7.1 INTRODUCTION
• In the development process a property developer’s second major financial
commitment is to place a contract to construct the development.
• Construction is a crucial stage in the development process and the key aim is
to construct a good quality building that performs on time and on budget.
• The selection of the procurement route needs to be decided early on as it has
an effect on the composition and the size of the professional team.
• After the initial brief is decided, a schedule of accommodation is prepared
and the broad design constraints are decided, the choice of building contract
can be made.
7.2 PROCUREMENT
• The decision on the form of contract will depend on the developer’s
requirements and the size and complexity of the development. Time, cost and
performance are key influencing factors.
• Different types of developer and stakeholder attach varying degrees of
importance to time, cost and performance (quality) and these factors will
influence the procurement strategy to be selected (Table 7.1).
Table 7.1 Examples of Prioritised Criteria by Client Type
(Source: based on Morledge in Kelly et al. 2002)
7.3 THE TRADITIONAL APPROACH: DESIGN-BID-BUILD
• This type of contract tends to be used on relatively straightforward small to
medium sized schemes where the developer is able to use a number of
variations and amendments to tailor the contract to the needs of the project.
• Developers appoint their own professional team who are responsible for
designing the building to meet the specified requirements, for supervising the
construction phase and for administering the contract.
7.3.1 The Traditional Roles of Professional Team Members
• The architect is responsible for the design of the buildings in terms of
aesthetics and functions following the developer’s brief and budget.
• The quantity surveyor is responsible for preparing estimates of building cost,
preparing the Bill of Quantities (i.e. measured specification of materials and
work to enable the contractor to submit a price) and, during construction, for
preparing valuations of work.
• A clerk of works or resident engineer may carry out a full-time ‘on-site’
supervisory role.
• Other members of the team can vary and may include a project manager,
structural engineers, mechanical and electrical engineers.
Discussion points:
Who are the key professionals a developer
needs to bring into the development team?
What role does each professional play in the
team?
7.3 THE TRADITIONAL APPROACH: DESIGN-BID-BUILD
7.3.2 Choosing the Contractor
• Once the detailed design is completed, the quantity surveyor prepares the Bill
of Quantities, which specifies and quantifies the materials and the work to be
carried out in great detail.
• When choosing contractors to be invited to submit competitive tenders for
carrying out the work, it is necessary to limit the total number of contractors
invited to submit competitive tenders.
• If the work is specialised, contractors skilled in that type of work are selected.
Sometimes it will be preferable to use a large national contractor, while at
other times local or regional contractors are favoured.
• Developers are often guided by their architect, project manager and/or
quantity surveyor on the selection of the contractors for the tender.
• The prices submitted by each of the contractors are examined by the quantity
surveyor and the project manager to ascertain what is offered.
• The reliability and financial stability of the contractor are vital considerations
since the failure of a contractor is a major disaster from the developer’s
perspective as long delays occur while the legal position is resolved and
another contractor is found to complete the work.
7.3 THE TRADITIONAL APPROACH: DESIGN-BID-BUILD
7.3.3 Paying the Contractor
• The method of payment for the works has a substantial impact on the
developer’s cash-flow position. It also has significant impact on the cash-flow
of the contractor, who has to consider the method of payment when
preparing the price for the work.
• The developer has to pay out very substantial sums of money over a
considerable period of time before obtaining the benefit of a completed
building at the end of the contract.
• The ideal arrangement for developers is for the whole of the contract price to
be paid when the building is handed over, so that they do not part with their
money until the time when they should be receiving an income from the
building or have the benefit of occupation of it.
• The method of paying for the work has to be related to the circumstances of
each contract. The contractor is more likely to be flexible if they are a partner
in the scheme and stand to benefit in terms of a profit share.
7.3 THE TRADITIONAL APPROACH: DESIGN-BID-BUILD
7.3.4 Calculating the Cost
• An accepted approach is for the contractor to submit a bid on either a ‘firm
price’ or a ‘fluctuations’ basis.
• Quantity surveyor’s re-measurements, architect’s variation orders and
instructions and extensions of time may affect the cost.
• Developers and their professional advisers must decide on what basis they
wish contractors to prepare their competitive bids in order that the
contractors submit prices on the same basis.
• Often there are two main alternative methods of calculating the cost:
(i) A cost-plus contract where the contractor is paid on the basis of the
actual cost of the building work (‘prime cost’) plus a fee to cover their
overheads and profit.
(ii) A target cost contract might be negotiated or established by tender. A
target cost is agreed with the contractor plus the contractor’s fee and
any savings or additions to the target cost are shared by the parties.
7.3 THE TRADITIONAL APPROACH: DESIGN-BID-BUILD
7.3.5 The Duration of the Contract
• The date agreed in the contract for the completion of the building is not
certain as the contractor can apply for extensions of time for a number of
reasons.
• Extensions of time usually result in an increase in the cost which will certainly
include the contractor’s ‘preliminaries’ (overheads such as insurance, cost of
plant hire, etc.). The impact of an extension is felt twice by the developer:
firstly, it affects cash-flow and, secondly, it increases costs.
• The main reasons for extension of time which entitle the contractor to
recover additional loss and expenses include inadequacy and/or errors in the
contract documents, the drawings and/or the Bill of Quantities; delays by the
architect in issuing drawings or instructions; delays caused by tradesmen
directly employed by the developer; failure by the nominated subcontractors;
bad weather; strikes and lockouts; shortage of labour; damage by fire and
natural disasters.
• Key advantages and disadvantages of the traditional approach are
summarised in Table 7.2.
Table 7.2 Advantages and Disadvantages of Design-Bid-Build Procurement
Advantages Disadvantages
Competitive equity and fairness
Design-led facilitates high quality
design
Reasonable price certainty based on
market forces with reduced unknowns
Acceptable strategy in terms of public
accountability and transparency
Well-known procedure and prove
approach
Flexibility – changes are easy to arrange
and have limited effect on value
Strategy is potentially open to abuse
resulting in less certainty
Overall construction timeframe may be
longer than other options because there
is no parallel working
No ‘buildability’ input from contractor
The strategy can lead to adversarial
relationships between the parties
Approach is not fully promoted by all
stakeholders
Discussion points:
For what reasons might a developer select a
traditional (design-bid-build) contract for a
development project?
What are the two types of bids that a contractor
can submit?
7.4 DESIGN AND BUILD
• Typically the contractor actually assumes the risk and responsibility for the
design and construction of the scheme in return for a fixed-price lump sum.
Design and build is a fast track strategy.
• Use has become more widespread due to dissatisfaction with other types of
contracts and the problems encountered with splitting design and
construction responsibilities. Design and build was originally used on simple
and straightforward schemes but is now used on many types of building
projects.
• The contract is based upon a performance specification by or on behalf of the
developer. Performance specifications vary from being fairly simple to very
detailed depending on the nature of the scheme.
• A developer using this type of contract may appoint a specific contractor with
which they have successfully worked before or who has expertise in
constructing buildings similar to the one proposed.
• The advantages of this type of contract for the developer are that while it is
possible to provide for fluctuations in the contract price, and there are various
alternative ways of paying for the buildings as the contract proceeds, usually a
lump-sum fixed price is agreed.
7.5 MANAGEMENT CONTRACTING
• A management contractor is engaged by the developer to manage the
building process and is paid a fee. Initially developed in the USA, this type of
contract became more widespread in an international context because
developers were impressed with the fast track methods of construction.
• The developer appoints the professional team to prepare the drawings and
specification for the project. The quantity surveyor prepares a cost plan based
on the drawings and specification. The actual cost incurred by the
management contractor (‘prime cost’) is paid by the developer, having been
certified by the architect and monitored by the quantity surveyor.
• Note that the management contract itself is not a ‘lump-sum’ contract. The
management contract is based on the contract cost plan prepared by the
quantity surveyor, which is only an indication of the price.
• The developer may have to accept a very high degree of risk with this type of
contract. Developers who have used this type of contract have found cost
control the biggest problem as there is no tender sum.
• The key advantage is the saving of time, achieved by overlapping the design
and construction of each package and involving the construction manager at
the beginning of the design process.
7.6 PROJECT MANAGEMENT
• The appointment of a project manager is not necessary for every project. A
project manager tends to be needed for large and complicated rather than
small, simple projects.
• Project management is an occupation and project managers may be
architects, quantity surveyors, real estate managers, valuers/agents, or have a
building/contracting background.
• The project manager is concerned with the overall management of the project
and is not involved in carrying out any part of the project. The project
manager needs plenty of common sense, administrative ability and a good
knowledge of construction.
• The objectives are to ensure that the finished project is suitable for its
intended purpose, that it is built to satisfactory standards, that completion
occurs on time and that the project is carried out within the budget.
Discussion points:
What are the benefits of having a project
manager in the development team?
Under what circumstances might a developer
decide to appoint a project manager?
7.6 PROJECT MANAGEMENT
7.6.1 Pre-Contract Preparations
• The project manager should check that the developer has the necessary legal
title on the site, whether it is freehold or leasehold, and that vacant
possession of the whole site is available immediately.
• The project manager will arrange, if not previously carried out by the
developer, all of the necessary ground investigations, structural surveys and
site surveys, and communicate the results to the rest of the professional
team.
7.6.2 Preparing the Contract Documents
• The project manager’s most important job is to ensure that the contract is not
allowed to commence without adequate documentation. Incomplete
drawings are probably the most common cause of delays and cost increases.
• The project manager needs to be absolutely satisfied with the availability of
the drawings by the architect, as well as satisfied that the Bill of Quantities is
as complete and accurate as possible.
7.6 PROJECT MANAGEMENT
7.6.3 Appointing the Contractor
• If it is proposed to invite competitive bids from selected contractors, the
project manager should agree with the architect and the developer the names
of the contractors who will be invited to tender.
• The quantity surveyor compares each tender against their priced Bill of
Quantities. Once satisfied on all matters, the project manager then authorises
the placing of the building contract.
7.6.4 Site Supervision
• The project manager should be continually satisfied about the arrangements
made by the architect for site supervision during construction.
• The size and complexity of the scheme may merit the appointment of a full-
time site supervisor, such as a clerk of works or a resident engineer or indeed
a resident architect.
7.6 PROJECT MANAGEMENT
7.6.5 Construction Period
• When the contractor has taken possession of the site, the project manager
ensures that the works are carried out on schedule and that the overall cost is
kept within the budget.
• To carry out his duties effectively, regular meetings of the project team are
held, such as on a monthly or fortnightly basis. The architect should report as
to whether any variation orders or instructions have been given to the
contractor, the quantity surveyor then presents a report on the financial
situation and other professionals provide their reports.
• The project manager summarises the overall financial situation, particularly
with regard to payments to the contractor, compares them with the budget,
checks on dates of handover and compares the estimated date for the receipt
of income or capital payments with the budgetary expectation.
• These are matters of vital importance to the developer’s cash-flow. If it
appears that the project is running behind schedule, then methods of
speeding up the work to recover the position are considered, together with
the implications for cost.
7.6 PROJECT MANAGEMENT
7.6.6 Handover of the Completed Development
• A short time before the date for completion and handover of the building
from the contractor to the developer, the architect prepares a list of all minor
defects that must be remedied before handover occurs.
• If the development has been pre-let or pre-sold to an owner-occupier, then
the occupiers and/or their contractors may wish to have access before formal
handover by the main contractor working for the developer.
• The project manager, with the architect, needs to attribute and resolve
problems quickly.
• The quantity surveyor should then be asked when any outstanding
re-measurement work will be completed and be in a position to agree the
final account with the contractor, so that the architect may issue a final
certificate.
• The importance of inspecting the site and its immediate environs on the
handover date should not be overlooked.
• Where an occupier is not taking possession immediately, then the developer
is responsible for a vacant building and a programme of regular cleaning and
maintenance should be instigated.
7.6 PROJECT MANAGEMENT
7.6.7 Monitoring Construction Process
• The project manager’s objective is to produce the building on time and within
budget for the developer client.
• Any delays in completion or increase in costs will affect the profitability of the
development; therefore it is essential that a developer is kept regularly
informed on progress and cost.
• Typical reporting methods include: bar (or Gantt) chart (Figure 7.1), cashflow
table and graph, financial report, checklist.
• Whilst regular reporting on progress and cost is a way of keeping the
developer informed, it also provides the project manager with an essential
tool, especially if the developer insists on regular reporting. The project
manager will know whether the aims are being achieved and it will bring into
sharp focus the targets that need to be achieved and the problems that need
to be tackled.
Figure 7.1 Overall Development Programme – Gantt Chart
Discussion points:
What are the main issues that developers need
to consider during the construction phase of a
project?
What are the major risks the developer faces
during this stage?
7.7 PUBLIC-PRIVATE PARTNERSHIPS (PPP)
• In the public sector, there are three main procurement approaches:
(a) PPP, (b) Design and Build and (c) Prime Contracting.
• In bringing the public and private sector together, the aim is that the business
community’s management and financial skills will lead to better value for
money for taxpayers.
• Clients, designers and contractors have evolved their relationships with
developments and developed different types of business relationships, among
these is partnering.
• Partnering is a business relationship for the benefit of all parties, built on
trust, openness and respect.
• There is a requirement to develop an environment for long-term profitability
and to encourage innovation.
• Partners commit to improved project buildability and a lowering of project
costs through the process of value management.
7.8 PARTNERING
Chapter 7 Construction
Property Development (6th Edition)
Publisher: Routledge www.routledge.com
Authors: Professor R.G. Reed and Dr S. Sims

More Related Content

What's hot

Construction process
Construction processConstruction process
Construction process
Mazen Al-Qadi
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
Pundlik Rathod
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 
Estimation (power point)
Estimation (power point)Estimation (power point)
Estimation (power point)
Waqas Aslam
 

What's hot (20)

Construction process
Construction processConstruction process
Construction process
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Construction phases
Construction phasesConstruction phases
Construction phases
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Quantity Surveyor presentation
Quantity Surveyor presentationQuantity Surveyor presentation
Quantity Surveyor presentation
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Types of resources in civil engineering field
Types of resources in civil engineering fieldTypes of resources in civil engineering field
Types of resources in civil engineering field
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 
Estimation (power point)
Estimation (power point)Estimation (power point)
Estimation (power point)
 
Construction Material Management
Construction Material ManagementConstruction Material Management
Construction Material Management
 
Estimating & Costing - I
Estimating & Costing - IEstimating & Costing - I
Estimating & Costing - I
 
Bar chart
Bar chartBar chart
Bar chart
 
Construction tender process
Construction tender processConstruction tender process
Construction tender process
 

Similar to Preparation of boq

Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
Timun Loh
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
Lee Pei Gie
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
마 이환
 

Similar to Preparation of boq (20)

TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment Structure
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project delivery
 
Lecture 1.pptx
Lecture 1.pptxLecture 1.pptx
Lecture 1.pptx
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
 
TOPIC1.pdf
TOPIC1.pdfTOPIC1.pdf
TOPIC1.pdf
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Professional Practice
Professional PracticeProfessional Practice
Professional Practice
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 report
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management Contracting
 
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy pptCON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
 
PP1 presentation slide.
PP1 presentation slide.PP1 presentation slide.
PP1 presentation slide.
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 

More from R.R.G.S Bandara (6)

Prolongation cost calculation
Prolongation cost  calculation Prolongation cost  calculation
Prolongation cost calculation
 
Legal system of sri lanaka
Legal system of sri lanakaLegal system of sri lanaka
Legal system of sri lanaka
 
General notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATESGeneral notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATES
 
Automo lesson3
Automo lesson3Automo lesson3
Automo lesson3
 
පිලිකා cancer protection
පිලිකා cancer protectionපිලිකා cancer protection
පිලිකා cancer protection
 
00 eng tech note1
00 eng tech note100 eng tech note1
00 eng tech note1
 

Recently uploaded

The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
heathfieldcps1
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
PECB
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
QucHHunhnh
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
negromaestrong
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
QucHHunhnh
 

Recently uploaded (20)

Role Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptxRole Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptx
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 

Preparation of boq

  • 1. 7.1 INTRODUCTION • In the development process a property developer’s second major financial commitment is to place a contract to construct the development. • Construction is a crucial stage in the development process and the key aim is to construct a good quality building that performs on time and on budget. • The selection of the procurement route needs to be decided early on as it has an effect on the composition and the size of the professional team. • After the initial brief is decided, a schedule of accommodation is prepared and the broad design constraints are decided, the choice of building contract can be made.
  • 2. 7.2 PROCUREMENT • The decision on the form of contract will depend on the developer’s requirements and the size and complexity of the development. Time, cost and performance are key influencing factors. • Different types of developer and stakeholder attach varying degrees of importance to time, cost and performance (quality) and these factors will influence the procurement strategy to be selected (Table 7.1). Table 7.1 Examples of Prioritised Criteria by Client Type (Source: based on Morledge in Kelly et al. 2002)
  • 3. 7.3 THE TRADITIONAL APPROACH: DESIGN-BID-BUILD • This type of contract tends to be used on relatively straightforward small to medium sized schemes where the developer is able to use a number of variations and amendments to tailor the contract to the needs of the project. • Developers appoint their own professional team who are responsible for designing the building to meet the specified requirements, for supervising the construction phase and for administering the contract. 7.3.1 The Traditional Roles of Professional Team Members • The architect is responsible for the design of the buildings in terms of aesthetics and functions following the developer’s brief and budget. • The quantity surveyor is responsible for preparing estimates of building cost, preparing the Bill of Quantities (i.e. measured specification of materials and work to enable the contractor to submit a price) and, during construction, for preparing valuations of work. • A clerk of works or resident engineer may carry out a full-time ‘on-site’ supervisory role. • Other members of the team can vary and may include a project manager, structural engineers, mechanical and electrical engineers.
  • 4. Discussion points: Who are the key professionals a developer needs to bring into the development team? What role does each professional play in the team?
  • 5. 7.3 THE TRADITIONAL APPROACH: DESIGN-BID-BUILD 7.3.2 Choosing the Contractor • Once the detailed design is completed, the quantity surveyor prepares the Bill of Quantities, which specifies and quantifies the materials and the work to be carried out in great detail. • When choosing contractors to be invited to submit competitive tenders for carrying out the work, it is necessary to limit the total number of contractors invited to submit competitive tenders. • If the work is specialised, contractors skilled in that type of work are selected. Sometimes it will be preferable to use a large national contractor, while at other times local or regional contractors are favoured. • Developers are often guided by their architect, project manager and/or quantity surveyor on the selection of the contractors for the tender. • The prices submitted by each of the contractors are examined by the quantity surveyor and the project manager to ascertain what is offered. • The reliability and financial stability of the contractor are vital considerations since the failure of a contractor is a major disaster from the developer’s perspective as long delays occur while the legal position is resolved and another contractor is found to complete the work.
  • 6. 7.3 THE TRADITIONAL APPROACH: DESIGN-BID-BUILD 7.3.3 Paying the Contractor • The method of payment for the works has a substantial impact on the developer’s cash-flow position. It also has significant impact on the cash-flow of the contractor, who has to consider the method of payment when preparing the price for the work. • The developer has to pay out very substantial sums of money over a considerable period of time before obtaining the benefit of a completed building at the end of the contract. • The ideal arrangement for developers is for the whole of the contract price to be paid when the building is handed over, so that they do not part with their money until the time when they should be receiving an income from the building or have the benefit of occupation of it. • The method of paying for the work has to be related to the circumstances of each contract. The contractor is more likely to be flexible if they are a partner in the scheme and stand to benefit in terms of a profit share.
  • 7. 7.3 THE TRADITIONAL APPROACH: DESIGN-BID-BUILD 7.3.4 Calculating the Cost • An accepted approach is for the contractor to submit a bid on either a ‘firm price’ or a ‘fluctuations’ basis. • Quantity surveyor’s re-measurements, architect’s variation orders and instructions and extensions of time may affect the cost. • Developers and their professional advisers must decide on what basis they wish contractors to prepare their competitive bids in order that the contractors submit prices on the same basis. • Often there are two main alternative methods of calculating the cost: (i) A cost-plus contract where the contractor is paid on the basis of the actual cost of the building work (‘prime cost’) plus a fee to cover their overheads and profit. (ii) A target cost contract might be negotiated or established by tender. A target cost is agreed with the contractor plus the contractor’s fee and any savings or additions to the target cost are shared by the parties.
  • 8. 7.3 THE TRADITIONAL APPROACH: DESIGN-BID-BUILD 7.3.5 The Duration of the Contract • The date agreed in the contract for the completion of the building is not certain as the contractor can apply for extensions of time for a number of reasons. • Extensions of time usually result in an increase in the cost which will certainly include the contractor’s ‘preliminaries’ (overheads such as insurance, cost of plant hire, etc.). The impact of an extension is felt twice by the developer: firstly, it affects cash-flow and, secondly, it increases costs. • The main reasons for extension of time which entitle the contractor to recover additional loss and expenses include inadequacy and/or errors in the contract documents, the drawings and/or the Bill of Quantities; delays by the architect in issuing drawings or instructions; delays caused by tradesmen directly employed by the developer; failure by the nominated subcontractors; bad weather; strikes and lockouts; shortage of labour; damage by fire and natural disasters. • Key advantages and disadvantages of the traditional approach are summarised in Table 7.2.
  • 9. Table 7.2 Advantages and Disadvantages of Design-Bid-Build Procurement Advantages Disadvantages Competitive equity and fairness Design-led facilitates high quality design Reasonable price certainty based on market forces with reduced unknowns Acceptable strategy in terms of public accountability and transparency Well-known procedure and prove approach Flexibility – changes are easy to arrange and have limited effect on value Strategy is potentially open to abuse resulting in less certainty Overall construction timeframe may be longer than other options because there is no parallel working No ‘buildability’ input from contractor The strategy can lead to adversarial relationships between the parties Approach is not fully promoted by all stakeholders
  • 10. Discussion points: For what reasons might a developer select a traditional (design-bid-build) contract for a development project? What are the two types of bids that a contractor can submit?
  • 11. 7.4 DESIGN AND BUILD • Typically the contractor actually assumes the risk and responsibility for the design and construction of the scheme in return for a fixed-price lump sum. Design and build is a fast track strategy. • Use has become more widespread due to dissatisfaction with other types of contracts and the problems encountered with splitting design and construction responsibilities. Design and build was originally used on simple and straightforward schemes but is now used on many types of building projects. • The contract is based upon a performance specification by or on behalf of the developer. Performance specifications vary from being fairly simple to very detailed depending on the nature of the scheme. • A developer using this type of contract may appoint a specific contractor with which they have successfully worked before or who has expertise in constructing buildings similar to the one proposed. • The advantages of this type of contract for the developer are that while it is possible to provide for fluctuations in the contract price, and there are various alternative ways of paying for the buildings as the contract proceeds, usually a lump-sum fixed price is agreed.
  • 12. 7.5 MANAGEMENT CONTRACTING • A management contractor is engaged by the developer to manage the building process and is paid a fee. Initially developed in the USA, this type of contract became more widespread in an international context because developers were impressed with the fast track methods of construction. • The developer appoints the professional team to prepare the drawings and specification for the project. The quantity surveyor prepares a cost plan based on the drawings and specification. The actual cost incurred by the management contractor (‘prime cost’) is paid by the developer, having been certified by the architect and monitored by the quantity surveyor. • Note that the management contract itself is not a ‘lump-sum’ contract. The management contract is based on the contract cost plan prepared by the quantity surveyor, which is only an indication of the price. • The developer may have to accept a very high degree of risk with this type of contract. Developers who have used this type of contract have found cost control the biggest problem as there is no tender sum. • The key advantage is the saving of time, achieved by overlapping the design and construction of each package and involving the construction manager at the beginning of the design process.
  • 13. 7.6 PROJECT MANAGEMENT • The appointment of a project manager is not necessary for every project. A project manager tends to be needed for large and complicated rather than small, simple projects. • Project management is an occupation and project managers may be architects, quantity surveyors, real estate managers, valuers/agents, or have a building/contracting background. • The project manager is concerned with the overall management of the project and is not involved in carrying out any part of the project. The project manager needs plenty of common sense, administrative ability and a good knowledge of construction. • The objectives are to ensure that the finished project is suitable for its intended purpose, that it is built to satisfactory standards, that completion occurs on time and that the project is carried out within the budget.
  • 14. Discussion points: What are the benefits of having a project manager in the development team? Under what circumstances might a developer decide to appoint a project manager?
  • 15. 7.6 PROJECT MANAGEMENT 7.6.1 Pre-Contract Preparations • The project manager should check that the developer has the necessary legal title on the site, whether it is freehold or leasehold, and that vacant possession of the whole site is available immediately. • The project manager will arrange, if not previously carried out by the developer, all of the necessary ground investigations, structural surveys and site surveys, and communicate the results to the rest of the professional team. 7.6.2 Preparing the Contract Documents • The project manager’s most important job is to ensure that the contract is not allowed to commence without adequate documentation. Incomplete drawings are probably the most common cause of delays and cost increases. • The project manager needs to be absolutely satisfied with the availability of the drawings by the architect, as well as satisfied that the Bill of Quantities is as complete and accurate as possible.
  • 16. 7.6 PROJECT MANAGEMENT 7.6.3 Appointing the Contractor • If it is proposed to invite competitive bids from selected contractors, the project manager should agree with the architect and the developer the names of the contractors who will be invited to tender. • The quantity surveyor compares each tender against their priced Bill of Quantities. Once satisfied on all matters, the project manager then authorises the placing of the building contract. 7.6.4 Site Supervision • The project manager should be continually satisfied about the arrangements made by the architect for site supervision during construction. • The size and complexity of the scheme may merit the appointment of a full- time site supervisor, such as a clerk of works or a resident engineer or indeed a resident architect.
  • 17. 7.6 PROJECT MANAGEMENT 7.6.5 Construction Period • When the contractor has taken possession of the site, the project manager ensures that the works are carried out on schedule and that the overall cost is kept within the budget. • To carry out his duties effectively, regular meetings of the project team are held, such as on a monthly or fortnightly basis. The architect should report as to whether any variation orders or instructions have been given to the contractor, the quantity surveyor then presents a report on the financial situation and other professionals provide their reports. • The project manager summarises the overall financial situation, particularly with regard to payments to the contractor, compares them with the budget, checks on dates of handover and compares the estimated date for the receipt of income or capital payments with the budgetary expectation. • These are matters of vital importance to the developer’s cash-flow. If it appears that the project is running behind schedule, then methods of speeding up the work to recover the position are considered, together with the implications for cost.
  • 18. 7.6 PROJECT MANAGEMENT 7.6.6 Handover of the Completed Development • A short time before the date for completion and handover of the building from the contractor to the developer, the architect prepares a list of all minor defects that must be remedied before handover occurs. • If the development has been pre-let or pre-sold to an owner-occupier, then the occupiers and/or their contractors may wish to have access before formal handover by the main contractor working for the developer. • The project manager, with the architect, needs to attribute and resolve problems quickly. • The quantity surveyor should then be asked when any outstanding re-measurement work will be completed and be in a position to agree the final account with the contractor, so that the architect may issue a final certificate. • The importance of inspecting the site and its immediate environs on the handover date should not be overlooked. • Where an occupier is not taking possession immediately, then the developer is responsible for a vacant building and a programme of regular cleaning and maintenance should be instigated.
  • 19. 7.6 PROJECT MANAGEMENT 7.6.7 Monitoring Construction Process • The project manager’s objective is to produce the building on time and within budget for the developer client. • Any delays in completion or increase in costs will affect the profitability of the development; therefore it is essential that a developer is kept regularly informed on progress and cost. • Typical reporting methods include: bar (or Gantt) chart (Figure 7.1), cashflow table and graph, financial report, checklist. • Whilst regular reporting on progress and cost is a way of keeping the developer informed, it also provides the project manager with an essential tool, especially if the developer insists on regular reporting. The project manager will know whether the aims are being achieved and it will bring into sharp focus the targets that need to be achieved and the problems that need to be tackled.
  • 20. Figure 7.1 Overall Development Programme – Gantt Chart
  • 21. Discussion points: What are the main issues that developers need to consider during the construction phase of a project? What are the major risks the developer faces during this stage?
  • 22. 7.7 PUBLIC-PRIVATE PARTNERSHIPS (PPP) • In the public sector, there are three main procurement approaches: (a) PPP, (b) Design and Build and (c) Prime Contracting. • In bringing the public and private sector together, the aim is that the business community’s management and financial skills will lead to better value for money for taxpayers. • Clients, designers and contractors have evolved their relationships with developments and developed different types of business relationships, among these is partnering. • Partnering is a business relationship for the benefit of all parties, built on trust, openness and respect. • There is a requirement to develop an environment for long-term profitability and to encourage innovation. • Partners commit to improved project buildability and a lowering of project costs through the process of value management. 7.8 PARTNERING
  • 23. Chapter 7 Construction Property Development (6th Edition) Publisher: Routledge www.routledge.com Authors: Professor R.G. Reed and Dr S. Sims