Earned Value Management
Drexel University, Goodwin College CT431-120 Project Management
R. Gottardi, Instructor/Author                                    May 31, 2009
Some Definitions
• Planned Value, PV (BCWS): the portion
  of the approved total cost estimate during
  a given period
• Actual Cost, AC: the total of the direct &
  indirect costs incurred in accomplishing
  work on a task or project during a given
  period
                                               2
Project Tracking without Earned Value
                                         Project Performance

                                                      BCWS      Actual Cost


              200
              180
              160
              140
              120
$000




              100
              80
              60
              40
              20
               0
                     1    2    3    4         5        6            7         8     9     10    11    12
       BCWS          10   20   25   40        62       80           98        125   137   149   160   175
       Actual Cost   30   48   52   55        60       65           70        72
                                                            Weeks


       Conclusion: It looks like we are under budget. What’s missing?
                                                                                                            3
What’s Missing
• Any measure of how much work has been
  accomplished
• Earned Value: an estimate of the value of
  the physical work actually completed
• Can be
  – currency, e.g., $
  – Quantities, e.g., tons, yds3, SF, etc.
  – Any agreed upon value for the tasks
                                             4
How Can We Measure Progress?
• % complete of the tasks’ durations
• Rate of performance (RP): % complete actual/%
  compete planned
• Physical quantities (works for some tasks but not
  others)
   –   Tons of earth moved
   –   Cubic yards of cement poured
   –   Floors completed
   –   Sq ft completed
• Let’s use RP because it is common to many tasks &
  gives us a schedule related measure
                                                      5
Establish Earning Rules
Rule         Credit at Start         Credit at End

0/100                          0%                    100%

50/50                          50%                   50%

25/75                          25%                   75%

20/80                          20%                   80%

  Credit means the budgeted cost of work
    performed is included in the earned value
    calculation to the extent of the % indicated.
                                                            6
Earned Value Vs. Planned Value
                                      Project Performance

                                      PV(BCWS)   EV(BCWP)


           200
           180
           160
           140
           120
$000




                                                                            Schedule Variance
           100
                                                                            Behind Schedule
            80
            60
            40
            20
             0
                  1    2    3    4          5       6            7    8        9        10      11    12
       PV(BCWS)   10   20   25   40        62       80           98   125     137      149      160   175
       EV(BCWP)   28   60   62   70        72       80           82   92
                                                         Weeks


                                                                                                            7
Earned Value vs. Actual Cost
                                         Project Performance

                                                    Actual Cost     EV(BCWP)


             100
              90
                                                                                    Cost Variance ($)
              80                                                                    Under Budget
              70
              60
$000




              50
              40
              30
              20
              10
               0
                     1    2    3    4         5        6            7          8    9         10        11   12
       Actual Cost   30   48   52   55        60       65           70         72
       EV(BCWP)      28   60   62   70        72       80           82         92
                                                            Weeks

                                                                                                              8
Combine All Variables
                                            Project Performance

                                            PV(BCWS)        AC(Actual Cost)        EV(BCWP)


                  200
                  180
                  160
                                                                                                          PV
                  140
                  120
$000




                  100
                                                                                               EV
                  80
                  60                                                                AC
                  40
                  20
                   0
                         1    2    3    4              5          6           7           8         9          10    11    12

       PV(BCWS)          10   20   25   40             62        80           98         125        137        149   160   175
       AC(Actual Cost)   30   48   52   55             60        65           70          72
       EV(BCWP)          28   60   62   70             72        80           82          92
                                                                      Weeks
                                                                                                                                9
Variance Computations
•   Cost Variance (CV)=EV-AC
•   Schedule Variance (SV)=EV-PV
•   Negative values are unfavorable
•   Positive values are favorable



                                      10
Performance Indices
• Cost Performance Index (CPI)=EV/AC
• Schedule Performance Index
  (SPI)=EV/PV
• <1= unfavorable
• >1=favorable


                                       11
Earned Value
• Integrates schedule & cost data
• Explains causes of variances
• Encourages objective measurement of
  progress
• Measures performance


                                        12
Problem
• Given:
  • EV = $5,000
  • PV = $10,000
  • AC = $15,000
• Solve:
  •   CV =
  •   SV =
  •   CPI =
  •   SPI =
                   13
Problem
• Given:
  • EV = $5,000 = Earned Value
  • PV = $10,000
  • AC = $15,000
• Solve:
  •   CV =
  •   SV =
  •   CPI =
  •   SPI
                                 14
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000
  • AC = $15,000
• Solve:
  •   CV =
  •   SV =
  •   CPI =
  •   SPI =
                                        15
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value
  • AC = $15,000
• Solve:
  •   CV =
  •   SV =
  •   CPI =
  •   SPI =
                                        16
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BCWS
  • AC = $15,000
• Solve:
  •   CV =
  •   SV =
  •   CPI =
  •   SPI =
                                         17
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BCWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV =
  •   SV =
  •   CPI =
  •   SPI =
                                         18
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC
  •   SV =
  •   CPI =
  •   SPI =
                                         19
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000
  •   SV =
  •   CPI =
  •   SPI =
                                         20
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV =
  •   CPI =
  •   SPI =
                                            21
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV
  •   CPI =
  •   SPI =
                                            22
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000
  •   CPI =
  •   SPI =
                                            23
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI =
  •   SPI =
                                            24
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI = EV/AC
  •   SPI =
                                            25
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI = EV/AC = 5,000/15,000
  •   SPI =
                                            26
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI = EV/AC = 5,000/15,000 = .33
  •   SPI =
                                            27
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI = EV/AC = 5,000/15,000 = .33
  •   SPI = EV/PV
                                            28
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI = EV/AC = 5,000/15,000 = .33
  •   SPI = EV/PV = 5,000/10,000
                                            29
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BCWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI = EV/AC = 5,000/15,000 = .33
  •   SPI = EV/PV = 5,000/10,000 = .5
                                            30
Other Terms & Computations
• BAC: Budget at Completion: The
  original total budget for a project
• EAC: Estimate at Completion =
  BAC/CPI (CPI = Cost Performance Index)
• ETC: Estimate to Complete: EAC-AC
• Variance at Completion: BAC-EAC

                                       31
Earned Value
•   Title: Earned Value Management
•   Filename: Earned Value Management Lecture 2009eMY31
•   Author: Ron Gottardi
•   Author Affiliation: Drexel University, Goodwin College of
    Professional Studies
•   Course: CT431-120 Project management
•   Date: May 31, 2009
•   Copyright 2009 Ron Gottardi




                                                                32

More Related Content

Viewers also liked

AmyandSusan
AmyandSusanAmyandSusan
AmyandSusan
sgrobins
 
Question 3 – what have you learnt from
Question 3 – what have you learnt fromQuestion 3 – what have you learnt from
Question 3 – what have you learnt from
nushy1993
 
XING Q3 report 2012 english version
XING Q3 report 2012 english versionXING Q3 report 2012 english version
XING Q3 report 2012 english version
XING SE
 

Viewers also liked (19)

Wxig points update
Wxig points updateWxig points update
Wxig points update
 
AmyandSusan
AmyandSusanAmyandSusan
AmyandSusan
 
Hugps138
Hugps138Hugps138
Hugps138
 
Question 3 – what have you learnt from
Question 3 – what have you learnt fromQuestion 3 – what have you learnt from
Question 3 – what have you learnt from
 
No tlp Polisi
No tlp PolisiNo tlp Polisi
No tlp Polisi
 
SGGSWU Prospectus 2016-17
SGGSWU Prospectus 2016-17SGGSWU Prospectus 2016-17
SGGSWU Prospectus 2016-17
 
VW Santana Vista - Brochure
VW Santana Vista - BrochureVW Santana Vista - Brochure
VW Santana Vista - Brochure
 
33559
3355933559
33559
 
Focusing on the Threats to the Detriment of the Vulnerabilities
Focusing on the Threats to the Detriment of the VulnerabilitiesFocusing on the Threats to the Detriment of the Vulnerabilities
Focusing on the Threats to the Detriment of the Vulnerabilities
 
Freefixer log
Freefixer logFreefixer log
Freefixer log
 
Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"
Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"
Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"
 
Oppa (13)
Oppa (13)Oppa (13)
Oppa (13)
 
The Anatomy Of The Idea
The Anatomy Of The IdeaThe Anatomy Of The Idea
The Anatomy Of The Idea
 
01 introduction E-Commerce
01 introduction E-Commerce01 introduction E-Commerce
01 introduction E-Commerce
 
Jft 13-desktop-optical-power-meter-jfopt
Jft 13-desktop-optical-power-meter-jfoptJft 13-desktop-optical-power-meter-jfopt
Jft 13-desktop-optical-power-meter-jfopt
 
Google Ground Kiajánló
Google Ground KiajánlóGoogle Ground Kiajánló
Google Ground Kiajánló
 
Unit 1 the universe
Unit 1 the universeUnit 1 the universe
Unit 1 the universe
 
XING Q3 report 2012 english version
XING Q3 report 2012 english versionXING Q3 report 2012 english version
XING Q3 report 2012 english version
 
205180 cm with jde
205180 cm with jde205180 cm with jde
205180 cm with jde
 

Similar to Earned value management lecture 2009e my31

Similar to Earned value management lecture 2009e my31 (20)

SPICE MODEL of TPCA8004-H (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCA8004-H (Professional+BDP Model) in SPICE PARKSPICE MODEL of TPCA8004-H (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCA8004-H (Professional+BDP Model) in SPICE PARK
 
SPICE MODEL of TPCA8004-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPCA8004-H (Standard+BDS Model) in SPICE PARKSPICE MODEL of TPCA8004-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPCA8004-H (Standard+BDS Model) in SPICE PARK
 
SPICE MODEL of TPCM8002-H (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCM8002-H (Professional+BDP Model) in SPICE PARKSPICE MODEL of TPCM8002-H (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCM8002-H (Professional+BDP Model) in SPICE PARK
 
SPICE MODEL of TPCA8014 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPCA8014 (Standard+BDS Model) in SPICE PARKSPICE MODEL of TPCA8014 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPCA8014 (Standard+BDS Model) in SPICE PARK
 
SPICE MODEL of TPC8117 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPC8117 (Standard+BDS Model) in SPICE PARKSPICE MODEL of TPC8117 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPC8117 (Standard+BDS Model) in SPICE PARK
 
SPICE MODEL of TPC8A02-H (Professional+ZDSP Model) in SPICE PARK
SPICE MODEL of TPC8A02-H (Professional+ZDSP Model) in SPICE PARKSPICE MODEL of TPC8A02-H (Professional+ZDSP Model) in SPICE PARK
SPICE MODEL of TPC8A02-H (Professional+ZDSP Model) in SPICE PARK
 
SPICE MODEL of TPCA8014 (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCA8014 (Professional+BDP Model) in SPICE PARKSPICE MODEL of TPCA8014 (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCA8014 (Professional+BDP Model) in SPICE PARK
 
SPICE MODEL of TPCM8002-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPCM8002-H (Standard+BDS Model) in SPICE PARKSPICE MODEL of TPCM8002-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPCM8002-H (Standard+BDS Model) in SPICE PARK
 
SPICE MODEL of RN1417 in SPICE PARK
SPICE MODEL of RN1417 in SPICE PARKSPICE MODEL of RN1417 in SPICE PARK
SPICE MODEL of RN1417 in SPICE PARK
 
SPICE MODEL of RN1114FT in SPICE PARK
SPICE MODEL of RN1114FT in SPICE PARKSPICE MODEL of RN1114FT in SPICE PARK
SPICE MODEL of RN1114FT in SPICE PARK
 
SPICE MODEL of TPC8032-H (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPC8032-H (Professional+BDP Model) in SPICE PARKSPICE MODEL of TPC8032-H (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPC8032-H (Professional+BDP Model) in SPICE PARK
 
Free SPICE Model of S3K60 in SPICE PARK
Free SPICE Model of S3K60 in SPICE PARKFree SPICE Model of S3K60 in SPICE PARK
Free SPICE Model of S3K60 in SPICE PARK
 
SPICE MODEL of 2SK3906 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of 2SK3906 (Standard+BDS Model) in SPICE PARKSPICE MODEL of 2SK3906 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of 2SK3906 (Standard+BDS Model) in SPICE PARK
 
SPICE MODEL of RN1107FS in SPICE PARK
SPICE MODEL of RN1107FS in SPICE PARKSPICE MODEL of RN1107FS in SPICE PARK
SPICE MODEL of RN1107FS in SPICE PARK
 
SPICE MODEL of TPC8032-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPC8032-H (Standard+BDS Model) in SPICE PARKSPICE MODEL of TPC8032-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPC8032-H (Standard+BDS Model) in SPICE PARK
 
SPICE MODEL of 2SK3435 (Professional+BDP Model) in SPICE PARK
SPICE MODEL of 2SK3435 (Professional+BDP Model) in SPICE PARKSPICE MODEL of 2SK3435 (Professional+BDP Model) in SPICE PARK
SPICE MODEL of 2SK3435 (Professional+BDP Model) in SPICE PARK
 
SPICE MODEL of DTC123JM in SPICE PARK
SPICE MODEL of DTC123JM in SPICE PARKSPICE MODEL of DTC123JM in SPICE PARK
SPICE MODEL of DTC123JM in SPICE PARK
 
SPICE MODEL of TPC8110 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPC8110 (Standard+BDS Model) in SPICE PARKSPICE MODEL of TPC8110 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPC8110 (Standard+BDS Model) in SPICE PARK
 
Schedule variance = 0 and we’re a year late
Schedule variance = 0 and we’re a year lateSchedule variance = 0 and we’re a year late
Schedule variance = 0 and we’re a year late
 
SPICE MODEL of TPCA8014-H (Professional+BDSP Model) in SPICE PARK
SPICE MODEL of TPCA8014-H (Professional+BDSP Model) in SPICE PARKSPICE MODEL of TPCA8014-H (Professional+BDSP Model) in SPICE PARK
SPICE MODEL of TPCA8014-H (Professional+BDSP Model) in SPICE PARK
 

Recently uploaded

Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
amitlee9823
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Sheetaleventcompany
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
dlhescort
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
dollysharma2066
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
amitlee9823
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
amitlee9823
 

Recently uploaded (20)

Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdf
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 

Earned value management lecture 2009e my31

  • 1. Earned Value Management Drexel University, Goodwin College CT431-120 Project Management R. Gottardi, Instructor/Author May 31, 2009
  • 2. Some Definitions • Planned Value, PV (BCWS): the portion of the approved total cost estimate during a given period • Actual Cost, AC: the total of the direct & indirect costs incurred in accomplishing work on a task or project during a given period 2
  • 3. Project Tracking without Earned Value Project Performance BCWS Actual Cost 200 180 160 140 120 $000 100 80 60 40 20 0 1 2 3 4 5 6 7 8 9 10 11 12 BCWS 10 20 25 40 62 80 98 125 137 149 160 175 Actual Cost 30 48 52 55 60 65 70 72 Weeks Conclusion: It looks like we are under budget. What’s missing? 3
  • 4. What’s Missing • Any measure of how much work has been accomplished • Earned Value: an estimate of the value of the physical work actually completed • Can be – currency, e.g., $ – Quantities, e.g., tons, yds3, SF, etc. – Any agreed upon value for the tasks 4
  • 5. How Can We Measure Progress? • % complete of the tasks’ durations • Rate of performance (RP): % complete actual/% compete planned • Physical quantities (works for some tasks but not others) – Tons of earth moved – Cubic yards of cement poured – Floors completed – Sq ft completed • Let’s use RP because it is common to many tasks & gives us a schedule related measure 5
  • 6. Establish Earning Rules Rule Credit at Start Credit at End 0/100 0% 100% 50/50 50% 50% 25/75 25% 75% 20/80 20% 80% Credit means the budgeted cost of work performed is included in the earned value calculation to the extent of the % indicated. 6
  • 7. Earned Value Vs. Planned Value Project Performance PV(BCWS) EV(BCWP) 200 180 160 140 120 $000 Schedule Variance 100 Behind Schedule 80 60 40 20 0 1 2 3 4 5 6 7 8 9 10 11 12 PV(BCWS) 10 20 25 40 62 80 98 125 137 149 160 175 EV(BCWP) 28 60 62 70 72 80 82 92 Weeks 7
  • 8. Earned Value vs. Actual Cost Project Performance Actual Cost EV(BCWP) 100 90 Cost Variance ($) 80 Under Budget 70 60 $000 50 40 30 20 10 0 1 2 3 4 5 6 7 8 9 10 11 12 Actual Cost 30 48 52 55 60 65 70 72 EV(BCWP) 28 60 62 70 72 80 82 92 Weeks 8
  • 9. Combine All Variables Project Performance PV(BCWS) AC(Actual Cost) EV(BCWP) 200 180 160 PV 140 120 $000 100 EV 80 60 AC 40 20 0 1 2 3 4 5 6 7 8 9 10 11 12 PV(BCWS) 10 20 25 40 62 80 98 125 137 149 160 175 AC(Actual Cost) 30 48 52 55 60 65 70 72 EV(BCWP) 28 60 62 70 72 80 82 92 Weeks 9
  • 10. Variance Computations • Cost Variance (CV)=EV-AC • Schedule Variance (SV)=EV-PV • Negative values are unfavorable • Positive values are favorable 10
  • 11. Performance Indices • Cost Performance Index (CPI)=EV/AC • Schedule Performance Index (SPI)=EV/PV • <1= unfavorable • >1=favorable 11
  • 12. Earned Value • Integrates schedule & cost data • Explains causes of variances • Encourages objective measurement of progress • Measures performance 12
  • 13. Problem • Given: • EV = $5,000 • PV = $10,000 • AC = $15,000 • Solve: • CV = • SV = • CPI = • SPI = 13
  • 14. Problem • Given: • EV = $5,000 = Earned Value • PV = $10,000 • AC = $15,000 • Solve: • CV = • SV = • CPI = • SPI 14
  • 15. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 • AC = $15,000 • Solve: • CV = • SV = • CPI = • SPI = 15
  • 16. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value • AC = $15,000 • Solve: • CV = • SV = • CPI = • SPI = 16
  • 17. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BCWS • AC = $15,000 • Solve: • CV = • SV = • CPI = • SPI = 17
  • 18. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BCWS • AC = $15,000 = Actual Cost • Solve: • CV = • SV = • CPI = • SPI = 18
  • 19. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC • SV = • CPI = • SPI = 19
  • 20. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 • SV = • CPI = • SPI = 20
  • 21. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = • CPI = • SPI = 21
  • 22. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV • CPI = • SPI = 22
  • 23. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 • CPI = • SPI = 23
  • 24. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = • SPI = 24
  • 25. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = EV/AC • SPI = 25
  • 26. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = EV/AC = 5,000/15,000 • SPI = 26
  • 27. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = EV/AC = 5,000/15,000 = .33 • SPI = 27
  • 28. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = EV/AC = 5,000/15,000 = .33 • SPI = EV/PV 28
  • 29. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = EV/AC = 5,000/15,000 = .33 • SPI = EV/PV = 5,000/10,000 29
  • 30. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BCWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = EV/AC = 5,000/15,000 = .33 • SPI = EV/PV = 5,000/10,000 = .5 30
  • 31. Other Terms & Computations • BAC: Budget at Completion: The original total budget for a project • EAC: Estimate at Completion = BAC/CPI (CPI = Cost Performance Index) • ETC: Estimate to Complete: EAC-AC • Variance at Completion: BAC-EAC 31
  • 32. Earned Value • Title: Earned Value Management • Filename: Earned Value Management Lecture 2009eMY31 • Author: Ron Gottardi • Author Affiliation: Drexel University, Goodwin College of Professional Studies • Course: CT431-120 Project management • Date: May 31, 2009 • Copyright 2009 Ron Gottardi 32