start Up and Commissioning of Supercritical Power Stations: Risk Management P...
 

Recently uploaded

Types of Cyberattacks - ASG I.T. Consulting.pdf
Types of Cyberattacks - ASG I.T. Consulting.pdfTypes of Cyberattacks - ASG I.T. Consulting.pdf
Types of Cyberattacks - ASG I.T. Consulting.pdfASGITConsulting
 
Neha Jhalani Hiranandani: A Guide to Her Life and Career
Neha Jhalani Hiranandani: A Guide to Her Life and CareerNeha Jhalani Hiranandani: A Guide to Her Life and Career
Neha Jhalani Hiranandani: A Guide to Her Life and Careerr98588472
 
Interoperability and ecosystems: Assembling the industrial metaverse
Interoperability and ecosystems:  Assembling the industrial metaverseInteroperability and ecosystems:  Assembling the industrial metaverse
Interoperability and ecosystems: Assembling the industrial metaverseSiemens
 
Exploring Elite Translation Services in Your Vicinity
Exploring Elite Translation Services in Your VicinityExploring Elite Translation Services in Your Vicinity
Exploring Elite Translation Services in Your VicinityThe Spanish Group
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckHajeJanKamps
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers referencessuser2c065e
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersPeter Horsten
 
Darshan Hiranandani (Son of Niranjan Hiranandani).pdf
Darshan Hiranandani (Son of Niranjan Hiranandani).pdfDarshan Hiranandani (Son of Niranjan Hiranandani).pdf
Darshan Hiranandani (Son of Niranjan Hiranandani).pdfShashank Mehta
 
Simplify Your Funding: Quick and Easy Business Loans
Simplify Your Funding: Quick and Easy Business LoansSimplify Your Funding: Quick and Easy Business Loans
Simplify Your Funding: Quick and Easy Business LoansNugget Global
 
Customizable Contents Restoration Training
Customizable Contents Restoration TrainingCustomizable Contents Restoration Training
Customizable Contents Restoration TrainingCalvinarnold843
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...Operational Excellence Consulting
 
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...SOFTTECHHUB
 
WSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfWSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfJamesConcepcion7
 
Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...
Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...
Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...PRnews2
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdfMintel Group
 
Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...
Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...
Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...Aggregage
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterJamesConcepcion7
 
Roman Kyslyi: Використання та побудова LLM агентів (UA)
Roman Kyslyi: Використання та побудова LLM агентів (UA)Roman Kyslyi: Використання та побудова LLM агентів (UA)
Roman Kyslyi: Використання та побудова LLM агентів (UA)Lviv Startup Club
 
Fundamentals Welcome and Inclusive DEIB
Fundamentals Welcome and  Inclusive DEIBFundamentals Welcome and  Inclusive DEIB
Fundamentals Welcome and Inclusive DEIBGregory DeShields
 

Recently uploaded (20)

Types of Cyberattacks - ASG I.T. Consulting.pdf
Types of Cyberattacks - ASG I.T. Consulting.pdfTypes of Cyberattacks - ASG I.T. Consulting.pdf
Types of Cyberattacks - ASG I.T. Consulting.pdf
 
Neha Jhalani Hiranandani: A Guide to Her Life and Career
Neha Jhalani Hiranandani: A Guide to Her Life and CareerNeha Jhalani Hiranandani: A Guide to Her Life and Career
Neha Jhalani Hiranandani: A Guide to Her Life and Career
 
Interoperability and ecosystems: Assembling the industrial metaverse
Interoperability and ecosystems:  Assembling the industrial metaverseInteroperability and ecosystems:  Assembling the industrial metaverse
Interoperability and ecosystems: Assembling the industrial metaverse
 
Exploring Elite Translation Services in Your Vicinity
Exploring Elite Translation Services in Your VicinityExploring Elite Translation Services in Your Vicinity
Exploring Elite Translation Services in Your Vicinity
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deck
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers reference
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exporters
 
Darshan Hiranandani (Son of Niranjan Hiranandani).pdf
Darshan Hiranandani (Son of Niranjan Hiranandani).pdfDarshan Hiranandani (Son of Niranjan Hiranandani).pdf
Darshan Hiranandani (Son of Niranjan Hiranandani).pdf
 
Simplify Your Funding: Quick and Easy Business Loans
Simplify Your Funding: Quick and Easy Business LoansSimplify Your Funding: Quick and Easy Business Loans
Simplify Your Funding: Quick and Easy Business Loans
 
Customizable Contents Restoration Training
Customizable Contents Restoration TrainingCustomizable Contents Restoration Training
Customizable Contents Restoration Training
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
 
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
 
WSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfWSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdf
 
WAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdfWAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdf
 
Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...
Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...
Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
 
Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...
Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...
Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare Newsletter
 
Roman Kyslyi: Використання та побудова LLM агентів (UA)
Roman Kyslyi: Використання та побудова LLM агентів (UA)Roman Kyslyi: Використання та побудова LLM агентів (UA)
Roman Kyslyi: Використання та побудова LLM агентів (UA)
 
Fundamentals Welcome and Inclusive DEIB
Fundamentals Welcome and  Inclusive DEIBFundamentals Welcome and  Inclusive DEIB
Fundamentals Welcome and Inclusive DEIB
 

Plant Commissioning and Start-Up Procedures Workshop

  • 1. Workshop on “Plant Commissioning and Start-Up Procedures” Dr. Himadri Banerji MD EcoUrja Ex Reliance and Tata Organized By :
  • 3. The Commissioning Process Key State Preparation and planning Mechanical Completion and Integrity checking Pre-commissioning & Operational Testing Start Up & Initial Operation Performance and Acceptance testing Post Commissioning
  • 4. The Commissioning Process Detail - 1 Preparation and • Appointment of Commissioning planning Manager or Lead Commissioning Engineer Mechanical • Appointment of Commissioning Team Completion Members and Support Staff and Integrity checking • Training Pre-commissioning & • Information Compilation Operational Testing • Safety and Risk Assessment Start Up & Initial • Commissioning Strategy Operation Development; • Procedures and Checklist Performance and Development Acceptance testing • Post Commissioning Post Commissioning • Detailed Plan and Budget Preparation;
  • 5. The Commissioning Process Details – 1 Facility Commissioning Issues Time phasing construction and commissioning activities Time phasing the commissioning of the various parts of the plant relative to each other Relationships and timings determining when various systems need to be available: Electrical, Steam, Water, Instrumentation Sequencing of the overall plant startup and shutdown to ensure we do not create unsafe conditions Initial start up Process Control and Shutdown Performance testing
  • 6. Developing Startup Procedures Engineering and construction companies generally follow a systematic procedure where by their startup engineers review the process design several times as it is developed After the first review, a preliminary start-up and operations procedure is written Decide what must be added to the design to make the process capable of being started up and operated; By the time the final engineering flow-sheets have been released a complete startup and operating instructions manual should have been completed.
  • 7. Issues Considered Are various part of the process too depend on one another Is there enough surge capacity Are there provisions to prevent abnormal pressures, temperatures and rates of reaction Where are additional valves and bypass lines needed Special lines to allow equipment to be started up and rerun product/raw materials.
  • 8. System Level Activities Utilities systems - steam, instrument air, process water, fire water, drainage, condensate return Electrical systems Instrumentation and instrumentation systems; Cleaning and flushing Purging Initial start up and shutdowns Performance testing
  • 9. Equipment Level Activities Pressure testing & mechanical integrity testing of vessel, columns and pipe work. Heat Echanger, condensers, coolers etc. Mechanical equipment and machinery. Control Systems and Instrumentation. Operational testing. Proof testing and acceptance.
  • 10. What can be done before mechanical completion Utilities commissioning Lube and Seal-Oil Systems Cleaned Instrumentation and Control Loops Proven Piping, Towers and Vessels Cleaned Boil-Out, Dry-Out and Acid Cleaning Turbine, Motor and Pump Run-Ins Nitrogen Purge and Tightness Testing
  • 11. Building Organisational Learning Best Practice Benchmarking Improvement Industry Processes Standards Corporate Procedures and Knowledge Base Check sheets Legislation Experience Process Design Specific Machinery &Equipment
  • 12.
  • 13. Procedures Procedures are written routines/instructions that describe the logical sequence of activities required to perform a work process and the specific actions required to perform each activity. If there are no written procedures, there is no basis for monitoring performance, focus for improvement or mechanism by which to capture learning. The establishment of procedures and routines allow more time and mental energy to deal with the unexpected, which always happen during commissioning.
  • 14. Commissioning / Startup Logic A Critical Path Network (Plan) with written procedures with related documents are required. These should define for the facility, each plant system: • The order in which the systems will be started up. • Individual activities at each stage. • Operation testing requirements. • Durations, waiting times, cooling times. • Total duration for starting up each system. • Resources required - labour, materials, equipment services • Temperatures, pressures, fluid flows used.
  • 15. BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 15
  • 16. Commissioning / Startup and Shutdown Issues At the facility, system and equipment level, we want to avoid: • Creation/existence of explosive mixtures, usually because of the presence of air. • Water hammer and water based explosion effects, due to contact between water and hot substances (steam, oil, etc.) In particular, during commissioning hot fluids and gases will be coming into contact with cold surfaces in places that would be hot under normal operations.
  • 17. Mechanical Completion and Integrity Checking
  • 18. Mechanical Completion and Integrity Inspection Preparation and planning • Inspection Mechanical Completion • Pressure testing and Integrity checking • Cleaning and Flushing • Machinery checkout Pre-commissioning & Operational Testing Start Up & Initial Operation Performance and Acceptance testing Post Commissioning
  • 19. Categories of Process Equipment Distillation Towers / Fractionation Towers Re-boilers & Other Shell & Tube Heat Exchangers Boilers and Fired Heaters Pressure Vessels and Pipe-work Fin-Fan Coolers Condensers Machinery/Rotating Equipment Valves Instrumentation Electrical Equipment
  • 20. Machinery / Rotating Equipment Pumps Steam Turbines Gas Turbines Compressors Gas Engines Electric Motors
  • 21. Mechanical Completion and Integrity Inspection Involves checking that everything has been built and it there as per specification. Refer: • Piping Plan Drawings • Layout and construction drawings • P & ID’s Electrical systems, Instrumentation and control systems checkout done by appropriately qualified personnel (Electricians and Instrumentation technicians). General commissioning engineers generally do not get involved in this in a hands-on manner.
  • 22. Mechanical Completion and Integrity Inspection Procedure Divide plant into manageable areas; In a large plant, assign individuals or teams to specific areas; Establish a master set of piping plan drawings and P&ID’s, mark up areas: Individual commissioning engineers or teams walk every line and mark up every item that can be confirmed as present on master set of drawings. Use different colored “highlighter” pens to indicate different services.
  • 23. Mechanical Completion and Integrity Inspection Every line must be walked! Physically see every
  • 24. Mechanical Completion and Integrity Inspection Procedure Hints / Tips Ensure pipes, vessels, valves etc. are all in the right place. Valves are correct type - globe, gate, control; Vents, drains, steam traps etc. Flanges, bolts, types of bolts. Blind flanges and swing able blinds in place, correct rating. Check all tag numbers. Punch list any non-conformances.
  • 25. Pipe Stressing Piping should provide adequately for expansion and contraction due to temperature changes, without placing excessive stresses on equipment; Misalignment between matching flanges on pipe work particular where there are changes indirection (elbows) can cause stressing; Misalignments where pipe-work connects to machinery, vessels and other process equipment; Can often be seen visually, or checked with gauges using the same procedures we use to align rotating equipment.
  • 27. Piping and equipment support Mobile supports permit and guide the thermal growth of equipment undergoing temperature change; If they do not function correctly, vessels, equipment, pipe work, nozzles heat exchangers etc. may be damaged.
  • 29. Piping and Equipment Supports Inspection prior to start up: • Check that installed according to specification and not jammed; Inspection during warm up: • Check thermal growth is occurring and supports are responding as per design; • Check that there is no surface buckling or crimping - this needs to be corrected; • Check expansion joints; • Check long straight runs of piping for bowing or support shoe that may have slipped; • Rule of thumb - bowing is excessive if you can see it.
  • 30. Piping and Equipment Supports Inspection after cool-down: • Check that sliding supports have returned to original positions; • Establish that equipment can expand and contract as required.
  • 31. Inspection of Spring Supports Before hydro-testing: • Check that spring stops are installed. (If not, the weight of water in pipe will deform the spring). After hydro-testing but before heating: • Check that stops are removed; • Check that spring pointer is positioned to cold setting;
  • 32. Inspection of Spring Supports During and at end of heating: • Check pointer has not exceeded hot setting; After cool down: • check to establish piping can expand and • establish that springs can absorb loads.
  • 34. Inspection of Vessels and Columns The inspection of vessels, columns and reactors should be scheduled to be completed before construction has closed them up; Other inspections - e.g. for completeness or piping, insulation, safety etc. can be scheduled later; If a vessel has been sealed up by construction, it is your duty to inspect it, even it construction resist.
  • 35. Inspection of Vessels and Columns Check that distributors have been installed correctly; De-misters installed correctly and of correct materials, design, type; Vortex breakers in place; Trays - packed or “bubble-cap” are correct: • Bubble caps not jammed or damaged, down comers clear, supports all OK.
  • 37. Pressure Testing - Objectives The objective of pressure testing is to confirm the mechanical integrity of the plant; Verifying capability of containing the pressures it has been designed to hold; Ensure there are no leaks and verify that the plant can be reliably made leak free; Identify any vulnerabilities well before the plant is placed into service; Meet the requirements of legislation, local, international and industry standards.
  • 38. Pressure Testing – Responsibilities Pressure tests of tanks, reactors and piping for mechanical strength and tightness of joints is usually done by the construction team; Commissioning team representatives should witness and certify the tests; Need to verify that all necessary safety precautions have been taken;
  • 39. Pressure Testing - Procedures Water for testing and flushing should contain a rust inhibitor - one low in chloride content for stainless steel lines; After testing, water should be drained completely from all lines that do not normally carry water, steam or steam condensate; All low points should be checked for presence of water; Lines should be dried by blowing hot air, dry inert gas or instrument air.
  • 40. Pressure Testing – Vacuum Systems Final checks of vacuum systems are best performed by pulling a vacuum and observing the rate of pressure rise in the blocked in system; Excessive leaks can then be located by applying a mild positive pressure and testing each flange with bubble solution.
  • 41. Pressure Testing – Procedures 2 Isometric drawings of all systems to be tested should be displayed on a board and marked up as each section is tested; Hydro testing of piping and equipment according to code requirements to confirm mechanical strength should be carried out on groups of equipment naturally suggested by design pressure and function; All water, steam, condensate, oil, gas and process steam piping should be hydro tested; Major equipment that has already been tested as part of manufacturing may be isolated by blanks.
  • 43. Cleaning and Flushing Need to ensure no construction debris is left in pipes of vessels - welding rods, bolts, gloves, rags etc. Large debris (lumber, cable, packaging) should have been removed during mechanical integrity inspections; Small debris (rags, nuts, dirt) must be flushed out of all pipe and vessels; Where oil coatings must be removed, chemical cleaning is necessary.
  • 44. Cleaning and Flushing Before flushing is started, check the process thoroughly to ensure: • Screens have been installed in front of pump suctions. • Blinds in front of equipment such as compressors and turbines; • “Jumper” spool pieces to allow for continuity of flow.
  • 45. Flushing Can be handled by geographic plant area; Sections too large for water flushing: • Pipes greater than 30 in diameter (0.75 m), or • Pipes that should not be touched with water; Should all be blown out with air or inert gas.
  • 46. Flushing Regardless of whether pipes are cleaned with water, steam, air or nitrogen, flow velocities should be high enough to ensure that pipes will be suitably scoured; Need to ensure that the debris from one piece of equipment will not simply be flushed into another; Water velocities should be at least 12 ft/sec (approx. 3.75 m/sec); Air velocities a minimum of 200 ft/sec (approx.65 m/sec).
  • 48. The Commissioning Process Detail - 3 Preparation and planning Mechanical • Steam and other utilities Completion commissioned and introduced; and Integrity checking • Dry running trials; • Hot running trials; Pre-commissioning & • Safe-fluid dynamic testing; Operational Testing • Solvent dynamic testing; • Process fluid tests. Start Up & Initial Operation Performance and Acceptance testing Post Commissioning
  • 50. Commissioning Utilities Utilities commissioning usually represents the first phase of commissioning, as these usually need to operational first, before the rest of the plant can be commissioned; The steps for commissioning each utility should be planned in detail; Provides planning practice for planning the startup of the main plant.
  • 51. Commissioning Utilities – Broad Guidelines Check supply pressures of all services - steam, cooling water, instrument air, nitrogen etc. At the most distant points, open drains, vent valves or pipe flanges and purge until fluids come out clean and rust free; Purge/blow out lines to each piece of equipment; Check that instrument air is clean and dry, and at correct pressure; Circulate water to waste water system until water lines clear and clean; Flush waste water and drain systems to ensure no blockages; Check operation of steam traps; Drain condensate to waste water until is clean.
  • 52. Commissioning Utilities Introducing Steam Steam usually represents the first “hazardous” fluid introduced into the “new” system; Admit steam slowly into the distribution system with atmospheric bleeds open: • Cold pipes will condense steam in places where it would not under normal operation; • Can lead to “water hammer”- can distort and rupture lines; After system has been warmed, slowly raise pressure and blow down the system with traps bypassed, until clean; Then place steam traps into service and check operation.
  • 53. High Pressure Steam Systems Specific Issues The cleanliness and purity of high pressure steam systems - particularly where the steam is used to drive a steam turbine should be checked by use of a “target”; For new boilers, or new sections added to steam system - blow down at full pressure; When steam appears clean, fit a target with a “mirrored” surface (ie. Small steel plate which has been polished, so that it is in the steam blow down stream; Blow down the boiler or system so that the target is impinged upon for a few minutes; Check target - ensure there are no small “pock marks” left on the target. If pock marked - repeat process.
  • 55. Machinery and System Check-Out Check-out A crew of specialized individuals need to be mobilized to do the check-out and pre-commissioning in a plant: • All control loops, settings of PID loops, stroking of valves, transmitter calibration, etc… • P&ID conformity; is the plant built according the P&ID, is all instrumentation correctly installed, are they connected, are all valves correctly installed, etc… • Mechanical installation of all (major) equipment; levelling correct, alignments done, oil flushing satisfactory, etc… • Analyzer calibration, checking of tubing, problem assessment and identification. • Control systems functional check, communications check, integrity check, safety features checking, emergency stops check, critical operating parameters checking, etc… • Electrical check-out; check-out of MCC’s, switchgears, selectivity studies, protection systems, functional checks, etc…
  • 56. Commissioning Electrical Systems The following checks are typical of what is required Open circuit breakers and switches; Check that all bus-bars are free of dirt and foreign matter; Check grounding systems for continuity and resistance. Make sure all electrical equipment, vessels, structures are connected to the grounding system in accordance with drawings and specifications; Check that all sealed fittings are filled with proper sealants, all explosion proof, vapour-tight, dust-tight and weather tight enclosures are properly closed and secured; Check motor control and power circuitry for correct hookup.
  • 57. Commissioning Electrical Systems – 2 The Following checks are typical of what is required Check all nameplates and panel directories to ensure that each circuit breaker and switch does control the proper circuit. Label all switches even though their application may seem obvious; Close main transformer primary disconnect switch and switch-gear main circuit breaker; Check voltmeter at switch-gear for proper voltage; Close first switch-gear circuit breaker, second, third etc. Close first motor control centre main circuit breaker, then each motor starter circuit breaker. Repeat for each MCC. Check overload breakers and heaters to ensure that the correct capacity units have been installed.
  • 58. Commissioning Electrical Systems – 3 The following checks are typical of what is required Check that all lighting and power circuits are functioning correctly; Check motor bearings for proper lubrication; Remove motor power fuses and check main contractor, interlock and sequencing devices; Uncouple each motor, replace fuses and check direction of rotation by momentarily pressing the start button, then stop; Check manual, then automatic operation. Replace all couplings, check drive belts and make sure guards are installed.
  • 61. Operational Testing Progresses through several stages; Dry runs of individual items of equipment Hot testing of individual items of equipment and systems; Several stages of Dynamic Testing of: • Individual items of equipment; • Individual Systems/processes in isolation; • The whole new process plant installation.
  • 62. Dry Runs and Hot Tests Check that motors are connected correctly and turn in the right direction; Shafts and impellers move freely; Equipment that is to be operated at temperature, raise to temperature and check; These tests should be performed by the manufacturer’s representative but witnessed by members of the client’s operating/commissioning personnel.
  • 63. Hot Testing Equipment Applies to equipment whose leak-tightness must be tested at operating temperatures and after temperature reversals; Fixed-bed catalytic reactors that in normal conditions are heated by heat transfer fluids where leakage would contaminate the catalyst; Critical exchangers whose steam or cooling water is at a high pressure than the process fluid; Any equipment having complicated seals through which leakage could occur; Rotating machinery which must be able to rotate freely at temperature eg. Steam turbines, etc.
  • 64. Hot Testing Procedures The thermal shock tolerance of equipment must be determined beforehand; To avoid thermal shock, the temperature of the heating medium may have to be raised gradually; Time required for a hot test must be established in advance; Establish a uniform temperature in all parts of equipment that are supposed to be uniformly hot during operation to avoid setting up stresses;
  • 66. Dynamic Testing Involves operating the equipment, before introducing “live” process fluid; During dynamic testing, we progress through: • Safe-fluid dynamic testing; • Dynamic testing with solvent; • Closed loop testing with process fluid. Once process fluid is introduced, normal plant safety procedures must come into effect as if it were a live operating plant.
  • 67. Safe-Fluid Dynamic Testing Closed loop dynamic testing with safe fluids consists of operating equipment systems with air, water, inert gases etc. This permits flow testing of equipment; Gives first indication of how control loops work; Establishes performance while there is still time to modify the plant; Familiarizes operators with the operation of the equipment before hazardous materials are introduced; Gets rid of a lot of dirt which would be more difficult to Clear once the process fluid has been introduced.
  • 68. General Principles for Testing For most plants, a period of 2-3 weeks is usually sufficient for operational testing, after the mechanical dry running of individual pieces of equipment and hot testing complete; Air and water tests should be set up in a closed loop with fluids continuously recycled, with loops as large as possible; The loop should ideally be the same loop that will be subject to solvent testing; Tests should continue for several days in order to give all shifts a chance to conduct the same tests; All shifts should be given the opportunity to start up and shutdown each closed loop test.
  • 69. General Principles for Testing A rough flow-sheet should be developed for air and water tests, predicting all information that normally appears on a process flow sheet - flow, temperature, pressure, heat transfer, power etc. will assist in alerting commissioning team for risks from over- pressuring, over loading temperature-shocking and stressing equipment;
  • 70. Cautions During Testing Dynamic testing may lead to: • Unusual or unforeseen differential expansions; • Corrosion • Excessive weight of liquid into parts of the system; Care must be taken not to collapse or burst pressure vessels and tanks: • ensure there is always adequate venting; • avoid pulling a vacuum.
  • 71. Dynamic Testing – Simulated Operations Safe Fluid Testing Auxiliary services must be brought into operation first: • water cooling, inert gas generators, boiler feed water, firewater, steam production, etc. Water is pumped through the process (except where special conditions do not permit it) and boiled up in columns; Compressors and blowers should be operated on air or inert gas.
  • 72. The Value of Dynamic Testing – Simulated Operations Value of simulated operations will be to allow operator to become familiar with the operation of the process, before hazardous fluids are introduced; Equipment deficiencies can become apparent during dynamic testing; Failures and problems more easily corrected with safe fluids present Leaks should be found and tightened; Instruments can be placed into service - although selection of set-points will have to be deferred; Inspect the plant for evidence of design and construction errors.
  • 73. Dynamic Testing – Simulated Operations
  • 74. Dynamic Testing with a Solvent After safe fluid testing and subsequent repairs and modifications, we are ready for dynamic closed loop testing with a solvent; The “solvent” is a relatively safe fluid whose properties are close to that of the process fluid, or the process fluid itself; In order to allow for continuous re-circulation of the solvent and the use of different solvents in different parts of the plant, temporary lines will need to be installed.
  • 75. Dynamic Testing with Process Solvent Introduce the process solvent. (if there is more than one, introduce only one at this stage); The dynamic testing procedure used for the safe fluid test is repeated for the process solvent dynamic testing; After operations with the first solvent have been brought completely under control, should the second solvent be introduced (if there is one).
  • 76. Dynamic Testing with a Solvent The purpose of dynamic testing with a solvent is to check out equipment and instrument loops at, or near design conditions prior to the introduction of more hazardous process fluid; No reactions should be allowed to occur during these tests, so as to ensure that test fluids remain predictable in composition and properties; Guidelines used for safe-testing apply; Need to plan how solvent will be fed into the system and later removed.
  • 77. Stages of Dynamic Testing with a “Solvent” Drain safe fluid and purge air used in the previous test from the system; Dry out equipment where safe fluid was water. Check flow sheets for where water is likely to accumulate. Fill systems with the solvent. Ensure provisions made for venting and drains closed; When adequate levels established, place pumps and compressors online to complete filling; Start closed loop circulation; Heat up the systems to simulate operating conditions by placing reflux, re-boiler and condensation systems into operation
  • 78. Stages of Dynamic Testing with a “Solvent” Systematically check out instrumentation and control loops; After instruments have checked out, place as many as possible on automatic control; All shifts should go through starting and stopping equipment, heating and cooling closed loop systems; Dynamic “solvent "testing offers the best opportunity for operator training before the “real thing”; Operate equipment as near as possible to design capacities; Reliability of emergency shutdown systems and alarms must be proven; Critical instruments must be calibrated over their full range.
  • 79. Stages of Dynamic Testing with a “Solvent” Deliberately operate equipment near its limits: Flood columns; Ease compressors into mild surges and plot surge curves; Overload condensers; Do not fear blowing a relief valve or two! After tests have been completed, plant should be ready for initial operation.
  • 80. Closed Loop Dynamic Testing with Process Fluid Finally, introduce process fluid; During this step, instruments should be calibrated to cover their full range of flow, temperature and pressure; Ensure that instruments, process analysers and safety devices are kept work properly during these processes; After operations with process fluid are brought completely under control should the final stage of start-up be attempted.
  • 81. Preparing to Introduce Process Fluid Before introducing hazardous liquids into the plant, we complete additional pressure testing and purging; Need to check that the stresses and strains of dynamic testing has not caused any leaks – these must be found and fixed;
  • 82. Pressure Testing and Purging Consists of pressuring and de-pressuring with nitrogen several times, until at least <3% oxygen is reached; Vacuum systems should be evacuated and then re-pressured with nitrogen; Long runs of piping are swept with nitrogen; While under pressure, rate of pressure loss of the “blocked in "system is monitored as a check for leaks and that no vents or drains have been left open.
  • 83. Dehydrating by Circulation It is usually not possible to water-free equipment simply by draining; Only positive method to water-free process equipment is oil circulation followed by repeated draining of low points; Ensure sufficient low point drains are provided on piping, control valve loops, vessels and process machinery; Startup lines - deliver oil to upper part (trays) of distillation towers (size for 20% of net distillate product rate);
  • 84. Start Up and Initial Operation
  • 85. Preparation and planning Mechanical Completion and Integrity checking Pre-commissioning & Operational Testing • Introduction of process fluid • Start-up and initial operation • Trouble-shooting and Start Up & Initial Operation problem correction. • Plant taken to full operations. Performance and Acceptance testing Post Commissioning
  • 86. Most plants in petrochemical/chemical industry have the following “general ”form. Feed Reaction Recovery Product Preparation refining Start Up from the End of the Process and Work back
  • 87. Start Up Logic It is common practice to buy in product and start up the last past of the process first and work backwards to the front. E.g. • Start up refining, get this working and in control; • Then possibly start up reaction and recovery; • Finally, feed preparation.
  • 88. Into the Initial Operation Once raw materials are fed into the plant – usually at reduced rate until reaction conditions have been established; As each section is started up, establish as quickly as possible that process conditions are as expected; If potentially serious problems develop, there should be no hesitation on going into an emergency shutdown.
  • 89. Ramping up the Plant Plant is brought slowly to design feed-rates and operating conditions; Usually done in steps with operating data evaluated and verified as OK at each step; Plant and laboratory data are now being collected and should be being evaluated promptly;
  • 90. Coordination and Supervision During Start Up Additional personnel, both supervisory and “on the- ground” are required at this stage; Cooperation between startup personnel and plant supervisory personnel is critical at this stage: • Need a daily meeting at least; • Often, a briefing each shift.
  • 91. Trouble Shooting At this stage, many problem with equipment of the process itself may become apparent; The commissioning process goes through what is often an intense (and hopefully short) period of problem trouble shooting, problem solving, engineering correction and plant modification;
  • 93. Preparation and planning Mechanical Completion and Integrity checking Pre-commissioning & Operational Testing Start Up & Initial Operation Performance and • Performance trails; Acceptance testing • Formal Acceptance test Post Commissioning
  • 94. The Performance Trials Once the plant is fully operational, the final “proving trial” or performance run is performed in order to prove the plant can do what it is supposed to do; The values or range of values for each independent variable - flow, temperature, pressure, level, concentrations, etc. to which the plant must be operated to are determined; The plant is brought up to those conditions and the pre- agreed trial period begins.
  • 95. Before the Trails of Performance Run Need to Ensure that… Control of plant operating conditions has been achieved. I.e. temperature, pressures, levels and analyses are reasonably constant or in the case of a batch process, there is repeatability; Daily material and energy balanced can be performed and that these agree with “official” production figures; Product specifications are being achieved consistently.
  • 96. Need to Verify … Physical operation, capability and capacity of plant and equipment; Energy and mass balance; Process chemistry; Efficiencies, yields and quality; All to specification.
  • 97. Acceptance When the plant has met the Performance and Acceptance test requirements designed by the commissioning team there is usually a formal acceptance process involving signing of acceptance certificates; Once the plant is accepted it is officially part of the normal operations - the responsibility of operations and maintenance; Commissioning is officially over; The may still be outstanding punchlist items
  • 98. Acceptance Testing It is common practice to prove performance repeatability and plant integrity as part of the performance test. That is: • Shutdown and Start Up the plant on several occasions and bring it up to test conditions to prove repeatability. Also ramp down and ramp up while online; • Re-inspection of critical process equipment - particularly columns to ensure they have not been damaged by the performance run.
  • 99. Commercial Significant of Acceptance Formal Acceptance represents formal acknowledgment that the: • Contractor has full-filled their contractual obligations; • Commissioning team have full-filled their obligations; Completion of the Capital Project and transfer to Operations; Expenses and costs from acceptance onwards are now operating expenses not capital project costs; All subject to agreed punch-list items.
  • 101. Preparation and planning Mechanical Completion and Integrity checking Pre-commissioning & Operational Testing Start Up & Initial • From plant on-stream to settled down Operation and in regular production; Performance and • Adjustments, modifications and fault Acceptance testing correction; • Completion of outstanding punch list Post Commissioning items
  • 102. Post Commissioning Covers the period immediately after Acceptance; Outstanding punch-list items are completed; The first routine maintenance checks are performed, findings evaluated and reported; Process equipment and items covered by warranty are scrutinized for signs of premature wear-out or problems; Operating data is collected and evaluated to ensure consistent plant operations are maintained and sustainable.
  • 103. BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 103
  • 104. WORKSHOP ON PLANT START UP AND COMMISSIONING SEQUENTIAL START UP AUTOMATION IN PLANT START UP AND COMISSIONING BY DR. HIMADRI BANERJI (EX RELIANCE AND TATA) www.ecourja.com BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 104
  • 105. Automation for Controlled Start Up To advocate the usage of process integration in industrial practice, it is important to be able to guarantee not only robust control during near steady state operation, but also to provide procedures for generating fast and reliable start-up sequences. BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 105
  • 106. Sequential Start Up and Shutdown Using Automation in Plant…Burner Management System 1. Burner Management System in Power Plants General The Burner Management System must be designed to ensure a safe, orderly operating sequence in the start-up and shutdown of fuel firing equipment and to reduce possible errors by following the operating procedure. The system is intended to protect against malfunction of fuel firing equipment and associated systems. The safety features of the system shall be designed to provide protection in most common emergency situations, however, the system cannot replace an intelligent operators reasonable judgment in all situations. In some phases of operation, the BMS shall provide permissive interlocks only to insure safe start-up of equipment. Once the equipment is in service, the operator must follow acceptable safe operating practices. BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 106
  • 107. Sequential Start Up…BMS Functions The BMS shall be designed to perform the following functions: 1.Prevent firing unless a satisfactory furnace purge has first been completed. 2. Prohibit start-up of the equipment unless certain permissive interlocks have first been completed. 3. Monitor and control the correct component sequencing during start-up and shut- down of the equipment. 4. Conditionally allow the continued operation of the equipment only while certain safety interlocks remaining satisfied. 5. Provide component condition feedback to the operator and, if so equipped, to the plant control systems and/or data loggers. 6. Provide automatic supervision when the equipment is in service and provide means to make a Master Fuel Trip (MFT) should certain unacceptable firing conditions occur. 7. Execute a MFT upon certain adverse unit operating conditions. BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 107
  • 108. Furnace Explosions A common cause of furnace explosions is “Fuel leakage into an idle furnace and the ignition of the accumulation by a spark or other source of ignition”. Proper attention to the design of the interlocks and trip system to provide a safe light up of the boiler furnace is required. BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 108
  • 109. Furnace Purge…Permissives Before any fuel firing is permitted, either initially or after a boiler trip, a satisfactory furnace purge cycle must be completed. Prior to starting a furnace purge cycle, the operator must ensure that the following purge requirements are satisfied[i]: 1. Drum level within operating range (not high, not low) 2. Instrument air header pressure within operating range 3. Fan is in service 4. Purge airflow capable of a minimum of 70% of the full load airflow established through the unit[ii]. BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 109
  • 110. Furnace Purge…Permissives 5. All flame scanners reading "No Flame“ 6. Natural gas block valves are proven closed 7. Fuel oil block valves are proven closed 8. Air dampers are in the fully open position 9. Natural gas, or fuel oil, header pressure upstream of block valve is satisfactory 10. Pilot gas header pressure is satisfactory 11. Burner Control System is energized 12. A "No Master Fuel Trip condition" condition is established BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 110
  • 111. Pre Purge Permissives Pre purge permissive condition checks and furnace purge are to be initiated by the operator from the local BMS panel (you may see detailed guidelines on cold starting using fuel oil, cold starting using natural gas from operating manuals). Purge air flow: The total furnace airflow shall not be reduced below the purge rate airflow (70% of the maximum continuous airflow capacity). Reducing airflow below these limits will lead to a MFT, and a new furnace purge will be required. Suggested color design: Purge Permissives indicating lights: white Purge Available indicating light: green Purge in progress indicating light: amber Purge complete indicating light: white MFT reset indicating light: red BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 111
  • 112. Main Flame Start-Up Sequence The main flame start-up sequence, from the lighting the of the pilot flame through main flame light-off, is an automated sequence. Once the start-up sequence has begun, only the “BOILER STOP” switch and the “EMERGENCY STOP” will interrupt the start-up sequence. Any interruption of the start-up sequence requires a post-fire purge prior to attempting to start the boiler again. To initiate the start-up sequence, the operator activates the “START BOILER” switch. BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 112
  • 113. Pilot Flame Light-Off Before the burner can be started, satisfactory light-off conditions for the pilot and main burners must be met. This is accomplished when the following conditions are satisfied: For the pilot igniter: 1. MFT relay reset 2. Pilot gas header pressure normal For natural gas: 1. All of the above mentioned for the pilot igniter 2. Natural gas pressure normal 3. Natural gas control valve is in light-off position BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 113
  • 114. Pilot Flame Light-Off For fuel oil: 1. All of the above mentioned for the pilot igniter 2. Oil gun is in place in the burner 3. Oil pressure is normal 4. Fuel oil atomizing interlocks are satisfied 5. Fuel oil atomizing medium is provided to the burner 6. Oil control valve is in light-off position Other Conditions: 1. No MFT condition after purge 2. All flame scanners report no flame 3. All natural gas, or all fuel oil, block valves shown closed 4. All air dampers are in light-off position BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 114
  • 115. Pilot Flame Light-Off Failure to meet any of these conditions shall prevent the burner light-off operation. To light the pilot flame, the pilot header vent valve, and, for natural gas fuel, the natural gas vent valve shall be closed by the boiler control system. Then, sequentially, the igniter transformer is energized, the pilot gas block valves are open and a 10 second pilot ignition timer starts counting down. When ignition timer cycle is completed, the igniter transformer is de-energized and the pilot flame scanner is checked by the control system. If the pilot flame is present, the main flame light-off sequence continues. BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 115
  • 116. Pilot Flame Light-Off If the pilot flame fails, the boiler control system initiates a pilot flame failure shutdown. Additional attempts of pilot light-off are permissible provided a successful pilot light-off is made within 10 minutes after the furnace purge. Note that if the pilot flame continues to fail after several attempts, the boiler should be inspected to determine the fault and the condition corrected. BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 116
  • 117. Main Flame Light-Off Once the pilot flame is made, the boiler control system opens the header block valves for the selected fuel. A main flame light-off timer begins a 15 second countdown for natural gas, or 20 seconds for fuel oil, to establish and stabilize the main flame. At 5 seconds before time out, the boiler control system closes the pilot block valves and opens the pilot vent valve. The remaining 5 seconds are used to detect the main flame. For the typical dual flame scanner design, a main flame failure shutdown is initiated if both flame scanners return a “no flame” signal to the burner control system. This will generate a boiler trip, and another furnace purge will be required. Once the burner is lit, the system is in the NORMAL RUN CONDITION and combustion controls should be released to modulation control BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 117
  • 118. Shutdown Shutdown Per NFPA 8501, section 6-2.4.5, “The normal shutdown cycle for the boiler shall accomplish the following in the order listed: (a) Shut off fuel supply to the main burner. (b) Interrupt spark and shut off fuel supply to igniters, if in operation. (c) For oil: 1. Where used, open the recirculating valve. 2. Shut off atomizing medium, if desired. (d) For gas, vent piping between safety shutoff valves to atmosphere. (e) Perform a post purge of the boiler furnace enclosure. (f) Shut down fan, if desired.” For a safety shutdown, a manual reset is also required. Normal Boiler Shutdown A normal shutdown is initiated by operating BOILER SHUTDOWN switch. This will initiate the shut down sequence listed above. BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 118
  • 119. Boiler Master Fuel Trip Any of the following conditions shall cause a boiler trip to occur. This results in the shutdown of all fuel and requires another furnace purge cycle before any attempt at re-lighting. For fuel oil: 1. Excessive steam pressure. 2. Low water level. 3. Low fuel pressure. 4. Low oil temperature. 5. Loss of combustion air supply. 6. Loss of flame. 7. Loss of control system power. 8. Loss of atomizing medium, if used. BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 119
  • 120. Boiler Master Fuel Trip For natural gas: 1. Excessive steam pressure or water temperature. 2. Low water level. 3. High or low gas pressure. 4. Loss of combustion air supply. 5. Loss of flame. 6. Loss of control system power. BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 120
  • 121. Boiler Master Fuel Trip In the event of an MFT, the control system shall initiate the following: 1. Execute a shut down as listed above. 2. Illuminate the appropriate indicator lights and alarms. 3. Return the system to the pre-purge state Boiler restart will be inhibited until all pre-purge requirements are satisfied. BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 121
  • 122. Alarms The following is a list of recommended alarm conditions: 1. Any boiler or burner trip signal 2. High or low water level 3. High furnace pressure 4. Partial Loss of flame (For the typical two scanner system, one indicates “no flame”) 5. Main fuel shutoff valves closed 6. Loss of control system power 7. Unsuccessful burner shutdown BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 122
  • 123. Interface with the Combustion Control System (CCS) The following list, at a minimum, of signals should be sent to the Combustion Control System: 1. Controls to purge position 2. Controls to light-off position 3. Normal run condition: release controls to modulation 4. Main natural gas block valve open: permissive to place gas control valve in automatic. 5. Master fuel trip: run boiler load to zero and place combustion controls in manual. 6. Oil recirculation signal Under the provisions of NFPA 8501, section 6-5.2.3, for a single burner boiler, the BMS and CCS may reside in the same processor. This option can reduce the integration complexity and increase the BMS to CCS interface reliability. BY DR.HIMADRI BANERJI MD ECOURJA EX. RELIANCE AND TATA Copyright www.ecouja.com 123
  • 124. Operator Interface The above describes a traditional operator interface using discrete switches and indicator lights. The control designer is encouraged to incorporate a graphical user interface or similar options in order to enhance the ease of use and readability of the boiler control system operator interface Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 125. SEQUENTIAL START UP AUTOMATION DESIGN PRINCIPLES OF BURNER MANAGEMENT SYSTEM Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 126. Design Principles of Sequential Start-Up… Case Study in Burner Management System Design Introduction Burner Management System Objectives BMS Design Standards and Definitions BMS Logic BMS Strategies and Hardware ◦ Types of Burner Management Systems BMS Interface to SCADA Systems Summary Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 127. Introduction Burner Management Systems.. ..a starting point. Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 128. Introduction What is a BMS? A Burner Management System is defined as the following: ◦ A Control System that is dedicated to boiler safety, operator assistance in the sequential safe starting and stopping of fuel preparation and burning equipment, and the prevention of mis-operation of and damage to fuel preparation and fuel burning equipment. 1 1. From NFPA 8501 “Standard for Single Burner Boiler Operation” Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 129. Burner Management Objective Sequence burner through safe start-up Insure a complete pre-purge of boiler Supervise safety limits during operation Supervise the flame presence during operation Sequence a safe shutdown at end of cycle Integrate with combustion control system for proper fuel and air flows Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 130. BMS Design Standards Each Burner Management System should be designed in accordance with the below listed guidelines to control and monitor all sequences of the start-up and shutdown of the burner ◦ National Fire Protection Association (NFPA 8501 /8502 or others) ◦ Industrial Risk Insurers (IRI) ◦ Factory Mutual loss prevention guidelines o Each burner management system should be designed to accomplish a safety shutdown in the event of an unsafe condition. (FAIL SAFE) Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 131. BMS Design Standards U.S. National Fire Protection Association (NFPA) ◦ Governs safety system design on virtually all boilers (regardless of the process to be used to combust the fuel) ◦ Requires the separation of the Burner Management System from any other control system ◦ Requires the use of a hardwired backup tripping scheme for microprocessor based systems ◦ Requires that a single failure NOT prevent an appropriate shutdown ◦ Factory Mutual loss prevention guidelines. Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 132. NFPA 8501 NFPA 8501 Standard for Single Burner Boiler Operation ◦ Single Burner Boilers with fuel input greater than 12.5 mBTU/Hr (Approx. 250 BHP) ◦ Single Fuel or Combination of Fuels (Common being Natural Gas / No.2 Oil / No. 6 Oil) ◦ Simultaneous Firing Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 133. NFPA 8502 NFPA 8502 Standard for Prevention of Furnace Explosions / Implosions in Multiple Burner Boilers ◦ Multiple Burner Boilers with fuel input greater than 12.5 mBTU/Hr ◦ Single Fuel or Combination of Fuels including Pulverized Coal ◦ Emphasis on implosion protection (larger boilers with induced draft systems) Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 134. BMS Definitions Furnace Explosions ◦ “Ignition of accumulated combustible mixture within the confined space of a furnace or associated boiler passes, ducts, and fans that convey gases of combustion to the stack”1 ◦ Magnitude and intensity of explosion depends on relative quantity of combustibles and the proportion of air at the time of ignition 1. From NFPA 8502 “Prevention of Furnace Explosions / Implosions in Multiple Burner Boilers” Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 135. BMS Definitions Furnace Explosions can occur with any or a combination of the following:1 ◦ Momentary loss of flame followed by delayed re-ignition ◦ Fuel leakage into an idle furnace ignited by source of ignition (such as a welding spark) ◦ Repeated Light-off attempts without proper purging ◦ Loss of Flame on one Burner while others are in operation ◦ Complete Furnace Flame-out followed by an attempt to light a burner 1. From NFPA 8502 “Prevention of Furnace Explosions / Implosions in Multiple Burner Boilers” Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 136. BMS Definitions Furnace Implosions ◦ More common in large Utility Boilers ◦ Caused by any of the following: Malfunction of equipment regulating boiler gas flow resulting in furnace exposure to excessive induced draft fan head capability Rapid decay for furnace gas temperature and pressure due to furnace trip 1. From NFPA 8502 “Prevention of Furnace Explosions / Implosions in Multiple Burner Boilers” Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 137. BMS Basic Definitions Common Terminology ◦ Supervised Manual Manual Burner Light-off with Interlocks ◦ Automatic Recycling (Single Burner Only) Automatic Burner Start and Stop based on preset operating range (ie.. Drum pressure) ◦ Automatic Non Recycling (Single Burner Only) Automatic Burner Start and Stop based on Manual command to start. Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 138. Types of Flame Scanners Infrared (IR) Detectors ◦ Single Burner Applications ◦ More Suitable with Oil Burning Flames Ultra-Violet (UV) Detectors ◦ Multiple Burner Applications ◦ More Suitable for Gas Burners and Combination Gas / Oil Burners Self Check Scanners ◦ Flame Signal is interrupted at set intervals to verify proper operation of scanner Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 139. Single Burner BMS Inputs Low Low Drum Level (D) High Steam Pressure (D) (D) Purge Purge Air Flow Minimum Air Flow (D) (D) Limits Made Flame / No Flame Hold to Purge SCRL RESET MO DE BURNER FUEL SELECT FD FAN OFF ON GAS OIL HAND OFF AUTO (D) Fuel Oil Temp Low Fuel Oil Temp High (D) (D) Fuel Oil Press Low Fuel Oil Flow (A) (D) Atomizing Medium Flow > Min Atomizing AE TE (D) Medium Common Alarm Output Press Low (D) Remote Annunciator (By Others) FEEDWATER PSH PSL STEAM PT PSH FT IGNITER Safety Shut Off GAS LSLL & Vent Valves LSLL Fuel Fuel Gas Gas FT PSL TSH TSL FS Press Press Low High (D) (D) PSL PSL OIL Safety Shut Off Control Valves Valve ATOMIZING Control Valve & MEDIUM Shut Off Valve (D) - Descrete Signal Used By Flame Safeguard System FT PSL PSH GAS Safety Shut Off & Control Vent Valves Valve Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 140. BMS Logic Burner Management Systems can be broken down into “Interlock Groups” Typical BMS Interlock Groups: ◦ Boiler Purge ◦ Igniter Header Valve Management ◦ Main Fuel Header Valve Management ◦ MFT (Master Fuel Trip) Logic Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 141. Purge Interlocks BOILER TRIPPED AND PURGE / RESET PB START-UP TIMER START FD FAN PERMISSIVES SATISFIED: - MAIN FUEL VALVES CLOSED - NO FLAME PRESENT - FD FAN RUNNING AND - MINIMUM AIR FLOW SWITCH MADE - WATER LEVEL SATISFACTORY - ATOMIZING MEDIUM ON - FUEL SUPPLY PRESSURE NOT LOW ENERGIZE FUEL RELAY NOT AND PURGE SIGNAL TO CCS PURGE AIR FD DAMPER IN FLOW SWITCH AND FULL OPEN MADE POSITION PURGE TIMER SET PURGE COMPLETE NO YES REMOVE PURGE TO CCS SYSTEM TRIP Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 142. Igniter Interlocks PURGE COMPLETE AIR DAMPER IN LOW FIRE FUEL VALVE IN LOW FIRE AND POSITION POSITION ENERGIZE IGNITER AND IGNITER HEADER VALVES 10 SECOND DELAY 10 SEC PILOT TRIAL FOR IGNITION TIMER COMPLETE FLAME PROVEN NOT AND SYSTEM TRIP PERMIT FOR MAIN FLAME Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 143. Main Flame Interlocks IGNITER TIMER COMPLETE FLAME AND PROVEN ENERGIZE MAIN FUEL VALVES 10 SEC MAIN FLAME TRIAL TIMER COMPLETE NOT AND DE-ENERGIZE IGNITION COMPONENTS RELEASE TO MODULATE TO CCS SYSTEM TRIP Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 144. Single Burner Main Fuel Trip FOR OIL: FOR GAS: - LOWFUEL PRESSURE - LOWFUEL GAS PRESSURE - LOWTEM PERATURE (HEATED OILS) - HIGH GAS PRESSURE - LOSS OF COM BUSTION AIR - LOSS OF COM BUSTION AIR - LOSS OF FLAM OR FAIL TO ESTABLISH E - LOSS OF FLAM OR FAIL TO ESTABLISH E - LOSS OF CONTROL SYSTEMENERGY - LOSS OF CONTROL SYSTEMENERGY - POWER FAILURE - POWER FAILURE - LOWWATER LEVEL (AUXLEVEL CONTACT) - LOWWATER LEVEL (AUXLEVEL CONTACT) - LOSS OF ATOM IZING MEDIUM - EXCESSIVE STEAMDRUMPRESSURE - EXCESSIVE STEAMDRUMPRESSURE - HIGH OIL TEMPERATURE (HEATED OILS) OR OR TRIP BOILER TRIP IGNITER, TRIP MAIN FUEL FUEL CONTROL IGNITER VALVES, VALVES, OPEN VALVE TO TRIP MFT RELAY OPEN IGNITER VENT VALVE CLOSED VENT (GAS ONLY) POSITION Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 145. BMS System Types Early Burner Management Systems ◦ Hardwired Systems ◦ Solid State Systems Microprocessor Based Systems ◦ Honeywell 7800 series with fixed Logic. PLC Based Systems ◦ Programmable Logic Controller (PLC) Based ◦ Powerful, versatile, expandable, more reliable. Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 146. Early Burner Management Systems Hardwired Systems ◦ Relay and Timer Driven. Found on older installations ◦ Typical of Late 50’s, 60’s Solid State Systems ◦ Solid State Processors and Relays ◦ Found on Systems provided in the 70’s and 80’s ◦ Proprietary Hardware (ie.. Forney and Peabody) ◦ Spare Parts are extremely hard to find. Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 147. MicroProcessor Based Systems Microprocessor Based System providing: ◦ Burner Sequencing ◦ Ignition ◦ Flame Monitoring Fixed Program with Limited Configuration Changes Components Selected Based on Requirements ◦ Programmers, Flame Amplifiers, Message Displays Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 148. Typical BMS Layout AMPLIFIER EP PROGRAMMER AUTOMATIC PRIMARY SAFETY CONTROL FIELD WIRING FIELD WIRING FLAME SCANNER Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 149. Micro Processor Capabilities Simple, Cost Effective Features ◦ Selectable Flame Amplifiers / Scanners ◦ Remote Display ◦ Remote Data Communications via Modbus Port ◦ Modernization kits are available to integrate with older systems ◦ Spare Parts Normally Readily Available Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 150. When These Systems are Used “Simple” Boiler Installations ◦ Packaged Fire tube / Water tube Boilers (Steam / Hot Water) ◦ Single Burner ◦ One Fuel at a Time ◦ No Flue Gas Re-Circulation ◦ Upgrades from Previous MicroProcessor Based Systems Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 151. PLC Based Burner Management Systems PLC Based Features ◦ NFPA 8501, 8502 ◦ Watchdog timer ◦ UL 508 Certification Redundant Scanners Logic+ Message Center ◦ Shows program status ◦ Displays alarms ◦ Prompts operator Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 152. PLC System Basic Design Features Each PLC based burner management system should incorporate a number of design techniques which help detect and act upon unsafe failure modes which can occur in any microprocessor based system. These design features include the following: ◦ Critical Input Checking ◦ Critical output channel monitoring ◦ Electro-mechanical Master Fuel Trip (MFT) Relay ◦ Redundant Watchdog Timers ◦ Low Water Cut-out Monitoring During Blow Down Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 153. PLC Based System Capabilities Provision for Multiple Fuel Firing ◦ Capped gas input during curtailment ◦ Changeover from gas to oil at any load ◦ Simultaneous firing of waste and fossil fuels Redundant Scanners, change scanner with fuel Single or Multiple Burner Applications Integration of BMS with SCADA Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 154. PLC Based Operator Interfaces Features ◦ Clear Written Messages to indicate status, required operator interaction, trip/alarm indication ◦ High Visibility through two lines of display ◦ Messages reduce time consuming troubleshooting ◦ Prioritizes Messages First Out Alarms Warning / Alarm Messages Status Messages / Prompts Operator Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 155. PLC System Layout Door Mounted Lights / Pushbuttons Logic+ Message SWITCH SILENCE LIGHT Display PLC CPU I/O I/O I/O I/O COMBUSTION CONTROL SYSTEM FLAME AMPLIFIER (SINGLE / REDUNDANT) I/O EXPANSION I/O FIELD DEVICES Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 156. Benefits of PLC Based Systems Flexibility / Reliability ◦ Programming Software allows changes to system Choice of PLCs ◦ GE / Modicon / Allen Bradley / Koyo Choice of Flame Scanners ◦ PPC / Fireye / Honeywell / Iris / Coen Application Specific Quantity of Burners / Fuels is not restricted Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 157. When to Use PLC Based Systems “Complex” Boiler Installations ◦ Larger Packaged Units / Field Erected Units ◦ Multiple Burners ◦ Multiple Fuels, On-line Fuel Changeovers ◦ Flue Gas Re-Circulation ◦ Replace Existing Relay Logic Systems ◦ Requirement to maintain consistent control platform (spare parts, etc..) Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 158. BMS SCADA Interface BMS Systems can be integrated into a SCADA System ◦ Allows Remote Monitoring of Flame Status ◦ Allows Remote Control of BMS ◦ Events (ie.. Burner trip) can be routed to Historical Portion of SCADA for fault evaluation ◦ Burner Operation can be trended over time Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 159. BMS SCADA Interface Interface Methods: SCADA PC MODBUS COMMUNICATION PROTOCOL MODBUS COMMUNICATION Communication PROTOCOL Interface (If Necessary) PLC CPU I/O I/O I/O I/O BMS LOGIC+ SYSTEM FIREYE E110 SYSTEM Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 160. BMS SCADA Interface Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 161. Summary Benefits Associated with Sequential Start Up Automation and Burner Management Systems ◦ Help Improve plant safety ◦ Help qualify for reduced insurance cost ◦ Reduce Startup and Down Time with comprehensive alarming and diagnostics Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 162. Summary Review of Topics Discussed ◦ Sequential Start Up Automation, ◦ Objectives of Burner Management Systems ◦ BMS Design Considerations ◦ Basic BMS Logic ◦ Types of Burner Management Systems ◦ How BMS Systems can be integrated with Plant Wide SCADA Systems Workshop on Start Up and Commissioning Dr. Himadri Banerji MD EcoUrja, Ex Reliance and Tata www.ecourja.com
  • 163. SAFETY ISSUES THE WORK PERMIT SYSTEM (Reference Document : <<AIGA 011/04 >>) Presented by Dr Himadri Banerji EcoUrja www.ecourja.com
  • 164. Summary Acknowledgement This document is adopted from the European Industrial Gases Association document TP 10/04 – The Work Permit System, and acknowledgement and thanks are hereby given to EIGA for permission granted for the use of their document Presented by Dr Himadri Banerji EcoUrja www/ecourja.com
  • 165. The Work Permit System. What is it? A work permit system consists primarily of a standard procedure designed to ensure that potentially hazardous routine and non routine work on industrial installations can be carried out safely. The procedure should define the need for the following essential steps: Details of the necessary preparatory work Clear definition of responsibilities Appropriate training of the work force Provision of adequate safety equipment A formal work permit with or without attached specific checklists. This work permit: specifies the work to be accomplished and authorizes it to be started under the strict observance of consigned work and safety procedures After information and agreement of all other concerned parties (process, safety, customers, suppliers,…)
  • 166. The Work Permit System : When? For all non-routine works, For hazardous routine works not covered by procedures, When work is performed: by your employees and/or third parties
  • 167. The Work Permit System (1/2): For what kind of work? A work permit is required in case of: Potential oxygen deficiency or enrichment Potential flammable/explosive atmosphere Potential high temperature/pressure Potential hazardous chemicals, e.g.: toxic substances Confined space entry, e.g.: tanks, cold box, pit, normally closed vessels Bypassing or removing/altering safety devices or equipment Elevated works Introduction of ignited sources where not permanently allowed (fire permit), e.g.: open flame, welding, grinding, Electrical troubleshooting or repair on live circuits Maintenance or repairs in areas or to equipment or lines, containing or supposed to contain hazardous materials or conditions,
  • 168. The Work Permit System (2/2): For what kind of work? Or also in case of: Manual or powered excavations Use of mobile cranes Insulation or catalysts handling Use of adapters Product conversion of stationary or mobile or portable vessels and containers Temporary or permanent changes, alterations, modification of equipment or processes, Exposure to traffic, Exposure to moving/rotating machinery In proximity of vents, liquid of gas On process lines with gas release Etc..
  • 169. The Work Permit System : Why? 1. Because: In charge of the work, you don’t know everything about the site and the process around about the work Safety measures have to be prepared You cannot start the work without the OK of the production personnel or the customer or the supplier The production needs your OK in order to re-start the plant after your work is achieved 2. To obtain a safe as well as a quick and cost effective work
  • 170. The Work Permit System : Why? In order to define the scope of work for everyone concerned/involved by and during the work, the Work Permit must be prepared with: The person responsible for the work The person(s) in charge of the production, the customer or supplier, who will release the process before the work starts The other work bodies The person in charge of HSE measures
  • 171. The Work Permit System : How? Before issuing the Work Permit, you must: Describe the work to be done List all the specifications and drawings which are required Issue detailed planning with all involved entities Determine the logging and tagging procedures Fill-in together the work permit and sign, The start of the work must be authorized by production and/or user, The re-start of the process must take place after the work is finished.
  • 172. The Work Permit System : Review of Flowsheets, Drawings and Specification Purpose of the review is to ensure all key persons involved in job planning have a thorough understanding of the job. It should include: Process fluids and materials involved, Degree of isolation, Effect of other processes, Power supply isolation, Specialist advice, Location of underground services and pipes, Location of elevated power cables, Location of elevated pipelines and walkways, Purging and lock-out requirements, Pressure, Temperature, Valve identification, Equipment specification, Operating and maintenance instructions, Materials of construction and compatibilities
  • 173. The Work Permit System : Work site inspection Anyone involved and signing the Safe Work Permit must visit the work place in order: •To inspect the work area Neighbouring activities, site rules, overhead, underground, access, natural hazards (flood, rain, snow…), etc,.. •To identify potential hazards Flammable, oxygen, toxic substances, confined spaces, electricity, pressure, temperature, moving objects, traffic, falls/trips/slips, etc,..
  • 174. The Work Permit System : Development of Work Procedures Preparation of a detailed work procedure is essential to ensure the work will proceed safely in a planned and logical manner: Following requirements to be considered: Reference drawings, Timing of various operations, Details of any special equipment, Needs to inform local authorities, safety precautions and equipment, Emergency procedures, etc,.. The procedure should include: Logging and tagging procedures: Electricity, process fluids Instrumentation, utilities (water, air, oil,…) Depressurising, Draining, Venting, Purging, Flushing, Isolating, Atmosphere checking, Disassembly of equipment, Method of repair, Reassembly and installation, Quality control, Pressure and leak testing, Reinstatement of equipment, Hand-back procedure, etc..
  • 175. The Work Permit System : Example form Appendix 1 EIGA/IGC WORK PERMIT n° …….. Any attached document or log sheet ? YES NO HOW MANY ……….. List of attached documents ……………….……………………….…………..……………...……………………………………………….. 1. WORK ACTIVITY Plant / Unit :………………...……………….…………………………………………………………………………………………………………..………...… Description of work to be done………………....……..….………….…………….……………………………………………………………………….......… Permit valid from :………………………………………………………… Hours/date To :……………………………………………………………………. Hours/date Have all relevant departments/personnel been consulted ? YES NOT APPLICABLE 2. POTENTIAL HAZARDS & HAZARDOUS JOBS YES NO YES NO . Jobs performed by contractors or temporary workers . Maintenance or repairs in areas, or to equipment or lines, . Potential oxygen deficiency or enrichment containing or supposed to contain hazardous materials or conditions . Potential flammable / explosive atmosphere . Manual or powered excavations . Potential high temperature / pressure . Use of mobile cranes . Potential exposure to hazardous chemicals (toxic, reactive, . Insulation or catalyst handling acid, caustic….) . Use of adapters . Confined space entry . Product conversion of stationary or mobile or portable vessels . Bypassing or removing/altering safety devices and equipment and containers . Elevated work . Temporary or permanent changes, alterations, modifications of . Introduction of ignition sources where not permanently equipment or processes allowed (fire permit) . Exposure to traffic (road, mail) . Electrical troubleshooting or repair on live circuits . Exposure to moving / rotating machinery Others (state) ……………………..……...………………………………………………………………………… 3. SAFETY PRECAUTIONS YES NO YES NO YES NO . Draining . Remove hazardous materials . Standby man . Depressurising . Fresh air ventilation . Elevated work . Physical Isolation . Atmosphere analysis : . Contractors trained . Electrical Isolation . Oxygen . Eliminate ignition sources