Change Control
2 of 12
What is Change Control?
Change Control is the recording, assessing, authorising and implementation of changes
Changes are anything that alters the project baseline
Changes arise from Fixing Defects or Bugs – generally funded by project contingency
New Requirements – generally requiring additional funding
A bug found during the course of delivering a project may lead to a Problem Report
The problem will typically be investigated and a solution proposed
An Issue is a problem that cannot be resolved within the project team
Issues are escalated – initially to the project Sponsor – for resolution
A problem together with a solution will often lead to a Change Request
Implemented change request(s) require a Change Note describing the change
3 of 12
Problems
During the execution of tasks problems will arise
If within the scope of the task, they are generally fixed during the course of task execution
If outside the scope of the task the task owner may raise a Problem Report
An authority then decides whether to authorise work to investigate the problem
In some cases the authority will decide not to investigate and closes the PR
The authority is usually a Team Leader or Technical Authority or Project Manager
If deciding to investigate the authority will Assign the PR to a suitable person to investigate
The investigator first makes a rough assessment of the effort required to investigate
…giving the authority a means to assess the progress of the investigation
The investigator then investigates and devises and verifies a potential solution
4 of 12
Problem Reporting
Raise PR
Schedule
Investigation
Assign PR
Estimate
Analysis Effort
Devise
Solution
Verify
Solution
Raise CR
Close PRInvestigate?
Identify
Problem
State: New
State: Assess
State: Action
State: Closed
State: New
Y
N
The process is shown
graphically, along with the
workflow States
A Problem Reporting Tool
implements these States
Tools may define alternative States
Many Problem Reporting Tools are
available with varying capabilities,
but all are essentially databases
Use the same database for problem
reporting and change control to minimise
documentation and administration effort
Most problem reporting tools can be
setup in this manner
5 of 12
Issues
An Issue is a problem that cannot be resolved by the project team
Issues are escalated – initially to the project Sponsor – for assistance
Most problems should be resolvable by the project team, so Issues should be few in number
The term Issue Tracking System is also used in place of Problem Reporting Tool
Here, the term issue is used to mean problem, defect or bug
Issues can be managed using the same tool but take care to differentiate Issues for escalation
6 of 12
Changes
State: Assess
State: Action
State: New
State: Closed
State: Action
State: Review
Y
N
Y
N
Y
N
Impact Analysis
& Estimation
Schedule
Change
Implement
Change
Raise CN
Change
Issue Status
Close CR
Contract
Change?
Revise Contract
(& PO Release)
Review
Authorise
Change?
Customer
Review
Contract
Change?
Change
Review
Once a problem and potential solution exist,
a Change Request may be raised
There does not have to be a PR first
A CR is handled in a similar manner to a PR
as shown in this process diagram, starting
with impact analysis and implementation effort estimation
If the change is outside the agreed project scope of work, the
customer may be asked to fund the change, otherwise the
change will be funded by the project contingency
CR
7 of 12
Control
The authority decision steps are important for control of budget and timing
Spend is controlled by authorising the amount of effort and who undertakes the work
Problem and change task timing is controlled to optimise both work flow and spend
Typically, it is from early in the implementation phase where the control of change along
with the historical record is beneficial and worth the effort
As the number of problem reports and change requests increases it is often worth holding a
Change Control Meeting – at a frequency to suit the volume of PRs and CRs
Change Control Meetings involve all interested parties and are decision making meetings
The decisions are: Accept or Reject, When and Who for each PR and CR
Change Control should cover all aspects of the project in a unified manner
A Change Note documents what change was implemented and can include multiple CRs
8 of 12
Classification
Classification is often used to aid decision making
Severity and Priority are typically used but often with varying definitions: examples below
Severity Name Meaning
1 Critical A significant requirement is broken or blocking product use
2 Major A requirement is not implemented
3 Minor A requirement implementation may be improved
4 Nice to Have An out of scope improvement
WIBNIF (wouldn’t it be nice if) item
Priority Name Meaning
1 Immediate As soon as possible (and before priority 2 & 3)
2 Normal As scheduled (and after priority 1 and before priority 3)
3 Low After all other tasks
Severity 1 and 2 are always fixed; Severity 3 may be fixed if budget permits
Severity 4 are usually only addressed with customer direction and additional funding
9 of 12
Reporting
A standard format for reporting should be defined to avoid confusion and nugatory work
Problem Reports and Change Requests can easily number 100’s and often 1,000’s
Graphical reporting is recommended – use trends to indicate progress and completion
Most Problem Reporting tools include analysis and reporting which can provide a
breakdown of PR assignment and area of work to aid tasking and resource management
Forecasting capability is often missing or weak and this may need additional analysis
outside of the PR tool – fortunately almost all PR tools allow the PR list to be exported
10 of 12
Reporting Example
11 of 12
Cautions
Avoid more than one problem reporting and change control database on a single project
Multiple databases will as a minimum require administration overhead
At worst, multiple databases lead to confusion, nugatory work and mismatched expectations
The best problem reporting and change control databases link to code base, drawings and
the configuration management system and should be agreed before the project starts
Adopt the same definitions for severity and priority across all projects
and with all customers if possible
Don’t over complicate Change Control – a tool may offer ten severity levels and eight
priority levels but you probably do not need them all
Take care to differentiate Issues for escalation outside the project team
12 of 12
Author Profile
In my board role I led a team of 22 Project Managers and 5 Quality Engineers, and ensured Roke’s £79m
project portfolio delivered better than budget profit. I set-up and ran a virtual PMO and created REP,
the Roke Engineering Process, also managing the engineering tools to support it.
After 4 years as an electronics engineer for Siemens, achieving Chartered Engineer,
I moved into project management for 14 years, at Siemens and Roke Manor Research.
Successfully delivering Roke’s most challenging whole lifecycle product developments
on time and under budget led to a role as Director and board member for 6 years.
In 2013 I returned to hands-on project management as Programme Director at
Cambridge Consultants, founder member of the Cambridge Science Park.
Creator of the APM corporate accredited PM Excellence Programme,
I chaired a quarterly PM forum to share best practice and built a
supportive PM community. I coached seven PMs to RPP, five to PQ,
and all passed APMP.
These investments in PM professionalism led to a turn-around and
annual improvement in project results across a 400 project portfolio
and delivered an above budget performance in five consecutive years
with profits totalling £7.9m above budget.
Passionate advocate of PM professionalism, Fellow of the APM and
the IET and author of articles published in Project and PM Today.
Professional Development
Winning Project Work
Planning
Estimating
Risk Management
Earned Value Management
Change Control
Stakeholder Management
3 Steps to Professional Project Management: Case Study
ProjectManagementTopics

More Related Content

What's hot

Project Closing Process
Project Closing ProcessProject Closing Process
Project Closing ProcessNishant Munjal
 
PMBOK 6th Processes Flow Main Lines
PMBOK 6th Processes Flow Main LinesPMBOK 6th Processes Flow Main Lines
PMBOK 6th Processes Flow Main LinesSasan Hosseyni
 
Pmi - Project Management Professional (Pmp) Certification Study Guide
Pmi - Project Management Professional (Pmp)   Certification Study GuidePmi - Project Management Professional (Pmp)   Certification Study Guide
Pmi - Project Management Professional (Pmp) Certification Study Guiderobsonnasc
 
Managing Project Execution
Managing Project ExecutionManaging Project Execution
Managing Project Executionpajames36
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Agus Suhanto
 
PMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep PresentationPMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep Presentationscottdreynolds
 
Project Management Control
Project Management ControlProject Management Control
Project Management Controlahmad bassiouny
 
WaterFall Project Management Methodology
WaterFall Project Management MethodologyWaterFall Project Management Methodology
WaterFall Project Management MethodologyAnish Krishnan
 
4 p’s of management spectrum and the w5hh principle
4 p’s of management spectrum and the w5hh principle4 p’s of management spectrum and the w5hh principle
4 p’s of management spectrum and the w5hh principleMohammad Hafiz-Al-Masud
 
Project, Program & Portfolio Management
Project, Program & Portfolio ManagementProject, Program & Portfolio Management
Project, Program & Portfolio ManagementAnand Subramaniam
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Saad Merie
 
post project review
post project reviewpost project review
post project reviewVinold John
 
Planning in Software Projects
Planning in Software ProjectsPlanning in Software Projects
Planning in Software ProjectsJayakumar PP
 

What's hot (20)

Project Closing Process
Project Closing ProcessProject Closing Process
Project Closing Process
 
Pgmp Certification Overview
Pgmp Certification OverviewPgmp Certification Overview
Pgmp Certification Overview
 
PMBOK 6th Processes Flow Main Lines
PMBOK 6th Processes Flow Main LinesPMBOK 6th Processes Flow Main Lines
PMBOK 6th Processes Flow Main Lines
 
Pmi - Project Management Professional (Pmp) Certification Study Guide
Pmi - Project Management Professional (Pmp)   Certification Study GuidePmi - Project Management Professional (Pmp)   Certification Study Guide
Pmi - Project Management Professional (Pmp) Certification Study Guide
 
Final Project Closing
Final Project ClosingFinal Project Closing
Final Project Closing
 
Pmbok6 to 7 transformation
Pmbok6 to 7 transformationPmbok6 to 7 transformation
Pmbok6 to 7 transformation
 
Project quality management
Project quality managementProject quality management
Project quality management
 
Managing Project Execution
Managing Project ExecutionManaging Project Execution
Managing Project Execution
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
PMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep PresentationPMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep Presentation
 
Project Management Control
Project Management ControlProject Management Control
Project Management Control
 
WaterFall Project Management Methodology
WaterFall Project Management MethodologyWaterFall Project Management Methodology
WaterFall Project Management Methodology
 
4 p’s of management spectrum and the w5hh principle
4 p’s of management spectrum and the w5hh principle4 p’s of management spectrum and the w5hh principle
4 p’s of management spectrum and the w5hh principle
 
Project, Program & Portfolio Management
Project, Program & Portfolio ManagementProject, Program & Portfolio Management
Project, Program & Portfolio Management
 
Project management
Project managementProject management
Project management
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7
 
post project review
post project reviewpost project review
post project review
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
 
Planning in Software Projects
Planning in Software ProjectsPlanning in Software Projects
Planning in Software Projects
 
Prince2 Methodology
Prince2 MethodologyPrince2 Methodology
Prince2 Methodology
 

Similar to Change Control: 12 Steps to Effective Management

Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12Jason Uyder
 
Sas Presentation
Sas PresentationSas Presentation
Sas Presentationpats384888
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overviewcford1973
 
12 Terms You Should Know Project Management Fundamentals
12 Terms You Should Know Project Management Fundamentals12 Terms You Should Know Project Management Fundamentals
12 Terms You Should Know Project Management FundamentalsInsaf Ali Soomro PMP
 
Expanding PMO service- The ultimate Tetris challenge - Wellingtone | Future...
  Expanding PMO service- The ultimate Tetris challenge - Wellingtone | Future...  Expanding PMO service- The ultimate Tetris challenge - Wellingtone | Future...
Expanding PMO service- The ultimate Tetris challenge - Wellingtone | Future...Wellingtone
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"David Pedreno
 
Cassidy.jim
Cassidy.jimCassidy.jim
Cassidy.jimNASAPMC
 
MG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTMG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTKathirvel Ayyaswamy
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"David Pedreno
 
Project Management in Health and Human Services
Project Management in Health and Human ServicesProject Management in Health and Human Services
Project Management in Health and Human ServicesBrandon Olson
 
Critical success factors in effective project implementation
Critical success factors in effective project implementationCritical success factors in effective project implementation
Critical success factors in effective project implementationSk. Mohtasim Billah
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidyNASAPMC
 
Identifying a project in trouble and re-planning
Identifying a project in trouble and re-planningIdentifying a project in trouble and re-planning
Identifying a project in trouble and re-planningmfarbstein
 
Sony Ericsson Case Study
Sony Ericsson Case StudySony Ericsson Case Study
Sony Ericsson Case Studyguest8537cf
 
Chapter 3 Lecture Slides
Chapter 3 Lecture SlidesChapter 3 Lecture Slides
Chapter 3 Lecture Slidesdotesch
 

Similar to Change Control: 12 Steps to Effective Management (20)

Software Engineering I by hmftj
Software Engineering I by hmftj Software Engineering I by hmftj
Software Engineering I by hmftj
 
Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12
 
Sas Presentation
Sas PresentationSas Presentation
Sas Presentation
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overview
 
Executing Successful Projects
Executing  Successful  ProjectsExecuting  Successful  Projects
Executing Successful Projects
 
12 Terms You Should Know Project Management Fundamentals
12 Terms You Should Know Project Management Fundamentals12 Terms You Should Know Project Management Fundamentals
12 Terms You Should Know Project Management Fundamentals
 
Expanding PMO service- The ultimate Tetris challenge - Wellingtone | Future...
  Expanding PMO service- The ultimate Tetris challenge - Wellingtone | Future...  Expanding PMO service- The ultimate Tetris challenge - Wellingtone | Future...
Expanding PMO service- The ultimate Tetris challenge - Wellingtone | Future...
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"
 
Cassidy.jim
Cassidy.jimCassidy.jim
Cassidy.jim
 
MG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTMG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENT
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"
 
Project Management in Health and Human Services
Project Management in Health and Human ServicesProject Management in Health and Human Services
Project Management in Health and Human Services
 
Critical success factors in effective project implementation
Critical success factors in effective project implementationCritical success factors in effective project implementation
Critical success factors in effective project implementation
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidy
 
Identifying a project in trouble and re-planning
Identifying a project in trouble and re-planningIdentifying a project in trouble and re-planning
Identifying a project in trouble and re-planning
 
stopHorseTrading
stopHorseTradingstopHorseTrading
stopHorseTrading
 
Sony Ericsson Case Study
Sony Ericsson Case StudySony Ericsson Case Study
Sony Ericsson Case Study
 
Chapter 3 Lecture Slides
Chapter 3 Lecture SlidesChapter 3 Lecture Slides
Chapter 3 Lecture Slides
 
Project Management
Project ManagementProject Management
Project Management
 
Pmbok
PmbokPmbok
Pmbok
 

More from Russell Taylor BEng CEng FAPM FIET (7)

Winning Project Work
Winning Project WorkWinning Project Work
Winning Project Work
 
Stakeholder Management
Stakeholder ManagementStakeholder Management
Stakeholder Management
 
Planning
PlanningPlanning
Planning
 
Estimating
EstimatingEstimating
Estimating
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
PM Professional Development
PM Professional DevelopmentPM Professional Development
PM Professional Development
 

Recently uploaded

Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningCIToolkit
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...Pooja Nehwal
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptxAss.Prof. Dr. Mogeeb Mosleh
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxalinstan901
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 

Recently uploaded (20)

Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for Learning
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdfImagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 

Change Control: 12 Steps to Effective Management

  • 1. 1 of 12 Change Control
  • 2. 2 of 12 What is Change Control? Change Control is the recording, assessing, authorising and implementation of changes Changes are anything that alters the project baseline Changes arise from Fixing Defects or Bugs – generally funded by project contingency New Requirements – generally requiring additional funding A bug found during the course of delivering a project may lead to a Problem Report The problem will typically be investigated and a solution proposed An Issue is a problem that cannot be resolved within the project team Issues are escalated – initially to the project Sponsor – for resolution A problem together with a solution will often lead to a Change Request Implemented change request(s) require a Change Note describing the change
  • 3. 3 of 12 Problems During the execution of tasks problems will arise If within the scope of the task, they are generally fixed during the course of task execution If outside the scope of the task the task owner may raise a Problem Report An authority then decides whether to authorise work to investigate the problem In some cases the authority will decide not to investigate and closes the PR The authority is usually a Team Leader or Technical Authority or Project Manager If deciding to investigate the authority will Assign the PR to a suitable person to investigate The investigator first makes a rough assessment of the effort required to investigate …giving the authority a means to assess the progress of the investigation The investigator then investigates and devises and verifies a potential solution
  • 4. 4 of 12 Problem Reporting Raise PR Schedule Investigation Assign PR Estimate Analysis Effort Devise Solution Verify Solution Raise CR Close PRInvestigate? Identify Problem State: New State: Assess State: Action State: Closed State: New Y N The process is shown graphically, along with the workflow States A Problem Reporting Tool implements these States Tools may define alternative States Many Problem Reporting Tools are available with varying capabilities, but all are essentially databases Use the same database for problem reporting and change control to minimise documentation and administration effort Most problem reporting tools can be setup in this manner
  • 5. 5 of 12 Issues An Issue is a problem that cannot be resolved by the project team Issues are escalated – initially to the project Sponsor – for assistance Most problems should be resolvable by the project team, so Issues should be few in number The term Issue Tracking System is also used in place of Problem Reporting Tool Here, the term issue is used to mean problem, defect or bug Issues can be managed using the same tool but take care to differentiate Issues for escalation
  • 6. 6 of 12 Changes State: Assess State: Action State: New State: Closed State: Action State: Review Y N Y N Y N Impact Analysis & Estimation Schedule Change Implement Change Raise CN Change Issue Status Close CR Contract Change? Revise Contract (& PO Release) Review Authorise Change? Customer Review Contract Change? Change Review Once a problem and potential solution exist, a Change Request may be raised There does not have to be a PR first A CR is handled in a similar manner to a PR as shown in this process diagram, starting with impact analysis and implementation effort estimation If the change is outside the agreed project scope of work, the customer may be asked to fund the change, otherwise the change will be funded by the project contingency CR
  • 7. 7 of 12 Control The authority decision steps are important for control of budget and timing Spend is controlled by authorising the amount of effort and who undertakes the work Problem and change task timing is controlled to optimise both work flow and spend Typically, it is from early in the implementation phase where the control of change along with the historical record is beneficial and worth the effort As the number of problem reports and change requests increases it is often worth holding a Change Control Meeting – at a frequency to suit the volume of PRs and CRs Change Control Meetings involve all interested parties and are decision making meetings The decisions are: Accept or Reject, When and Who for each PR and CR Change Control should cover all aspects of the project in a unified manner A Change Note documents what change was implemented and can include multiple CRs
  • 8. 8 of 12 Classification Classification is often used to aid decision making Severity and Priority are typically used but often with varying definitions: examples below Severity Name Meaning 1 Critical A significant requirement is broken or blocking product use 2 Major A requirement is not implemented 3 Minor A requirement implementation may be improved 4 Nice to Have An out of scope improvement WIBNIF (wouldn’t it be nice if) item Priority Name Meaning 1 Immediate As soon as possible (and before priority 2 & 3) 2 Normal As scheduled (and after priority 1 and before priority 3) 3 Low After all other tasks Severity 1 and 2 are always fixed; Severity 3 may be fixed if budget permits Severity 4 are usually only addressed with customer direction and additional funding
  • 9. 9 of 12 Reporting A standard format for reporting should be defined to avoid confusion and nugatory work Problem Reports and Change Requests can easily number 100’s and often 1,000’s Graphical reporting is recommended – use trends to indicate progress and completion Most Problem Reporting tools include analysis and reporting which can provide a breakdown of PR assignment and area of work to aid tasking and resource management Forecasting capability is often missing or weak and this may need additional analysis outside of the PR tool – fortunately almost all PR tools allow the PR list to be exported
  • 11. 11 of 12 Cautions Avoid more than one problem reporting and change control database on a single project Multiple databases will as a minimum require administration overhead At worst, multiple databases lead to confusion, nugatory work and mismatched expectations The best problem reporting and change control databases link to code base, drawings and the configuration management system and should be agreed before the project starts Adopt the same definitions for severity and priority across all projects and with all customers if possible Don’t over complicate Change Control – a tool may offer ten severity levels and eight priority levels but you probably do not need them all Take care to differentiate Issues for escalation outside the project team
  • 12. 12 of 12 Author Profile In my board role I led a team of 22 Project Managers and 5 Quality Engineers, and ensured Roke’s £79m project portfolio delivered better than budget profit. I set-up and ran a virtual PMO and created REP, the Roke Engineering Process, also managing the engineering tools to support it. After 4 years as an electronics engineer for Siemens, achieving Chartered Engineer, I moved into project management for 14 years, at Siemens and Roke Manor Research. Successfully delivering Roke’s most challenging whole lifecycle product developments on time and under budget led to a role as Director and board member for 6 years. In 2013 I returned to hands-on project management as Programme Director at Cambridge Consultants, founder member of the Cambridge Science Park. Creator of the APM corporate accredited PM Excellence Programme, I chaired a quarterly PM forum to share best practice and built a supportive PM community. I coached seven PMs to RPP, five to PQ, and all passed APMP. These investments in PM professionalism led to a turn-around and annual improvement in project results across a 400 project portfolio and delivered an above budget performance in five consecutive years with profits totalling £7.9m above budget. Passionate advocate of PM professionalism, Fellow of the APM and the IET and author of articles published in Project and PM Today. Professional Development Winning Project Work Planning Estimating Risk Management Earned Value Management Change Control Stakeholder Management 3 Steps to Professional Project Management: Case Study ProjectManagementTopics