SlideShare a Scribd company logo
1 of 34
Download to read offline
Saudi Aramco Project Development
Wastewater Treatment Facilities
Jeddah Refinery And Marine Area
Facilities Planning Dept.
December 2007
OBJECTIVE:
Provide an overview of the complexities of
developing a project scope for Upgrading the
Industrial and Sanitary Wastewater Treatment
Facilities at Jeddah Refinery attributed to:
• Difficult to treat industrial oily wastewater stream
requiring multiple studies
• Multiple changes in the future operations of the
Jeddah Refinery
PRESENTATION OUTLINE
• Background
• Initial Study – Conventional Biological Treatment
• Second Study – Physical Chemical Treatment
• 1st Revised Operating Scenario for Jeddah Refinery
• Third Study – Membrane Bio-Reactor
• 2nd Revised Operating Scenario for Jeddah Refinery
• Overall summary of the project development
BACKGROUND
General Information
• Environmental Master Plan (EMP) issued by Company
in 2001
• EMP indicates that upgrades required for Jeddah
Refinery Industrial Wastewater Treatment System
and Sanitary Sewage System
• Consultant contracted in 2002 to perform field
evaluation and tests and recommend upgrade
requirements
BACKGROUND (cont’d)
Location & Existing Facilities
• Jeddah Refinery:
– Located adjacent to the Islamic Port in Jeddah
– Commissioned in 1982
– Currently operating at 90,000 barrel crude oil refinery
producing gasoline, fuel oil, and asphalt
– Major process units include crude distillation, vacuum,
platformer unit, naphtha hydrotreating, fluid catalytic
cracker (FCC)
– Tank Farm for Crude and Product and Terminal
Facilities
– Provides feedstock/some utilities and treats
wastewater from adjacent Luberef Plant
BACKGROUND (cont’d)
Location & Facilities (cont’d)
• Existing Industrial Wastewater Treatment
Facilities, Jeddah Refinery
– Located adjacent to the refinery in the Marine Area
– Holding Basin for incoming wastewater flow conditions
– API Separators for removal of oil & grease and solids
– Media Filter for removal of total suspended solids (TSS)
– All equipment more than 25 years old
– Treats wastewater from the refinery, tank farm, & Luberef
– Design wastewater flow 2.66 million gpd (10,000 M3
/d)
• Existing Sanitary Wastewater System
– Sewage collected from buildings into holding tanks
– Sewage removed via vacuum trucks and sent to Saudi Aramco’s
Al-Rehab Community Center STP
– Approximate quantity of sewage generated: 12,000 gpd (45 M3
/d)
Jeddah Refinery & Marine Area
Industrial
WWTP
Marine Area
Jeddah
Refinery
Tank Farm
Area
Luberef
Red Sea
Lagoons
Industrial & Sanitary Wastewater Treatment
Existing Flow Scheme – Jeddah Refinery
Sand
Filtration
Refinery Tank Farm, and
Luberef Plant Wastewater,
Stormwater
To Effluent
Lagoons/
Oil to Slop Oil System
Sanitary
Wastewater
Septic
Tanks
Vacuum Tank Trucks –
To Al-Rehab STP
Holding
Basin
API
Separators
Industrial Wastewater Treatment
Sanitary Wastewater Handling
Oil &
Grease Removal
Suspended
Solids Removal
Solids
Red Sea
JRMA - Holding Basin
JRMA - API Separators
JRMA - Sand Filters
INITIAL STUDY (2002)
FINDINGS
• Major Deficiencies with JR Industrial
Wastewater Treatment and Sewage
System
– API Separators at end of useful life
– Separator solids difficult to remove
– Media Filters in constant state of repair and often
unavailable
– Removal of Organic/Inorganic contaminants not
possible
– No onsite sanitary waste treatment facility
INITIAL STUDY (2002)
FINDINGS
• PME Discharge Limits are not met
Chemical Constituent PME
Discharge
Limits
JR Industrial Wastewater
Discharge
Max Max Avg
pH, units 6 - 9 8.62 8.14
BOD5, mg/l 25 490
COD, mg/l
TOC
150
50
878
199
Phenol, mg/l 0.1 26 23
Oil & Grease, mg/l 8 57 39
Total Suspended Solids, mg/l 15 199 170
Ammonia, mg/l 1 77 69
Cyanide (T/F), mg/l 0.05 0.5/ 0.05 0.3/ 0.05
INITIAL STUDY (Cont’d)
FINDINGS
• Other Physical Characteristics of Wastewater
– Highly Variable Total Dissolved Solids, up to
16,000 ppm
– Extreme Variability of Wastewater Parameters
– High Temperatures 30 -50 o
C
– Highly Variable Flow Rate
INITIAL STUDY (Cont’d)
Treatment Alternatives
• Industrial Wastewater Treatment
– Conventional Biological Treatment
– Physical Chemical Treatment (Steam Stripping)
• Sanitary Wastewater Treatment
– Conventional Biological Treatment
INITIAL STUDY (Cont’d)
Recommended Industrial Wastewater Treatment Scheme –
Conventional Biological Treatment
Dissolved/
Air
Flotation
Activated
Sludge with
Nitrification
Refinery Tank Farm, and
Luberef Plant Wastewater,
Stormwater
To Effluent
Lagoons/
Red Sea
Oil to Slop
Oil System
Chiller
Methanol &
pH Control
Biosludge
Thickening &
DewateringDewatered Biosludge
to Disposal
Sanitary
Wastewater
API
Separators
Skim
Tanks
Sand Filters
Chlorination
Storm
Water
Basin
Primary Oil &
Grease Removal
Secondary Oil &
Grease Removal
Suspended
Solids Removal
Removal of Organic &
Inorganic Compounds;
pH Adjustment
INITIAL STUDY (Cont’d)
Issues with Recommended Biological Treatment
Advantages
• Most commonly used process for “normal”
industrial oily wastewater streams
• Can be also used to treat sanitary waste
Disadvantages
• Difficult to sustain biomass due to high swings in
wastewater concentrations, TDS, and temperature
• Requires complex operations (as currently
experienced at Rabigh Refinery)
• Not supported by EPD
SECOND STUDY (2003)
Background Information
• EPD – Identify Simpler Treatment Process
• R&DC – Recommended resins for treatment via
polymeric adsorption of contaminants
• Consultant – Contracted to perform bench testing &
field pilot tests
• Physical Chemical Treatment – Proposed scheme
developed
Second Study (Cont’d)
Recommended Physical Chemical Treatment – Resin Adsorption
Dissolved/
Air
Flotation
Refinery Tank Farm, and
Luberef Plant Wastewater,
Stormwater
To Effluent
Lagoons/
Red Sea
Oil to Slop
Oil System
GAC
Columns
To Sanitary
Wastewater
Treatment
Plant
Sand
Filters
Resin
Columns
Cartridge
Filters
Air
StripperChlorination
Steam
pH
Adjust
pH
Adjust
Storm
Water
Basin
API
Separators
Skim
Tanks
Primary Oil &
Grease Removal
Secondary Oil &
Grease Removal
Suspended
Solids Removal
Phenol & Organics
Removal
Ammonia Removal
Second Study (Cont’d)
Recommended Sanitary Wastewater Treatment Scheme – Membrane
Bio-Reactor (MBR)
New MBR
Treatment
Plant
To Effluent
Lagoons
Sanitary
Wastewater
Treated
Water
Existing Septic
Basins w/New
Pumps & Lines
Main
Collection
Sump*
Regenerant from
Industrial Wastewater
Plant
Irrigation
Sludge To
Landfill
*With Grit Chamber & Screens
Second Study (Cont’d)
Physical Chemical Treatment - Resin Adsorption
• Advantages
– Simple unit operations
– High tolerance to swings in effluent conditions
– Easy to restart after shutdown
• Disadvantages
– High steam requirements
– Frequent replacement of GAC (Regeneration possible)
– Requires separate sanitary wastewater treatment plant
1st Revised Operating Scenario for Jeddah Refinery (2004)
• New Rabigh Refinery/Petrochemical Complex – may affect future
operation of Jeddah Refinery
• Jeddah Refinery – partial or complete shutdown of process units;
study being performed by Facilities Planning Dept. (FPD)
• Industrial Wastewater Treatment Plant (IWTP) for Jeddah Refinery –
capacity & treatment scheme could vary with process units remaining
in operation
• Two - Phase Implementation of IWTP at Jeddah Refinery
• Phase 1 – install equipment for removal of oil & grease and total
dissolve solids from the industrial wastewater to meet PME regulations
• Phase 2 – based on FPD study results and management
recommendations, install remaining equipment for removal of all other
contaminants from the industrial wastewater and provide onsite
sanitary sewage to meet PME regulations
1st Revised Operating Scenario for Jeddah Refinery
• Phase 1 Industrial Wastewater Treatment Facilities
– Design Capacity: flexibility to allow for any changes in the
operation of Jeddah Refinery
– Project Proposal Engineering: commenced on August 2004
– Detailed Engineering: commenced on December 2005
– Construction: currently under
– Plant Start Up: July 2008
1st Revised Operating Scenario for Jeddah Refinery (Cont’d)
Phase 1 Industrial Wastewater Treatment Facilities
Walnut
Shell
Filters
Refinery Tank Farm,
and Luberef Plant
Wastewater,
Stormwater
Oil to Slop
Oil System
Storm
Water
Tank
API
Separator
Skim
Tanks
Primary Oil &
Grease Removal
Secondary Oil &
Grease Removal
and TSS
To Effluent
Lagoons/
Red Sea
1st Revised Operating Scenario for Jeddah Refinery
• FPD Study Results for Future Operations of
Jeddah Refinery Released in Early 2005
– Based on study recommendations and management decision
in May 2005, Jeddah Refinery process units to be shutdown
in 2010
– Jeddah Refinery Tank Farm (including marine area) and
Luberef to remain in operation
– Proceed with implementation of Phase 2 Wastewater
Treatment Facilities
Third Study (2005)
Phase II Industrial Wastewater Treatment Facilities
• Shutdown of Jeddah Refinery
– expect lower concentrations of phenols and ammonia in
wastewater
– cooler wastewater temperatures
– wastewater flowrate reduced by 33%
• Membrane Bio-Reactor (MBR)
– EPD recommends the evaluating the use of an MBR in lieu
of physical chemical treatment for industrial wastewater
and sanitary sewage at Jeddah Refinery
– Consultant contracted to perform bench testing and
conducts pilot plant evaluation
– Test Results indicate MBR viable & economical process
Third Study
Phase 2 Industrial Wastewater Treatment Facilities (Base)
Walnut
Shell
Filters
Refinery Tank
Farm, and Luberef
Plant Wastewater,
Stormwater
Oil to Slop
Oil System
Storm
Water
Tank
API
Separators
Skim
Tanks
To Effluent
Lagoons/
Red Sea Equalization
Tanks
MBR
Units
Granulated
Activated
Carbon
Units
From Sanitary
Waste Collection
System
To Sludge Pit/
Sludge Beds
Phase 1 Equipment
Third Study
Phase 2 Industrial Wastewater Treatment Facilities (Alternate)
Walnut
Shell
Filters
Refinery Tank
Farm, and Luberef
Plant Wastewater,
Stormwater
Oil to Slop
Oil System
Storm
Water
Tank
API
Separators
Skim
Tanks
From Sanitary
Waste Collection
System
Phase 1
Equipment
To Effluent
Lagoons/
Red Sea Equalization
Tanks
Powder
Activated
Carbon
MBR
Units
To Sludge Pit/
Sludge Beds
2nd Revised Operating Scenario for Jeddah Refinery
(2007)
• Future Operation of Jeddah Refinery
– In lieu of shutting down the Jeddah Refinery process units, the JR is
to continue to run as a topping refinery until 2014 for the
production of fuel oil and asphalt only
– Jeddah Refinery Tank Farm (including marine area) and Luberef to
remain in operation
• Impact on Phase 1 & 2 Wastewater Treatment
Facilities
– Phase 1 Facilities: none, except install 2nd API Separator in Phase 2
– Phase 2 Facilities: re-size equipment to handle 33% more flow &
provide wastewater cooling
 Project Proposal: commenced on September 2007
 Plant Start-Up: March 2011
Currently Proposed Facilities
Phase 1 & 2 Industrial & Sanitary Wastewater Treatment Facilities
Walnut
Shell
Filters
Refinery Tank
Farm, and Luberef
Plant Wastewater,
Stormwater
Oil to Slop
Oil System
Storm
Water
Tank
API
Separators
Skim
Tanks
From Sanitary
Waste Collection
System
Chiller
Equalization
Tanks
Powder
Activated
Carbon
MBR
Units
To Sludge Pit/
Sludge Beds
To Effluent
Lagoons/
Red Sea
Design Capacity: ~ 2MM gpd (7900 M3/d)
PROJECT DEVELOPMENT SUMMARY
JEDDAH REFINERY WASTEWATER TREATMENT FACILITIES
• Pre-2001: Company conducts survey of all major plants
and facilities for environmental compliance
• 2001: Company issues Environmental Master Plan
• 2002: Initial Study for Jeddah Refinery with
conventional biological treatment recommended
• 2003: EPD recommends physical chemical treatment
to facilitate operations (2nd Study)
• 2004: Future continued operations of Jeddah Refinery
under study
• 2004: Implementation of JR WWTP in two phases;
Phase I treatment for oil & grease and TSS only;
Phase I engineering commences
• 2005: Management decision to discontinue operation of
process refining units at Jeddah Refinery
(1st Operational Change)
PROJECT DEVELOPMENT SUMMARY (Cont’d)
JEDDAH REFINERY WASTEWATER TREATMENT FACILITIES
• 2005: EPD recommends MBR for treatment of industrial
wastewater & sanitary sewage (3rd Study)
• 2006: Evaluation of MBR treatment indicates viability
• 2007: In lieu of shutting down the Jeddah Refinery
process units, the JR is to continue to run as topping
refinery until 2014 (2nd Operational Change)
• 2007: Commence with engineering of Phase 2 wastewater
treatment facilities
• 2008: 3rd Operational Change?????
• 2008: Startup of Phase 1
• 2011: Startup of Phase 2
Thank you
John yee   saudi aramco project development

More Related Content

What's hot

Wastewater Treatment Refineries
Wastewater Treatment Refineries Wastewater Treatment Refineries
Wastewater Treatment Refineries Ali Safaa97
 
Industrial wastewater treatment
Industrial wastewater treatment Industrial wastewater treatment
Industrial wastewater treatment Ali Safaa97
 
Water and Air Effluents Treatment Technologies
Water and Air Effluents Treatment Technologies Water and Air Effluents Treatment Technologies
Water and Air Effluents Treatment Technologies Ajjay Kumar Gupta
 
Sludge thickening and stabilization processes
Sludge thickening and stabilization processes  Sludge thickening and stabilization processes
Sludge thickening and stabilization processes Natthu Shrirame
 
Primary and secondary wastewater treatment..
Primary and secondary wastewater treatment..Primary and secondary wastewater treatment..
Primary and secondary wastewater treatment..snehalmenon92
 
Dissolve air flotation technology to treat highly polluted wastewater
Dissolve air flotation technology to treat highly polluted wastewaterDissolve air flotation technology to treat highly polluted wastewater
Dissolve air flotation technology to treat highly polluted wastewaterIndia Water Portal
 
Activated Sludge Process
Activated Sludge ProcessActivated Sludge Process
Activated Sludge ProcessNiaz Memon
 
Waste Water Treatment Process Presentation
Waste Water Treatment Process PresentationWaste Water Treatment Process Presentation
Waste Water Treatment Process PresentationAshish Kakadia
 
Effluent treatment plant - design, operation and analysis of waste water trea...
Effluent treatment plant - design, operation and analysis of waste water trea...Effluent treatment plant - design, operation and analysis of waste water trea...
Effluent treatment plant - design, operation and analysis of waste water trea...Shubham Hydrosys Pvt. Ltd
 
Waste water treatment.pptx [autosaved]
Waste water treatment.pptx [autosaved]Waste water treatment.pptx [autosaved]
Waste water treatment.pptx [autosaved]Ashika Raveendran
 
Wastewater treatment Plant of Interloop Industry, Lahore
Wastewater treatment Plant of Interloop Industry, LahoreWastewater treatment Plant of Interloop Industry, Lahore
Wastewater treatment Plant of Interloop Industry, LahoreUmay Habiba
 
UPFLOW ANAEROBIC SLUDGE BLANKET REACTOR
UPFLOW ANAEROBIC SLUDGE BLANKET REACTORUPFLOW ANAEROBIC SLUDGE BLANKET REACTOR
UPFLOW ANAEROBIC SLUDGE BLANKET REACTORMd Aftab Saifi
 
Effluent Treatment Plant-Project-02
Effluent Treatment Plant-Project-02Effluent Treatment Plant-Project-02
Effluent Treatment Plant-Project-02Nilusha Rajashilpa
 
Report on Effluent Treatment Plant (ETP) Operation and Maintenance of Interst...
Report on Effluent Treatment Plant (ETP) Operation and Maintenance of Interst...Report on Effluent Treatment Plant (ETP) Operation and Maintenance of Interst...
Report on Effluent Treatment Plant (ETP) Operation and Maintenance of Interst...Kowshick Sen
 

What's hot (20)

Wastewater Treatment Refineries
Wastewater Treatment Refineries Wastewater Treatment Refineries
Wastewater Treatment Refineries
 
Industrial wastewater treatment
Industrial wastewater treatment Industrial wastewater treatment
Industrial wastewater treatment
 
Etp presentation
Etp presentationEtp presentation
Etp presentation
 
Water and Air Effluents Treatment Technologies
Water and Air Effluents Treatment Technologies Water and Air Effluents Treatment Technologies
Water and Air Effluents Treatment Technologies
 
Etp Final Report
Etp Final ReportEtp Final Report
Etp Final Report
 
Sludge thickening and stabilization processes
Sludge thickening and stabilization processes  Sludge thickening and stabilization processes
Sludge thickening and stabilization processes
 
L 30 fertilizer industry
L 30 fertilizer industryL 30 fertilizer industry
L 30 fertilizer industry
 
Primary and secondary wastewater treatment..
Primary and secondary wastewater treatment..Primary and secondary wastewater treatment..
Primary and secondary wastewater treatment..
 
Dissolve air flotation technology to treat highly polluted wastewater
Dissolve air flotation technology to treat highly polluted wastewaterDissolve air flotation technology to treat highly polluted wastewater
Dissolve air flotation technology to treat highly polluted wastewater
 
Activated Sludge Process
Activated Sludge ProcessActivated Sludge Process
Activated Sludge Process
 
Waste Water Treatment Process Presentation
Waste Water Treatment Process PresentationWaste Water Treatment Process Presentation
Waste Water Treatment Process Presentation
 
Sewage treatment
Sewage treatmentSewage treatment
Sewage treatment
 
water treatment plant
water treatment plantwater treatment plant
water treatment plant
 
Effluent treatment plant - design, operation and analysis of waste water trea...
Effluent treatment plant - design, operation and analysis of waste water trea...Effluent treatment plant - design, operation and analysis of waste water trea...
Effluent treatment plant - design, operation and analysis of waste water trea...
 
Waste water treatment.pptx [autosaved]
Waste water treatment.pptx [autosaved]Waste water treatment.pptx [autosaved]
Waste water treatment.pptx [autosaved]
 
Thermax
ThermaxThermax
Thermax
 
Wastewater treatment Plant of Interloop Industry, Lahore
Wastewater treatment Plant of Interloop Industry, LahoreWastewater treatment Plant of Interloop Industry, Lahore
Wastewater treatment Plant of Interloop Industry, Lahore
 
UPFLOW ANAEROBIC SLUDGE BLANKET REACTOR
UPFLOW ANAEROBIC SLUDGE BLANKET REACTORUPFLOW ANAEROBIC SLUDGE BLANKET REACTOR
UPFLOW ANAEROBIC SLUDGE BLANKET REACTOR
 
Effluent Treatment Plant-Project-02
Effluent Treatment Plant-Project-02Effluent Treatment Plant-Project-02
Effluent Treatment Plant-Project-02
 
Report on Effluent Treatment Plant (ETP) Operation and Maintenance of Interst...
Report on Effluent Treatment Plant (ETP) Operation and Maintenance of Interst...Report on Effluent Treatment Plant (ETP) Operation and Maintenance of Interst...
Report on Effluent Treatment Plant (ETP) Operation and Maintenance of Interst...
 

Viewers also liked

Removal of heavy metals from wastewater by carbon nanotubes
Removal of heavy metals from wastewater by carbon nanotubesRemoval of heavy metals from wastewater by carbon nanotubes
Removal of heavy metals from wastewater by carbon nanotubesAshish Gadhave
 
kamal cert 3 in process plant operations
kamal cert 3 in process plant operationskamal cert 3 in process plant operations
kamal cert 3 in process plant operationsKamal Singh
 
Natalie Lewes Short Course Process Plant Operations Cranfield University 2001
Natalie Lewes Short Course Process Plant Operations Cranfield University 2001Natalie Lewes Short Course Process Plant Operations Cranfield University 2001
Natalie Lewes Short Course Process Plant Operations Cranfield University 2001Natalie Lewes
 
Ingerem india - operating manual presentation
Ingerem india -  operating manual presentation Ingerem india -  operating manual presentation
Ingerem india - operating manual presentation Vidhya Biju
 
Chlor alkali plant Control room operator & Plant Operations
Chlor alkali plant Control room operator & Plant OperationsChlor alkali plant Control room operator & Plant Operations
Chlor alkali plant Control room operator & Plant OperationsSURESHKUMAR MUTHURAMALINGAM
 
Saudi Aramco IPO - A Reality of Mythical Proportions
Saudi Aramco IPO - A Reality of Mythical ProportionsSaudi Aramco IPO - A Reality of Mythical Proportions
Saudi Aramco IPO - A Reality of Mythical ProportionsAranca
 
BIIE Final Evaluation Report 22nd January 2015
BIIE Final Evaluation Report 22nd January 2015BIIE Final Evaluation Report 22nd January 2015
BIIE Final Evaluation Report 22nd January 2015Jitendra Sinha
 
Major Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperMajor Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperIan Heptinstall
 
Ground breaking ceremony of nghi son refinery project on 24 oct 2013
Ground breaking ceremony of nghi son refinery project on 24 oct 2013Ground breaking ceremony of nghi son refinery project on 24 oct 2013
Ground breaking ceremony of nghi son refinery project on 24 oct 2013Pham Hai
 
Final Evaluation Report Samudram
Final Evaluation Report SamudramFinal Evaluation Report Samudram
Final Evaluation Report SamudramJitendra Sinha
 
Saudi National Water Company Vision & Projects
Saudi National Water Company Vision & ProjectsSaudi National Water Company Vision & Projects
Saudi National Water Company Vision & ProjectsIbrahim Al-Hudhaif
 

Viewers also liked (14)

Saudi Aramco presentation
Saudi Aramco presentationSaudi Aramco presentation
Saudi Aramco presentation
 
Removal of heavy metals from wastewater by carbon nanotubes
Removal of heavy metals from wastewater by carbon nanotubesRemoval of heavy metals from wastewater by carbon nanotubes
Removal of heavy metals from wastewater by carbon nanotubes
 
kamal cert 3 in process plant operations
kamal cert 3 in process plant operationskamal cert 3 in process plant operations
kamal cert 3 in process plant operations
 
Natalie Lewes Short Course Process Plant Operations Cranfield University 2001
Natalie Lewes Short Course Process Plant Operations Cranfield University 2001Natalie Lewes Short Course Process Plant Operations Cranfield University 2001
Natalie Lewes Short Course Process Plant Operations Cranfield University 2001
 
Ingerem india - operating manual presentation
Ingerem india -  operating manual presentation Ingerem india -  operating manual presentation
Ingerem india - operating manual presentation
 
Chlor alkali plant Control room operator & Plant Operations
Chlor alkali plant Control room operator & Plant OperationsChlor alkali plant Control room operator & Plant Operations
Chlor alkali plant Control room operator & Plant Operations
 
Saudi Aramco IPO - A Reality of Mythical Proportions
Saudi Aramco IPO - A Reality of Mythical ProportionsSaudi Aramco IPO - A Reality of Mythical Proportions
Saudi Aramco IPO - A Reality of Mythical Proportions
 
BIIE Final Evaluation Report 22nd January 2015
BIIE Final Evaluation Report 22nd January 2015BIIE Final Evaluation Report 22nd January 2015
BIIE Final Evaluation Report 22nd January 2015
 
BP WRMP Project
BP WRMP ProjectBP WRMP Project
BP WRMP Project
 
Major Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperMajor Projects - Faster Better Cheaper
Major Projects - Faster Better Cheaper
 
Opportunity Arabia 2014: Joep Straathof
Opportunity Arabia 2014: Joep StraathofOpportunity Arabia 2014: Joep Straathof
Opportunity Arabia 2014: Joep Straathof
 
Ground breaking ceremony of nghi son refinery project on 24 oct 2013
Ground breaking ceremony of nghi son refinery project on 24 oct 2013Ground breaking ceremony of nghi son refinery project on 24 oct 2013
Ground breaking ceremony of nghi son refinery project on 24 oct 2013
 
Final Evaluation Report Samudram
Final Evaluation Report SamudramFinal Evaluation Report Samudram
Final Evaluation Report Samudram
 
Saudi National Water Company Vision & Projects
Saudi National Water Company Vision & ProjectsSaudi National Water Company Vision & Projects
Saudi National Water Company Vision & Projects
 

Similar to John yee saudi aramco project development

UlSD Hydrotreater Challenges Overcome to Improve on Stream Factor - MEPEC 2013
UlSD Hydrotreater Challenges Overcome to Improve on Stream Factor - MEPEC 2013UlSD Hydrotreater Challenges Overcome to Improve on Stream Factor - MEPEC 2013
UlSD Hydrotreater Challenges Overcome to Improve on Stream Factor - MEPEC 2013Alpesh Gurjar
 
Industrial wastewater reuse_Anil Sharma_2013
Industrial wastewater reuse_Anil Sharma_2013Industrial wastewater reuse_Anil Sharma_2013
Industrial wastewater reuse_Anil Sharma_2013India Water Portal
 
Presentation_for_IICHE_students_for__orientation_training_on_Environment__1_....
Presentation_for_IICHE_students_for__orientation_training_on_Environment__1_....Presentation_for_IICHE_students_for__orientation_training_on_Environment__1_....
Presentation_for_IICHE_students_for__orientation_training_on_Environment__1_....nehasharma58143
 
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?Society of Petroleum Engineers
 
Produced water overview ppt, Oct 2011, M Rashid
Produced water overview ppt, Oct 2011, M RashidProduced water overview ppt, Oct 2011, M Rashid
Produced water overview ppt, Oct 2011, M RashidMahbubur Rashid
 
Converde colombia
Converde   colombiaConverde   colombia
Converde colombiaconverde
 
The project of oil refinery
The project of oil refineryThe project of oil refinery
The project of oil refinerysergio014
 
SCIMEE is a rare-earth magnet-based wastewater treatment company equipped wit...
SCIMEE is a rare-earth magnet-based wastewater treatment company equipped wit...SCIMEE is a rare-earth magnet-based wastewater treatment company equipped wit...
SCIMEE is a rare-earth magnet-based wastewater treatment company equipped wit...dun yang
 
Green Recycling of Used Lead Acid Batteries
Green Recycling of Used Lead Acid BatteriesGreen Recycling of Used Lead Acid Batteries
Green Recycling of Used Lead Acid Batteriesrsmahwar
 
Phytorid for bio-remediation of lakes
Phytorid for bio-remediation of lakesPhytorid for bio-remediation of lakes
Phytorid for bio-remediation of lakesbiomeshubha
 
Converde colombia
Converde   colombiaConverde   colombia
Converde colombiaconverde
 
Bioblend presentation tampa
Bioblend presentation tampaBioblend presentation tampa
Bioblend presentation tamparacr2s2
 
Bioblend presentation tampa
Bioblend presentation tampaBioblend presentation tampa
Bioblend presentation tampaconverde
 
REDUCED DISPOSAL COST OF PRODUCED AND FLOWBACK WATER
REDUCED DISPOSAL COST OF PRODUCED AND FLOWBACK WATERREDUCED DISPOSAL COST OF PRODUCED AND FLOWBACK WATER
REDUCED DISPOSAL COST OF PRODUCED AND FLOWBACK WATERiQHub
 
Alternative Opportunities
Alternative Opportunities Alternative Opportunities
Alternative Opportunities T. MAJID KHAN
 
p28-29 JebelAli reprint
p28-29 JebelAli reprintp28-29 JebelAli reprint
p28-29 JebelAli reprintT. MAJID KHAN
 
Oil Sands Water Management Initiative Notes
Oil Sands Water Management Initiative NotesOil Sands Water Management Initiative Notes
Oil Sands Water Management Initiative Noteswilliampatricklaw
 

Similar to John yee saudi aramco project development (20)

UlSD Hydrotreater Challenges Overcome to Improve on Stream Factor - MEPEC 2013
UlSD Hydrotreater Challenges Overcome to Improve on Stream Factor - MEPEC 2013UlSD Hydrotreater Challenges Overcome to Improve on Stream Factor - MEPEC 2013
UlSD Hydrotreater Challenges Overcome to Improve on Stream Factor - MEPEC 2013
 
Industrial wastewater reuse_Anil Sharma_2013
Industrial wastewater reuse_Anil Sharma_2013Industrial wastewater reuse_Anil Sharma_2013
Industrial wastewater reuse_Anil Sharma_2013
 
Presentation_for_IICHE_students_for__orientation_training_on_Environment__1_....
Presentation_for_IICHE_students_for__orientation_training_on_Environment__1_....Presentation_for_IICHE_students_for__orientation_training_on_Environment__1_....
Presentation_for_IICHE_students_for__orientation_training_on_Environment__1_....
 
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
Your Field is Getting Older: Is your Process Engineering Still Cost Effective?
 
Produced water overview ppt, Oct 2011, M Rashid
Produced water overview ppt, Oct 2011, M RashidProduced water overview ppt, Oct 2011, M Rashid
Produced water overview ppt, Oct 2011, M Rashid
 
Converde colombia
Converde   colombiaConverde   colombia
Converde colombia
 
The project of oil refinery
The project of oil refineryThe project of oil refinery
The project of oil refinery
 
SCIMEE is a rare-earth magnet-based wastewater treatment company equipped wit...
SCIMEE is a rare-earth magnet-based wastewater treatment company equipped wit...SCIMEE is a rare-earth magnet-based wastewater treatment company equipped wit...
SCIMEE is a rare-earth magnet-based wastewater treatment company equipped wit...
 
Green Recycling of Used Lead Acid Batteries
Green Recycling of Used Lead Acid BatteriesGreen Recycling of Used Lead Acid Batteries
Green Recycling of Used Lead Acid Batteries
 
Phytorid for bio-remediation of lakes
Phytorid for bio-remediation of lakesPhytorid for bio-remediation of lakes
Phytorid for bio-remediation of lakes
 
Converde colombia
Converde   colombiaConverde   colombia
Converde colombia
 
Bioblend presentation tampa
Bioblend presentation tampaBioblend presentation tampa
Bioblend presentation tampa
 
Bioblend presentation tampa
Bioblend presentation tampaBioblend presentation tampa
Bioblend presentation tampa
 
REDUCED DISPOSAL COST OF PRODUCED AND FLOWBACK WATER
REDUCED DISPOSAL COST OF PRODUCED AND FLOWBACK WATERREDUCED DISPOSAL COST OF PRODUCED AND FLOWBACK WATER
REDUCED DISPOSAL COST OF PRODUCED AND FLOWBACK WATER
 
Alternative Opportunities
Alternative Opportunities Alternative Opportunities
Alternative Opportunities
 
p28-29 JebelAli reprint
p28-29 JebelAli reprintp28-29 JebelAli reprint
p28-29 JebelAli reprint
 
Csu venture pitch_tong
Csu venture pitch_tongCsu venture pitch_tong
Csu venture pitch_tong
 
Overview on capture technologies
Overview on capture technologiesOverview on capture technologies
Overview on capture technologies
 
B3 0 ricardo_fuel prep
B3 0 ricardo_fuel prepB3 0 ricardo_fuel prep
B3 0 ricardo_fuel prep
 
Oil Sands Water Management Initiative Notes
Oil Sands Water Management Initiative NotesOil Sands Water Management Initiative Notes
Oil Sands Water Management Initiative Notes
 

More from Robson Pessoa

Project standards and_specifications_waste_water_sewer_system_rev01
Project standards and_specifications_waste_water_sewer_system_rev01Project standards and_specifications_waste_water_sewer_system_rev01
Project standards and_specifications_waste_water_sewer_system_rev01Robson Pessoa
 
Epa water treatment_manual_preliminary
Epa water treatment_manual_preliminaryEpa water treatment_manual_preliminary
Epa water treatment_manual_preliminaryRobson Pessoa
 
Edital 6.2016 dou_de_16.06.2016_-_retificacao_3 (1)
Edital 6.2016 dou_de_16.06.2016_-_retificacao_3 (1)Edital 6.2016 dou_de_16.06.2016_-_retificacao_3 (1)
Edital 6.2016 dou_de_16.06.2016_-_retificacao_3 (1)Robson Pessoa
 
Edital 12.2016 dou_de_17.06.2016_-_resultado_processo_seletivo_-_retificacao_1
Edital 12.2016 dou_de_17.06.2016_-_resultado_processo_seletivo_-_retificacao_1Edital 12.2016 dou_de_17.06.2016_-_resultado_processo_seletivo_-_retificacao_1
Edital 12.2016 dou_de_17.06.2016_-_resultado_processo_seletivo_-_retificacao_1Robson Pessoa
 
Edital 12.2016 dou_de_14.06.2016_-_resultado_processo_seletivo
Edital 12.2016 dou_de_14.06.2016_-_resultado_processo_seletivoEdital 12.2016 dou_de_14.06.2016_-_resultado_processo_seletivo
Edital 12.2016 dou_de_14.06.2016_-_resultado_processo_seletivoRobson Pessoa
 

More from Robson Pessoa (6)

project systems
project systemsproject systems
project systems
 
Project standards and_specifications_waste_water_sewer_system_rev01
Project standards and_specifications_waste_water_sewer_system_rev01Project standards and_specifications_waste_water_sewer_system_rev01
Project standards and_specifications_waste_water_sewer_system_rev01
 
Epa water treatment_manual_preliminary
Epa water treatment_manual_preliminaryEpa water treatment_manual_preliminary
Epa water treatment_manual_preliminary
 
Edital 6.2016 dou_de_16.06.2016_-_retificacao_3 (1)
Edital 6.2016 dou_de_16.06.2016_-_retificacao_3 (1)Edital 6.2016 dou_de_16.06.2016_-_retificacao_3 (1)
Edital 6.2016 dou_de_16.06.2016_-_retificacao_3 (1)
 
Edital 12.2016 dou_de_17.06.2016_-_resultado_processo_seletivo_-_retificacao_1
Edital 12.2016 dou_de_17.06.2016_-_resultado_processo_seletivo_-_retificacao_1Edital 12.2016 dou_de_17.06.2016_-_resultado_processo_seletivo_-_retificacao_1
Edital 12.2016 dou_de_17.06.2016_-_resultado_processo_seletivo_-_retificacao_1
 
Edital 12.2016 dou_de_14.06.2016_-_resultado_processo_seletivo
Edital 12.2016 dou_de_14.06.2016_-_resultado_processo_seletivoEdital 12.2016 dou_de_14.06.2016_-_resultado_processo_seletivo
Edital 12.2016 dou_de_14.06.2016_-_resultado_processo_seletivo
 

Recently uploaded

Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyAlfredo García Lavilla
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfPrecisely
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clashcharlottematthew16
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsRizwan Syed
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenHervé Boutemy
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Scott Keck-Warren
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningLars Bell
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
Search Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfSearch Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfRankYa
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 
Advanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionAdvanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionDilum Bandara
 

Recently uploaded (20)

Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easy
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clash
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL Certs
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache Maven
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine Tuning
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
Search Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfSearch Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdf
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 
Advanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionAdvanced Computer Architecture – An Introduction
Advanced Computer Architecture – An Introduction
 

John yee saudi aramco project development

  • 1. Saudi Aramco Project Development Wastewater Treatment Facilities Jeddah Refinery And Marine Area Facilities Planning Dept. December 2007
  • 2. OBJECTIVE: Provide an overview of the complexities of developing a project scope for Upgrading the Industrial and Sanitary Wastewater Treatment Facilities at Jeddah Refinery attributed to: • Difficult to treat industrial oily wastewater stream requiring multiple studies • Multiple changes in the future operations of the Jeddah Refinery
  • 3. PRESENTATION OUTLINE • Background • Initial Study – Conventional Biological Treatment • Second Study – Physical Chemical Treatment • 1st Revised Operating Scenario for Jeddah Refinery • Third Study – Membrane Bio-Reactor • 2nd Revised Operating Scenario for Jeddah Refinery • Overall summary of the project development
  • 4. BACKGROUND General Information • Environmental Master Plan (EMP) issued by Company in 2001 • EMP indicates that upgrades required for Jeddah Refinery Industrial Wastewater Treatment System and Sanitary Sewage System • Consultant contracted in 2002 to perform field evaluation and tests and recommend upgrade requirements
  • 5. BACKGROUND (cont’d) Location & Existing Facilities • Jeddah Refinery: – Located adjacent to the Islamic Port in Jeddah – Commissioned in 1982 – Currently operating at 90,000 barrel crude oil refinery producing gasoline, fuel oil, and asphalt – Major process units include crude distillation, vacuum, platformer unit, naphtha hydrotreating, fluid catalytic cracker (FCC) – Tank Farm for Crude and Product and Terminal Facilities – Provides feedstock/some utilities and treats wastewater from adjacent Luberef Plant
  • 6. BACKGROUND (cont’d) Location & Facilities (cont’d) • Existing Industrial Wastewater Treatment Facilities, Jeddah Refinery – Located adjacent to the refinery in the Marine Area – Holding Basin for incoming wastewater flow conditions – API Separators for removal of oil & grease and solids – Media Filter for removal of total suspended solids (TSS) – All equipment more than 25 years old – Treats wastewater from the refinery, tank farm, & Luberef – Design wastewater flow 2.66 million gpd (10,000 M3 /d) • Existing Sanitary Wastewater System – Sewage collected from buildings into holding tanks – Sewage removed via vacuum trucks and sent to Saudi Aramco’s Al-Rehab Community Center STP – Approximate quantity of sewage generated: 12,000 gpd (45 M3 /d)
  • 7. Jeddah Refinery & Marine Area Industrial WWTP Marine Area Jeddah Refinery Tank Farm Area Luberef Red Sea Lagoons
  • 8. Industrial & Sanitary Wastewater Treatment Existing Flow Scheme – Jeddah Refinery Sand Filtration Refinery Tank Farm, and Luberef Plant Wastewater, Stormwater To Effluent Lagoons/ Oil to Slop Oil System Sanitary Wastewater Septic Tanks Vacuum Tank Trucks – To Al-Rehab STP Holding Basin API Separators Industrial Wastewater Treatment Sanitary Wastewater Handling Oil & Grease Removal Suspended Solids Removal Solids Red Sea
  • 10. JRMA - API Separators
  • 11. JRMA - Sand Filters
  • 12. INITIAL STUDY (2002) FINDINGS • Major Deficiencies with JR Industrial Wastewater Treatment and Sewage System – API Separators at end of useful life – Separator solids difficult to remove – Media Filters in constant state of repair and often unavailable – Removal of Organic/Inorganic contaminants not possible – No onsite sanitary waste treatment facility
  • 13. INITIAL STUDY (2002) FINDINGS • PME Discharge Limits are not met Chemical Constituent PME Discharge Limits JR Industrial Wastewater Discharge Max Max Avg pH, units 6 - 9 8.62 8.14 BOD5, mg/l 25 490 COD, mg/l TOC 150 50 878 199 Phenol, mg/l 0.1 26 23 Oil & Grease, mg/l 8 57 39 Total Suspended Solids, mg/l 15 199 170 Ammonia, mg/l 1 77 69 Cyanide (T/F), mg/l 0.05 0.5/ 0.05 0.3/ 0.05
  • 14. INITIAL STUDY (Cont’d) FINDINGS • Other Physical Characteristics of Wastewater – Highly Variable Total Dissolved Solids, up to 16,000 ppm – Extreme Variability of Wastewater Parameters – High Temperatures 30 -50 o C – Highly Variable Flow Rate
  • 15. INITIAL STUDY (Cont’d) Treatment Alternatives • Industrial Wastewater Treatment – Conventional Biological Treatment – Physical Chemical Treatment (Steam Stripping) • Sanitary Wastewater Treatment – Conventional Biological Treatment
  • 16. INITIAL STUDY (Cont’d) Recommended Industrial Wastewater Treatment Scheme – Conventional Biological Treatment Dissolved/ Air Flotation Activated Sludge with Nitrification Refinery Tank Farm, and Luberef Plant Wastewater, Stormwater To Effluent Lagoons/ Red Sea Oil to Slop Oil System Chiller Methanol & pH Control Biosludge Thickening & DewateringDewatered Biosludge to Disposal Sanitary Wastewater API Separators Skim Tanks Sand Filters Chlorination Storm Water Basin Primary Oil & Grease Removal Secondary Oil & Grease Removal Suspended Solids Removal Removal of Organic & Inorganic Compounds; pH Adjustment
  • 17. INITIAL STUDY (Cont’d) Issues with Recommended Biological Treatment Advantages • Most commonly used process for “normal” industrial oily wastewater streams • Can be also used to treat sanitary waste Disadvantages • Difficult to sustain biomass due to high swings in wastewater concentrations, TDS, and temperature • Requires complex operations (as currently experienced at Rabigh Refinery) • Not supported by EPD
  • 18. SECOND STUDY (2003) Background Information • EPD – Identify Simpler Treatment Process • R&DC – Recommended resins for treatment via polymeric adsorption of contaminants • Consultant – Contracted to perform bench testing & field pilot tests • Physical Chemical Treatment – Proposed scheme developed
  • 19. Second Study (Cont’d) Recommended Physical Chemical Treatment – Resin Adsorption Dissolved/ Air Flotation Refinery Tank Farm, and Luberef Plant Wastewater, Stormwater To Effluent Lagoons/ Red Sea Oil to Slop Oil System GAC Columns To Sanitary Wastewater Treatment Plant Sand Filters Resin Columns Cartridge Filters Air StripperChlorination Steam pH Adjust pH Adjust Storm Water Basin API Separators Skim Tanks Primary Oil & Grease Removal Secondary Oil & Grease Removal Suspended Solids Removal Phenol & Organics Removal Ammonia Removal
  • 20. Second Study (Cont’d) Recommended Sanitary Wastewater Treatment Scheme – Membrane Bio-Reactor (MBR) New MBR Treatment Plant To Effluent Lagoons Sanitary Wastewater Treated Water Existing Septic Basins w/New Pumps & Lines Main Collection Sump* Regenerant from Industrial Wastewater Plant Irrigation Sludge To Landfill *With Grit Chamber & Screens
  • 21. Second Study (Cont’d) Physical Chemical Treatment - Resin Adsorption • Advantages – Simple unit operations – High tolerance to swings in effluent conditions – Easy to restart after shutdown • Disadvantages – High steam requirements – Frequent replacement of GAC (Regeneration possible) – Requires separate sanitary wastewater treatment plant
  • 22. 1st Revised Operating Scenario for Jeddah Refinery (2004) • New Rabigh Refinery/Petrochemical Complex – may affect future operation of Jeddah Refinery • Jeddah Refinery – partial or complete shutdown of process units; study being performed by Facilities Planning Dept. (FPD) • Industrial Wastewater Treatment Plant (IWTP) for Jeddah Refinery – capacity & treatment scheme could vary with process units remaining in operation • Two - Phase Implementation of IWTP at Jeddah Refinery • Phase 1 – install equipment for removal of oil & grease and total dissolve solids from the industrial wastewater to meet PME regulations • Phase 2 – based on FPD study results and management recommendations, install remaining equipment for removal of all other contaminants from the industrial wastewater and provide onsite sanitary sewage to meet PME regulations
  • 23. 1st Revised Operating Scenario for Jeddah Refinery • Phase 1 Industrial Wastewater Treatment Facilities – Design Capacity: flexibility to allow for any changes in the operation of Jeddah Refinery – Project Proposal Engineering: commenced on August 2004 – Detailed Engineering: commenced on December 2005 – Construction: currently under – Plant Start Up: July 2008
  • 24. 1st Revised Operating Scenario for Jeddah Refinery (Cont’d) Phase 1 Industrial Wastewater Treatment Facilities Walnut Shell Filters Refinery Tank Farm, and Luberef Plant Wastewater, Stormwater Oil to Slop Oil System Storm Water Tank API Separator Skim Tanks Primary Oil & Grease Removal Secondary Oil & Grease Removal and TSS To Effluent Lagoons/ Red Sea
  • 25. 1st Revised Operating Scenario for Jeddah Refinery • FPD Study Results for Future Operations of Jeddah Refinery Released in Early 2005 – Based on study recommendations and management decision in May 2005, Jeddah Refinery process units to be shutdown in 2010 – Jeddah Refinery Tank Farm (including marine area) and Luberef to remain in operation – Proceed with implementation of Phase 2 Wastewater Treatment Facilities
  • 26. Third Study (2005) Phase II Industrial Wastewater Treatment Facilities • Shutdown of Jeddah Refinery – expect lower concentrations of phenols and ammonia in wastewater – cooler wastewater temperatures – wastewater flowrate reduced by 33% • Membrane Bio-Reactor (MBR) – EPD recommends the evaluating the use of an MBR in lieu of physical chemical treatment for industrial wastewater and sanitary sewage at Jeddah Refinery – Consultant contracted to perform bench testing and conducts pilot plant evaluation – Test Results indicate MBR viable & economical process
  • 27. Third Study Phase 2 Industrial Wastewater Treatment Facilities (Base) Walnut Shell Filters Refinery Tank Farm, and Luberef Plant Wastewater, Stormwater Oil to Slop Oil System Storm Water Tank API Separators Skim Tanks To Effluent Lagoons/ Red Sea Equalization Tanks MBR Units Granulated Activated Carbon Units From Sanitary Waste Collection System To Sludge Pit/ Sludge Beds Phase 1 Equipment
  • 28. Third Study Phase 2 Industrial Wastewater Treatment Facilities (Alternate) Walnut Shell Filters Refinery Tank Farm, and Luberef Plant Wastewater, Stormwater Oil to Slop Oil System Storm Water Tank API Separators Skim Tanks From Sanitary Waste Collection System Phase 1 Equipment To Effluent Lagoons/ Red Sea Equalization Tanks Powder Activated Carbon MBR Units To Sludge Pit/ Sludge Beds
  • 29. 2nd Revised Operating Scenario for Jeddah Refinery (2007) • Future Operation of Jeddah Refinery – In lieu of shutting down the Jeddah Refinery process units, the JR is to continue to run as a topping refinery until 2014 for the production of fuel oil and asphalt only – Jeddah Refinery Tank Farm (including marine area) and Luberef to remain in operation • Impact on Phase 1 & 2 Wastewater Treatment Facilities – Phase 1 Facilities: none, except install 2nd API Separator in Phase 2 – Phase 2 Facilities: re-size equipment to handle 33% more flow & provide wastewater cooling  Project Proposal: commenced on September 2007  Plant Start-Up: March 2011
  • 30. Currently Proposed Facilities Phase 1 & 2 Industrial & Sanitary Wastewater Treatment Facilities Walnut Shell Filters Refinery Tank Farm, and Luberef Plant Wastewater, Stormwater Oil to Slop Oil System Storm Water Tank API Separators Skim Tanks From Sanitary Waste Collection System Chiller Equalization Tanks Powder Activated Carbon MBR Units To Sludge Pit/ Sludge Beds To Effluent Lagoons/ Red Sea Design Capacity: ~ 2MM gpd (7900 M3/d)
  • 31. PROJECT DEVELOPMENT SUMMARY JEDDAH REFINERY WASTEWATER TREATMENT FACILITIES • Pre-2001: Company conducts survey of all major plants and facilities for environmental compliance • 2001: Company issues Environmental Master Plan • 2002: Initial Study for Jeddah Refinery with conventional biological treatment recommended • 2003: EPD recommends physical chemical treatment to facilitate operations (2nd Study) • 2004: Future continued operations of Jeddah Refinery under study • 2004: Implementation of JR WWTP in two phases; Phase I treatment for oil & grease and TSS only; Phase I engineering commences • 2005: Management decision to discontinue operation of process refining units at Jeddah Refinery (1st Operational Change)
  • 32. PROJECT DEVELOPMENT SUMMARY (Cont’d) JEDDAH REFINERY WASTEWATER TREATMENT FACILITIES • 2005: EPD recommends MBR for treatment of industrial wastewater & sanitary sewage (3rd Study) • 2006: Evaluation of MBR treatment indicates viability • 2007: In lieu of shutting down the Jeddah Refinery process units, the JR is to continue to run as topping refinery until 2014 (2nd Operational Change) • 2007: Commence with engineering of Phase 2 wastewater treatment facilities • 2008: 3rd Operational Change????? • 2008: Startup of Phase 1 • 2011: Startup of Phase 2