CONTENTS
1. INTRODUCTION II
2. GENERALNOTES IV
3. PRICING PREAMBLE IX
4. SPECIFICATIONS XXXI
5. SAMPLE PRELIMINARIES BILL XLIV
6. B.S.R. 1 TO 89
7. BASIC MATERIAL PRICES PRICE LIST P1TO P29
II
INTRODUCTION
The Building Schedule of Rates, (abbreviated as B.S.R.) has been prepared based on work
norms generally adopted for Building Construction work with eight hour labour input. The
rates include an over-head and profit margin of 22%. The rates are intended to be adopted in
pricing an Engineering estimate for the Construction, Maintenance or Additions and
Improvements to a Building.
The item description of the B.S.R. has been drafted with a view to directly incorporated in to
a Bill of quantities which in turn will be used as a bidding document for measure and pay
type contract along with specifications, drawings etc.
The Preamble Notes which include General Preamble Notes and Pricing Preamble Notes
indicate the basis upon which the each and every trade item of the B.S.R. has been arrived at;
there fore same preamble notes shall be attached to the B.O.Q. in the event of B.O.Q. items
been derived from the B.S.R. The abbreviations B.S.R. and B.O.Q. has been used inter-alia to
facilitate the same notes been directly adopted to the B.O.Q.
For any clarifications or suggestions please feel free to communication with the Director-
Engineering of the Western Provincial Council on phone/ Fax 2675438 or e-mail
Please note that each and every B.O.Q. shall consist of the following documents
a) General Notes
b) Pricing Preamble
c) The B.O.Q. it self
Please refer clause 1 of the General notes for the definition of B.O.Q.
Data relating to B.S.R. trade items.
01. The approved rates for the following trade items listed in the following table are
meant for single storied (Ground floor only) buildings.
Hence, allowances to be made in the rates for lift in respect of work on upper floors.
The percentages indicated in the Table below should be added to obtain the rates
applicable to the upper floors.
02. Following conversion factors should apply for the rates when it is necessary to
convert from the Imperial Units to Metric.
Trade Item Unit First Floor Second Floor Third Floor
Formwork (
s)
1% 2% 3%
Plastering (Sqrs) 5% 10% 15%
Floor Tiling (Sqrs) 2% 4% 6%
Wall Tiling (Sqrs) 2% 4% 6%
Roof Calicut Tile (Sqrs) 3% 6% 9%
Roof asbestos (Sqrs) 3% 5% 7%
Ceiling Works (Sqrs) 3% 5% 7%
Painting (Sqrs) 3% 6% 9%
Rendering (Sqrs) 4% 7% 10%
Block work (Sqrs) 3% 5% 7%
III
Conversion Imperial to Metric factor (1foot x 0.3048 = metre)
To convert Rate per To Rate per Multiply the Present Rate by
Cube M3 0.353
Square M2 0.108
Sq.ft. M2 10.764
L.ft. M 3.281
03. IRON and STEEL gauge systems
Standard Wire Gauge. Birmingham Wire Gauge
No. SWG BWG
mm inch mm inch
20 0.914 0.036 0.996 0.0392
18 1.219 0.048 1.257 0.0495
16 1.626 0.064 1.588 0.0625
04. Units
To convert “Litres to “Galloons” multiply by 0.2205
“Miles to “Kilometers” multiply 1.6090
“Kilo to “Pounds” multiply by 2.2050
05. Steel
Dia. Mm Dia. Inch Normal Weight
Kg per meter
25 1 3.854
20 3/4 2.466
16 5/8 1.579
12 1/2 0.888
10 3/8 0.617
6 1/4 0.222
IV
GENERAL NOTES
1) The preamble notes which include General notes, Pricing Preamble and B.O.Q. are
collectively referred to herein as the Bills Of Quantities and shall jointly constitute the
Bills Of Quantities referred to in the Conditions Of Contract. The specifications and
the Drawings are to be read in conjunction with the Bill Of Quantities.
2) The Bills Of Quantities have been prepared generally in accordance with the
principles laid down in the Method of measurement of Building works (First
Revision) SLS 573:1999 published by Sri Lanka Standards Institution and rates shall
include for everything required for completion of each item of work in accordance
with the specifications and drawings. The relevant clause of this preamble notes shall
be deemed to apply equally to work subsequently ordered for execution by the Bidder,
either under Provisional Sum orders or variation orders, except where specifically
varied therein.
3) The works as executed will be measured for payment in accordance with the method
adopted in the Bill Of Quantities and under the item as therein set forth. The net
measurement or weight of the finished work in place will always be taken, and except
where otherwise stated or where separate items are provided, no allowance will be
made for cutting, waste, laps, circular works, etc., and no deductions will be made for
grout nicks, joggle holes, rounded arises or for shrinkage for fitting ironwork and the
like.
Payment will be made for only those materials, which are specified and permanently
installed in the works to the approval of the Engineer. Construction materials supplied
and delivered to the site by the bidder which become surplus to the requirements of
the works shall become the property of the bidder who shall reimburse the Employer
any money that was paid to the Bidder for the Supply and delivery to the site of the
surplus materials.
4) Unit Rates and extensions shall be given in Sri Lankan Rupees to a maximum of two
significant places of decimals.
5) Inspection of site
Bidders are requested to visit the site to acquaint themselves with all existing
conditions, and with the nature and extend of work to be done under the contract as no
extras will be allowed on the plea of want of information due to neglect of their part
in this regard.
V
Hence bidders are advised to inspect the site and acquaint themselves regarding the
following in addition to any other information that may be required.
1. Extent and nature of the work to be done
2. Site conditions
3. Storage facilities etc.
4. Transport facilities.
5. Weather conditions in the locality
6. Limitation of working time
7. Transporting and handling materials etc., including security clearances.
6) Type of Contract
The contract shall be a measure and Pay fixed Rate Contract
7) Quality of Materials & General Standards of Works
All materials used in the work shall be the best quality of their respective kinds as
specified in the B.O.Q. , the “Particular Specification” or in the General specifications
(i.e the specifications listed in the bidding document) and shall obtain the same from
manufacturers’ , agents or suppliers approved by the Engineer and shall comply
strictly with the test prescribed herein or in the standard specifications (Both General
or Special). When such specifications or tests are not laid down in the said
specifications the material and works shall comply with the latest issue of the relevant
British Standards or other standards approved by the Engineer.
Where trade names, Brands and/or catalogue numbers are referred to; this is done in
order to establish a standard, quality, or other reference benchmark and sole
preference for any manufacturer is not intended. Similar items may be used, provided
they are equivalent and provided the characteristics of type, quality, appearance,
finish, Method of Construction and/or performance are proved by the Bidder to be not
less than specified and provided also that the approval is first obtained from the
Engineer.
Where the Bidder wishes to use materials or components etc. obtained from
manufacturers other than those mentioned in these specifications or on lists of
approved manufacturers, it shall be incumbent upon him to prove to the complete
satisfaction of the Engineer that the products which he proposes to substitute are equal
in quality and appearance to those mentioned or described in the specifications, and
that the manufacturer is a reputable business of long standing, producing quality
products.
Unless otherwise stated, the cost of the tests required by this specification or the
relevant British or other approved Standards shall be deemed to be including in the
contract sum and rates.
Test certificates covering all materials for which certificates are required and are
supplied for the works shall be submitted to the Engineer for approval.
VI
No materials shall be used in the works unless the same has been approved by the
Engineer.
Approval by the Engineer of materials inspected by him or acceptance by the
Engineer of certificates of Tests in lieu of inspection shall vitiate the right of the
Engineer to reject after delivery to site or incorporation in the works, material found
to be unsuitable or not in accordance with this specification.
Before ordering materials of any description, the contractor shall submit, for the
approval of the Engineer the names of the manufacturers or suppliers proposed, and
shall afterwards send to the Engineer, copies in duplicate of the orders placed by the
contractor for the said materials.
8) Units and Extension of Bill Of Quantities
All sizes and quantities have been entered in the Bills Of Quantities in Metric
/Imperials Units. Figures involving decimals, including sums of money are written in
the British tradition, namely, with a full stop in the decimal position and commas
between each successive group of three digits to the left of the decimal position.
9) Rates and Sums to be for Work Complete
Notwithstanding any limits which may be implied by the wording of the individual
items and/or explanation in this preamble it is to be clearly understood by the Bidder
that the rates and sums which he enters in the Bills Of Quantities shall be for the
works finished complete in every respect, he shall be deemed to have taken full
account of all requirements and obligations, where expressed or implied, covered by
all parts of the contract, and to have priced the items herein accordingly. The rates and
sums must therefore include for all incidental and contingent expenses and risks of
every kind necessary to construct. Full allowance shall be made in the rates and/or
sums against the various items in the Bills Of Quantities for all costs involved in the
following inter-alia, which are referred to and/or specified herein except where
separate are provided.
1. All site investigations, which may be necessary;
2. All setting Out and Survey work;
3. Temporary fencing, watching, and lighting;
4. Paying fees and giving notice to authorities;
5. Payment of all patent rights and royalties;
6. Reinstatement of the site;
7. Safety precautions and all measures to prevent and suppress fire and other
hazards;
8. Interference to the works by persons, vehicles, and the like who may use
the existing facilities;
9. Works in connection with the protection and safety of adjacent structures;
10. Supplying, Maintaining and removing on completion Contractor’s own
accommodation, Offices, stores, workshops, Transport, Welfare services
VII
and all charge in connection therewith; except those for which a separate
BOQ item is provided;
11. Working in the dry except where otherwise permitted by the specification;
12. Maintaining internal roads;
13. The supply, Inspection, sampling and testing of materials and of the works
under construction, including the provision and use of equipment;
14. Except where separate items are provided for bringing construction plant
to the site and removing on completion, for providing, transporting to site,
setting to work operating (including all fuel and consumable stores),
maintaining and removing from the site upon completion all construction
plant and equipment necessary for the execution of the work, including the
cost of all tests and other requirements in respect to such plant and
equipment;
15. The recruitment, bringing to and from the site accommodating and feeding
and all incidental costs and expenses involved in the provision of all
necessary skilled and unskilled labour and supervision, except for whom a
separate BOQ item is provided;
16. All statutory taxes and levy, surcharges etc. including stamp duty payable
on the contract, which will have to be borne by the Bidder.
17. Establishment charges, Overhead Charges and profit.
No claim will be considered for further payment in respect of any work or
method of execution, which may be described in the contract or is inherent in
the construction of the work and detailed on the drawings on account of
1. Any omission from the wording of the items or from a clause in the
preamble or
2. No mention of such work or method of execution having been in the
preamble
10) Rates and Sums to Bear Proper Relation to work Described
The rates and sums entered by the Bidder against all items in the Bills Of Quantities
must bear a proper relationship to the cost of carrying out the work described in the
contract; all on costs and similar charges which are applicable to the contract as a
whole are to be spread over all the rates in the Bills Of Quantities, whilst those which
are applicable only to particular sections of the contract are only to be spread over
items to which these sections refer.
However, the Bidder shall ascertain the exact nature and extent of work to be
performed with reference to the Drawings, Specifications and Conditions of Contract
as the case may be.
11) Provisional Sum Items
Provisional sums will be dealt with as provided for in the Conditions Of Contract.
Provisional sums are represented by the words “Provisional Sum”, or “PS” entered
under the description.
12) “Provisional Quantity” , “Lump Sum” & “ Items”
VIII
Certain items in the Bills Of Quantities are designated as “ Provisional Quantities” or
“Lump sum” or merely as an “Item” in the description column.
“Provisional Quantities” may used to indicate that the quantities for the work covered
by such items are “provisional”, or that the provision of such facilities as are
described in the item may not in the event be required under the contract. All items so
designated will be used only at the direction and discretion of the Engineer, and if not
used either wholly or in part shall, as to the amount not used, be deducted from the
Contract Price.
Where such items are designated as of a “Lump Sum” or “Item”, the Bidder shall
enter a lump sum, which shall be the price for the work if executed, as distinct from a
“Provisional Sum” as defined herein. No claim will be entertained in respect of
overhead charges or any other costs, which may allegedly result from the omission of
all, or part of the work covered by such “Provisional Quantity” or “Lump Sum” Items.
13) Day Works Schedules
For a work of a minor or incidental nature for which a realistic rate analysis may not
be possible to arrive at the Engineer may instruct that portion of the work to be
executed on a day works schedule, provided a Day work schedule is included in the
contract.
14) Payment of Items in a Monthly Basis
Payment under items, which are measured on a monthly basis, will not be certified by
the engineer until the facilities described in the items and the Specification has been
provided to the satisfaction of the Engineer. Payment will continue until such time as
the Engineer shall signify that facilities are no longer required.
15) Protection Of Work and Clearing upon Completion
The Bidder shall allow, in his rates, for protection of completed work from
subsequent operations, making good all damage to complete work, for clearing away
all rubbish as it accumulates, and leaving the site in a tidy condition to the satisfaction
of the Engineer.
16) The Unit and Lump Sum prices of the Bill Of Quantities (referred to as the contract
rates) shall, except in so far as is otherwise provided for under the contract, be
deemed to cover all obligations set out in the contract, and all matters or things
necessary for the proper completion and maintenance of the works, and shall be fixed
and binding upon the Bidder.
17) Unit Prices when applied to the quantity of work performed under the contract shall,
and other sums specifically determined under the Provisions of the Contract,
constitute full remuneration to the Bidder under the contract.
18) The quantities set out in the Bill Of Quantities are provisional and cover the
approximate scope of the work which is anticipated that the contractor may be
required to perform. The actual quantities to be used for final measurement purposes
will be determined by the Engineer by measurement of the work completed by the
Bidder.
IX
19) Abbreviations
Abbreviations used in this Bill Of Quantities denote the following.
Sqr - Square
Ft - Feet
Ft2 - Square feet
m - metre
m2 - square metre
m3 - cubic metre
mm - milli metre
cm - centi metre
kg - kilogramme
h - hour
Nr - Number (to indicate a quantity)
No. - Number(to indicate an item number, page number etc)
B.O.Q. - Bill Of Quantities
Ele. - Elevation
G.L. - Ground Level
G.W.T. - Ground Water Table
c/c - center to center
@ - each
Gr - Grade
Approx - approximately
Thk. - thick
R.C.C. - Reinforced Cement Concrete
M.S. - Mild Steel
T.S. - Tor Steel
R - Mild Steel
Y/T - Tor Steel
C.I. - Cast Iron
W.I. - Wrought Iron
F/w - Formwork
R/F - Reinforcement
Wk - Week
Mon - Month
L.day - Labour day
MM - Man Month
Rs. - Sri Lanka Rupees
Cts. - Cents
X
PRICING PREAMBLE
Unless otherwise specified in the respective trade sections, the following pricing
preamble from 1 to 30 shall be inclusive for respective trades.
01.Demolition
Rates for Demolition shall include demolishing, dismantling and removing etc. with
the minimum damage to the material in the process of dismantling, temporary
supporting and protecting existing work and adjacent properties against damage, dust
and weather and stacking all serviceable materials as directed and disposal of debris
from site including spraying water periodically to reduce the amount of dust.
All serviceable materials in demolished structures shall be the property of the Client.
Necessary approvals to be taken from suitable authority prior to disposal of
demolished parts.
01.Excavation and Earth Work
Rates for Excavation & Earth Work shall include:
1) Excavation in all Material except Rock
The rate and prices for excavations shall be for all types of material encountered
except rock including ground conditions above or below water level. The Bidder
must make due allowance for the possibility of permission not being granted to
the use of explosives for blasting and other operations.
a) For structures, volume of material excavated measured as a product of the
horizontal area of the base of permanent works to be constructed and the
mean depth below ground level, or measured as the volume to be occupied
by permanent work below ground level, whichever is the greater.
In no case shall any of the following quantities be included in the
measurement for payment.
I. Quantity outside the vertical planes of neat outline of foundation
structures unless shown otherwise on the drawings.
II. Quantity of excavation and/or backfill for water supply pipe lines,
sewer pipe lines, and storm drainage except as allowed for in pipe
line construction as specified.
III. Quantity of any excavation performed prior to the taking of
measurements of the undisturbed natural ground.
XI
IV. Quantity of any material re-handled, except where the drawings
indicate or the Engineer directed the excavation after embankment
has been placed.
V. Removal of slides, cave-ins, silting or filling due to the action of
the elements or weather and/or carelessness of the Bidder.
b) For unsuitable material, volume of excavated material shall be measured
as volume of material (below base of the permanent works) directed to be
removed by the Engineer.
No allowance is made for bulking or for any extra transport required due to
bulking. The rates shall include, if separate items are not provided but not by
way of limitation for;
a. Excavation to the correct depth and preserving the bottoms of excavations in a
state suitable for the reception of concrete or other foundation work, and no
payment will be made for any concrete any bedding required for filling over
excavated volumes or disturbed areas to the net dimensions as indicated on the
Drawings.
b. Any additional excavation required for shuttering, working space, temporary
or permanent shoring, as subsequent refilling and ramming and disposal of
surplus and back fills behind structures.
c. Provision of storage areas for the temporary storage of any material required
for back filling which cannot be stored alongside the excavation for any
reason, together with the cost of transporting, loading including disposal of
surplus and unloading such material and all other charges incurred in this
respect.
d. Trimming the bottoms of excavations including bottoming to falls and
trimming to sloping surfaces where required or indicated on the Drawings.
e. Taking all precautions by supporting faces of excavation to ensure the safety
of the workmen and to prevent damage to adjacent walls, building and all
other structures and services, including permanent and/or temporary shoring of
trenches.
f. Keeping the site and trenchers and all other excavations free from water from
whatever because arising.
g. For clearing any scrub or other vegetable growth including all trees and for
disposing of the whole of the cleared material to tip provided by the
contractor.
h. All temporary and permanent measures required to protect and support all
existing pipes cables and services, including all chambers, gullies and
foundations thereto, or repair or replace them should they become damaged
due to the contractor’s activities.
i. All barriers, lighting, warning signs and any other measures necessary to
ensure complete safety around the area of works.
XII
j. Reinstatement except where separate items are included.
2) Excavation in Rock
Excavation in rock, which shall, in all cases, be measured extra over measurement
under 1(a) or 1(b) above by volume from the level at which rock is encountered.
For work described under 1(a) and 1(b), measurement shall be as specified therein
3) Fill
Fill shall be measured as the net volume above ground level of the permanent
earthwork to the detentions shown on the Drawings or ordered by the Engineer,
irrespective of source of material. The rate shall include for selection, handling,
placing, compaction of excavated or imported material and cost of control and
material selecting tests (field and laboratory). Costs incurred in connection with
the remedial work ordered by the Engineer consequent to the results of control
tests falling below the minimum specified shall be borne by the Bidder.
Rate for Hard Earth Filling shall include
1. Filling in layers, (not more than 1'0") well ramming and consolidating.
2. The earth shall be free of vegetation, roots, boulders easily decomposable
materials, chemicals, industrial waste, plastic etc.
3. The maximum size of particle shall not exceed 75mm.
4. The earth shall be well graded and contain silt and clay (fines) not more
than 30%.
02.Clearing Site
Removal of roots and growth of every description, removing top soil up to a depth of
6" (150mm) and extended up to 10'0" (3 Meter) beyond the outer walls of the
proposed structure and carting away the waste materials from the site where directed.
Existing trees or other plants shall not be removed or cut without instructions from
suitable Authority.
Trees to be retained shall be protected from damage of any sort.
03.Concrete
THE RATES FOR CONCRETE ARE TO INCLUDE FOR
a. All costs incurred in determining the mixes to satisfy the specification(including
any admixtures);
XIII
b. Supplying all material (including any admixtures), storing, mixing, transporting,
placing and compaction (whether by hand or vibration);
c. Excavation as required below previously filled levels and back filling (except
where separate items are provided)
d. Roughening the surface of previously executed work as required in order to
provide the necessary bond with new concrete;
e. Achieving specified tolerance;
f. Forming sloping, falls and the like;
g. Forming holes or boxing out for pipes, bolts, frames for covers and other steel
work;
h. Building in cable conduit, pipes, junction boxes etc.
i. Forming 25mm chamfers an all external arises to exposed concrete;
j. Forming all construction joints, keys, stop ends, temporary stops and shuttering of
other than permanently exposes faces( except where separate items are provide)
k. Curing the concrete and all measures to protect freshly poured concrete from
direct sunlight and wave action;
l. Toweling, rubbing down etc. and making good the concrete surfaces to provide
the specified finishes;
m. The cost of control testing throughout the period of concreting and for the testing
of concrete and remedial work ordered by the Engineer consequent to the results
of control tests falling below the minimum specified;
n. Overtime working to maintain continuity of casting;
o. A daily return to the Engineer showing the quantities of cement and the volume of
concrete placed and compacted in position, of each class of concrete in each
section of the works and temporary works.
The measurement of concrete shall be by cubic metre, square metre or linear metre of
completed structure. Where volumetric measure is used, no deductions will be made
for channels, recesses or rebates less than 600mm girth for splays or chamfers less
than 300mm measured on the splay nor for holes or ducts formed in the concrete less
than 1m girth. Fillets less than 300mm on the splay will be measured.
04.Form work
Rates for Form Work shall include, necessary boarding, supporting, erecting, framing,
cutting angles, striking or removal, cleaning and wetting.
Form work is measured in same order as the concrete items.
Form work is measured as the nett contact surface measurement between concrete and
form work.
(a). Form work to columns and beams is given as a girth measurements.
(b). (i). Form work for footing, column, beams, lintel, walls, and slabs are of
15mm thick ply-boards.
(ii). Slab thickness up to 4", soffit form work should be 3/4" thick
minimum size planks and less than 3/4" thickness is not allowed.
XIV
(iii). Slab thickness over 4", soffit form work should be of 1" thick
minimum planks sizes and less than 1" thickness is not allowed.
(iv). Sides of form work (columns, beams and slabs) 1" thick minimum and
less than 1" thickness is not allowed.
(v). Soffit of form work (beam) 1 1/4" thick minimum less than 1 1/4"
thickness is not allowed.
In case of timber form work the size of material shall comply to 5.2.1.1 and
the size of props and prop interval shall be as 5.2.4.
05.Reinforcement
The rates for steel bar and steel fabric reinforcement shall include for supplying,
transporting, storing, clearing bending, all labour in working, distribution to the
various parts of the works, fixing in position and supporting and for the use of binding
wire and for welding where indicated.
The unit of measurement for steel reinforcement is the Kilogram (kg.) and the weight
of steel has been calculated net with no allowance made for wastage or laps and the
cost of these will be deemed to be covered in the rates.
The weight of steel supports, spacer bars and ties, but including stirrups and binders,
used to locate and hold the reinforcement in place is not included in the quantity and
the cost of these will be deemed to be covered in the rates.
06.Brick Work
Rates for Brick Work shall include rough and fair cutting, plumbing angles, forming
arches, raking out joints, for pointing, plastering etc., cutting and pinning, making
good and sundry items of a like nature.
07.Cement and Sand Hollow Block Work
(a). Notes shall be applicable to Cement Sand Hollow Block Work as well.
(b). Cement sand hollow blocks shall conform to SLS 855.
Unless otherwise specified mortar for cement sand hollow block work shall be cement
and sand 1:5.
08.Masonry
(a) Rates for Masonry shall include all joggles, cramps, dowels, ties, templates,
rough and fair cutting, forming splays, angles, reveals, settings, joining, fixing
in position and pointing including hoisting not exceeding 20'0" above ground
level, protecting and cleaning down.
(b) Rates shall include for Builder's work in connection with all services and
installations.
09.Structural Steel Work
(a). Rates for Structural Steel Work shall include shop fabrication work
including cutting, drilling, bolting, riveting, welding, grinding, marking,
delivering, un-loading, hoisting, erecting and fixing in position.
XV
(b). Rate shall include for two coats of matt oil paint after treating with a coat of
anti-corrosive paint to all exposed faces of trusses, angles, irons and channels.
(c). All bolt holes to be machine drilled.
(d). Steel shall normally be welded by the metal area process conforming to B.S.
5135. Other methods shall be subject to the approval of the authorities.
(e). Unless otherwise specified all structural steel shall be Grade 43A.
(f). Structural steel shall conform to BS 4360.
10.Stainless Steel
Type and Quality
All stainless steel for external applications shall be type 316S16 (18% chromium/
10% nickel alloy/ 2.5% molybdenum) austenitic stainless steel cold formed, flat rolled
plate, sheet and strip to BS 1449: Part 2: 1983, and shall agree with requirements of
BS 970: Part 1: 1983.
For internal applications type 304S16 *18% chromium/ 10% nickel alloy) may be
considered as an alternative, at the discretion of the Consultant.
Bars and strips shall be ‘brushed finish’ and sheet to be “embossed” finish in heavy
duty areas e.g. life doors, kicking-plates, elsewhere ‘brushed finish’. Both finishes
being as per samples provided by the Consultant.
Where thin gauge stainless steel is used as a cladding materials, the problem of
kinking or “oil canning” shall be overcome by bonding the sheets to plywood,
(Marine plywood to BS 4079: 1966 for exterior applications), polymetric material, or
by use of stiffening ribs of stainless steel as specified in this Article, at appropriate
positions, bonding to plywood being done using a 2-part epoxy resin adhesive.
All bolted or screwed fixing shall be of stainless steel, or if of other metals to be fully
isolated from the stainless steel by use of nylon or neoprene washers, sheet, etc.
Stainless Steel sheeting shall be 1.25 minimum thickness when bonded to plywood
backing, except in heavy duty applications mentioned above, where 1.5 is the
minimum thickness allowed. Where not bonded to plywood backing 1.5 shall be the
minimum thickness.
Welding
Where stainless steels are welded, this shall be carried out using chromium nickel
austenitic or other compatible electrodes for manual metal are welding to BS 2926:
1984
Care shall be taken to avoid distortion during welding or damage to or discoloration
of surrounding finished surfaces.
All welds shall be carefully ground and polished as required to blend the weld in the
surrounding metal
XVI
11.Metal Work
(a). Notes in particular specification shall be applicable to Metal Work as well.
(b). Flashing shall be 22 S.W.G. Aluminum
12.Suspended ceilings
The rates for suspended ceiling tiles and panels and the like shall include for
chamfering all cut edges; vertical bulkheads and cutting around light fittings, grills
and diffusers or the like are also deemed to be included.
Rates shall also be deemed to include any depth between the soffit of the slab to
which the ceiling is suspended and the finished level.
All linear shall include for angles, ends and the like.
13.Roof Covering and Roof Plumbing
Rates for Roof Covering shall include laps, straight cutting and waste, nails, screws,
clips rivets, straps and the like including hoisting and fixing complete.
Zinc Alum roofing:
1 Zinc Alum profile sheet (minimum base metal thickness o.4mm and minimum
thickness of 0.47mm.)
2 Zinc Alum gutter (minimum base metal thickness o.4mm and minimum thickness
of 0.47mm.)
3 Zinc Alum down pipes (minimum base metal thickness o.4mm and minimum
thickness of 0.47mm.)
4 Zinc Alum cladding (minimum base metal thickness o.4mm thick)
5 Up channel, 'C' channel and purling galvanized iron
6 material : 55% Aluminum zinc
Al: Aloycoated Az 150, Hitensile (Grade 560) sheet.
Purling - Hitensile - Hitensile strength - 400 mpa (minimum)
Rates for Roof Plumbing shall include solder, rivets, screws, nails, clips, straps,
straight cutting and waste for patterns mould or templates and for all hoisting and
fixing complete with type 400 PVC fittings.
14.Wood Work
No application of any description shall be made on any timber unless and until the
timber is approved by the suitable Authority.
Rates for Carpentry shall include for all cutting, notching, drilling, sinking,
trimming, framing, jointing splayed edges, and like, fixing in position complete with
nails spikes, screws and priming to joints and ends, application of two coats of wood
preservative for all frame works and one coat of wood primer for un-exposed sides of
ceiling boards. Treating roof and ceiling timber (imported timber) in approved kiln.
XVII
All coconut timber shall be matured, selected, swan coconut timber. The finish of
coconut timber shall be mechanically sanded and painted with one coat of sanding
sealer and two coats of polyurethane varnish.
Structural timber for Roof work, ceiling frames
Palu, Wewarana(Ranei), Liyan, Alubo, Pihimbiya.
Imported timber Balau, Kempas, Bitis
Valance board
Ginisapu, Gammalu
Floor Boarding
Teak, Kumbuk, Tina
Timber for Joinery (Doors, Windows, Fan lights etc)
Mahogany, Margosa(Kohomba)
For Frame: Balau, Thulang, Hadawaka, Milla
For sashes: Halmilla
a. All timber shall be seasoned to a moisture content of 12% or less and shall be free of
defects such as end splits, surface cracks, warping, sap wood etc.
b. If imported timber is to be used, a certificate from the exporter, giving particular of
method of seasoning and preservative treatment along with grade classification shall
be furnished by the Bidder to the Engineer.
c. All timber sizes indicated in the description shall be finished sizes after planning.
Note on Prescribed timber Sizes
During the past two years, Divisional Engineers have reported that exact imperial
sizes on the timber on following categories are not readily available in the market,
unless logs are being purchased and sawn to the exact size. Contractor's Association
has also made representation indicating that the imperial size specified in the BSR is
not available on imported timber varieties, and due to scarcity of the local timber,
small scale Contractors are unable to purchase logs and seasoned the timber and sawn
to the imperial sizes. Market survey has confirmed the same. Accordingly, it has
been decided to indicate the cross sectional size roof timber in the following manner
to be in par with sectional sizes readly available in the local market, as it may not be
worthwhile to prescribe timber sizes and, then request Contractors to by a large
section and produce it to the required size, since there is no standardization of the
timber imports. This has been done to avoid subjective decision taken by the
Divisional Engineers during the project implementation phase.
Accordingly, the following imperial sizes are being now replaced by the following
Metric sizes.
1” to be replaced by 22mm
2” to be replaced by 45mm
XVIII
3” to be replaced by 70mm
4” to be replaced by 94mm
5” to be replaced by 117mm
6” to be replaced by 140mm
7” to be replaced by 165mm
8” to be replaced by 190mm.
Hence, timber will now be prescribed as
2"x 1" as 45mmx22mm
2”x 2” as 45mm x 45mm
4”x 2” as 94mm x 45mm
5”x 2” as 117mm x 45mm
5”x 3” as 117mm x 70mm
4”x 3” as 94mm x 70mm
6”x 2” as 140mm x 94mm
6”x 3” as 140mm x 70mm
6”x 4” as 140mm x 94mm
8”x 4” as 190mm x 94mm
Rates for Joinery shall include:
(a). All labour in framing, jointing and fixing in position complete with all nails,
spikes, screws etc.
(b). Application of one coat of hot tar to the surfaces come in contact with brick or
concrete.
(c). Application of one coat of wood primer for un-exposed surfaces.
Unless otherwise specified door, window, fanlight and other frames shall be
3 3/4" x 2 3/4" (finished size) in section and out of Jak, Milla or Mahogany. Sashes
and counter tops shall be 1" thick (finished size) out of "Jak" or "Mahogany".
Valance, barge boards and valley gutter boarding shall be 1" thick Ginisapu. Brass
screws shall be used for all fittings.
All exposed faces of timber in Joinery are to be wrote the sizes given below are
nominal without allowance for planning, except where described as finished sizes.
15.Ironmongery
Rates for Ironmongery shall include all fittings, cutting, sinking, boring, mortising
and the like and fixing complete including supplying matching screws.
(a) Unless otherwise stated, all fittings shall be polished brass with oxidized
finish, heavy quality type and make of the lock shall be "Union" or "Yale".
(b) Brass Fitting & Furniture
For doors, windows, cupboards etc. shall be of heavy type oxidized brass
fittings to approved samples, hinges shall have steel pins with the ends
welded.
XIX
(c). Parliamentary Hinges, Brass
Size A x B 2 1/2"x 3 1/2", 3 1/2"x 4", 4"x 4 1/2", 4 1/2"x 5"
Weight per pair 14 Ozs. 1lb., 2 Ozs.1lb. 5 Ozs. 1lb., 11Ozs.
Diameter of pin 0.170", 0.170", 0.184", 0.184"
(d). Butt Hinges
Size A x B 4"x 2 1/2", 4"x 3", 5"x 2 1/2", 5"x 3"
Weight per pin 1ib. 1 Pzs., 1lb. 3)zs., 1 lb. 7 Ozs. 1 lb. 12 Ozs.
Diameter of pin 0.184", 0.184", 0.184", 0.1184"
(e). Casement Stays
Size 10" straight 10" curved 12" straight 12" curved
Channel type 9 Ozs. 10 Ozs. 12 Ozs. 14 Ozs.
10 Ozs. 11 )zs. 14 Ozs. 17 Ozs.
(f). Bolts
The handles of bolts shall be cast in one piece with the shoot which shall be
not less than 3/10" dia. for bolts 6" and above and not less than 5/16" for
smaller bolts.
The distance of travel of the shoot shall not be less than 1 1/4" in the case of
bolts 6" and above.
16.Sanitary Fittings and Plumbing
The whole of the sanitary works shall be carried out by a licensed sanitary plumber
according to the layout and as specified and as directed at site. It should be noted that
the positions shown on plans are approximate. Exact positions would be indicated at
site.
All plumbing fixtures and fittings should be approved by the Architect, Engineer prior
to ordering same for installation.
All items of pipes, specials and fittings shall be suitable for sewerage works purposes
and for use with raw domestic sewage and installation and operation in a damp
tropical climate with temperature between 200C to 400C and relative humidity of
80%
(a). Unless otherwise specified rate for wash basin shall include 22"x 15" overall
white vitreous China wash basin conformed to SLS 229, leaflet or approved
equivalent with 1/2" dia. Chromium plated pillar tap, 1 1/4" dia. rubber plug,
Chromium plated chain waste and brackets in painted iron, screwed to plastic
rawl plugs buried in wall. Water supply and waste water connections all fixed
complete to working order.
XX
(b). Unless otherwise specified rate for low level closet shall include white
Vitreous China, low level closet conformed to SLS 229, leaflet or approved
equivalent comprising closet with 'P' or 'S' trap as directed and hinged seat
with lid in black plastic all fixed complete to working order.
(c). Unless otherwise specified rate for low level cistern shall include White
Vitreous China, low level cistern conformed to SLS 229, leaflet or approved
equivalent comprising shell and cover with supporting brackets screwed to
plastic rawl plugs buried in wall. Water supply and discharge connections all
complete to working order.
(d). Unless otherwise specified rate for Eastern Closet shall include ( 21 1/2"x 15
1/2") overall White Vitreous China closet as per Model No, 1001 as detailed
in Ceylon Ceramic Ltd. leaflet or approved equivalent 'P' or 'S' trap as directed
and foot rest in cement concrete 1:2:4 (3/4") rendered with grooved in cement
and sand 1:2 fixed complete to working order.
(e). Unless otherwise specified rate for high level cistern shall include plastic
cistern of approved manufacture comprising shell and cover with supporting
brackets screwed to plastic rawl plugs buried in wall PVC flush bend and all
other necessary accessories with supply and discharge connections all
complete to working order.
(f). Unless otherwise specified rate for Mirror above wash basin plate glass mirror
of super quality free from effect of wavy image with fiberglass frame fixed to
wall with plastic rawl plugs and chromium plated brass screws.
Rates for sanitary fittings shall include for:
a. Fittings such as taps, waste water outlets, flushing cisterns, flush valves,
internal overflows etc., the supporting brackets and incidental materials for
fixing.
b. Assembling, joining together, fixing component and jointing to pipes inclusive
for necessary couplings and for leaving perfectly clean undamaged and perfect
working order as on completion.
c. Jointing and connecting pipes to sanitary fittings.
d. Testing and commissioning of installation.
e. Making good the work disturbed
(g). Rate for Sanitary Plumbing shall include:
(1) Screws, nails, pipe hooks, saddles, brackets, sockets, connections,
short lengths, back nuts, nipples, all laps, straight cutting and waste.
(2) All excavations, supports to sides of trenches, if necessary keeping
trenches free from water, back filling, disposal of surplus soil, all
jointing and other incidental materials and testing upon completion.
Unless otherwise stated, PVC piping for water service and waste water etc. shall be
rated to Type 1000 PVC such plastic piping and fittings shall comply with the SLS
147 or latest BSS.
XXI
Copper piping shall be used for hot water service and such copper piping and fittings
shall comply with the latest BSS specification.
Unless otherwise stated separately in the BOQ, any special water supply and drainage
fittings such as bends, tees, reducers etc. shall be deemed to have been included in the
relevant items, and such items should accordingly be rated to include for such specials
etc. and for any extra work involved for the satisfactory completion of such items
17.Water Supply
The Bidder is to pressure test pipes after fixing taps and stop cocks and fittings prior
to concealing, under the supervision of the Engineer or his representative.
The contractor shall provide the Engineer with the manufacturers’ certificates of the
standards, quality of the materials before commencing the works
All water pumps should be mounted on inertia bases fitted with anti-vibration
mountings. Flexible connections should be provided on connections between pump
units and pipe work.
Where pipes pass through walls or slabs these shall be wrapped with a layer of insert
material. For pipes exceeding 50mm dia. sleeve pipes shall be used for the full
thickness of the slab walls, beams, retaining walls through which the pipe passes.
All taps, shower appliances, cocks and floor waste covers, used in the plumbing
installation shall be chromium plated brass (CP brass) or stainless steel item unless
otherwise stated.
Rates for Water Supply Plumbing work shall include:
a. Cutting and waste of pipes etc., and jointing of pipes.
b. All specials such as elbows, bends, tees, junctions, plugs, reducers and similar pipe
fittings except for valves which would be measured separately.
c. Connecting pipes to sanitary fixtures and appliances.
d. Chasing to brick or concrete walls, columns, beams etc., and making good all
works disturbed.
e. Necessary screws, nails, sockets, connection back nuts, standard pipe fixing or
supporting clips, saddles, brackets, racks, straps etc.
f. Connecting different type of pipes.
g. Testing and disinfecting after completion.
h. Preparing and making applications and giving notice to the relevant authorities to
obtain service connections to the building inclusive of any statutory payments to
relevant statutory authorities.
All cold water piping should be provided with flexible connections in pipe work and
provided with the required pipe supports & anchoring as per the manufacturer’s
specifications.
18.Drainage
Unless otherwise specified, pipes in Drainage shall be Type 600 PVC.
XXII
Rate for Drainage Work shall include for:
a. Excavation, backfilling, Planking & strutting, dewatering and disposal for surplus
spoil.
b. Laying of pipe to falls and gradient and all jointing and other incidental materials.
c. All pipe specials such as bends, tees, junctions, elbows, etc.
d. Connection to sides of manholes etc.
e. Providing sleeves etc., when pipes pass through walls, foundations etc.
f. Giving notices, obtaining permits, paying fees etc.
g. Testing installation as specified in specifications, and/or American, British or Sri
Lankan standards.
19.Plastering
Rates for Plastering shall include for all temporary rules, screeds, grounds etc. for
raking out joints of new brick work, or hacking new concrete for key, internal and
coved angles, joints between different surfaces and between new and old plastering,
arisers, quicks intersection between curved or irregular surfaces etc. and making good
around pipes, sanitary fittings and similar fixtures.
Unless otherwise stated internal wall plaster shall be 5/8" thick in cement, lime and
sand 1:1:5 finished smooth with lime putty.
Unless otherwise stated external wall plaster shall be 5/8" thick in cement, lime and
sand 1:1:5 finished semi-rough.
Unless otherwise stated plinth plaster shall be 5/8" thick in cement and sand 1:3
finished smooth with neat cement floating.
Unless otherwise stated Soffit plaster shall be 3/8" thick in cement and sand 1:3
finished smooth with lime putty.
20.Paving
Rates for paving shall include all temporary rules, screeds, ground etc. all normal
cutting arisers, rounded angles and the like bedding and point making good between
different surfaces and around pipes, sanitary fittings and other fixtures and cleaning
down upon completion including curing.
Unless otherwise stated Cement rendering shall be 1/2" thick in cement and sand 1:3
finished smooth with thick coat of colored pigment mixed neat cement floating and
smooth with Caberendum stone.
Unless otherwise stated skirting shall be 4" high (100mm high) 1/2" thick (12mm
thick) in cement and sand 1:3 laid with the floor rendering, finished smooth with a
sunk bed of junction of the skirting with the plaster above the angle between the floor
and the skirting to be rounded off to a radius of one Inch.
21.Tiling
Tile should comply with European standard specification LEN 177.
Industrial grade (heavy duty) vitreous ceramic floor tile shall be homogeneous.
XXIII
The tiles manufactured by European standards and are of colored as specified by an
Architect.
Rates for tile work shall include the cost of cement and sand 1:3 screed, pointing
joints with neat cement of tile grout to match the color of tiles.
Unless otherwise stated floor tile paving shall be any size non-skid pattern ceramic
floor tiles of approved local manufacture, bedded with cement and sand 1:3 1/2" thick
screed.
Unless otherwise stated wall tiling shall be any size glazed ceramic wall tiles of
approved local manufacture fixed on cement and sand 1:3 backing 3/8" thick.
Approval of floor and wall tiles colour to be obtained from suitable authority.
All floor tiles shall be locally produced ceramic tiles and shall agree in colour,
dimensions, tolerances, finishes, and quality with samples provided by the consultant.
All tiles to be true to shape, uniform in size and free from blemishes.
The recommendations of C.P.202 and BS 5385: part 3, shall be complied with,
subject to any qualifications hereunder.
Preparation
The sub –floors to be cleaned of cement film, mortar spills, paint and other impurities,
oil sports to be chiseled. The sub-floor is to be well wetted with water
Everything necessary shall be done to obtain a satisfactory bond between concrete,
screeds, beddings and finishes.
The cleaned sub-floor shall be grouted with a 1:1 cement/water mixture by broom
application, prior to placing the mortar bed
Setting-out
Corrected floor levels shall be established and finished levels of tiling controlled by a
series of spot levels.
Movement joint in sub-floors and screeds shall be carried up into tiling.
Generally the tiles shall be divided symmetrically over the areas, so that pieces
smaller than half a tile will not occur; the layout of the tilling and width of joints to be
determined with the consultant.
The tilling to be laid to falls, towards floor gullies as shown on the drawings, and/or in
co-ordination with the consultant.
At joints to walls, skirtings, pits, passages etc., the to be cut, sawn or ground to size.
Bedding of Tiles
Care shall be taken that tiles are well soaked in clean water and are free of dust before
laying.
A mortar bed of 1 part cement to 3 parts sand, of thickness as specified in the Bill Of
Quantity to be spread by means of a float in beds of a width of approx. 700 and
allowed to stiffen. Acid proof mortar for acid-proof tiles is to be applied in
accordance with the manufacturer’s instructions.
XXIV
The back of the tiles shall be buttered with a coat of cement slurry and the tiles laid
with straight joints 3mm wide, on the mortar bed.
Grouting shall take place at any time after tiles are firmly fixed but before any dirt or
contamination can enter the joints.
Dampen the joints and grout with cement: fine sand(1:1). Do not use more water than
necessary to avoid subsequent joint shrinkage work the grout well into the joint until
flush and remove surplus grout. At the discretion of the consultant, tinted grout shall
be used. Grouting for acid-proof tiles is to be applied in accordance with
manufacturer’s instruction.
If a depression or bump in surface level in excess of 6mm in any 2 meter length is
found, then the floor shall be taken up and re-laid, at the contractor’s expense, to the
satisfaction of the Consultant.
Protection
Finished tiled floors are completely covered with sheets of hardboard; walls and
skirting to be washed with soap and water, the floor to be similarly treated after
removal of temporary floor coverings.
22.Painting
Rates for Painting shall include preparation of surfaces, cleaning down, smoothing,
knotting, stopping etc., protection of floors and fittings, removing and replacing door
and window furniture and cleaning doors and windows upon completion.
Unless otherwise specified internal wall paint shall be one coat of Alkali Resistant
Primer and two coats of Emulsion paint of approved make and colour.
Unless otherwise specified external wall paint shall be one coat of Alkali Resistant
Primer and two coats of Weather shield Emulsion paint of approved make and colour.
Unless otherwise specified paint for wooden surfaces shall be one coat of aluminum
primer and two coats of Enamel paint of approved make and colour.
Spray painting shall do in ICTAD SCA/4/1 clause 14.9(f).
23.Glazing
Unless otherwise specified, thickness of glass panes shall be not less than 4.0mm and
rates for Glazing shall include waste in cutting to required sizes, brass pins, screws,
"Teak' or 'Halmilla' beads, fixed complete and protecting.
24.Electrical Installation
Unless otherwise specified internal lighting wiring shall comply with the drawings
and shall be in full PVC insulated copper cables. All conduits shall be buried into
brick walls, slabs, beams or columns to the entire satisfaction of the Engineer. All
switches and socket outlets shall be "Tenby", M.K., Clipsal or similar approved sunk
type unless otherwise specified. All fluorescent fittings should be complete with good
quality power factor correcting capacitor and choke, starter etc. and the tube should be
"Thorn", "Philips" of good quality of similar approved make. All fans and regulators
XXV
shall be "National", "Hitachi", "KDK", or similar approved make to approved colour.
Rate to include for all necessary PVC switch boxes, plugs, round or square blocks.
Chromium plated chains, brass hooks, ceiling roses, holders (Angle batten and
ordinary battens) and any other item necessary, whole installation shall be carried out
according to CEB/IEE regulations. All other distribution boards should be Merlin
Gerin flush mounting type or similar approved type. Switch gears shall be MEM or
similar approved type. Earth leakage circuit breakers shall be Cabtree, Fugi or
approved make, MCCB's and MCB's shall be "Square D" or similar approved make.
Unless otherwise specified wiring shall be as follows :
All lamp points wired through a 5 Amp. Sunk switch using 2x1x1/1.13 PVC insulated
copper wire and 1x1x7/0.67 PVC insulated copper earth wire in concealed PVC
conduits.
Ceiling fan points wired through regulator using 2x1x1/1.13 PVC insulated copper
wire and 1x1x7/0.67 PVC insulated copper earth wire in concealed PVC conduits.
All flush mounted 5 Amp. Switched socket outlets wired using 2x1x1/1.13 PVC
insulated copper wire and 1x1x7/0.67 PVC insulated copper earth wire in concealed
PVC conduits.
All flush mounted 15Amp. Switched socket outlet wired using 2x1x7/0.67 PVC
insulated copper wire and 1x1x7/0.67 PVC insulated copper earth wire in concealed
PVC conduits.
General Specification - Electrical Installations
1.0 General
(a). Work shall be carried out in conformity with the regulations for electrical
equipment in buildings issued by the I.E.E. London ICTAD Specifications and
any other relevant C.E.B. Regulations.
(b). All materials and equipment used shall conform to the relevant current B.S.
Specifications, Sri Lanka Standard Specification or any other Internationally
recognized Specification not less rigid.
(c). The rate quoted for wiring per point, shall provide for the supplying and
installation of all materials necessary for the complete wiring of that point
from the Distribution Board onwards, exclusive of the cost of supplying and
installing Distribution Board, Lamps and Shades but will include all other
materials in the sub-circuit wiring.
1.1 Wiring Points
1.1 1 A Pendant point will include :-
(a). Cord grip suspension lamp holder
(b). Flexible 2 core cord upto 1.5m in length.
(c). Ceiling rose on square or round, Teak or Halmilla base.
(d). Associated casings and covers except for the runs as defined in Item
1.2.5.
XXVI
(e). A single pole Tumbler Switch (5a) on round or square, Teak or
Halmilla base or a single pole flush type switch on Teak or Halmilla
base.
(f). Complete wiring of the point.
1.1.2 A Batten Point will include :-
(a). Straight or Angle batten holder on square or round, Teak or Halmilla
base.
(b). A single pole Tumbler switch on a square or round Teak or Halmilla
base or a single pole flush type switch on Teak or Halmilla base.
(c). Associated casings and covers except for the runs as defined in Item
1.2.5.
(d). Complete wiring of the point.
1.1.3 A socket Outlet shall consist of :
(a). A three pin 5A socket outlet (shuttered type)/three pin 5A socket outlet
(shuttered type), on a Teak or Halmilla base.
(b). Associated casings and covers except for the runs as defined in Item
1.2.5.
(c). The earth continuity conductor.
(d). Complete wiring of the point.
1.1.4 A fan point shall consist of :
(a). A ceiling rose on a square or round Teak or Halmilla base.
(b). A 200mm x 150mm Teak or Halmilla base on which the regulator to
be mounted.
(c). An earth continuity conductor for earthing of the regulator, where
required.
(d). Associated casings and covers except for the runds as defined in Item
1.2.5.
(e). Complete wiring of the point.
1.1.5 A fan under light point shall consist of :
(a). Bracket holder
(b). Adequate length of flexible 2 core cord.
(c). Single pole switch on square or round Teak or Halmilla base.
(d). Associated casings and covers except for the runs as defined in Item
1.2.5.
(e). Complete wiring of the point.
N.B. 1. Fan Under-light
Where a fan under-light point is required as common 3 plate
ceiling rose may be used for the fan point and under-light. A fan
under-light point will be paid as an additional point.
2. Two-way 5A Switch
When a two way 5A switch is required, it will be treated as two
separate points.
XXVII
1.2 Method of Installation :
1.2.1 Cables :
(a) All cables to be colour coded/red and black for phase and neutral
respectively.
(i). All runs on walls to be enclosed in casings and covers where
Tumbler switches are used.
Or
(ii). All runs on walls to be laid in PVC conduit of not less than
18mm diameter concealed in the wall plaster.
(b) All runs above ceilings to be clipped, clips spaced not more than
200mm on the horizontal runs and 350mm on vertical runs.
(c) Where cables have to be run on iron support, wooden battens of
suitable size shall be used. These battens shall be secured to the iron
by metal clips, spaced not more than 600mm apart. These battens shall
be paid for as extras and the Tendered should quote for the supply and
installation of various sizes.
1.2.2 Troughings and covers
(a) Troughings to be fitted to wall, secured with iron screws on to dove tail
plugs cemented to wall, or by some other approved method.
(b) Covers to be fitted on troughings with suitable nails spaced not more
than 200mm apart on either side.
(c) These to be sand papered.
Conduits
1.2.3 The following accessories shall be mounted on Teak or Halmill a bases,
secured to the wall brass screws driven into dove tail plugs cement4d to the
wall Main Switch fuses, Distribution Boards, Switches, Socket outlets, and
wall racket fittings, ceiling rose, batten holders shall be mounted on Teak or
Halmilla base secured to the ceiling batten with brass screws.
1.2.4 Horizontal runs of cables, mains or otherwise when exposed to view under the
ceiling or in the absence of a ceiling, shall be enclosed in casings and covers.
These casings and covers will be paid for as extras at the rate accepted in the
Tender.
1.2.5 Suspension type fluorescent fittings shall be hung from eye hooks on ceiling
plate securely fixed to the ceiling or beam overhead. Suspension shall be by
means of galvanized iron chains of suitable size.
1.2.6 Where wires have to pass through walls, PVC conduits shall be used. These
conduits should be of suitable size to carry the number of wires used and
should be securely fixed to the wall before the wires are drawn through. Care
should be taken to prevent damage to wires at the end s of the tubes.
XXVIII
1.3 Wiring
1.3.1 All wiring to be done in strict accordance with the wiring regulations for
buildings Institution of Electrical Engineers (London) latest edition and in
accordance with the requirements of the Ceylon Electricity Board.
1.3.2 The wiring shall commence at the main switch fuse. The loop in system of
wiring shall be used and no joints will be permitted in the cable runs.
1.3.3 All cables to be colour coded red and black for phase and neutral respectively.
1.4 Earthing
1.4.1 The earth pin of all sockets to be connected to an earth continuity conductor.
All joints on this conductor to be soldered. The conductor is to be finally
terminated outside the building for connection to the earth electrode. The size
of the earth continuity conductor shall be in accordance with the I.E.E.
Regulations for Electrical Installations in buildings (latest edition) - the
minimum size being as in Item 1.7 of the Specifications for materials.
1.4.2 Where required, the wiring of a fan point shall provide for the connection of a
fan regulator to the earth continuity conductor.
1.4.3 The earth continuity shall be securely fixed by means of a suitable earth clip to
one or more earth electrode as required. Earth electrode should be positioned
outside the building at a suitable location.
1.4.4 Where the earth continuity conductor is run in casing, it shall be secured to
casing by small staples. For runs above the ceiling, it shall be secured to the
roof timber with copper staples. The length of the earth continuity conductor
buried in ground shall be drawn through a G.I. pipe of suitable size not less
than 50mm diameter.
1.4.5 The runs to the earth electrode, below ceiling level, shall be in conduit or
enclosed in casing and covers.
Part I - Chapter 13 of the I.E.E. Regulations
Fundamental Requirements for Safety
Workmanship and material
13-1 Good workmanship and proper material shall be used.
General
13-2 All equipment shall be constructed, installed and protected, and shall be
capable of being maintained, inspected and tested, so as to prevent danger so
far as is reasonably practicable.
13-3 All equipment shall be suitable for the maximum power demanded by the
current using equipment when it is functioning in its intended manner.
13-4 All electrical conductors shall be of sufficient size and current carrying
capacity for the purposes for which they are intended.
13-5 All conductors shall either -
XXIX
(i) be so insulated, and where necessary further effectively protected, or
(ii) be so placed and safeguarded
as to prevent danger, so far as is reasonably practicable.
13-6 Every electrical joint and connection shall be of proper construction as regards
conductance, insulation and mechanical strength and protection.
Over-current Protective Devices
13-7 Where necessary to prevent danger, every installation and every circuit thereof
shall be protected against over-current by devices which -
(i) will operate automatically at values of current which are suitable
related to the safe current ratings of the circuit, and
(ii) are of adequate breaking capacity and where appropriate making
capacity and
(iii) are suitably located and are constructed so as to prevent danger from
overheating, arching or the scattering of hot particles when they come
into operation and to permit ready restoration of the supply without
danger.
Precautions against earth leakage and earth fault currents
13-8 Where metal work of electrical equipment, other than current-carrying
conductors, may become charged with electricity in such a manner as to cause
danger if the insulation of a conductor should become defective or if a fault
should occur in any equipment.
(i) The metal work shall be earthed in such a manner as will cause
discharge of electrical energy without danger or
(ii) other equally effective precautions shall be taken to prevent danger.
13-9 Every circuit shall be arranged so as to prevent the persistence of dangerous
earth leakage currents.
13-10 Where metal work is earthed in accordance with Regulation 13.8(i) the circuits
concerned shall be protected against the persistence of dangerous earth fault
currents by -
(i) the over-current protective devices required by Regulation 13-7 or
(ii) a residual current device or equally effective device.
The method described in Item (ii) above shall be used whenever the
prospective earth fault current is insufficient to cause prompt operation of the
over-current protective devices.
13-11 Where necessary to prevent danger, where metal work of electrical equipment
is earthed for compliance with Regulation 13-8(i) and is accessible
simultaneously with substantial exposed metal parts of other services, the
latter parts shall be effectively connected to the main earthing terminal of the
installation.
Position of Protective Devices and Switches
13-12 No fuse, or circuit breaker other than a linked circuit breaker shall be inserted
in an earthed neutral conductor, and any linked circuit breaker inserted in an
XXX
earthed neutral conductor shall be arranged to break also all the related phase
conductors.
13-13 Every single pole switch shall be inserted in the phase conductor only, and any
switch connected in an earthed neutral conductor shall be a linked switch and
shall be arranged to break also all the related phase conductors.
Isolation and Switching
13-14 Effective means, suitably placed for ready operation shall be provided so that
all voltage may be cut off from every installation from every circuit thereof
and from all equipment, as may be necessary to prevent or remove danger.
13-15 For every electric motor an efficient means of disconnection shall be provided
which shall be readily accessible, easily operated and so placed as to prevent
danger.
Accessibility of equipment
13-16 Every piece of equipment which requires operation or attention by a person in
normal use shall be so installed that adequate and safe means of access and
working space are afforded for such operation or attention.
Precautions in Adverse Conditions
13-17 All equipment likely to be exposed to weather, corrosive atmosphere or other
adverse conditions shall be constructed or protected, as may be necessary to
prevent danger arising from such exposure.
13-18 All equipment in surroundings susceptible to risk of fire or explosion shall be
so constructed or protected and such other special precautions shall be taken,
as may be necessary to prevent danger.
Additions and alterations to an installation
13-19 No additions or alterations, temporary or permanent, shall be made to an
existing installation, unless it has been ascertained that the ratings and the
condition of any existing equipment (including that of the supply undertaking)
which will have to carry any additional load is adequate for the altered
circumstances and that the earthing arrangements are also adequate.
Inspection and Testing
13-20 On completion of an installation or an extension or alteration of an
installation, appropriate tests and inspections shall be made to verify so far as
reasonably practicable that the requirements of Regulations 13.1 to 13.19
have been met.
13-21 Standard Mounting Heights Electrical wiring Accessories
(Height from Fin. FLF)
2400mm Pendant Lamp
2250mm Wall Bracket Lamp
2400mm Exit sign Board
1500mm Switch Board
1500mm Fan Regulator
2000mm MCB Distribution board
300mm - Common area Socket Outlet
XXXI
LIST OF APPROVED ELECTRICAL FITTINGS
No.
Item
Relevant Standard
Specifications
Recommended Brand
Names
01 Sunk Switches, 10A B.S. 3676 Clipsal, Legrand,
M.K.
02 13A Switched Socket Outlets, Plugs &
Adopters.
B.S. 1363 Clipsal, Legrand,
M.K.
03 5A and 15A Switched Socket Outlets B.S. 546 Clipsal, Legrand,
M.K.
04 R.C.C.B./R.C.D. B.S.4293, IEC1008
BS EN 61008
F & G (Austria)
Siemens (Germany)
Clipsal (Australia)
Crabtree (U.K.)
Merlin Gern (France)
Legrand (France)
05 M.C.B. IEC 898 or BS
EN60898 or IEC
947-2 or
B.S.3871:Part 1
F & G (Austria)
Siemens (Germany)
Clipsal (Australia)
Crabtree (U.K.)
Merlin Gern (France)
Legrand (France)
06 Consumer Unit B.S. 5486 Part 1 &
Part 13 L.E.C.439-
1 or BS EN 60439-
3 IEC 695-2-1
ABB (Germany)
ABC (Singapore)
Crabtree (U.K.)
Hager (France)
Legrand (France)
07 M.C.C.B. I.E.C.947-2:1989 BS
EN60947-2:1992
Legrand (France)
Merlin Gern (France)
Terasaki (Japan)
Klokner
Moeller (Germany)
Crabtree (U.K.)
08 Cu/PVC/SWA/PVC Cables
Cu/PVC/PVC Cables
B.S. 6346
B.S. 6004:1995 &
SLS 733:1995
ACL (Sri Lanka)
Wilson (Singapore)
Kelani (Sri Lanka)
09 Cu/XLPE/SWA/PVC Cables
Cu/XLPE/PVC Cables
B.S. 5467
B.S. 5467
ACL (Sri Lanka)
Wilson (Singapore)
Kelani (Sri Lanka)
No.
Item
Relevant Standard
Specifications
Recommended Brand
Names
XXXII
10 Fluorescent Ballasts with Screw Type
Terminals
I.E.C. 920, 921 &
922
BSEN 60928
Schwabe (German)
ATCO (Australia)
B.G. (U.K.)
11 fluorescent Lamps
Colour : Cool White (4000 K)
I.E.C.81
B.S. 1853
Osram (Germany)
Tungsram (Hungary)
Philips (Holland)
GE (USA)
Sylvania (USA)
Westinghouse (USA)
12 Lighting Fixtures EN 60598
BS 4533
Thorn UK)
Philips (Holland)
13 Steel Enclosures (Epoxy Powder
coated finish)
I.E.C.529 for degree
of protection
BSEN 60529
Elsteel (Sri Lanka)
Legrand (France)
Himel (Spain)
Enclotek (India)
Metalix (Sri Lanka)
14 Exhaust Fans BS 5060
I.E.C.879:1987)
KDK (Japan)
Alstom (UK)
National (Japan)
15 PVC Conduits BS 4607 & BS 6099 National, Anton,
Duro, S-lon
16 G.I. Conduits BS 4568 Part 1 Matsushita, Maruichi,
Pusan or any U.L.
approved U.S.
Brands.
List of Cable brands in Sri Lanka with SLS Certificate ACL, KML, KELANI,
ALUCOP, RUHUNU
25.Air-conditioning
Unless otherwise specified Air-conditioning work shall conform the following design
criteria and conditions.
(a) Inside temperature should be maintained at 250C + 1.50C.
(b) The inside relative humidity should be maintained at 55% + 15%.
(c) Outside conditions to be taken as
Dry bulb temperature - 330C
Wet bulb temperature - 290C
i.e. relative humidity - 75%
(d) Noise level should be not more than 35db
(e) A minimum of 1.3 Litres/S/m2 of fresh air should be supplied.
(f) Air Velocity should be maintained at between 0.3m/s at a height of
1.5m from ground level.
(g) The Co2 content should be less than 0.1%.
(h) The Contractor should give a guarantee to the client that he will
maintain the above design conditions inside the air-conditioned areas.
(i) The attached plans indicate the areas to be air-conditioned.
(j) The Contractor should indicate as an extra item the conditions and cost
of an annual maintenance contract.
XXXIII
(k) The Contractor should submit the Technical Literature with the
quotation.
(l) A guarantee that spares will be available for all equipment supplied for
at least a period of 5 years should be given by the local agent.
(m) Performance tests to ascertain that the specified design conditions are
maintained should be carried out at the time of commissioning.
26.Waterproofing
(a). The waterproofing Contractor (or Sub-Contractor) should be a registered
specialist contractor at the ICTAD on the particular area.
(b). The Contractor should issue a written warranty of at least 5 year to cover on
the quality of the material, suitability of the material for the situation and the
workmanship.
(c). The waterproofing material shall conform to relevant British, Euro or ASTM
specifications.
(d). Rates shall include for cutting, notching, bending and extra material for
lapping making into recesses, inserts, pipes and the like and for working to
falls and cross falls.
(i). Internal and external angles, angles fillets, arisers, edges, intersection
and the like.
(ii). Cleaning with wire brush where necessary priming all joints including
necessary additional materials.
(iii) Application of liquid polymer cement water proofing agents for the
following.
Flat roofs, concrete/masonry tanks, wet areas of toilets including
bathrooms, exposed balconies, concrete gutters. "Smart flex",
"Thoroseal" or any other approved equivalent product marketed by
specialist contractor registered at ICTAD.
(iv) Application of cementations type agents with positive and negative
(back-flow resistance) properties on newly cast under ground sumps,
swimming pool basements, "Osmoseal", "Xypesx", "Vandex" or any
other approved equivalent product marketed/installed by a specialist
contractor registered at ICTAD.
(iv) Application of membrane type agents and insulation of same less
membrane type water proofing on large flat roofs, gutters, basements.
Material thickness not less than 3mm and comply to
BS/ASTM/JIS/AU Standards.
28 Steel Grill Work
(a). Rates for Steel Grill Work shall include shop fabrication work
including cutting, drilling, bolting, welding, grinding, marking,
delivering, un-loading, , erecting and fixing in position.
(b). Rate shall include for two coats of matt oil paint after treating with a
coat of anti-corrosive paint to all exposed faces of grill.
XXXIV
(c). All bolt holes to be machine drilled.
(d). Steel shall normally be welded by the metal area process conforming
to
B.S. 5135. Other methods shall be subject to the approval of the
authorities.
(e). Unless otherwise specified all steel shall be Grade 43A.
(f). Structural steel shall conform to BS 4360.
29 Steel Balustrade Work
(a). Rates for Steel Balustrade Work shall include shop fabrication work
including cutting, drilling, bolting, , welding, grinding, marking,
delivering, un-loading, , erecting and fixing in position.
(b). Rate shall include for two coats of matt oil paint after treating with a
coat of anti-corrosive paint to all exposed faces of grill.
(c). All bolt holes to be machine drilled.
(d). Steel shall normally be welded by the metal area process conforming
to
B.S. 5135. Other methods shall be subject to the approval of the
authorities.
(e). Unless otherwise specified all steel shall be Grade 43A.
(f). Structural steel shall conform to BS 4360.
30 RollerShutter Door
(a) Slats: Color bonded/Zinc coated slats to the thickness of 0.7mm and
0.8mm respectively to the width of 75mm (3") and 100mm (4")
(b) Flat & curve special feature. Specially imported hard rubber beading
on
side channels to minimize the rough flow of the shutter colours, choice
of 10 colors.
SPECIFICATIONS
Specifications comprise of two sections. The “General Specifications” and “Particular
Specifications” together comprise the specification governing the works described in the
B.O.Q. and B.S.R.
Several national and international standards have been quoted in the specifications. All
Workmanship Materials and Components throughout shall where applicable and unless
otherwise stated in the Specification comply with the relevant American, British or Sri
Lankan
XXXV
Standards, current on the date fixed for receipt of Bids together with additional clauses or
amendments set out in the specifications.
Order or precedence of the standards shall be as follows:
1. Sri Lanka Standards
2. British Standards
3. American Standards
Bidders may offer materials in accordance with such other standards or specifications which
provide for quality and workmanship not inferior to the standards quoted together with the
additional clauses or amendment set out in these specifications. Such standards or
specifications shall be submitted in full at the time of bidding. Authenticated English
translation shall be submitted if the specifications are in other language.
When reference is made within these documents to certain standards, specifications or
regulations, the reference shall be construed to mean the standards with all subsequent
amendments and changes or additions as thereafter adopted and published that are in effect at
the date fixed for receipt of Bidders.
Bidders are instructed that any clarifications and/or additional information etc. pertaining to
the scope of work should be obtained fully before Bid submission and that the quality and
quantum of work which should be as per the above standards properly understood since no
extra works would be due any subsequent clarifications of lack of information.
General Specifications
The general Specifications are the specifications given in the following documents issued by
the Institute for Construction Training And Development (ICTAD).
The Bidders are expected to be conversant with these documents, since the said documents
will not be issued to the Bidders under this Bid, however the Bidders may purchase the
documents from ICTAD, “Savsiripaya”, Wijerama Mawatha, Colombo 7.
Publication No. Description
SCA/4(Vol. I) Specification for Building Works Vol. I
SCA/4(Vol. II) Specification for Building Works Vol. II
SCA/8 Specification for Electrical & Mechanical works
associated with Building and Civil Engineering
SCA/3/1 Specifications for Irrigation and Land Drainage
SCA/3/2 Specifications for Water Supply, Sewerage and Storm
water Drainage work.
Standard specifications for Construction and
Maintenance of roads and Bridges issued by the RDA.
XXXVI
Special Specifications
1. Special Specifications for Concreting
2. Special Specifications for Aluminum Works
3. Special Specifications for Electrical Installation
4. Special Specifications for Air-Conditioning System
5. Special Specifications for Water Proofing
1. Special Specifications for Concrete
Criteria of rejection of concrete
Hardened concrete shall be liable for rejection if any of the following defects occur,
a. The concrete is heavily porous, segregated or honeycombed.
b. A construction joint has been made at a location or in a manner not in
accordance with this specification.
c. The construction tolerances have not been met.
d. The reinforcing steel has been displaced from its correct location.
e. The embedded items in concrete have been displaced from their correct
position.
f. The required surface finish has not been achieved.
g. The test results and/or load test fails.
Curing of Concrete (refer clause 4.3.5)
Recommended methods for curing
a. Ponding or continues sprinkling with water.
b. The use of an absorptive cover kept continuously wet
c. The use of curing compounds to be approved by the Engineer.
d. The use of an impermeable sheet membrane over a moistened surface so fixed
and lapped that circulation can occur at the concrete surface
Frequency of Sampling Test Specimen’s
1. At test three (3) specimens shall be taken from a sample and cured.
2. A record on the full history of sampling and testing of all specimens.
Concrete Acceptance criteria
The concrete shall be deemed to comply with the strength requirements if the
characteristic strength of the concrete meets the following,
Grade 28 days characteristic 28 days compressive strength (N/m2)
Description strength (N/m2) Average of any group individual
Of three (3) consecutive test result
XXXVII
25 25 Test results shall be shall be
Greater than 32.5 greater
Than 21.5
Concrete Sampling and Testing
1. Cement
2. Fine Aggregate
3. Course Aggregate
4. Slump
Sampling
1. A sample for reinforcement bars shall mean three samples of reinforcement bars
representing each diameter; for each 10 Metric Ton.
2. A sample for concrete shall mean seven numbers of concrete cubes
(150mmx150mmx150mm) obtained at the location of placing concrete.
Fine Aggregate
a. Offshore sea sand – marketed by SLRDC
i . Sea sand passing 5mm sieve shall be permitted
ii. The origin of the sea sand shall be established at from a SLRDC Depot (Lorry
No. and permit copy to be annexed)
iii. Limit of grading
Based on sieve analysis of sand, limits are as below reference clause 4.1.3.5 –
table 4.2
Sieve size overall limits Grading
Zone-C Zone-M Zone-F
10mm 100 - - -
5.00mm 89-100 - - -
2.36mm 60-100 60-100 65-100 80-100
1.18mm 30-100 30-90 45-100 70-100
600µm 15-100 15-54 25-80 55-100
300µm 5-70 5-40 5-48 5-70
150µm 0-15 - - -
iv. The quantity of material passing the 75 µm sieve should not be 4% by weight.
Course Aggregate
Refer table 4.1 / clause 4.1.3.5 0f ICTAD SCA/4/1 for grading.
2. Special Specifications for Aluminum Works
Specimen Notes for Aluminum Doors, Windows & Fanlights
(c). The Aluminum alloy to be used shall conform to the requirements of BS
1474:1987 - AA 6063 surface treatment shall conform to BS 1615 & BS 3987.
(d). Physical Properties:
1. Minimum tensile strength 150 Mpa.
2. Elongation 7%.
XXXVIII
(e). Anodic Oxidation coating should conform to BS 1615:1987 and BS
3987:1974 and the minimum coating thickness should be 20 + 25 Microns.
The Supplier should furnish the manufacturer's certificate that the anodized
finish complies with the specified Microns content.
(f). Minimum section thickness 1.8mm door frame, 1.5mm window frame and
1.00mm partition.
(g). Joints shall be made mechanically sound by welding or by concealed
mechanical connectors. A water tight joint shall be made at the junctions and
side frames members and water will not be trapped anywhere in or around
frames.
(h). All ironmongery shall be of the same material and satisfactorily performed the
function for which intended and shall be securely attached.
(i). Caulking compound shall be the best quality available for caulking between
the contact surfaces of the structure and the aluminum windows conforming
the adhering qualities, temperature resistance from 50F - 160F and humidity
changes of 5% - 100%.
(j). Screws used in the construction of frames shall be high tensile stainless steel
or a non-corrosive material compatible with aluminum.
(k). Neoprene weather stripping shall be of the highest commercial standards for
normal temperature, water and abrasion resistance.
(l). Frames shall be fixed to the structural opening with proper fixing devices. If
any discrepancies occurring between approved drawings and site conditions
these shall be brought to the notice of the Engineer.
(m). Material and dimensions should be confirmed before any fabrication and
installation.
(n). A Ten year guarantee period is required and this to be transferred to the Client
after practical completion.
(o) At the same time of bidding, all the Bidders shall specifically be requested to
submit the following information.
i The specifications and thickness of aluminum extrusions bidder
proposes to use on the work.
ii Full size cross sections
iii Documentary evidence from the Profile Manufacturer to the effect that
the proposed profile will serve for the intended purpose.
iv A Manufacturer's test certificate be produced as evidence that the
powder coating is of required thickness.
3. Special Specifications for Electrical Installation
1.0 All material and equipment used shall conform to the relevant current B.S.
specification, Sri Lanka standard specification or any other internationally
recognized specification not less rigid.
XXXIX
1.1 Cable for Sub-circuit Wiring shall be of Copper 1/1.13 cross section
to be in PVC cables in accordance with B.S.S.6004/1969 and
amendments to it.
1.2 Ceiling roses shall be of shock proof, bakelite covered two plate type
or three plate type with an efficient cord grip.
1.3 Lamp holder suspension type shall be of the bayonet socket pattern
of shock proof bakelite having an efficient cord grip solid plunger,
brass reinforcing barrel liner shade ring and all metal parts to be of
brass.
Lamp holder batten type shall be of the bayonet socket pattern of
shock proof bakelite straight or angle type as required, having solid
plungers brass reinforcing barrel liner, shade ring and all metal parts of
brass.
1.4A Switches shall be single pole, single way of the shock proof bakelite
covered type, screws, contacts and springs to be made of brass, base to
be of porcelain or ceramic.
1.4B Sunk type switches shall be single pole, single way of the shock proof
covered type, screws, contacts and springs to be made of brass, base
and cover to be made of bakelite with area moulding powder and
approved quality.
1.5 Flexible cord 16/0.0.20 to be of Copper twin PVC insulated and PVC
Overheated.
1.6 Wiring clips shall be of tinned brass or aluminum with counter sunk
holes short, medium, large or small according to requirements. These
shall be fixed by means of gimp pins of brass.
1.7 Earth Conductors and Continuity Conductors shall be of PVC
Insulated copper and be of relevant cross sectional area as given in the
latest I.E.E. regulations.
1.8 Wooden blocks shall be of Teak, Halmilla circular, square or
Rectangular according to requirements and smooth finished.
1.9 Wooden battens shall be of Teak or Halmilla of rectangular cross
section 50mm x 12mm.
1.10 Screws all screws used in the fixing of casting blocks, covers, witches
etc. shall be of brass except where otherwise stated.
1.11 Fuse carrier and base this section is applicable to all fuse carriers and
bases used in distribution boards and main switches provided under the
Contract.
(a). The base shall be vitreous porcelain with holes for cable entry
at top and bottom and two holes for screws. Base contacts shall
be in brass.
(b). The fuse carrier shall be of vitreous porcelain.
(c). The fuse wire shall be of tinned copper.
2.0 Troughings and covers shall be of seasoned Teak, Halmilla or approved
Class I timber must be of good workmanship smooth to finished with covers
XL
having suitable mouldings. All troughings and covers which are exposed
should be neatly finished (including sand papering).
3.0 Cable mains must be of specified size and to be in PVC in accordance with
B.S.S. 6004/1969 with copper conductors.
4.0 Main Switch
(1) Splitter type :
Two pole (5 Amp. and 10 Amp.) all insulated main switch suitable for
230V A.C. two wire 50Hz. system.
(2) All insulated shall be of the all insulated type and double pole single
way. The switch shall have all metal parts in brass and shall be so
arranged to prevent the cover being opened when the switch is at the
"ON" position. One pole to be fused.
(3) Metal Clad shall be S.P. and neutral or triple pole with fuses on three
phases and provided with removable link on the neutral. The switch to
be provided with interlocking device to prevent the cover being opened
when the switch is in the "ON" position. All current carrying metal
parts shall be in brass and switch to be provided with entry holes and
insulating bushes.
5.0 Socket outlets shall be of the standard 3 pins, shock proof type bakelite
covered with a porcelain ceramic or track free plastic base and provided with a
shutter mechanism operated by the earth pin on insertion and withdrawal of
plugs. All metal parts to be in brass. This item shall comply with B.S.S.
546/1979 and latest amendments thereto.
6.0 Earth pipe shall be of heavy quality galvanized iron pipe 50mm in diameter
and 2000mm long with one brass bolt welded to the pipe at top with two
brass hexagon nuts and washers. The pipes should be symmetrically tapered
at the bottom end.
7.0 Fan hooks shall be of mild steel rods 18mm size.
8.0 G.I. Pipes for fan beams shall be of galvanized 50mm size
9.0 Lamp shades plastic conical 250mm shallow type.
10.0 Earth leakage trips (current operated) shall be of shock proof bakelite cover
all insulated type two pole or 4 pole according to requirements having a
switch
and handle to "ON" and "OFF". The breaker shall be designed to operate
with the leakage current not exceeding 30MA through the trip coil complete
with test key. This earth leakage circuit breakers shall be mounted very close
to the apparatus to be protected on a wooden block of suitable size.
11.0 Distribution Board shall be SP & N or TP & N as specified in the design.
MCB board shall comply with BS 5486 Part III. Every distribution shall be
provided with a multi terminal earthling conduit.
12.0 Fluorescent lamp fitting whether batten or suspension type shall comprise of
a current limiting choke which assists starting a Thermal or glow type starter
having a radio interference suppression capacitor and a power factor
XLI
Correcting condenser.
Each fitting shall be complete with Metal/Copal Perspex reflector. Bi-pin
lampscaps fluorescent tubes and Bi-pin lamp holders all completely wired
internally. The fitting shall be suitable for the use on 230 Volts. Single phase,
50 Hz., A.C. supply. Suspension of fitting shall be rigid tubes or brass chain
fixed to hooks screwed into rawl or Phil plugs buried in ceiling or any other
approved method. Batten type fitting shall be fixed direct on to the support by
the air of Phil or rawl plug or any other approved method.
13.0 Ceiling fan fitting shall be of the three bladed type with insulator and shackle
and suitable length of down rod and canopy with motor for use on 230 Volts
50 Hz. single phase A.C. supply. The motor shall be of the totally enclosed
shaded pole induction or capacitor type fitted with grease packed ball bearings
and the fan shall be white enamel finished. Provisions shall also be made for
an electorlier when required. The terminal block in the fan as well as the
capacitor must be protected by removable covers.
14.0 Fan regulator shall be of the series choke or resistance type and shall have at
least 5 speeds and "OFF" position. Regulator unless fully insulated must be
earthen.
15.0 MCCB: 400V, 3 phase, 3 poles and neutral, 50 Hz.
B.S. 3871 Part II 1966.
The case shall be of moulded insulating material, possessing high thermal
stability and good mechanical strength to withstand rough usage without any
fracture of permanent distortion having front operating handle with trip free
feature for manual "ON" and "OFF" operation.
It shall comprise:
(1) A delayed thermal or magnetic release which shall be
adjustable between 60% to 100% of maximum continuous
current rating of the breaker.
(2) An instantaneous electromagnetic over current release which
shall be adjustable between 3 to 5 times to maximum current
rating of the breaker.
The making and breaking capacity in KA and the performance category as per
BS 4752 Part I 1977.
16.0 MCB : 400V/230V, 50Hz. as per BS 3871 Part I 1965; IEC 157-1
The case shall be of sealed type and made of moulding insulating material
possessing high thermal stability and good mechanical strength to withstand
rough usage without any fracture of permanent distortion.
The MCB should possess mechanical life span and component life span at the
rated current not of less than 20,000 operation or 40,000 movements. It shall
be single pole or triple pole type with separate detachable neutral link and
having provision for accommodating incoming and outgoing aluminum or
copper service wire up to 16mm2 for Amps. and 20mm2 for Amps.
4. Special Specifications for Air-conditioning
Technical Specifications for Split Type Air-conditioners
XLII
(A) From 12000 BTU/Hr upto 24000 BTU/Hr.
i Indoor Unit
(a) Fan shall be multiple speed
(b) Fan motor bearing - permanently lubricated ball bearing type
(c) Air filter shall be washable type
(d) Operational control shall be wired type remote control type
ii Out door Unit
(a) Casing and condenser shall be of weatherproof construction
suitable for tropical climate.
(b) Fans shall be suitable for outdoor use
(c) Fan motor bearing shall be permanently lubricated ball
bearings.
(d) Shall be supported in such away that casing is not exposed to
accumulated rainwater and also that there is sufficient room
and safety requirements to attend to servicing.
(e) Compressor shall be scroll type.
iii Protection Devices/Alarm
(a) Compressor - Overload protection
Internal thermostat
Anti re-cycling timer
Filter cleaner Notice
(b) Fan motor - internal thermostat.
iv Plants shall be suitable for single phase x 230V x 50Hz.
v Condensate lines shall be insulated (25mm thickness) in indoor areas.
vi Technical catalogues shall be submitted.
(B) For plant above 24000 BTU/Hr.
Following changes additions shall apply.
Protection devices (Additional)
(a) High pressure switch
(b) Low pressure switch
(c) Anti-phase protection
Plant shall be suitable for 3 phase 400V, 50Hz power supply.
(C) Quality Standards
Plants offered shall have ISO 9001 quality accreditation and a copy of certificate shall
accompany with the offer.
5. Special Specifications for Water Proofing
General:
(a) Warranty
(i) Insulation, waterproofing and tanking shall be applied in accordance
XLIII
with the directions of the manufacturer of the materials and
components, and the complete systems shall be fitted in the works by
experienced specialist crew.
(ii) Notwithstanding maintenance requirements for the works, the
Contractor shall warrant the Owner with the assurance of a reputable
local insurance Company that roof and tanks shall remain waterproof,
vapor proof and damp-proof in respect of workmanship and materials
for a minimum period of 10 years calculated from the time that the
works are certified as substantially completed.
(iii) The form of guarantee offered by the specialist, applicator shall be
submitted for the Consultant’s approval prior to
commencement of waterproofing. This guarantee shall in no way
indemnify the Contractor against the improper performance of
the waterproofing system.
(iv) All structural components that retained or exclude water or any other
liquid should be applied with approved waterproofing material.
(v) Roof slab should be externally waterproofed and insulated by an agent
approved by the Consultant.
(b) Structure
(i) It shall be the Contractor’s responsibility to ensure that the specialist
applicator takes note of the type of the structure, nature and the
location of waterproofing to be applied including any movement joints
provided, when designing his waterproofing system.
(ii) The laying of a waterproofing system on a concrete surface will be
taken as signifying the acceptance of that surface., both in terms of
surface quality, spacing and arrangement of movement joints and the
construction joints by the Contractor and his specialist applicator.
(c) Application
(i) Where applicable, aprons and other sections for roof/tank penetrations,
rims, side laps, bends and corners shall be incorporated, corrected,
finished and uniformly lined.
(ii) The waterproofing system shall be dressed up all pipes and other
penetrations to a minimum height of 250 above the top of the concrete
slab.
(iii) Sharp corners are to be filled with screed or other fillets and
waterproofing should be laid with generous over lap as per
manufacturer’s instructions.
(iv) When waterproofing is to be applied on exposed areas, colors have to
be approved by the Consultant.
(v) Where finishes such as concrete paving or tiles etc., are specified to be
laid over waterproofing membranes laid on concrete floors, the floor
shall be tested for water tightness prior to laying of these tiles/paving’s
etc. Sumps, tanks etc. shall also be tested after the application of
waterproofing systems. The cost of carrying out these tests including
XLIV
that of blocking any outlets etc. shall be borne by the Contractor.
Where it is seen that water tightness has not been achieved, the
Contractor shall take whatever remedial measures as are ordered by
the Consultant and the cost of all such measures shall be borne by the
Contractor.
(d) Joints with abutting walls, columns, piping etc.
(i) Joints with abutting structure shall be carried out with materials as
specified in the relevant Clause of other trades, such as weather sealant
etc. all as generally shown otherwise in typical details on the drawings.
(ii) Special joints, not shown on drawings or particular sections there of
requiring specials attention, are deemed to be included in the
Contractor’s Tender, and are to be executed in a workman like manner
nd in consent with and to the satisfaction of the Consultant.
Waterproofing System to roof slabs and machine floor areas
(a) Leveling Screed
(i) Before laying the leveling screed the concrete surface shall be cleaned
by removal of loose materials to the entire satisfaction of the
Consultant. Concrete which is contaminated by oil or grease shall be
chiseled away and refilled.
(ii) Concrete slab shall be grouted with cement/water slurry before the
laying of leveling screed.
(iii) 1:3 Cement: Sand leveling screed shall be mechanically bath mixed
and laid with a minimum thickness of 25mm, the falls to be achieved
are not less than 1:200 or as shown in the drawings. Screed shall be
laid with even slopes and internal and external corners shall have cover
fillets with a radius of at least 70mm. The screed shall be finished with
a wooden float.
(iv) The screed shall be covered with wet saw dust, sand or equal method
and kept damp for 5 days, or as ordered by the Consultant. Screed
shall be protected from rainfall. Waterproofing membrane shall not be
applied until the surface is thoroughly dried out.
(b) Waterproofing WP1
(i) The following specification is for a built-up waterproofing system of
non-metalic roofing compound of laminar bituminized construction
intended for this Project. The Contractor may submit alternative
reputable constructions together with the relevant specification and
method statement to the approval of the Consultant; such constructions
should in any case conform to the insurance requirement specified
under “Warranty” requirement (See Clause 3.1.1).
(ii) Waterproofing membrane shall be U.V. resistant mineralized atactic
polypropylene (APP) modified bituminous polyester sheet with
approximate weigh 4.0 kg/m2 and 4.0mm thick suitable for Torched-
on application over the substrate after application of the approved
primer.
XLV
An interruption of work the edges of the sheets have to be finished in
such a manner that rain water and dust cannot penetrate underneath.
(c) Insulation
(i) On top of the waterproofing membrane, polyurethane or extruded
polystyrene boards 50mm thick with Thermal conductivity of
0.027 W/m0C @ 250C (approx.).
(ii) Method should comply with the following standards ASTM D-1622,
ASTM C-518, ASTM C-272 and ASTM D-696.
(iii) The boards shall have rebated edges all round for interlocked laying.
In sizes 600 x 1200mm tightly laid in stretcher bond.
(iv) The compressive strength of the insulation boards shall be not less than
40kPa according to ASTM C-165 procedure B.
(v) Insulation boards shall be protected against rain and humidity.
(d) Concrete Covering Screed
(i) 60mm Thick, grade 25 concrete covering screed shall be laid over the
gauge 1000 polythene sheet as shown on the drawing. 50 x 50mm
(3mm dia.) galvanized steel wire-mesh shall be incorporated in the
concrete screed layer. 10mm Thick expansion joints shall be
provided in covering screed to limit the concrete screed panel size
approximately to 4.0 Sq.m.. Expansion joints shall be coincided with
the joints of the tile layer (if any) above and later filled by the
approved joint sealant (DOWCORNING 790 SILICONE
BUILDING
SEALANT).
(iii) Alternatively, reinforced concrete floating slab shall be constructed in
stead of concrete screed if there is any possibility of installation of
mechanical plants or equipment.
Waterproofing System to Basement Slab
(a) Concrete Screed
(i) Concrete screed shall be mechanically batch mixed and laid over the
well compacted and approved formation of the sub base or otherwise
directed by the Consultant. The concrete grade 15 shall be laid to
produce a concrete screed of 75mm thick.
(ii) The screed shall be covered with wet saw dust, sand or equal method
and kept damp for at least 5 days, or as instructed by the Consultant.
(iii) Before laying of the waterproofing membrane, the concrete surface
shall be thoroughly cleaned and dried out.
(b) Waterproofing Membrane (WP2)
(i) The prepared concrete surface shall be waterproofed by means APP
bituminous polyester sheet with approximate weight 4.0 kg/m2 and 4.0
mm thick suitable for torched-on application over the substrata after
application of approved primer.
General notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATES

More Related Content

What's hot

Fidic contract
Fidic contract Fidic contract
Fidic contract Yash Patel
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -artijagadish108
 
M3 Lecture 11 provisional sum prime cost sum
M3 Lecture 11 provisional sum  prime cost sumM3 Lecture 11 provisional sum  prime cost sum
M3 Lecture 11 provisional sum prime cost sumEst
 
Civil tenders and contracts spce
Civil tenders and contracts spceCivil tenders and contracts spce
Civil tenders and contracts spceirkportal
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment마 이환
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and ArbitrationJIT KUMAR GUPTA
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentationArchDuty
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract AdministrationGerald R. (Jerry) Genge
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver bookHani Saad
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
DEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESDEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESShivam Sood
 

What's hot (20)

Fidic contract
Fidic contract Fidic contract
Fidic contract
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
M3 Lecture 11 provisional sum prime cost sum
M3 Lecture 11 provisional sum  prime cost sumM3 Lecture 11 provisional sum  prime cost sum
M3 Lecture 11 provisional sum prime cost sum
 
Civil tenders and contracts spce
Civil tenders and contracts spceCivil tenders and contracts spce
Civil tenders and contracts spce
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and Arbitration
 
Lump Sum Contract
Lump Sum ContractLump Sum Contract
Lump Sum Contract
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Fidic
FidicFidic
Fidic
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Ms.jkr.20800.2005
Ms.jkr.20800.2005Ms.jkr.20800.2005
Ms.jkr.20800.2005
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentation
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver book
 
Construction process
Construction processConstruction process
Construction process
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
 
DEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESDEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSES
 

Similar to General notes to BSR BUILDING SCHEDULE OF RATES

Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationHarish Mahavar
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdfSaqib Imran
 
Measurement 4:presentation slides
Measurement 4:presentation slidesMeasurement 4:presentation slides
Measurement 4:presentation slides마 이환
 
Wagstaff and Cartmell stairs
Wagstaff and Cartmell stairsWagstaff and Cartmell stairs
Wagstaff and Cartmell stairsRichard Clark
 
Lec - 2.ppt ganbella university quantity estimta
Lec - 2.ppt ganbella university quantity estimtaLec - 2.ppt ganbella university quantity estimta
Lec - 2.ppt ganbella university quantity estimta2cd
 
ZA CONTRACT AL NOOR.docx
ZA CONTRACT AL NOOR.docxZA CONTRACT AL NOOR.docx
ZA CONTRACT AL NOOR.docxFairFASST
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2Shze Hwa Lee
 
STANDARD SPECIFICATIONS FOR BUILDING WORKS.pdf
STANDARD SPECIFICATIONS FOR BUILDING WORKS.pdfSTANDARD SPECIFICATIONS FOR BUILDING WORKS.pdf
STANDARD SPECIFICATIONS FOR BUILDING WORKS.pdfMehediHasan615606
 
Standard specifications for_building_wor
Standard specifications for_building_worStandard specifications for_building_wor
Standard specifications for_building_worGAJENDRAN MUTHUKRISHNAN
 
IMPORTANCE & PURPOSES OF SPECIFICATION
IMPORTANCE & PURPOSES OF SPECIFICATIONIMPORTANCE & PURPOSES OF SPECIFICATION
IMPORTANCE & PURPOSES OF SPECIFICATIONSagar Kaptan
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-IKishor Ade
 
Architectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsArchitectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsGalala University
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignmentlohwenjun
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017DarrenTofu
 
Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBESahl Buhary
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 

Similar to General notes to BSR BUILDING SCHEDULE OF RATES (20)

Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping station
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdf
 
Measurement 4:presentation slides
Measurement 4:presentation slidesMeasurement 4:presentation slides
Measurement 4:presentation slides
 
Wagstaff and Cartmell stairs
Wagstaff and Cartmell stairsWagstaff and Cartmell stairs
Wagstaff and Cartmell stairs
 
Lec - 2.ppt ganbella university quantity estimta
Lec - 2.ppt ganbella university quantity estimtaLec - 2.ppt ganbella university quantity estimta
Lec - 2.ppt ganbella university quantity estimta
 
15CV81-Module-3.pdf
15CV81-Module-3.pdf15CV81-Module-3.pdf
15CV81-Module-3.pdf
 
ZA CONTRACT AL NOOR.docx
ZA CONTRACT AL NOOR.docxZA CONTRACT AL NOOR.docx
ZA CONTRACT AL NOOR.docx
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
STANDARD SPECIFICATIONS FOR BUILDING WORKS.pdf
STANDARD SPECIFICATIONS FOR BUILDING WORKS.pdfSTANDARD SPECIFICATIONS FOR BUILDING WORKS.pdf
STANDARD SPECIFICATIONS FOR BUILDING WORKS.pdf
 
Standard specifications for_building_wor
Standard specifications for_building_worStandard specifications for_building_wor
Standard specifications for_building_wor
 
Practice notes for_quantity_surveyors_fi
Practice notes for_quantity_surveyors_fiPractice notes for_quantity_surveyors_fi
Practice notes for_quantity_surveyors_fi
 
IMPORTANCE & PURPOSES OF SPECIFICATION
IMPORTANCE & PURPOSES OF SPECIFICATIONIMPORTANCE & PURPOSES OF SPECIFICATION
IMPORTANCE & PURPOSES OF SPECIFICATION
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-I
 
Architectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsArchitectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction Documents
 
Tanmay presentation
Tanmay presentationTanmay presentation
Tanmay presentation
 
contract procedure
contract procedurecontract procedure
contract procedure
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
 
Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBE
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 

More from R.R.G.S Bandara

More from R.R.G.S Bandara (6)

Prolongation cost calculation
Prolongation cost  calculation Prolongation cost  calculation
Prolongation cost calculation
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Legal system of sri lanaka
Legal system of sri lanakaLegal system of sri lanaka
Legal system of sri lanaka
 
Automo lesson3
Automo lesson3Automo lesson3
Automo lesson3
 
පිලිකා cancer protection
පිලිකා cancer protectionපිලිකා cancer protection
පිලිකා cancer protection
 
00 eng tech note1
00 eng tech note100 eng tech note1
00 eng tech note1
 

Recently uploaded

Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxsomshekarkn64
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 

Recently uploaded (20)

Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptx
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 

General notes to BSR BUILDING SCHEDULE OF RATES

  • 1. CONTENTS 1. INTRODUCTION II 2. GENERALNOTES IV 3. PRICING PREAMBLE IX 4. SPECIFICATIONS XXXI 5. SAMPLE PRELIMINARIES BILL XLIV 6. B.S.R. 1 TO 89 7. BASIC MATERIAL PRICES PRICE LIST P1TO P29
  • 2. II INTRODUCTION The Building Schedule of Rates, (abbreviated as B.S.R.) has been prepared based on work norms generally adopted for Building Construction work with eight hour labour input. The rates include an over-head and profit margin of 22%. The rates are intended to be adopted in pricing an Engineering estimate for the Construction, Maintenance or Additions and Improvements to a Building. The item description of the B.S.R. has been drafted with a view to directly incorporated in to a Bill of quantities which in turn will be used as a bidding document for measure and pay type contract along with specifications, drawings etc. The Preamble Notes which include General Preamble Notes and Pricing Preamble Notes indicate the basis upon which the each and every trade item of the B.S.R. has been arrived at; there fore same preamble notes shall be attached to the B.O.Q. in the event of B.O.Q. items been derived from the B.S.R. The abbreviations B.S.R. and B.O.Q. has been used inter-alia to facilitate the same notes been directly adopted to the B.O.Q. For any clarifications or suggestions please feel free to communication with the Director- Engineering of the Western Provincial Council on phone/ Fax 2675438 or e-mail Please note that each and every B.O.Q. shall consist of the following documents a) General Notes b) Pricing Preamble c) The B.O.Q. it self Please refer clause 1 of the General notes for the definition of B.O.Q. Data relating to B.S.R. trade items. 01. The approved rates for the following trade items listed in the following table are meant for single storied (Ground floor only) buildings. Hence, allowances to be made in the rates for lift in respect of work on upper floors. The percentages indicated in the Table below should be added to obtain the rates applicable to the upper floors. 02. Following conversion factors should apply for the rates when it is necessary to convert from the Imperial Units to Metric. Trade Item Unit First Floor Second Floor Third Floor Formwork ( s) 1% 2% 3% Plastering (Sqrs) 5% 10% 15% Floor Tiling (Sqrs) 2% 4% 6% Wall Tiling (Sqrs) 2% 4% 6% Roof Calicut Tile (Sqrs) 3% 6% 9% Roof asbestos (Sqrs) 3% 5% 7% Ceiling Works (Sqrs) 3% 5% 7% Painting (Sqrs) 3% 6% 9% Rendering (Sqrs) 4% 7% 10% Block work (Sqrs) 3% 5% 7%
  • 3. III Conversion Imperial to Metric factor (1foot x 0.3048 = metre) To convert Rate per To Rate per Multiply the Present Rate by Cube M3 0.353 Square M2 0.108 Sq.ft. M2 10.764 L.ft. M 3.281 03. IRON and STEEL gauge systems Standard Wire Gauge. Birmingham Wire Gauge No. SWG BWG mm inch mm inch 20 0.914 0.036 0.996 0.0392 18 1.219 0.048 1.257 0.0495 16 1.626 0.064 1.588 0.0625 04. Units To convert “Litres to “Galloons” multiply by 0.2205 “Miles to “Kilometers” multiply 1.6090 “Kilo to “Pounds” multiply by 2.2050 05. Steel Dia. Mm Dia. Inch Normal Weight Kg per meter 25 1 3.854 20 3/4 2.466 16 5/8 1.579 12 1/2 0.888 10 3/8 0.617 6 1/4 0.222
  • 4. IV GENERAL NOTES 1) The preamble notes which include General notes, Pricing Preamble and B.O.Q. are collectively referred to herein as the Bills Of Quantities and shall jointly constitute the Bills Of Quantities referred to in the Conditions Of Contract. The specifications and the Drawings are to be read in conjunction with the Bill Of Quantities. 2) The Bills Of Quantities have been prepared generally in accordance with the principles laid down in the Method of measurement of Building works (First Revision) SLS 573:1999 published by Sri Lanka Standards Institution and rates shall include for everything required for completion of each item of work in accordance with the specifications and drawings. The relevant clause of this preamble notes shall be deemed to apply equally to work subsequently ordered for execution by the Bidder, either under Provisional Sum orders or variation orders, except where specifically varied therein. 3) The works as executed will be measured for payment in accordance with the method adopted in the Bill Of Quantities and under the item as therein set forth. The net measurement or weight of the finished work in place will always be taken, and except where otherwise stated or where separate items are provided, no allowance will be made for cutting, waste, laps, circular works, etc., and no deductions will be made for grout nicks, joggle holes, rounded arises or for shrinkage for fitting ironwork and the like. Payment will be made for only those materials, which are specified and permanently installed in the works to the approval of the Engineer. Construction materials supplied and delivered to the site by the bidder which become surplus to the requirements of the works shall become the property of the bidder who shall reimburse the Employer any money that was paid to the Bidder for the Supply and delivery to the site of the surplus materials. 4) Unit Rates and extensions shall be given in Sri Lankan Rupees to a maximum of two significant places of decimals. 5) Inspection of site Bidders are requested to visit the site to acquaint themselves with all existing conditions, and with the nature and extend of work to be done under the contract as no extras will be allowed on the plea of want of information due to neglect of their part in this regard.
  • 5. V Hence bidders are advised to inspect the site and acquaint themselves regarding the following in addition to any other information that may be required. 1. Extent and nature of the work to be done 2. Site conditions 3. Storage facilities etc. 4. Transport facilities. 5. Weather conditions in the locality 6. Limitation of working time 7. Transporting and handling materials etc., including security clearances. 6) Type of Contract The contract shall be a measure and Pay fixed Rate Contract 7) Quality of Materials & General Standards of Works All materials used in the work shall be the best quality of their respective kinds as specified in the B.O.Q. , the “Particular Specification” or in the General specifications (i.e the specifications listed in the bidding document) and shall obtain the same from manufacturers’ , agents or suppliers approved by the Engineer and shall comply strictly with the test prescribed herein or in the standard specifications (Both General or Special). When such specifications or tests are not laid down in the said specifications the material and works shall comply with the latest issue of the relevant British Standards or other standards approved by the Engineer. Where trade names, Brands and/or catalogue numbers are referred to; this is done in order to establish a standard, quality, or other reference benchmark and sole preference for any manufacturer is not intended. Similar items may be used, provided they are equivalent and provided the characteristics of type, quality, appearance, finish, Method of Construction and/or performance are proved by the Bidder to be not less than specified and provided also that the approval is first obtained from the Engineer. Where the Bidder wishes to use materials or components etc. obtained from manufacturers other than those mentioned in these specifications or on lists of approved manufacturers, it shall be incumbent upon him to prove to the complete satisfaction of the Engineer that the products which he proposes to substitute are equal in quality and appearance to those mentioned or described in the specifications, and that the manufacturer is a reputable business of long standing, producing quality products. Unless otherwise stated, the cost of the tests required by this specification or the relevant British or other approved Standards shall be deemed to be including in the contract sum and rates. Test certificates covering all materials for which certificates are required and are supplied for the works shall be submitted to the Engineer for approval.
  • 6. VI No materials shall be used in the works unless the same has been approved by the Engineer. Approval by the Engineer of materials inspected by him or acceptance by the Engineer of certificates of Tests in lieu of inspection shall vitiate the right of the Engineer to reject after delivery to site or incorporation in the works, material found to be unsuitable or not in accordance with this specification. Before ordering materials of any description, the contractor shall submit, for the approval of the Engineer the names of the manufacturers or suppliers proposed, and shall afterwards send to the Engineer, copies in duplicate of the orders placed by the contractor for the said materials. 8) Units and Extension of Bill Of Quantities All sizes and quantities have been entered in the Bills Of Quantities in Metric /Imperials Units. Figures involving decimals, including sums of money are written in the British tradition, namely, with a full stop in the decimal position and commas between each successive group of three digits to the left of the decimal position. 9) Rates and Sums to be for Work Complete Notwithstanding any limits which may be implied by the wording of the individual items and/or explanation in this preamble it is to be clearly understood by the Bidder that the rates and sums which he enters in the Bills Of Quantities shall be for the works finished complete in every respect, he shall be deemed to have taken full account of all requirements and obligations, where expressed or implied, covered by all parts of the contract, and to have priced the items herein accordingly. The rates and sums must therefore include for all incidental and contingent expenses and risks of every kind necessary to construct. Full allowance shall be made in the rates and/or sums against the various items in the Bills Of Quantities for all costs involved in the following inter-alia, which are referred to and/or specified herein except where separate are provided. 1. All site investigations, which may be necessary; 2. All setting Out and Survey work; 3. Temporary fencing, watching, and lighting; 4. Paying fees and giving notice to authorities; 5. Payment of all patent rights and royalties; 6. Reinstatement of the site; 7. Safety precautions and all measures to prevent and suppress fire and other hazards; 8. Interference to the works by persons, vehicles, and the like who may use the existing facilities; 9. Works in connection with the protection and safety of adjacent structures; 10. Supplying, Maintaining and removing on completion Contractor’s own accommodation, Offices, stores, workshops, Transport, Welfare services
  • 7. VII and all charge in connection therewith; except those for which a separate BOQ item is provided; 11. Working in the dry except where otherwise permitted by the specification; 12. Maintaining internal roads; 13. The supply, Inspection, sampling and testing of materials and of the works under construction, including the provision and use of equipment; 14. Except where separate items are provided for bringing construction plant to the site and removing on completion, for providing, transporting to site, setting to work operating (including all fuel and consumable stores), maintaining and removing from the site upon completion all construction plant and equipment necessary for the execution of the work, including the cost of all tests and other requirements in respect to such plant and equipment; 15. The recruitment, bringing to and from the site accommodating and feeding and all incidental costs and expenses involved in the provision of all necessary skilled and unskilled labour and supervision, except for whom a separate BOQ item is provided; 16. All statutory taxes and levy, surcharges etc. including stamp duty payable on the contract, which will have to be borne by the Bidder. 17. Establishment charges, Overhead Charges and profit. No claim will be considered for further payment in respect of any work or method of execution, which may be described in the contract or is inherent in the construction of the work and detailed on the drawings on account of 1. Any omission from the wording of the items or from a clause in the preamble or 2. No mention of such work or method of execution having been in the preamble 10) Rates and Sums to Bear Proper Relation to work Described The rates and sums entered by the Bidder against all items in the Bills Of Quantities must bear a proper relationship to the cost of carrying out the work described in the contract; all on costs and similar charges which are applicable to the contract as a whole are to be spread over all the rates in the Bills Of Quantities, whilst those which are applicable only to particular sections of the contract are only to be spread over items to which these sections refer. However, the Bidder shall ascertain the exact nature and extent of work to be performed with reference to the Drawings, Specifications and Conditions of Contract as the case may be. 11) Provisional Sum Items Provisional sums will be dealt with as provided for in the Conditions Of Contract. Provisional sums are represented by the words “Provisional Sum”, or “PS” entered under the description. 12) “Provisional Quantity” , “Lump Sum” & “ Items”
  • 8. VIII Certain items in the Bills Of Quantities are designated as “ Provisional Quantities” or “Lump sum” or merely as an “Item” in the description column. “Provisional Quantities” may used to indicate that the quantities for the work covered by such items are “provisional”, or that the provision of such facilities as are described in the item may not in the event be required under the contract. All items so designated will be used only at the direction and discretion of the Engineer, and if not used either wholly or in part shall, as to the amount not used, be deducted from the Contract Price. Where such items are designated as of a “Lump Sum” or “Item”, the Bidder shall enter a lump sum, which shall be the price for the work if executed, as distinct from a “Provisional Sum” as defined herein. No claim will be entertained in respect of overhead charges or any other costs, which may allegedly result from the omission of all, or part of the work covered by such “Provisional Quantity” or “Lump Sum” Items. 13) Day Works Schedules For a work of a minor or incidental nature for which a realistic rate analysis may not be possible to arrive at the Engineer may instruct that portion of the work to be executed on a day works schedule, provided a Day work schedule is included in the contract. 14) Payment of Items in a Monthly Basis Payment under items, which are measured on a monthly basis, will not be certified by the engineer until the facilities described in the items and the Specification has been provided to the satisfaction of the Engineer. Payment will continue until such time as the Engineer shall signify that facilities are no longer required. 15) Protection Of Work and Clearing upon Completion The Bidder shall allow, in his rates, for protection of completed work from subsequent operations, making good all damage to complete work, for clearing away all rubbish as it accumulates, and leaving the site in a tidy condition to the satisfaction of the Engineer. 16) The Unit and Lump Sum prices of the Bill Of Quantities (referred to as the contract rates) shall, except in so far as is otherwise provided for under the contract, be deemed to cover all obligations set out in the contract, and all matters or things necessary for the proper completion and maintenance of the works, and shall be fixed and binding upon the Bidder. 17) Unit Prices when applied to the quantity of work performed under the contract shall, and other sums specifically determined under the Provisions of the Contract, constitute full remuneration to the Bidder under the contract. 18) The quantities set out in the Bill Of Quantities are provisional and cover the approximate scope of the work which is anticipated that the contractor may be required to perform. The actual quantities to be used for final measurement purposes will be determined by the Engineer by measurement of the work completed by the Bidder.
  • 9. IX 19) Abbreviations Abbreviations used in this Bill Of Quantities denote the following. Sqr - Square Ft - Feet Ft2 - Square feet m - metre m2 - square metre m3 - cubic metre mm - milli metre cm - centi metre kg - kilogramme h - hour Nr - Number (to indicate a quantity) No. - Number(to indicate an item number, page number etc) B.O.Q. - Bill Of Quantities Ele. - Elevation G.L. - Ground Level G.W.T. - Ground Water Table c/c - center to center @ - each Gr - Grade Approx - approximately Thk. - thick R.C.C. - Reinforced Cement Concrete M.S. - Mild Steel T.S. - Tor Steel R - Mild Steel Y/T - Tor Steel C.I. - Cast Iron W.I. - Wrought Iron F/w - Formwork R/F - Reinforcement Wk - Week Mon - Month L.day - Labour day MM - Man Month Rs. - Sri Lanka Rupees Cts. - Cents
  • 10. X PRICING PREAMBLE Unless otherwise specified in the respective trade sections, the following pricing preamble from 1 to 30 shall be inclusive for respective trades. 01.Demolition Rates for Demolition shall include demolishing, dismantling and removing etc. with the minimum damage to the material in the process of dismantling, temporary supporting and protecting existing work and adjacent properties against damage, dust and weather and stacking all serviceable materials as directed and disposal of debris from site including spraying water periodically to reduce the amount of dust. All serviceable materials in demolished structures shall be the property of the Client. Necessary approvals to be taken from suitable authority prior to disposal of demolished parts. 01.Excavation and Earth Work Rates for Excavation & Earth Work shall include: 1) Excavation in all Material except Rock The rate and prices for excavations shall be for all types of material encountered except rock including ground conditions above or below water level. The Bidder must make due allowance for the possibility of permission not being granted to the use of explosives for blasting and other operations. a) For structures, volume of material excavated measured as a product of the horizontal area of the base of permanent works to be constructed and the mean depth below ground level, or measured as the volume to be occupied by permanent work below ground level, whichever is the greater. In no case shall any of the following quantities be included in the measurement for payment. I. Quantity outside the vertical planes of neat outline of foundation structures unless shown otherwise on the drawings. II. Quantity of excavation and/or backfill for water supply pipe lines, sewer pipe lines, and storm drainage except as allowed for in pipe line construction as specified. III. Quantity of any excavation performed prior to the taking of measurements of the undisturbed natural ground.
  • 11. XI IV. Quantity of any material re-handled, except where the drawings indicate or the Engineer directed the excavation after embankment has been placed. V. Removal of slides, cave-ins, silting or filling due to the action of the elements or weather and/or carelessness of the Bidder. b) For unsuitable material, volume of excavated material shall be measured as volume of material (below base of the permanent works) directed to be removed by the Engineer. No allowance is made for bulking or for any extra transport required due to bulking. The rates shall include, if separate items are not provided but not by way of limitation for; a. Excavation to the correct depth and preserving the bottoms of excavations in a state suitable for the reception of concrete or other foundation work, and no payment will be made for any concrete any bedding required for filling over excavated volumes or disturbed areas to the net dimensions as indicated on the Drawings. b. Any additional excavation required for shuttering, working space, temporary or permanent shoring, as subsequent refilling and ramming and disposal of surplus and back fills behind structures. c. Provision of storage areas for the temporary storage of any material required for back filling which cannot be stored alongside the excavation for any reason, together with the cost of transporting, loading including disposal of surplus and unloading such material and all other charges incurred in this respect. d. Trimming the bottoms of excavations including bottoming to falls and trimming to sloping surfaces where required or indicated on the Drawings. e. Taking all precautions by supporting faces of excavation to ensure the safety of the workmen and to prevent damage to adjacent walls, building and all other structures and services, including permanent and/or temporary shoring of trenches. f. Keeping the site and trenchers and all other excavations free from water from whatever because arising. g. For clearing any scrub or other vegetable growth including all trees and for disposing of the whole of the cleared material to tip provided by the contractor. h. All temporary and permanent measures required to protect and support all existing pipes cables and services, including all chambers, gullies and foundations thereto, or repair or replace them should they become damaged due to the contractor’s activities. i. All barriers, lighting, warning signs and any other measures necessary to ensure complete safety around the area of works.
  • 12. XII j. Reinstatement except where separate items are included. 2) Excavation in Rock Excavation in rock, which shall, in all cases, be measured extra over measurement under 1(a) or 1(b) above by volume from the level at which rock is encountered. For work described under 1(a) and 1(b), measurement shall be as specified therein 3) Fill Fill shall be measured as the net volume above ground level of the permanent earthwork to the detentions shown on the Drawings or ordered by the Engineer, irrespective of source of material. The rate shall include for selection, handling, placing, compaction of excavated or imported material and cost of control and material selecting tests (field and laboratory). Costs incurred in connection with the remedial work ordered by the Engineer consequent to the results of control tests falling below the minimum specified shall be borne by the Bidder. Rate for Hard Earth Filling shall include 1. Filling in layers, (not more than 1'0") well ramming and consolidating. 2. The earth shall be free of vegetation, roots, boulders easily decomposable materials, chemicals, industrial waste, plastic etc. 3. The maximum size of particle shall not exceed 75mm. 4. The earth shall be well graded and contain silt and clay (fines) not more than 30%. 02.Clearing Site Removal of roots and growth of every description, removing top soil up to a depth of 6" (150mm) and extended up to 10'0" (3 Meter) beyond the outer walls of the proposed structure and carting away the waste materials from the site where directed. Existing trees or other plants shall not be removed or cut without instructions from suitable Authority. Trees to be retained shall be protected from damage of any sort. 03.Concrete THE RATES FOR CONCRETE ARE TO INCLUDE FOR a. All costs incurred in determining the mixes to satisfy the specification(including any admixtures);
  • 13. XIII b. Supplying all material (including any admixtures), storing, mixing, transporting, placing and compaction (whether by hand or vibration); c. Excavation as required below previously filled levels and back filling (except where separate items are provided) d. Roughening the surface of previously executed work as required in order to provide the necessary bond with new concrete; e. Achieving specified tolerance; f. Forming sloping, falls and the like; g. Forming holes or boxing out for pipes, bolts, frames for covers and other steel work; h. Building in cable conduit, pipes, junction boxes etc. i. Forming 25mm chamfers an all external arises to exposed concrete; j. Forming all construction joints, keys, stop ends, temporary stops and shuttering of other than permanently exposes faces( except where separate items are provide) k. Curing the concrete and all measures to protect freshly poured concrete from direct sunlight and wave action; l. Toweling, rubbing down etc. and making good the concrete surfaces to provide the specified finishes; m. The cost of control testing throughout the period of concreting and for the testing of concrete and remedial work ordered by the Engineer consequent to the results of control tests falling below the minimum specified; n. Overtime working to maintain continuity of casting; o. A daily return to the Engineer showing the quantities of cement and the volume of concrete placed and compacted in position, of each class of concrete in each section of the works and temporary works. The measurement of concrete shall be by cubic metre, square metre or linear metre of completed structure. Where volumetric measure is used, no deductions will be made for channels, recesses or rebates less than 600mm girth for splays or chamfers less than 300mm measured on the splay nor for holes or ducts formed in the concrete less than 1m girth. Fillets less than 300mm on the splay will be measured. 04.Form work Rates for Form Work shall include, necessary boarding, supporting, erecting, framing, cutting angles, striking or removal, cleaning and wetting. Form work is measured in same order as the concrete items. Form work is measured as the nett contact surface measurement between concrete and form work. (a). Form work to columns and beams is given as a girth measurements. (b). (i). Form work for footing, column, beams, lintel, walls, and slabs are of 15mm thick ply-boards. (ii). Slab thickness up to 4", soffit form work should be 3/4" thick minimum size planks and less than 3/4" thickness is not allowed.
  • 14. XIV (iii). Slab thickness over 4", soffit form work should be of 1" thick minimum planks sizes and less than 1" thickness is not allowed. (iv). Sides of form work (columns, beams and slabs) 1" thick minimum and less than 1" thickness is not allowed. (v). Soffit of form work (beam) 1 1/4" thick minimum less than 1 1/4" thickness is not allowed. In case of timber form work the size of material shall comply to 5.2.1.1 and the size of props and prop interval shall be as 5.2.4. 05.Reinforcement The rates for steel bar and steel fabric reinforcement shall include for supplying, transporting, storing, clearing bending, all labour in working, distribution to the various parts of the works, fixing in position and supporting and for the use of binding wire and for welding where indicated. The unit of measurement for steel reinforcement is the Kilogram (kg.) and the weight of steel has been calculated net with no allowance made for wastage or laps and the cost of these will be deemed to be covered in the rates. The weight of steel supports, spacer bars and ties, but including stirrups and binders, used to locate and hold the reinforcement in place is not included in the quantity and the cost of these will be deemed to be covered in the rates. 06.Brick Work Rates for Brick Work shall include rough and fair cutting, plumbing angles, forming arches, raking out joints, for pointing, plastering etc., cutting and pinning, making good and sundry items of a like nature. 07.Cement and Sand Hollow Block Work (a). Notes shall be applicable to Cement Sand Hollow Block Work as well. (b). Cement sand hollow blocks shall conform to SLS 855. Unless otherwise specified mortar for cement sand hollow block work shall be cement and sand 1:5. 08.Masonry (a) Rates for Masonry shall include all joggles, cramps, dowels, ties, templates, rough and fair cutting, forming splays, angles, reveals, settings, joining, fixing in position and pointing including hoisting not exceeding 20'0" above ground level, protecting and cleaning down. (b) Rates shall include for Builder's work in connection with all services and installations. 09.Structural Steel Work (a). Rates for Structural Steel Work shall include shop fabrication work including cutting, drilling, bolting, riveting, welding, grinding, marking, delivering, un-loading, hoisting, erecting and fixing in position.
  • 15. XV (b). Rate shall include for two coats of matt oil paint after treating with a coat of anti-corrosive paint to all exposed faces of trusses, angles, irons and channels. (c). All bolt holes to be machine drilled. (d). Steel shall normally be welded by the metal area process conforming to B.S. 5135. Other methods shall be subject to the approval of the authorities. (e). Unless otherwise specified all structural steel shall be Grade 43A. (f). Structural steel shall conform to BS 4360. 10.Stainless Steel Type and Quality All stainless steel for external applications shall be type 316S16 (18% chromium/ 10% nickel alloy/ 2.5% molybdenum) austenitic stainless steel cold formed, flat rolled plate, sheet and strip to BS 1449: Part 2: 1983, and shall agree with requirements of BS 970: Part 1: 1983. For internal applications type 304S16 *18% chromium/ 10% nickel alloy) may be considered as an alternative, at the discretion of the Consultant. Bars and strips shall be ‘brushed finish’ and sheet to be “embossed” finish in heavy duty areas e.g. life doors, kicking-plates, elsewhere ‘brushed finish’. Both finishes being as per samples provided by the Consultant. Where thin gauge stainless steel is used as a cladding materials, the problem of kinking or “oil canning” shall be overcome by bonding the sheets to plywood, (Marine plywood to BS 4079: 1966 for exterior applications), polymetric material, or by use of stiffening ribs of stainless steel as specified in this Article, at appropriate positions, bonding to plywood being done using a 2-part epoxy resin adhesive. All bolted or screwed fixing shall be of stainless steel, or if of other metals to be fully isolated from the stainless steel by use of nylon or neoprene washers, sheet, etc. Stainless Steel sheeting shall be 1.25 minimum thickness when bonded to plywood backing, except in heavy duty applications mentioned above, where 1.5 is the minimum thickness allowed. Where not bonded to plywood backing 1.5 shall be the minimum thickness. Welding Where stainless steels are welded, this shall be carried out using chromium nickel austenitic or other compatible electrodes for manual metal are welding to BS 2926: 1984 Care shall be taken to avoid distortion during welding or damage to or discoloration of surrounding finished surfaces. All welds shall be carefully ground and polished as required to blend the weld in the surrounding metal
  • 16. XVI 11.Metal Work (a). Notes in particular specification shall be applicable to Metal Work as well. (b). Flashing shall be 22 S.W.G. Aluminum 12.Suspended ceilings The rates for suspended ceiling tiles and panels and the like shall include for chamfering all cut edges; vertical bulkheads and cutting around light fittings, grills and diffusers or the like are also deemed to be included. Rates shall also be deemed to include any depth between the soffit of the slab to which the ceiling is suspended and the finished level. All linear shall include for angles, ends and the like. 13.Roof Covering and Roof Plumbing Rates for Roof Covering shall include laps, straight cutting and waste, nails, screws, clips rivets, straps and the like including hoisting and fixing complete. Zinc Alum roofing: 1 Zinc Alum profile sheet (minimum base metal thickness o.4mm and minimum thickness of 0.47mm.) 2 Zinc Alum gutter (minimum base metal thickness o.4mm and minimum thickness of 0.47mm.) 3 Zinc Alum down pipes (minimum base metal thickness o.4mm and minimum thickness of 0.47mm.) 4 Zinc Alum cladding (minimum base metal thickness o.4mm thick) 5 Up channel, 'C' channel and purling galvanized iron 6 material : 55% Aluminum zinc Al: Aloycoated Az 150, Hitensile (Grade 560) sheet. Purling - Hitensile - Hitensile strength - 400 mpa (minimum) Rates for Roof Plumbing shall include solder, rivets, screws, nails, clips, straps, straight cutting and waste for patterns mould or templates and for all hoisting and fixing complete with type 400 PVC fittings. 14.Wood Work No application of any description shall be made on any timber unless and until the timber is approved by the suitable Authority. Rates for Carpentry shall include for all cutting, notching, drilling, sinking, trimming, framing, jointing splayed edges, and like, fixing in position complete with nails spikes, screws and priming to joints and ends, application of two coats of wood preservative for all frame works and one coat of wood primer for un-exposed sides of ceiling boards. Treating roof and ceiling timber (imported timber) in approved kiln.
  • 17. XVII All coconut timber shall be matured, selected, swan coconut timber. The finish of coconut timber shall be mechanically sanded and painted with one coat of sanding sealer and two coats of polyurethane varnish. Structural timber for Roof work, ceiling frames Palu, Wewarana(Ranei), Liyan, Alubo, Pihimbiya. Imported timber Balau, Kempas, Bitis Valance board Ginisapu, Gammalu Floor Boarding Teak, Kumbuk, Tina Timber for Joinery (Doors, Windows, Fan lights etc) Mahogany, Margosa(Kohomba) For Frame: Balau, Thulang, Hadawaka, Milla For sashes: Halmilla a. All timber shall be seasoned to a moisture content of 12% or less and shall be free of defects such as end splits, surface cracks, warping, sap wood etc. b. If imported timber is to be used, a certificate from the exporter, giving particular of method of seasoning and preservative treatment along with grade classification shall be furnished by the Bidder to the Engineer. c. All timber sizes indicated in the description shall be finished sizes after planning. Note on Prescribed timber Sizes During the past two years, Divisional Engineers have reported that exact imperial sizes on the timber on following categories are not readily available in the market, unless logs are being purchased and sawn to the exact size. Contractor's Association has also made representation indicating that the imperial size specified in the BSR is not available on imported timber varieties, and due to scarcity of the local timber, small scale Contractors are unable to purchase logs and seasoned the timber and sawn to the imperial sizes. Market survey has confirmed the same. Accordingly, it has been decided to indicate the cross sectional size roof timber in the following manner to be in par with sectional sizes readly available in the local market, as it may not be worthwhile to prescribe timber sizes and, then request Contractors to by a large section and produce it to the required size, since there is no standardization of the timber imports. This has been done to avoid subjective decision taken by the Divisional Engineers during the project implementation phase. Accordingly, the following imperial sizes are being now replaced by the following Metric sizes. 1” to be replaced by 22mm 2” to be replaced by 45mm
  • 18. XVIII 3” to be replaced by 70mm 4” to be replaced by 94mm 5” to be replaced by 117mm 6” to be replaced by 140mm 7” to be replaced by 165mm 8” to be replaced by 190mm. Hence, timber will now be prescribed as 2"x 1" as 45mmx22mm 2”x 2” as 45mm x 45mm 4”x 2” as 94mm x 45mm 5”x 2” as 117mm x 45mm 5”x 3” as 117mm x 70mm 4”x 3” as 94mm x 70mm 6”x 2” as 140mm x 94mm 6”x 3” as 140mm x 70mm 6”x 4” as 140mm x 94mm 8”x 4” as 190mm x 94mm Rates for Joinery shall include: (a). All labour in framing, jointing and fixing in position complete with all nails, spikes, screws etc. (b). Application of one coat of hot tar to the surfaces come in contact with brick or concrete. (c). Application of one coat of wood primer for un-exposed surfaces. Unless otherwise specified door, window, fanlight and other frames shall be 3 3/4" x 2 3/4" (finished size) in section and out of Jak, Milla or Mahogany. Sashes and counter tops shall be 1" thick (finished size) out of "Jak" or "Mahogany". Valance, barge boards and valley gutter boarding shall be 1" thick Ginisapu. Brass screws shall be used for all fittings. All exposed faces of timber in Joinery are to be wrote the sizes given below are nominal without allowance for planning, except where described as finished sizes. 15.Ironmongery Rates for Ironmongery shall include all fittings, cutting, sinking, boring, mortising and the like and fixing complete including supplying matching screws. (a) Unless otherwise stated, all fittings shall be polished brass with oxidized finish, heavy quality type and make of the lock shall be "Union" or "Yale". (b) Brass Fitting & Furniture For doors, windows, cupboards etc. shall be of heavy type oxidized brass fittings to approved samples, hinges shall have steel pins with the ends welded.
  • 19. XIX (c). Parliamentary Hinges, Brass Size A x B 2 1/2"x 3 1/2", 3 1/2"x 4", 4"x 4 1/2", 4 1/2"x 5" Weight per pair 14 Ozs. 1lb., 2 Ozs.1lb. 5 Ozs. 1lb., 11Ozs. Diameter of pin 0.170", 0.170", 0.184", 0.184" (d). Butt Hinges Size A x B 4"x 2 1/2", 4"x 3", 5"x 2 1/2", 5"x 3" Weight per pin 1ib. 1 Pzs., 1lb. 3)zs., 1 lb. 7 Ozs. 1 lb. 12 Ozs. Diameter of pin 0.184", 0.184", 0.184", 0.1184" (e). Casement Stays Size 10" straight 10" curved 12" straight 12" curved Channel type 9 Ozs. 10 Ozs. 12 Ozs. 14 Ozs. 10 Ozs. 11 )zs. 14 Ozs. 17 Ozs. (f). Bolts The handles of bolts shall be cast in one piece with the shoot which shall be not less than 3/10" dia. for bolts 6" and above and not less than 5/16" for smaller bolts. The distance of travel of the shoot shall not be less than 1 1/4" in the case of bolts 6" and above. 16.Sanitary Fittings and Plumbing The whole of the sanitary works shall be carried out by a licensed sanitary plumber according to the layout and as specified and as directed at site. It should be noted that the positions shown on plans are approximate. Exact positions would be indicated at site. All plumbing fixtures and fittings should be approved by the Architect, Engineer prior to ordering same for installation. All items of pipes, specials and fittings shall be suitable for sewerage works purposes and for use with raw domestic sewage and installation and operation in a damp tropical climate with temperature between 200C to 400C and relative humidity of 80% (a). Unless otherwise specified rate for wash basin shall include 22"x 15" overall white vitreous China wash basin conformed to SLS 229, leaflet or approved equivalent with 1/2" dia. Chromium plated pillar tap, 1 1/4" dia. rubber plug, Chromium plated chain waste and brackets in painted iron, screwed to plastic rawl plugs buried in wall. Water supply and waste water connections all fixed complete to working order.
  • 20. XX (b). Unless otherwise specified rate for low level closet shall include white Vitreous China, low level closet conformed to SLS 229, leaflet or approved equivalent comprising closet with 'P' or 'S' trap as directed and hinged seat with lid in black plastic all fixed complete to working order. (c). Unless otherwise specified rate for low level cistern shall include White Vitreous China, low level cistern conformed to SLS 229, leaflet or approved equivalent comprising shell and cover with supporting brackets screwed to plastic rawl plugs buried in wall. Water supply and discharge connections all complete to working order. (d). Unless otherwise specified rate for Eastern Closet shall include ( 21 1/2"x 15 1/2") overall White Vitreous China closet as per Model No, 1001 as detailed in Ceylon Ceramic Ltd. leaflet or approved equivalent 'P' or 'S' trap as directed and foot rest in cement concrete 1:2:4 (3/4") rendered with grooved in cement and sand 1:2 fixed complete to working order. (e). Unless otherwise specified rate for high level cistern shall include plastic cistern of approved manufacture comprising shell and cover with supporting brackets screwed to plastic rawl plugs buried in wall PVC flush bend and all other necessary accessories with supply and discharge connections all complete to working order. (f). Unless otherwise specified rate for Mirror above wash basin plate glass mirror of super quality free from effect of wavy image with fiberglass frame fixed to wall with plastic rawl plugs and chromium plated brass screws. Rates for sanitary fittings shall include for: a. Fittings such as taps, waste water outlets, flushing cisterns, flush valves, internal overflows etc., the supporting brackets and incidental materials for fixing. b. Assembling, joining together, fixing component and jointing to pipes inclusive for necessary couplings and for leaving perfectly clean undamaged and perfect working order as on completion. c. Jointing and connecting pipes to sanitary fittings. d. Testing and commissioning of installation. e. Making good the work disturbed (g). Rate for Sanitary Plumbing shall include: (1) Screws, nails, pipe hooks, saddles, brackets, sockets, connections, short lengths, back nuts, nipples, all laps, straight cutting and waste. (2) All excavations, supports to sides of trenches, if necessary keeping trenches free from water, back filling, disposal of surplus soil, all jointing and other incidental materials and testing upon completion. Unless otherwise stated, PVC piping for water service and waste water etc. shall be rated to Type 1000 PVC such plastic piping and fittings shall comply with the SLS 147 or latest BSS.
  • 21. XXI Copper piping shall be used for hot water service and such copper piping and fittings shall comply with the latest BSS specification. Unless otherwise stated separately in the BOQ, any special water supply and drainage fittings such as bends, tees, reducers etc. shall be deemed to have been included in the relevant items, and such items should accordingly be rated to include for such specials etc. and for any extra work involved for the satisfactory completion of such items 17.Water Supply The Bidder is to pressure test pipes after fixing taps and stop cocks and fittings prior to concealing, under the supervision of the Engineer or his representative. The contractor shall provide the Engineer with the manufacturers’ certificates of the standards, quality of the materials before commencing the works All water pumps should be mounted on inertia bases fitted with anti-vibration mountings. Flexible connections should be provided on connections between pump units and pipe work. Where pipes pass through walls or slabs these shall be wrapped with a layer of insert material. For pipes exceeding 50mm dia. sleeve pipes shall be used for the full thickness of the slab walls, beams, retaining walls through which the pipe passes. All taps, shower appliances, cocks and floor waste covers, used in the plumbing installation shall be chromium plated brass (CP brass) or stainless steel item unless otherwise stated. Rates for Water Supply Plumbing work shall include: a. Cutting and waste of pipes etc., and jointing of pipes. b. All specials such as elbows, bends, tees, junctions, plugs, reducers and similar pipe fittings except for valves which would be measured separately. c. Connecting pipes to sanitary fixtures and appliances. d. Chasing to brick or concrete walls, columns, beams etc., and making good all works disturbed. e. Necessary screws, nails, sockets, connection back nuts, standard pipe fixing or supporting clips, saddles, brackets, racks, straps etc. f. Connecting different type of pipes. g. Testing and disinfecting after completion. h. Preparing and making applications and giving notice to the relevant authorities to obtain service connections to the building inclusive of any statutory payments to relevant statutory authorities. All cold water piping should be provided with flexible connections in pipe work and provided with the required pipe supports & anchoring as per the manufacturer’s specifications. 18.Drainage Unless otherwise specified, pipes in Drainage shall be Type 600 PVC.
  • 22. XXII Rate for Drainage Work shall include for: a. Excavation, backfilling, Planking & strutting, dewatering and disposal for surplus spoil. b. Laying of pipe to falls and gradient and all jointing and other incidental materials. c. All pipe specials such as bends, tees, junctions, elbows, etc. d. Connection to sides of manholes etc. e. Providing sleeves etc., when pipes pass through walls, foundations etc. f. Giving notices, obtaining permits, paying fees etc. g. Testing installation as specified in specifications, and/or American, British or Sri Lankan standards. 19.Plastering Rates for Plastering shall include for all temporary rules, screeds, grounds etc. for raking out joints of new brick work, or hacking new concrete for key, internal and coved angles, joints between different surfaces and between new and old plastering, arisers, quicks intersection between curved or irregular surfaces etc. and making good around pipes, sanitary fittings and similar fixtures. Unless otherwise stated internal wall plaster shall be 5/8" thick in cement, lime and sand 1:1:5 finished smooth with lime putty. Unless otherwise stated external wall plaster shall be 5/8" thick in cement, lime and sand 1:1:5 finished semi-rough. Unless otherwise stated plinth plaster shall be 5/8" thick in cement and sand 1:3 finished smooth with neat cement floating. Unless otherwise stated Soffit plaster shall be 3/8" thick in cement and sand 1:3 finished smooth with lime putty. 20.Paving Rates for paving shall include all temporary rules, screeds, ground etc. all normal cutting arisers, rounded angles and the like bedding and point making good between different surfaces and around pipes, sanitary fittings and other fixtures and cleaning down upon completion including curing. Unless otherwise stated Cement rendering shall be 1/2" thick in cement and sand 1:3 finished smooth with thick coat of colored pigment mixed neat cement floating and smooth with Caberendum stone. Unless otherwise stated skirting shall be 4" high (100mm high) 1/2" thick (12mm thick) in cement and sand 1:3 laid with the floor rendering, finished smooth with a sunk bed of junction of the skirting with the plaster above the angle between the floor and the skirting to be rounded off to a radius of one Inch. 21.Tiling Tile should comply with European standard specification LEN 177. Industrial grade (heavy duty) vitreous ceramic floor tile shall be homogeneous.
  • 23. XXIII The tiles manufactured by European standards and are of colored as specified by an Architect. Rates for tile work shall include the cost of cement and sand 1:3 screed, pointing joints with neat cement of tile grout to match the color of tiles. Unless otherwise stated floor tile paving shall be any size non-skid pattern ceramic floor tiles of approved local manufacture, bedded with cement and sand 1:3 1/2" thick screed. Unless otherwise stated wall tiling shall be any size glazed ceramic wall tiles of approved local manufacture fixed on cement and sand 1:3 backing 3/8" thick. Approval of floor and wall tiles colour to be obtained from suitable authority. All floor tiles shall be locally produced ceramic tiles and shall agree in colour, dimensions, tolerances, finishes, and quality with samples provided by the consultant. All tiles to be true to shape, uniform in size and free from blemishes. The recommendations of C.P.202 and BS 5385: part 3, shall be complied with, subject to any qualifications hereunder. Preparation The sub –floors to be cleaned of cement film, mortar spills, paint and other impurities, oil sports to be chiseled. The sub-floor is to be well wetted with water Everything necessary shall be done to obtain a satisfactory bond between concrete, screeds, beddings and finishes. The cleaned sub-floor shall be grouted with a 1:1 cement/water mixture by broom application, prior to placing the mortar bed Setting-out Corrected floor levels shall be established and finished levels of tiling controlled by a series of spot levels. Movement joint in sub-floors and screeds shall be carried up into tiling. Generally the tiles shall be divided symmetrically over the areas, so that pieces smaller than half a tile will not occur; the layout of the tilling and width of joints to be determined with the consultant. The tilling to be laid to falls, towards floor gullies as shown on the drawings, and/or in co-ordination with the consultant. At joints to walls, skirtings, pits, passages etc., the to be cut, sawn or ground to size. Bedding of Tiles Care shall be taken that tiles are well soaked in clean water and are free of dust before laying. A mortar bed of 1 part cement to 3 parts sand, of thickness as specified in the Bill Of Quantity to be spread by means of a float in beds of a width of approx. 700 and allowed to stiffen. Acid proof mortar for acid-proof tiles is to be applied in accordance with the manufacturer’s instructions.
  • 24. XXIV The back of the tiles shall be buttered with a coat of cement slurry and the tiles laid with straight joints 3mm wide, on the mortar bed. Grouting shall take place at any time after tiles are firmly fixed but before any dirt or contamination can enter the joints. Dampen the joints and grout with cement: fine sand(1:1). Do not use more water than necessary to avoid subsequent joint shrinkage work the grout well into the joint until flush and remove surplus grout. At the discretion of the consultant, tinted grout shall be used. Grouting for acid-proof tiles is to be applied in accordance with manufacturer’s instruction. If a depression or bump in surface level in excess of 6mm in any 2 meter length is found, then the floor shall be taken up and re-laid, at the contractor’s expense, to the satisfaction of the Consultant. Protection Finished tiled floors are completely covered with sheets of hardboard; walls and skirting to be washed with soap and water, the floor to be similarly treated after removal of temporary floor coverings. 22.Painting Rates for Painting shall include preparation of surfaces, cleaning down, smoothing, knotting, stopping etc., protection of floors and fittings, removing and replacing door and window furniture and cleaning doors and windows upon completion. Unless otherwise specified internal wall paint shall be one coat of Alkali Resistant Primer and two coats of Emulsion paint of approved make and colour. Unless otherwise specified external wall paint shall be one coat of Alkali Resistant Primer and two coats of Weather shield Emulsion paint of approved make and colour. Unless otherwise specified paint for wooden surfaces shall be one coat of aluminum primer and two coats of Enamel paint of approved make and colour. Spray painting shall do in ICTAD SCA/4/1 clause 14.9(f). 23.Glazing Unless otherwise specified, thickness of glass panes shall be not less than 4.0mm and rates for Glazing shall include waste in cutting to required sizes, brass pins, screws, "Teak' or 'Halmilla' beads, fixed complete and protecting. 24.Electrical Installation Unless otherwise specified internal lighting wiring shall comply with the drawings and shall be in full PVC insulated copper cables. All conduits shall be buried into brick walls, slabs, beams or columns to the entire satisfaction of the Engineer. All switches and socket outlets shall be "Tenby", M.K., Clipsal or similar approved sunk type unless otherwise specified. All fluorescent fittings should be complete with good quality power factor correcting capacitor and choke, starter etc. and the tube should be "Thorn", "Philips" of good quality of similar approved make. All fans and regulators
  • 25. XXV shall be "National", "Hitachi", "KDK", or similar approved make to approved colour. Rate to include for all necessary PVC switch boxes, plugs, round or square blocks. Chromium plated chains, brass hooks, ceiling roses, holders (Angle batten and ordinary battens) and any other item necessary, whole installation shall be carried out according to CEB/IEE regulations. All other distribution boards should be Merlin Gerin flush mounting type or similar approved type. Switch gears shall be MEM or similar approved type. Earth leakage circuit breakers shall be Cabtree, Fugi or approved make, MCCB's and MCB's shall be "Square D" or similar approved make. Unless otherwise specified wiring shall be as follows : All lamp points wired through a 5 Amp. Sunk switch using 2x1x1/1.13 PVC insulated copper wire and 1x1x7/0.67 PVC insulated copper earth wire in concealed PVC conduits. Ceiling fan points wired through regulator using 2x1x1/1.13 PVC insulated copper wire and 1x1x7/0.67 PVC insulated copper earth wire in concealed PVC conduits. All flush mounted 5 Amp. Switched socket outlets wired using 2x1x1/1.13 PVC insulated copper wire and 1x1x7/0.67 PVC insulated copper earth wire in concealed PVC conduits. All flush mounted 15Amp. Switched socket outlet wired using 2x1x7/0.67 PVC insulated copper wire and 1x1x7/0.67 PVC insulated copper earth wire in concealed PVC conduits. General Specification - Electrical Installations 1.0 General (a). Work shall be carried out in conformity with the regulations for electrical equipment in buildings issued by the I.E.E. London ICTAD Specifications and any other relevant C.E.B. Regulations. (b). All materials and equipment used shall conform to the relevant current B.S. Specifications, Sri Lanka Standard Specification or any other Internationally recognized Specification not less rigid. (c). The rate quoted for wiring per point, shall provide for the supplying and installation of all materials necessary for the complete wiring of that point from the Distribution Board onwards, exclusive of the cost of supplying and installing Distribution Board, Lamps and Shades but will include all other materials in the sub-circuit wiring. 1.1 Wiring Points 1.1 1 A Pendant point will include :- (a). Cord grip suspension lamp holder (b). Flexible 2 core cord upto 1.5m in length. (c). Ceiling rose on square or round, Teak or Halmilla base. (d). Associated casings and covers except for the runs as defined in Item 1.2.5.
  • 26. XXVI (e). A single pole Tumbler Switch (5a) on round or square, Teak or Halmilla base or a single pole flush type switch on Teak or Halmilla base. (f). Complete wiring of the point. 1.1.2 A Batten Point will include :- (a). Straight or Angle batten holder on square or round, Teak or Halmilla base. (b). A single pole Tumbler switch on a square or round Teak or Halmilla base or a single pole flush type switch on Teak or Halmilla base. (c). Associated casings and covers except for the runs as defined in Item 1.2.5. (d). Complete wiring of the point. 1.1.3 A socket Outlet shall consist of : (a). A three pin 5A socket outlet (shuttered type)/three pin 5A socket outlet (shuttered type), on a Teak or Halmilla base. (b). Associated casings and covers except for the runs as defined in Item 1.2.5. (c). The earth continuity conductor. (d). Complete wiring of the point. 1.1.4 A fan point shall consist of : (a). A ceiling rose on a square or round Teak or Halmilla base. (b). A 200mm x 150mm Teak or Halmilla base on which the regulator to be mounted. (c). An earth continuity conductor for earthing of the regulator, where required. (d). Associated casings and covers except for the runds as defined in Item 1.2.5. (e). Complete wiring of the point. 1.1.5 A fan under light point shall consist of : (a). Bracket holder (b). Adequate length of flexible 2 core cord. (c). Single pole switch on square or round Teak or Halmilla base. (d). Associated casings and covers except for the runs as defined in Item 1.2.5. (e). Complete wiring of the point. N.B. 1. Fan Under-light Where a fan under-light point is required as common 3 plate ceiling rose may be used for the fan point and under-light. A fan under-light point will be paid as an additional point. 2. Two-way 5A Switch When a two way 5A switch is required, it will be treated as two separate points.
  • 27. XXVII 1.2 Method of Installation : 1.2.1 Cables : (a) All cables to be colour coded/red and black for phase and neutral respectively. (i). All runs on walls to be enclosed in casings and covers where Tumbler switches are used. Or (ii). All runs on walls to be laid in PVC conduit of not less than 18mm diameter concealed in the wall plaster. (b) All runs above ceilings to be clipped, clips spaced not more than 200mm on the horizontal runs and 350mm on vertical runs. (c) Where cables have to be run on iron support, wooden battens of suitable size shall be used. These battens shall be secured to the iron by metal clips, spaced not more than 600mm apart. These battens shall be paid for as extras and the Tendered should quote for the supply and installation of various sizes. 1.2.2 Troughings and covers (a) Troughings to be fitted to wall, secured with iron screws on to dove tail plugs cemented to wall, or by some other approved method. (b) Covers to be fitted on troughings with suitable nails spaced not more than 200mm apart on either side. (c) These to be sand papered. Conduits 1.2.3 The following accessories shall be mounted on Teak or Halmill a bases, secured to the wall brass screws driven into dove tail plugs cement4d to the wall Main Switch fuses, Distribution Boards, Switches, Socket outlets, and wall racket fittings, ceiling rose, batten holders shall be mounted on Teak or Halmilla base secured to the ceiling batten with brass screws. 1.2.4 Horizontal runs of cables, mains or otherwise when exposed to view under the ceiling or in the absence of a ceiling, shall be enclosed in casings and covers. These casings and covers will be paid for as extras at the rate accepted in the Tender. 1.2.5 Suspension type fluorescent fittings shall be hung from eye hooks on ceiling plate securely fixed to the ceiling or beam overhead. Suspension shall be by means of galvanized iron chains of suitable size. 1.2.6 Where wires have to pass through walls, PVC conduits shall be used. These conduits should be of suitable size to carry the number of wires used and should be securely fixed to the wall before the wires are drawn through. Care should be taken to prevent damage to wires at the end s of the tubes.
  • 28. XXVIII 1.3 Wiring 1.3.1 All wiring to be done in strict accordance with the wiring regulations for buildings Institution of Electrical Engineers (London) latest edition and in accordance with the requirements of the Ceylon Electricity Board. 1.3.2 The wiring shall commence at the main switch fuse. The loop in system of wiring shall be used and no joints will be permitted in the cable runs. 1.3.3 All cables to be colour coded red and black for phase and neutral respectively. 1.4 Earthing 1.4.1 The earth pin of all sockets to be connected to an earth continuity conductor. All joints on this conductor to be soldered. The conductor is to be finally terminated outside the building for connection to the earth electrode. The size of the earth continuity conductor shall be in accordance with the I.E.E. Regulations for Electrical Installations in buildings (latest edition) - the minimum size being as in Item 1.7 of the Specifications for materials. 1.4.2 Where required, the wiring of a fan point shall provide for the connection of a fan regulator to the earth continuity conductor. 1.4.3 The earth continuity shall be securely fixed by means of a suitable earth clip to one or more earth electrode as required. Earth electrode should be positioned outside the building at a suitable location. 1.4.4 Where the earth continuity conductor is run in casing, it shall be secured to casing by small staples. For runs above the ceiling, it shall be secured to the roof timber with copper staples. The length of the earth continuity conductor buried in ground shall be drawn through a G.I. pipe of suitable size not less than 50mm diameter. 1.4.5 The runs to the earth electrode, below ceiling level, shall be in conduit or enclosed in casing and covers. Part I - Chapter 13 of the I.E.E. Regulations Fundamental Requirements for Safety Workmanship and material 13-1 Good workmanship and proper material shall be used. General 13-2 All equipment shall be constructed, installed and protected, and shall be capable of being maintained, inspected and tested, so as to prevent danger so far as is reasonably practicable. 13-3 All equipment shall be suitable for the maximum power demanded by the current using equipment when it is functioning in its intended manner. 13-4 All electrical conductors shall be of sufficient size and current carrying capacity for the purposes for which they are intended. 13-5 All conductors shall either -
  • 29. XXIX (i) be so insulated, and where necessary further effectively protected, or (ii) be so placed and safeguarded as to prevent danger, so far as is reasonably practicable. 13-6 Every electrical joint and connection shall be of proper construction as regards conductance, insulation and mechanical strength and protection. Over-current Protective Devices 13-7 Where necessary to prevent danger, every installation and every circuit thereof shall be protected against over-current by devices which - (i) will operate automatically at values of current which are suitable related to the safe current ratings of the circuit, and (ii) are of adequate breaking capacity and where appropriate making capacity and (iii) are suitably located and are constructed so as to prevent danger from overheating, arching or the scattering of hot particles when they come into operation and to permit ready restoration of the supply without danger. Precautions against earth leakage and earth fault currents 13-8 Where metal work of electrical equipment, other than current-carrying conductors, may become charged with electricity in such a manner as to cause danger if the insulation of a conductor should become defective or if a fault should occur in any equipment. (i) The metal work shall be earthed in such a manner as will cause discharge of electrical energy without danger or (ii) other equally effective precautions shall be taken to prevent danger. 13-9 Every circuit shall be arranged so as to prevent the persistence of dangerous earth leakage currents. 13-10 Where metal work is earthed in accordance with Regulation 13.8(i) the circuits concerned shall be protected against the persistence of dangerous earth fault currents by - (i) the over-current protective devices required by Regulation 13-7 or (ii) a residual current device or equally effective device. The method described in Item (ii) above shall be used whenever the prospective earth fault current is insufficient to cause prompt operation of the over-current protective devices. 13-11 Where necessary to prevent danger, where metal work of electrical equipment is earthed for compliance with Regulation 13-8(i) and is accessible simultaneously with substantial exposed metal parts of other services, the latter parts shall be effectively connected to the main earthing terminal of the installation. Position of Protective Devices and Switches 13-12 No fuse, or circuit breaker other than a linked circuit breaker shall be inserted in an earthed neutral conductor, and any linked circuit breaker inserted in an
  • 30. XXX earthed neutral conductor shall be arranged to break also all the related phase conductors. 13-13 Every single pole switch shall be inserted in the phase conductor only, and any switch connected in an earthed neutral conductor shall be a linked switch and shall be arranged to break also all the related phase conductors. Isolation and Switching 13-14 Effective means, suitably placed for ready operation shall be provided so that all voltage may be cut off from every installation from every circuit thereof and from all equipment, as may be necessary to prevent or remove danger. 13-15 For every electric motor an efficient means of disconnection shall be provided which shall be readily accessible, easily operated and so placed as to prevent danger. Accessibility of equipment 13-16 Every piece of equipment which requires operation or attention by a person in normal use shall be so installed that adequate and safe means of access and working space are afforded for such operation or attention. Precautions in Adverse Conditions 13-17 All equipment likely to be exposed to weather, corrosive atmosphere or other adverse conditions shall be constructed or protected, as may be necessary to prevent danger arising from such exposure. 13-18 All equipment in surroundings susceptible to risk of fire or explosion shall be so constructed or protected and such other special precautions shall be taken, as may be necessary to prevent danger. Additions and alterations to an installation 13-19 No additions or alterations, temporary or permanent, shall be made to an existing installation, unless it has been ascertained that the ratings and the condition of any existing equipment (including that of the supply undertaking) which will have to carry any additional load is adequate for the altered circumstances and that the earthing arrangements are also adequate. Inspection and Testing 13-20 On completion of an installation or an extension or alteration of an installation, appropriate tests and inspections shall be made to verify so far as reasonably practicable that the requirements of Regulations 13.1 to 13.19 have been met. 13-21 Standard Mounting Heights Electrical wiring Accessories (Height from Fin. FLF) 2400mm Pendant Lamp 2250mm Wall Bracket Lamp 2400mm Exit sign Board 1500mm Switch Board 1500mm Fan Regulator 2000mm MCB Distribution board 300mm - Common area Socket Outlet
  • 31. XXXI LIST OF APPROVED ELECTRICAL FITTINGS No. Item Relevant Standard Specifications Recommended Brand Names 01 Sunk Switches, 10A B.S. 3676 Clipsal, Legrand, M.K. 02 13A Switched Socket Outlets, Plugs & Adopters. B.S. 1363 Clipsal, Legrand, M.K. 03 5A and 15A Switched Socket Outlets B.S. 546 Clipsal, Legrand, M.K. 04 R.C.C.B./R.C.D. B.S.4293, IEC1008 BS EN 61008 F & G (Austria) Siemens (Germany) Clipsal (Australia) Crabtree (U.K.) Merlin Gern (France) Legrand (France) 05 M.C.B. IEC 898 or BS EN60898 or IEC 947-2 or B.S.3871:Part 1 F & G (Austria) Siemens (Germany) Clipsal (Australia) Crabtree (U.K.) Merlin Gern (France) Legrand (France) 06 Consumer Unit B.S. 5486 Part 1 & Part 13 L.E.C.439- 1 or BS EN 60439- 3 IEC 695-2-1 ABB (Germany) ABC (Singapore) Crabtree (U.K.) Hager (France) Legrand (France) 07 M.C.C.B. I.E.C.947-2:1989 BS EN60947-2:1992 Legrand (France) Merlin Gern (France) Terasaki (Japan) Klokner Moeller (Germany) Crabtree (U.K.) 08 Cu/PVC/SWA/PVC Cables Cu/PVC/PVC Cables B.S. 6346 B.S. 6004:1995 & SLS 733:1995 ACL (Sri Lanka) Wilson (Singapore) Kelani (Sri Lanka) 09 Cu/XLPE/SWA/PVC Cables Cu/XLPE/PVC Cables B.S. 5467 B.S. 5467 ACL (Sri Lanka) Wilson (Singapore) Kelani (Sri Lanka) No. Item Relevant Standard Specifications Recommended Brand Names
  • 32. XXXII 10 Fluorescent Ballasts with Screw Type Terminals I.E.C. 920, 921 & 922 BSEN 60928 Schwabe (German) ATCO (Australia) B.G. (U.K.) 11 fluorescent Lamps Colour : Cool White (4000 K) I.E.C.81 B.S. 1853 Osram (Germany) Tungsram (Hungary) Philips (Holland) GE (USA) Sylvania (USA) Westinghouse (USA) 12 Lighting Fixtures EN 60598 BS 4533 Thorn UK) Philips (Holland) 13 Steel Enclosures (Epoxy Powder coated finish) I.E.C.529 for degree of protection BSEN 60529 Elsteel (Sri Lanka) Legrand (France) Himel (Spain) Enclotek (India) Metalix (Sri Lanka) 14 Exhaust Fans BS 5060 I.E.C.879:1987) KDK (Japan) Alstom (UK) National (Japan) 15 PVC Conduits BS 4607 & BS 6099 National, Anton, Duro, S-lon 16 G.I. Conduits BS 4568 Part 1 Matsushita, Maruichi, Pusan or any U.L. approved U.S. Brands. List of Cable brands in Sri Lanka with SLS Certificate ACL, KML, KELANI, ALUCOP, RUHUNU 25.Air-conditioning Unless otherwise specified Air-conditioning work shall conform the following design criteria and conditions. (a) Inside temperature should be maintained at 250C + 1.50C. (b) The inside relative humidity should be maintained at 55% + 15%. (c) Outside conditions to be taken as Dry bulb temperature - 330C Wet bulb temperature - 290C i.e. relative humidity - 75% (d) Noise level should be not more than 35db (e) A minimum of 1.3 Litres/S/m2 of fresh air should be supplied. (f) Air Velocity should be maintained at between 0.3m/s at a height of 1.5m from ground level. (g) The Co2 content should be less than 0.1%. (h) The Contractor should give a guarantee to the client that he will maintain the above design conditions inside the air-conditioned areas. (i) The attached plans indicate the areas to be air-conditioned. (j) The Contractor should indicate as an extra item the conditions and cost of an annual maintenance contract.
  • 33. XXXIII (k) The Contractor should submit the Technical Literature with the quotation. (l) A guarantee that spares will be available for all equipment supplied for at least a period of 5 years should be given by the local agent. (m) Performance tests to ascertain that the specified design conditions are maintained should be carried out at the time of commissioning. 26.Waterproofing (a). The waterproofing Contractor (or Sub-Contractor) should be a registered specialist contractor at the ICTAD on the particular area. (b). The Contractor should issue a written warranty of at least 5 year to cover on the quality of the material, suitability of the material for the situation and the workmanship. (c). The waterproofing material shall conform to relevant British, Euro or ASTM specifications. (d). Rates shall include for cutting, notching, bending and extra material for lapping making into recesses, inserts, pipes and the like and for working to falls and cross falls. (i). Internal and external angles, angles fillets, arisers, edges, intersection and the like. (ii). Cleaning with wire brush where necessary priming all joints including necessary additional materials. (iii) Application of liquid polymer cement water proofing agents for the following. Flat roofs, concrete/masonry tanks, wet areas of toilets including bathrooms, exposed balconies, concrete gutters. "Smart flex", "Thoroseal" or any other approved equivalent product marketed by specialist contractor registered at ICTAD. (iv) Application of cementations type agents with positive and negative (back-flow resistance) properties on newly cast under ground sumps, swimming pool basements, "Osmoseal", "Xypesx", "Vandex" or any other approved equivalent product marketed/installed by a specialist contractor registered at ICTAD. (iv) Application of membrane type agents and insulation of same less membrane type water proofing on large flat roofs, gutters, basements. Material thickness not less than 3mm and comply to BS/ASTM/JIS/AU Standards. 28 Steel Grill Work (a). Rates for Steel Grill Work shall include shop fabrication work including cutting, drilling, bolting, welding, grinding, marking, delivering, un-loading, , erecting and fixing in position. (b). Rate shall include for two coats of matt oil paint after treating with a coat of anti-corrosive paint to all exposed faces of grill.
  • 34. XXXIV (c). All bolt holes to be machine drilled. (d). Steel shall normally be welded by the metal area process conforming to B.S. 5135. Other methods shall be subject to the approval of the authorities. (e). Unless otherwise specified all steel shall be Grade 43A. (f). Structural steel shall conform to BS 4360. 29 Steel Balustrade Work (a). Rates for Steel Balustrade Work shall include shop fabrication work including cutting, drilling, bolting, , welding, grinding, marking, delivering, un-loading, , erecting and fixing in position. (b). Rate shall include for two coats of matt oil paint after treating with a coat of anti-corrosive paint to all exposed faces of grill. (c). All bolt holes to be machine drilled. (d). Steel shall normally be welded by the metal area process conforming to B.S. 5135. Other methods shall be subject to the approval of the authorities. (e). Unless otherwise specified all steel shall be Grade 43A. (f). Structural steel shall conform to BS 4360. 30 RollerShutter Door (a) Slats: Color bonded/Zinc coated slats to the thickness of 0.7mm and 0.8mm respectively to the width of 75mm (3") and 100mm (4") (b) Flat & curve special feature. Specially imported hard rubber beading on side channels to minimize the rough flow of the shutter colours, choice of 10 colors. SPECIFICATIONS Specifications comprise of two sections. The “General Specifications” and “Particular Specifications” together comprise the specification governing the works described in the B.O.Q. and B.S.R. Several national and international standards have been quoted in the specifications. All Workmanship Materials and Components throughout shall where applicable and unless otherwise stated in the Specification comply with the relevant American, British or Sri Lankan
  • 35. XXXV Standards, current on the date fixed for receipt of Bids together with additional clauses or amendments set out in the specifications. Order or precedence of the standards shall be as follows: 1. Sri Lanka Standards 2. British Standards 3. American Standards Bidders may offer materials in accordance with such other standards or specifications which provide for quality and workmanship not inferior to the standards quoted together with the additional clauses or amendment set out in these specifications. Such standards or specifications shall be submitted in full at the time of bidding. Authenticated English translation shall be submitted if the specifications are in other language. When reference is made within these documents to certain standards, specifications or regulations, the reference shall be construed to mean the standards with all subsequent amendments and changes or additions as thereafter adopted and published that are in effect at the date fixed for receipt of Bidders. Bidders are instructed that any clarifications and/or additional information etc. pertaining to the scope of work should be obtained fully before Bid submission and that the quality and quantum of work which should be as per the above standards properly understood since no extra works would be due any subsequent clarifications of lack of information. General Specifications The general Specifications are the specifications given in the following documents issued by the Institute for Construction Training And Development (ICTAD). The Bidders are expected to be conversant with these documents, since the said documents will not be issued to the Bidders under this Bid, however the Bidders may purchase the documents from ICTAD, “Savsiripaya”, Wijerama Mawatha, Colombo 7. Publication No. Description SCA/4(Vol. I) Specification for Building Works Vol. I SCA/4(Vol. II) Specification for Building Works Vol. II SCA/8 Specification for Electrical & Mechanical works associated with Building and Civil Engineering SCA/3/1 Specifications for Irrigation and Land Drainage SCA/3/2 Specifications for Water Supply, Sewerage and Storm water Drainage work. Standard specifications for Construction and Maintenance of roads and Bridges issued by the RDA.
  • 36. XXXVI Special Specifications 1. Special Specifications for Concreting 2. Special Specifications for Aluminum Works 3. Special Specifications for Electrical Installation 4. Special Specifications for Air-Conditioning System 5. Special Specifications for Water Proofing 1. Special Specifications for Concrete Criteria of rejection of concrete Hardened concrete shall be liable for rejection if any of the following defects occur, a. The concrete is heavily porous, segregated or honeycombed. b. A construction joint has been made at a location or in a manner not in accordance with this specification. c. The construction tolerances have not been met. d. The reinforcing steel has been displaced from its correct location. e. The embedded items in concrete have been displaced from their correct position. f. The required surface finish has not been achieved. g. The test results and/or load test fails. Curing of Concrete (refer clause 4.3.5) Recommended methods for curing a. Ponding or continues sprinkling with water. b. The use of an absorptive cover kept continuously wet c. The use of curing compounds to be approved by the Engineer. d. The use of an impermeable sheet membrane over a moistened surface so fixed and lapped that circulation can occur at the concrete surface Frequency of Sampling Test Specimen’s 1. At test three (3) specimens shall be taken from a sample and cured. 2. A record on the full history of sampling and testing of all specimens. Concrete Acceptance criteria The concrete shall be deemed to comply with the strength requirements if the characteristic strength of the concrete meets the following, Grade 28 days characteristic 28 days compressive strength (N/m2) Description strength (N/m2) Average of any group individual Of three (3) consecutive test result
  • 37. XXXVII 25 25 Test results shall be shall be Greater than 32.5 greater Than 21.5 Concrete Sampling and Testing 1. Cement 2. Fine Aggregate 3. Course Aggregate 4. Slump Sampling 1. A sample for reinforcement bars shall mean three samples of reinforcement bars representing each diameter; for each 10 Metric Ton. 2. A sample for concrete shall mean seven numbers of concrete cubes (150mmx150mmx150mm) obtained at the location of placing concrete. Fine Aggregate a. Offshore sea sand – marketed by SLRDC i . Sea sand passing 5mm sieve shall be permitted ii. The origin of the sea sand shall be established at from a SLRDC Depot (Lorry No. and permit copy to be annexed) iii. Limit of grading Based on sieve analysis of sand, limits are as below reference clause 4.1.3.5 – table 4.2 Sieve size overall limits Grading Zone-C Zone-M Zone-F 10mm 100 - - - 5.00mm 89-100 - - - 2.36mm 60-100 60-100 65-100 80-100 1.18mm 30-100 30-90 45-100 70-100 600µm 15-100 15-54 25-80 55-100 300µm 5-70 5-40 5-48 5-70 150µm 0-15 - - - iv. The quantity of material passing the 75 µm sieve should not be 4% by weight. Course Aggregate Refer table 4.1 / clause 4.1.3.5 0f ICTAD SCA/4/1 for grading. 2. Special Specifications for Aluminum Works Specimen Notes for Aluminum Doors, Windows & Fanlights (c). The Aluminum alloy to be used shall conform to the requirements of BS 1474:1987 - AA 6063 surface treatment shall conform to BS 1615 & BS 3987. (d). Physical Properties: 1. Minimum tensile strength 150 Mpa. 2. Elongation 7%.
  • 38. XXXVIII (e). Anodic Oxidation coating should conform to BS 1615:1987 and BS 3987:1974 and the minimum coating thickness should be 20 + 25 Microns. The Supplier should furnish the manufacturer's certificate that the anodized finish complies with the specified Microns content. (f). Minimum section thickness 1.8mm door frame, 1.5mm window frame and 1.00mm partition. (g). Joints shall be made mechanically sound by welding or by concealed mechanical connectors. A water tight joint shall be made at the junctions and side frames members and water will not be trapped anywhere in or around frames. (h). All ironmongery shall be of the same material and satisfactorily performed the function for which intended and shall be securely attached. (i). Caulking compound shall be the best quality available for caulking between the contact surfaces of the structure and the aluminum windows conforming the adhering qualities, temperature resistance from 50F - 160F and humidity changes of 5% - 100%. (j). Screws used in the construction of frames shall be high tensile stainless steel or a non-corrosive material compatible with aluminum. (k). Neoprene weather stripping shall be of the highest commercial standards for normal temperature, water and abrasion resistance. (l). Frames shall be fixed to the structural opening with proper fixing devices. If any discrepancies occurring between approved drawings and site conditions these shall be brought to the notice of the Engineer. (m). Material and dimensions should be confirmed before any fabrication and installation. (n). A Ten year guarantee period is required and this to be transferred to the Client after practical completion. (o) At the same time of bidding, all the Bidders shall specifically be requested to submit the following information. i The specifications and thickness of aluminum extrusions bidder proposes to use on the work. ii Full size cross sections iii Documentary evidence from the Profile Manufacturer to the effect that the proposed profile will serve for the intended purpose. iv A Manufacturer's test certificate be produced as evidence that the powder coating is of required thickness. 3. Special Specifications for Electrical Installation 1.0 All material and equipment used shall conform to the relevant current B.S. specification, Sri Lanka standard specification or any other internationally recognized specification not less rigid.
  • 39. XXXIX 1.1 Cable for Sub-circuit Wiring shall be of Copper 1/1.13 cross section to be in PVC cables in accordance with B.S.S.6004/1969 and amendments to it. 1.2 Ceiling roses shall be of shock proof, bakelite covered two plate type or three plate type with an efficient cord grip. 1.3 Lamp holder suspension type shall be of the bayonet socket pattern of shock proof bakelite having an efficient cord grip solid plunger, brass reinforcing barrel liner shade ring and all metal parts to be of brass. Lamp holder batten type shall be of the bayonet socket pattern of shock proof bakelite straight or angle type as required, having solid plungers brass reinforcing barrel liner, shade ring and all metal parts of brass. 1.4A Switches shall be single pole, single way of the shock proof bakelite covered type, screws, contacts and springs to be made of brass, base to be of porcelain or ceramic. 1.4B Sunk type switches shall be single pole, single way of the shock proof covered type, screws, contacts and springs to be made of brass, base and cover to be made of bakelite with area moulding powder and approved quality. 1.5 Flexible cord 16/0.0.20 to be of Copper twin PVC insulated and PVC Overheated. 1.6 Wiring clips shall be of tinned brass or aluminum with counter sunk holes short, medium, large or small according to requirements. These shall be fixed by means of gimp pins of brass. 1.7 Earth Conductors and Continuity Conductors shall be of PVC Insulated copper and be of relevant cross sectional area as given in the latest I.E.E. regulations. 1.8 Wooden blocks shall be of Teak, Halmilla circular, square or Rectangular according to requirements and smooth finished. 1.9 Wooden battens shall be of Teak or Halmilla of rectangular cross section 50mm x 12mm. 1.10 Screws all screws used in the fixing of casting blocks, covers, witches etc. shall be of brass except where otherwise stated. 1.11 Fuse carrier and base this section is applicable to all fuse carriers and bases used in distribution boards and main switches provided under the Contract. (a). The base shall be vitreous porcelain with holes for cable entry at top and bottom and two holes for screws. Base contacts shall be in brass. (b). The fuse carrier shall be of vitreous porcelain. (c). The fuse wire shall be of tinned copper. 2.0 Troughings and covers shall be of seasoned Teak, Halmilla or approved Class I timber must be of good workmanship smooth to finished with covers
  • 40. XL having suitable mouldings. All troughings and covers which are exposed should be neatly finished (including sand papering). 3.0 Cable mains must be of specified size and to be in PVC in accordance with B.S.S. 6004/1969 with copper conductors. 4.0 Main Switch (1) Splitter type : Two pole (5 Amp. and 10 Amp.) all insulated main switch suitable for 230V A.C. two wire 50Hz. system. (2) All insulated shall be of the all insulated type and double pole single way. The switch shall have all metal parts in brass and shall be so arranged to prevent the cover being opened when the switch is at the "ON" position. One pole to be fused. (3) Metal Clad shall be S.P. and neutral or triple pole with fuses on three phases and provided with removable link on the neutral. The switch to be provided with interlocking device to prevent the cover being opened when the switch is in the "ON" position. All current carrying metal parts shall be in brass and switch to be provided with entry holes and insulating bushes. 5.0 Socket outlets shall be of the standard 3 pins, shock proof type bakelite covered with a porcelain ceramic or track free plastic base and provided with a shutter mechanism operated by the earth pin on insertion and withdrawal of plugs. All metal parts to be in brass. This item shall comply with B.S.S. 546/1979 and latest amendments thereto. 6.0 Earth pipe shall be of heavy quality galvanized iron pipe 50mm in diameter and 2000mm long with one brass bolt welded to the pipe at top with two brass hexagon nuts and washers. The pipes should be symmetrically tapered at the bottom end. 7.0 Fan hooks shall be of mild steel rods 18mm size. 8.0 G.I. Pipes for fan beams shall be of galvanized 50mm size 9.0 Lamp shades plastic conical 250mm shallow type. 10.0 Earth leakage trips (current operated) shall be of shock proof bakelite cover all insulated type two pole or 4 pole according to requirements having a switch and handle to "ON" and "OFF". The breaker shall be designed to operate with the leakage current not exceeding 30MA through the trip coil complete with test key. This earth leakage circuit breakers shall be mounted very close to the apparatus to be protected on a wooden block of suitable size. 11.0 Distribution Board shall be SP & N or TP & N as specified in the design. MCB board shall comply with BS 5486 Part III. Every distribution shall be provided with a multi terminal earthling conduit. 12.0 Fluorescent lamp fitting whether batten or suspension type shall comprise of a current limiting choke which assists starting a Thermal or glow type starter having a radio interference suppression capacitor and a power factor
  • 41. XLI Correcting condenser. Each fitting shall be complete with Metal/Copal Perspex reflector. Bi-pin lampscaps fluorescent tubes and Bi-pin lamp holders all completely wired internally. The fitting shall be suitable for the use on 230 Volts. Single phase, 50 Hz., A.C. supply. Suspension of fitting shall be rigid tubes or brass chain fixed to hooks screwed into rawl or Phil plugs buried in ceiling or any other approved method. Batten type fitting shall be fixed direct on to the support by the air of Phil or rawl plug or any other approved method. 13.0 Ceiling fan fitting shall be of the three bladed type with insulator and shackle and suitable length of down rod and canopy with motor for use on 230 Volts 50 Hz. single phase A.C. supply. The motor shall be of the totally enclosed shaded pole induction or capacitor type fitted with grease packed ball bearings and the fan shall be white enamel finished. Provisions shall also be made for an electorlier when required. The terminal block in the fan as well as the capacitor must be protected by removable covers. 14.0 Fan regulator shall be of the series choke or resistance type and shall have at least 5 speeds and "OFF" position. Regulator unless fully insulated must be earthen. 15.0 MCCB: 400V, 3 phase, 3 poles and neutral, 50 Hz. B.S. 3871 Part II 1966. The case shall be of moulded insulating material, possessing high thermal stability and good mechanical strength to withstand rough usage without any fracture of permanent distortion having front operating handle with trip free feature for manual "ON" and "OFF" operation. It shall comprise: (1) A delayed thermal or magnetic release which shall be adjustable between 60% to 100% of maximum continuous current rating of the breaker. (2) An instantaneous electromagnetic over current release which shall be adjustable between 3 to 5 times to maximum current rating of the breaker. The making and breaking capacity in KA and the performance category as per BS 4752 Part I 1977. 16.0 MCB : 400V/230V, 50Hz. as per BS 3871 Part I 1965; IEC 157-1 The case shall be of sealed type and made of moulding insulating material possessing high thermal stability and good mechanical strength to withstand rough usage without any fracture of permanent distortion. The MCB should possess mechanical life span and component life span at the rated current not of less than 20,000 operation or 40,000 movements. It shall be single pole or triple pole type with separate detachable neutral link and having provision for accommodating incoming and outgoing aluminum or copper service wire up to 16mm2 for Amps. and 20mm2 for Amps. 4. Special Specifications for Air-conditioning Technical Specifications for Split Type Air-conditioners
  • 42. XLII (A) From 12000 BTU/Hr upto 24000 BTU/Hr. i Indoor Unit (a) Fan shall be multiple speed (b) Fan motor bearing - permanently lubricated ball bearing type (c) Air filter shall be washable type (d) Operational control shall be wired type remote control type ii Out door Unit (a) Casing and condenser shall be of weatherproof construction suitable for tropical climate. (b) Fans shall be suitable for outdoor use (c) Fan motor bearing shall be permanently lubricated ball bearings. (d) Shall be supported in such away that casing is not exposed to accumulated rainwater and also that there is sufficient room and safety requirements to attend to servicing. (e) Compressor shall be scroll type. iii Protection Devices/Alarm (a) Compressor - Overload protection Internal thermostat Anti re-cycling timer Filter cleaner Notice (b) Fan motor - internal thermostat. iv Plants shall be suitable for single phase x 230V x 50Hz. v Condensate lines shall be insulated (25mm thickness) in indoor areas. vi Technical catalogues shall be submitted. (B) For plant above 24000 BTU/Hr. Following changes additions shall apply. Protection devices (Additional) (a) High pressure switch (b) Low pressure switch (c) Anti-phase protection Plant shall be suitable for 3 phase 400V, 50Hz power supply. (C) Quality Standards Plants offered shall have ISO 9001 quality accreditation and a copy of certificate shall accompany with the offer. 5. Special Specifications for Water Proofing General: (a) Warranty (i) Insulation, waterproofing and tanking shall be applied in accordance
  • 43. XLIII with the directions of the manufacturer of the materials and components, and the complete systems shall be fitted in the works by experienced specialist crew. (ii) Notwithstanding maintenance requirements for the works, the Contractor shall warrant the Owner with the assurance of a reputable local insurance Company that roof and tanks shall remain waterproof, vapor proof and damp-proof in respect of workmanship and materials for a minimum period of 10 years calculated from the time that the works are certified as substantially completed. (iii) The form of guarantee offered by the specialist, applicator shall be submitted for the Consultant’s approval prior to commencement of waterproofing. This guarantee shall in no way indemnify the Contractor against the improper performance of the waterproofing system. (iv) All structural components that retained or exclude water or any other liquid should be applied with approved waterproofing material. (v) Roof slab should be externally waterproofed and insulated by an agent approved by the Consultant. (b) Structure (i) It shall be the Contractor’s responsibility to ensure that the specialist applicator takes note of the type of the structure, nature and the location of waterproofing to be applied including any movement joints provided, when designing his waterproofing system. (ii) The laying of a waterproofing system on a concrete surface will be taken as signifying the acceptance of that surface., both in terms of surface quality, spacing and arrangement of movement joints and the construction joints by the Contractor and his specialist applicator. (c) Application (i) Where applicable, aprons and other sections for roof/tank penetrations, rims, side laps, bends and corners shall be incorporated, corrected, finished and uniformly lined. (ii) The waterproofing system shall be dressed up all pipes and other penetrations to a minimum height of 250 above the top of the concrete slab. (iii) Sharp corners are to be filled with screed or other fillets and waterproofing should be laid with generous over lap as per manufacturer’s instructions. (iv) When waterproofing is to be applied on exposed areas, colors have to be approved by the Consultant. (v) Where finishes such as concrete paving or tiles etc., are specified to be laid over waterproofing membranes laid on concrete floors, the floor shall be tested for water tightness prior to laying of these tiles/paving’s etc. Sumps, tanks etc. shall also be tested after the application of waterproofing systems. The cost of carrying out these tests including
  • 44. XLIV that of blocking any outlets etc. shall be borne by the Contractor. Where it is seen that water tightness has not been achieved, the Contractor shall take whatever remedial measures as are ordered by the Consultant and the cost of all such measures shall be borne by the Contractor. (d) Joints with abutting walls, columns, piping etc. (i) Joints with abutting structure shall be carried out with materials as specified in the relevant Clause of other trades, such as weather sealant etc. all as generally shown otherwise in typical details on the drawings. (ii) Special joints, not shown on drawings or particular sections there of requiring specials attention, are deemed to be included in the Contractor’s Tender, and are to be executed in a workman like manner nd in consent with and to the satisfaction of the Consultant. Waterproofing System to roof slabs and machine floor areas (a) Leveling Screed (i) Before laying the leveling screed the concrete surface shall be cleaned by removal of loose materials to the entire satisfaction of the Consultant. Concrete which is contaminated by oil or grease shall be chiseled away and refilled. (ii) Concrete slab shall be grouted with cement/water slurry before the laying of leveling screed. (iii) 1:3 Cement: Sand leveling screed shall be mechanically bath mixed and laid with a minimum thickness of 25mm, the falls to be achieved are not less than 1:200 or as shown in the drawings. Screed shall be laid with even slopes and internal and external corners shall have cover fillets with a radius of at least 70mm. The screed shall be finished with a wooden float. (iv) The screed shall be covered with wet saw dust, sand or equal method and kept damp for 5 days, or as ordered by the Consultant. Screed shall be protected from rainfall. Waterproofing membrane shall not be applied until the surface is thoroughly dried out. (b) Waterproofing WP1 (i) The following specification is for a built-up waterproofing system of non-metalic roofing compound of laminar bituminized construction intended for this Project. The Contractor may submit alternative reputable constructions together with the relevant specification and method statement to the approval of the Consultant; such constructions should in any case conform to the insurance requirement specified under “Warranty” requirement (See Clause 3.1.1). (ii) Waterproofing membrane shall be U.V. resistant mineralized atactic polypropylene (APP) modified bituminous polyester sheet with approximate weigh 4.0 kg/m2 and 4.0mm thick suitable for Torched- on application over the substrate after application of the approved primer.
  • 45. XLV An interruption of work the edges of the sheets have to be finished in such a manner that rain water and dust cannot penetrate underneath. (c) Insulation (i) On top of the waterproofing membrane, polyurethane or extruded polystyrene boards 50mm thick with Thermal conductivity of 0.027 W/m0C @ 250C (approx.). (ii) Method should comply with the following standards ASTM D-1622, ASTM C-518, ASTM C-272 and ASTM D-696. (iii) The boards shall have rebated edges all round for interlocked laying. In sizes 600 x 1200mm tightly laid in stretcher bond. (iv) The compressive strength of the insulation boards shall be not less than 40kPa according to ASTM C-165 procedure B. (v) Insulation boards shall be protected against rain and humidity. (d) Concrete Covering Screed (i) 60mm Thick, grade 25 concrete covering screed shall be laid over the gauge 1000 polythene sheet as shown on the drawing. 50 x 50mm (3mm dia.) galvanized steel wire-mesh shall be incorporated in the concrete screed layer. 10mm Thick expansion joints shall be provided in covering screed to limit the concrete screed panel size approximately to 4.0 Sq.m.. Expansion joints shall be coincided with the joints of the tile layer (if any) above and later filled by the approved joint sealant (DOWCORNING 790 SILICONE BUILDING SEALANT). (iii) Alternatively, reinforced concrete floating slab shall be constructed in stead of concrete screed if there is any possibility of installation of mechanical plants or equipment. Waterproofing System to Basement Slab (a) Concrete Screed (i) Concrete screed shall be mechanically batch mixed and laid over the well compacted and approved formation of the sub base or otherwise directed by the Consultant. The concrete grade 15 shall be laid to produce a concrete screed of 75mm thick. (ii) The screed shall be covered with wet saw dust, sand or equal method and kept damp for at least 5 days, or as instructed by the Consultant. (iii) Before laying of the waterproofing membrane, the concrete surface shall be thoroughly cleaned and dried out. (b) Waterproofing Membrane (WP2) (i) The prepared concrete surface shall be waterproofed by means APP bituminous polyester sheet with approximate weight 4.0 kg/m2 and 4.0 mm thick suitable for torched-on application over the substrata after application of approved primer.