SlideShare a Scribd company logo
1 of 12
Prolongation cost calculation
RRGS BANDARA
Once a Contractor has secured an
extension of time and relief from liquidated
damages, thoughts will quickly turn to
recovery of the costs incurred due to the
delayed completion date – i.e.
“Prolongation Costs”.
If you ask an Employer’s QS how such
costs should be determined the answer is
often an unequivocal statement that the
rates and prices from the Preliminaries
BOQ shall be divided by the original
contract duration and the derived daily rate
for preliminaries shall then be applied to
the extended duration.
The sharp witted Employer’s QS may even refine this
logic with the caveat that the BOQ rates and prices
should first be adjusted to remove fixed costs,
mobilization and demobilization costs, overheads and
profit.
Whilst both answers are quite wrong, these
approaches are often used in order to achieve result,
despite the inaccurate answer. The problem is that
neither approach attempts to address the underlying
question of what costs / losses were actually incurred
by the Contractor as a consequence of the delaying
events for which the Employer was responsible.
The answer to this question cannot be found
in the BOQ, but can (and should) be found in
a detailed analysis of the Contractor’s cost
records The express wording of the contract
will dictate which heads of claim are
admissible, but in general terms an accurate
understanding of Prolongation Cost
entitlement can be derived by application of
the following basic principles:
-Identify the events that gave rise to the
extension of time – as it is the cost / loss
arising from these events that the Contractor
is entitled to recover;
-Identify the point in time that the delay
occurred – a common mistake is to
identify the costs that were incurred over
the extended duration at the end of the
contract period. This is incorrect. The delay
may have occurred prior to full mobilization
and thus the actual costs incurred at that
time may be lower;
-Identify the direct costs that follow
from the compensable delay events –
the Contractor is not entitled to costs
arising from delay events for which it is
responsible. Separation of the two can
defeat arguments that the claim is global
and includes elements of the Contractor’s
own culpability;
-Assess only time related costs and not
one off capital costs – time related costs
are those which necessarily arise as a
consequence of additional time spent on
the project and would typically include
staff salaries; insurance, rents, utilities,
bonds, accommodation, office services,
car leases & running costs, etc. but
would not include purchase costs of
offices, photocopiers, vehicles etc.
-Exclude task related costs – a
common mistake is to include task
related costs (e.g. labour, plant hire or
scaffolding costs) that would have
been incurred in any event. These
costs may only have been incurred at a
later point in time and are therefore not
additional. Such costs would need to
be separately recovered through a
properly formulated disruption cost
claim;
-Exclude profit – the purpose of the claim
is to put the Contractor back into the
position it would have been, but for the
delay. ‘Profit’ is not ‘cost’ and thus any
claim for profit can only be by way of a
‘loss of opportunity’ claim – which may be
expressly precluded by the wording of the
contract and would in any case have to
be proved, i.e. that opportunities did in
fact present themselves and were
refused because key resources could not
be released from the delayed project;
-Allow for off-site costs – costs incurred in the Contractor’s head
office (and elsewhere) may be as a direct result of the project
delay. The fact that these costs were incurred off site does not
mean that the Contractor is not entitled to receive them;
-If possible, avoid formulae for determining overheads (e.g.
Hudson’s, Emden’s etc.) – unless you are a Contractor and you
fully understand the basis of your ‘loss of opportunity’ claim and
how to present it! By indentifying actual incurred overhead costs
rather than rely on theory based formulae that commonly produce
high assessments;
-Interest / Finance Charges – remember that charging interest on
a debt may be prohibited in your jurisdiction or by your contract.
Most interest or finance claims suffer from a lack of facts and are
commonly: unsupported, theoretical assessments of loss.
However, a skilled claimant can often find ways to lend credibility
to this type of claim.
Calculation of Costs. Once the contractor is granted an extension
of time with costs, the computation of the recoverable items
must also be substantiated with properly maintained records and
invoices. Normally, the contractor should prove actual loss from
records. Only where this is not possible, and as an exception
rather than the rule, will calculation be allowed by reference to
formulae such as the Eichleay formula, and the Hudson or Emden
formulae. The formula is applied to assess loss where certain
things have been established proving that the contractor did
actually suffer loss. The contractor must show that it would have
secured work on another contractor and would have been
recovering overheads from this other project, and that there was
profit capable of being earned elsewhere and there was no
change in the market thereafter affecting profitability of the
work.
It must also be established that the
contractor was unable to deploy
resources elsewhere and had no
possibility of recovering the overheads
from other sources, e.g., from an
increased volume of work. Thus such
formulae are likely only to be relevant
and of value if the event causing the
delay has the characteristic of a breach
of contract.

More Related Content

What's hot

Construction delays
Construction delaysConstruction delays
Construction delaysSaida Njim
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysisADITYA GHUMARE
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsNam N.N Tran M.Eng, PMP
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact AnalysisChris Carson
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesMichael Pink
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedulesHatem Hegazi
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedMichael Pink
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m magedM Maged Hegazy, LLM, MBA, CCP, P3O
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMIChris Carson
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 

What's hot (20)

Construction delays
Construction delaysConstruction delays
Construction delays
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projects
 
Claims
ClaimsClaims
Claims
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
Concurrent Delay in Construction
Concurrent Delay in ConstructionConcurrent Delay in Construction
Concurrent Delay in Construction
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 

Similar to Prolongation cost calculation

Reasonableness of Construction Completion Costs
Reasonableness of Construction Completion CostsReasonableness of Construction Completion Costs
Reasonableness of Construction Completion CostsThe Vertex Companies, LLC
 
DIRECTED READING THREE PERCEPTIONS OF PROJECT COST D.H. Hamburg.docx
DIRECTED READING THREE PERCEPTIONS OF PROJECT COST D.H. Hamburg.docxDIRECTED READING THREE PERCEPTIONS OF PROJECT COST D.H. Hamburg.docx
DIRECTED READING THREE PERCEPTIONS OF PROJECT COST D.H. Hamburg.docxduketjoy27252
 
Liquidated damages contracts
Liquidated damages   contractsLiquidated damages   contracts
Liquidated damages contractsBhushan Goyal
 
Commercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesCommercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesAMILA GAYAN
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Bhalindra Bath - projects & M&A law
 
Handbook-for-Value-Based-Billing-Engagements
Handbook-for-Value-Based-Billing-EngagementsHandbook-for-Value-Based-Billing-Engagements
Handbook-for-Value-Based-Billing-EngagementsAlex Erines
 
Revenue Recognition Serial Part 6: Step 5 - Recognizing Revenue as or When Pe...
Revenue Recognition Serial Part 6: Step 5 - Recognizing Revenue as or When Pe...Revenue Recognition Serial Part 6: Step 5 - Recognizing Revenue as or When Pe...
Revenue Recognition Serial Part 6: Step 5 - Recognizing Revenue as or When Pe...MHM (Mayer Hoffman McCann P.C.)
 
Construction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of ResidencesConstruction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of ResidencesConstruction Cicerone
 
Quick Costs - how to avoid challenges to success fees.
Quick Costs - how to avoid challenges to success fees. Quick Costs - how to avoid challenges to success fees.
Quick Costs - how to avoid challenges to success fees. QuickCostsCostsCompa
 
What Was the FASB Thinking?
What Was the FASB Thinking? What Was the FASB Thinking?
What Was the FASB Thinking? DecosimoCPAs
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction ContractSarah Fox
 
Ind as 23 vs as-16
Ind as 23 vs as-16Ind as 23 vs as-16
Ind as 23 vs as-16UMESH SHARMA
 
Revenue Recognition for Contractors - NECA NOW Conference
Revenue Recognition for Contractors - NECA NOW Conference Revenue Recognition for Contractors - NECA NOW Conference
Revenue Recognition for Contractors - NECA NOW Conference CBIZ, Inc.
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 

Similar to Prolongation cost calculation (20)

Reasonableness of Construction Completion Costs
Reasonableness of Construction Completion CostsReasonableness of Construction Completion Costs
Reasonableness of Construction Completion Costs
 
DIRECTED READING THREE PERCEPTIONS OF PROJECT COST D.H. Hamburg.docx
DIRECTED READING THREE PERCEPTIONS OF PROJECT COST D.H. Hamburg.docxDIRECTED READING THREE PERCEPTIONS OF PROJECT COST D.H. Hamburg.docx
DIRECTED READING THREE PERCEPTIONS OF PROJECT COST D.H. Hamburg.docx
 
Liquidated damages contracts
Liquidated damages   contractsLiquidated damages   contracts
Liquidated damages contracts
 
Cost value reconciliation (cvr)
Cost value reconciliation (cvr)Cost value reconciliation (cvr)
Cost value reconciliation (cvr)
 
Commercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesCommercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and Penalties
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...
 
Management Reserve
Management ReserveManagement Reserve
Management Reserve
 
Liquidated damages
Liquidated damagesLiquidated damages
Liquidated damages
 
Handbook-for-Value-Based-Billing-Engagements
Handbook-for-Value-Based-Billing-EngagementsHandbook-for-Value-Based-Billing-Engagements
Handbook-for-Value-Based-Billing-Engagements
 
Contingencies and provisioning[1]
Contingencies and provisioning[1]Contingencies and provisioning[1]
Contingencies and provisioning[1]
 
Revenue Recognition Serial Part 6: Step 5 - Recognizing Revenue as or When Pe...
Revenue Recognition Serial Part 6: Step 5 - Recognizing Revenue as or When Pe...Revenue Recognition Serial Part 6: Step 5 - Recognizing Revenue as or When Pe...
Revenue Recognition Serial Part 6: Step 5 - Recognizing Revenue as or When Pe...
 
Construction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of ResidencesConstruction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of Residences
 
Quick Costs - how to avoid challenges to success fees.
Quick Costs - how to avoid challenges to success fees. Quick Costs - how to avoid challenges to success fees.
Quick Costs - how to avoid challenges to success fees.
 
What Was the FASB Thinking?
What Was the FASB Thinking? What Was the FASB Thinking?
What Was the FASB Thinking?
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract
 
Ind as 23 vs as-16
Ind as 23 vs as-16Ind as 23 vs as-16
Ind as 23 vs as-16
 
uap doc 207-208
uap doc 207-208uap doc 207-208
uap doc 207-208
 
End client value matrix
End client value matrixEnd client value matrix
End client value matrix
 
Revenue Recognition for Contractors - NECA NOW Conference
Revenue Recognition for Contractors - NECA NOW Conference Revenue Recognition for Contractors - NECA NOW Conference
Revenue Recognition for Contractors - NECA NOW Conference
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 

More from R.R.G.S Bandara

Legal system of sri lanaka
Legal system of sri lanakaLegal system of sri lanaka
Legal system of sri lanakaR.R.G.S Bandara
 
General notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATESGeneral notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATESR.R.G.S Bandara
 
පිලිකා cancer protection
පිලිකා cancer protectionපිලිකා cancer protection
පිලිකා cancer protectionR.R.G.S Bandara
 

More from R.R.G.S Bandara (6)

Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Legal system of sri lanaka
Legal system of sri lanakaLegal system of sri lanaka
Legal system of sri lanaka
 
General notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATESGeneral notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATES
 
Automo lesson3
Automo lesson3Automo lesson3
Automo lesson3
 
පිලිකා cancer protection
පිලිකා cancer protectionපිලිකා cancer protection
පිලිකා cancer protection
 
00 eng tech note1
00 eng tech note100 eng tech note1
00 eng tech note1
 

Recently uploaded

Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsSachinPawar510423
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 

Recently uploaded (20)

Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documents
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 

Prolongation cost calculation

  • 2. Once a Contractor has secured an extension of time and relief from liquidated damages, thoughts will quickly turn to recovery of the costs incurred due to the delayed completion date – i.e. “Prolongation Costs”.
  • 3. If you ask an Employer’s QS how such costs should be determined the answer is often an unequivocal statement that the rates and prices from the Preliminaries BOQ shall be divided by the original contract duration and the derived daily rate for preliminaries shall then be applied to the extended duration.
  • 4. The sharp witted Employer’s QS may even refine this logic with the caveat that the BOQ rates and prices should first be adjusted to remove fixed costs, mobilization and demobilization costs, overheads and profit. Whilst both answers are quite wrong, these approaches are often used in order to achieve result, despite the inaccurate answer. The problem is that neither approach attempts to address the underlying question of what costs / losses were actually incurred by the Contractor as a consequence of the delaying events for which the Employer was responsible.
  • 5. The answer to this question cannot be found in the BOQ, but can (and should) be found in a detailed analysis of the Contractor’s cost records The express wording of the contract will dictate which heads of claim are admissible, but in general terms an accurate understanding of Prolongation Cost entitlement can be derived by application of the following basic principles: -Identify the events that gave rise to the extension of time – as it is the cost / loss arising from these events that the Contractor is entitled to recover;
  • 6. -Identify the point in time that the delay occurred – a common mistake is to identify the costs that were incurred over the extended duration at the end of the contract period. This is incorrect. The delay may have occurred prior to full mobilization and thus the actual costs incurred at that time may be lower; -Identify the direct costs that follow from the compensable delay events – the Contractor is not entitled to costs arising from delay events for which it is responsible. Separation of the two can defeat arguments that the claim is global and includes elements of the Contractor’s own culpability;
  • 7. -Assess only time related costs and not one off capital costs – time related costs are those which necessarily arise as a consequence of additional time spent on the project and would typically include staff salaries; insurance, rents, utilities, bonds, accommodation, office services, car leases & running costs, etc. but would not include purchase costs of offices, photocopiers, vehicles etc.
  • 8. -Exclude task related costs – a common mistake is to include task related costs (e.g. labour, plant hire or scaffolding costs) that would have been incurred in any event. These costs may only have been incurred at a later point in time and are therefore not additional. Such costs would need to be separately recovered through a properly formulated disruption cost claim;
  • 9. -Exclude profit – the purpose of the claim is to put the Contractor back into the position it would have been, but for the delay. ‘Profit’ is not ‘cost’ and thus any claim for profit can only be by way of a ‘loss of opportunity’ claim – which may be expressly precluded by the wording of the contract and would in any case have to be proved, i.e. that opportunities did in fact present themselves and were refused because key resources could not be released from the delayed project;
  • 10. -Allow for off-site costs – costs incurred in the Contractor’s head office (and elsewhere) may be as a direct result of the project delay. The fact that these costs were incurred off site does not mean that the Contractor is not entitled to receive them; -If possible, avoid formulae for determining overheads (e.g. Hudson’s, Emden’s etc.) – unless you are a Contractor and you fully understand the basis of your ‘loss of opportunity’ claim and how to present it! By indentifying actual incurred overhead costs rather than rely on theory based formulae that commonly produce high assessments; -Interest / Finance Charges – remember that charging interest on a debt may be prohibited in your jurisdiction or by your contract. Most interest or finance claims suffer from a lack of facts and are commonly: unsupported, theoretical assessments of loss. However, a skilled claimant can often find ways to lend credibility to this type of claim.
  • 11. Calculation of Costs. Once the contractor is granted an extension of time with costs, the computation of the recoverable items must also be substantiated with properly maintained records and invoices. Normally, the contractor should prove actual loss from records. Only where this is not possible, and as an exception rather than the rule, will calculation be allowed by reference to formulae such as the Eichleay formula, and the Hudson or Emden formulae. The formula is applied to assess loss where certain things have been established proving that the contractor did actually suffer loss. The contractor must show that it would have secured work on another contractor and would have been recovering overheads from this other project, and that there was profit capable of being earned elsewhere and there was no change in the market thereafter affecting profitability of the work.
  • 12. It must also be established that the contractor was unable to deploy resources elsewhere and had no possibility of recovering the overheads from other sources, e.g., from an increased volume of work. Thus such formulae are likely only to be relevant and of value if the event causing the delay has the characteristic of a breach of contract.