SlideShare a Scribd company logo
1 of 138
Internal Controls at the Construction Site
           7th Jan, 2012, Hotel Inder Residency, Ellisbridge, Ahmedabad

From          To                                       Topic
10.00 am    10.25 am                           Registration and Breakfast
10.25 am    10.30 am                                     MOC
                                Overview and Relevance of Internal Controls at the
                                  Construction Site and Role of a Project Manager
                                       Statutory Compliances required at the
10.30 am    12.00 am        Construction Site under Labour Laws / VAT Laws / Other local
                                                    requirements
                             Control Points for Various Equipments like Transit Miller /
                                Batching Plant / Concrete Pump / Crane / Excavator

                              Understanding of Material & Labour Procurement Related
12.15 pm    1.30 pm                  Controls required at the Construction Site
01.30 pm    02.00 am                                     Lunch
                             HR Related Controls - Labour Colony / Mess / Attendance /
                                               Vehicle Management

                                 Stores Related Controls - Material Issue / Receipt /
02.00 pm    03.30 pm             Reconciliation Methods / Physical Verification Plan
03.30 pm    03.45 pm                                   Tea Break
                                Basics of MIS Preparation for various Departments -
                                    Engineering / Stores / Accounts / HR / Safety
                              Role of Site Accounts and Co-ordination with Head Office
03.45 pm    05.15 pm


                               info@consultconstruction.com
                               www.consultconstruction.com
Overview and Relevance of Internal Controls at
   the Construction Site and Role of a Project
                   Manager

Tendering
 Budgeting
 Site Mobilisation
 Role of a Project Manager
 Role of a Billing Engineer
 Material Reconciliation
 Project Completion
 Release of Retention Money



                   info@consultconstruction.com
                   www.consultconstruction.com
[Tendering]




info@consultconstruction.com
www.consultconstruction.com
Lets see how to approach the job
Of :-
•     Study of Tender Terms
•     Planning – Budgets, Funds, Project Timeline through PERT,
      CPM
•     Lining up various functions
      •   Engineering
      •   Stores
      •   HR
      •   Accounts
      •   Safety and Quality



                info@consultconstruction.com
                www.consultconstruction.com
Understanding the conditions of the tender

S.   Details sought for                                           Catch
N
1    Work order Value?                                            Qty Variation not more than 25-30%.
                                                                  Incentive / Penalty (0.5-5%)Clause.
1a   Physical visit of the work locations                         Material Rates / Terrain for Equipments
                                                                  / Labour colony area / Distance from
                                                                  city.
2    FIM - RMC / Cement / Steel?                                  Wastage Norms,         Debit Rates,
                                                                  Location of Client Stores (From Loading /
                                                                  Unloading perspective)
3    Work completion period                                       Subject to drawings, front, resources
4    Facilities from the Client - Labour colony, Land, Power & Free or Chargeable. Single / Multiple point
     Water supply.                                             at site / At Labour Colony

     Mobilisation Advance and Time Limit                       % given and recovery rate

5    Adhoc Payment against uncertified bills (75%) and Strict committment from client
     status of remaining bill.
6    Check whether any prescribed format for client bill? Compliance with local laws
7    Whether the job is new or left over one?                 Investigation required if it’s a left
                                                              over job – Impact of Margins
8    Safety / Quality Norms           info@consultconstruction.com on Time and Money
                                                              Impact
                                                              Formatting system of FQP
                                      www.consultconstruction.com
Cont...
S.N Details sought for                              Catch
9    What are the requirements with each RA bill? Third Party Physical Certification
                                                  Reconciliation Statement of FIM
10   What are the rates of principal items (like Higher Margin in items to be executed
     Excavation, RMC supply, Shuttering etc.)     first
                                                  Apart from FIM, what are other items are
                                                  kept in client scope (e.g. False Ceiling,
                                                  Roofing, Aluminium Doors and Windows)
11   What deductions shall be made by client from Only those agreed as per WO
     RA bill
12   Service tax / VAT / WCT extra or inclusive?  Exemptions – Paper Work
13   Whether running plant expansion or If in running plant – Scarce area /
     construction of new plant building?          Pollution – Impact on Labour.
15   Internal Logistics                           Location - Porta Cabin / Client office /
                                                  Labour Colony / Batching Plant / Store
16   Bank Guarantee                               Amt / Performance / Time Validity
17                                                Always cry in front of the client, don’t
                                                  give any inputs about high margin items
18   Statutory Compliance                         Insurance / PF / CAR - Who’s scope?
So proper Site Investigation Reports needs to be prepared at Tender Stage

                             info@consultconstruction.com
                             www.consultconstruction.com
You have received a tender from the
Client / consultant M/s XYZ for making
a 500 MW Thermal Power Plant in
                Gujarat.




            info@consultconstruction.com
            www.consultconstruction.com
[Budgeting]




info@consultconstruction.com
www.consultconstruction.com
• Lets now come back to Planning




              info@consultconstruction.com
              www.consultconstruction.com
info@consultconstruction.com
www.consultconstruction.com
• Cost Oriented Planning –
  Convincing the EIC to prepare the Budgets is the biggest task. Because
  the forces are so dynamic, actual scenario is expected to be different
  from the work orders, hence he is not in a position to do so.

   Most of the times he would argue that because of delay in submission
   of drawings by the client, planning is not very easy.

   But to meet the Project Deadline / it is in the best interests of the client
   to break the work order quantities into monthly quantities.

   Further an overall cap is required to be kept on the total quantities to
   be consumed for the project. Monthly requirements can then be
   prepared on the basis of monthly budgets.


                           info@consultconstruction.com
                           www.consultconstruction.com
Congrats!

                      You have got a
                        work order
                      from M/s XYZ
    Cement & Steel
                      in the state of
     shall be FIM
                         Gujarat.


 You have to
mobilise 500                  Value of the
labourers in                     job is
20 Days from                   Rs.100cr
   today.


           Time deadline is
             15 Months


       info@consultconstruction.com
       www.consultconstruction.com
• Manual for Compliance Verification          –
  Whenever a new site is about to begin:-




               info@consultconstruction.com
               www.consultconstruction.com
Budgeting
• Lets see a sample budget …




            info@consultconstruction.com
            www.consultconstruction.com
Different types of contracts

  – Item rate

  – Lumpsum contract

  – Cost-plus contract

  – Turnkey contract – engineering, inspections, erection, electrical.




                         info@consultconstruction.com
                         www.consultconstruction.com
[Mobilisation and Role of
       Engg Dept]




       info@consultconstruction.com
       www.consultconstruction.com
Mobilisation Checklist
•   Statutory registration numbers / Good Local consultants
•   Resource Mobilisation
     – Equipments – JCB & Loader, Batching plant capacity, Miller, Crane, etc.
     – Vehicles – Staff Bus, Sumo, Utility, Trailer, Tractor & Dumper, Bike etc.
     – IT – Computers/Printer/Scanner/Copier/Internet/Telecom Network
     – Functional Heads – PM / Store / HR / Accounts
     – Office Stationery – Reports / Registers / Blank Slips
     – From client – Power / FIM / Drawings / Work Front
•   Staff Accomodation / Mess / Guest House
•   Onsite office set up
•   Lining up the labour
•   Logistics – Movement to site from various locations
•   Local Survey – Materials and Services

                             info@consultconstruction.com
                             www.consultconstruction.com
Labour mobilisation Issues

• Special Points to be kept in mind for labour
  mobilisation
  – Areas where labour is available
  – Initial cost of mobilisation
  – Stay Arrangements
  – Facilities offered by competitors
  – Watch for the sudden movement of labour


                info@consultconstruction.com
                www.consultconstruction.com
• The site is now mobilised and you
  have to commence the work.




           info@consultconstruction.com
           www.consultconstruction.com
Role of Project Manager
– Work Planning Daily / Weekly / Monthly:
   When we plan for work – we need to keep in mind client priority,   availability of
   resources, availability of drawing & front, weather, Funds etc.
– Pre planning for FIM / Own Material:
   Pre planning (system and procedure) is required for FIM and Own material so as
   to make it available in time.
– Complete responsibility to ensure compliance of the functions by all the Dept.:
   Engineering, HR & Admin, Stores, Accounts
– Sub Contractor Work Order:
   Sub Contractor work order should be prepared on time with their acceptance.

– Timely submission of bills with due verification from QSD at HO, if any . If delay
  reasons need to be submitted to HO.

– Subcontractor bills are prepared in due time and are paid after pre-audit at HO.



                           info@consultconstruction.com
                           www.consultconstruction.com
Role of Project Manager – cont…
   – Understanding of Site Performance both in terms of actual execution
     and profitability and submitting regular MIS to head office.

   – Ensuring proper back up in case if any employee leaves the
     organization.

   – Weekly meetings with the Core team and ensuring due preparation of
     minutes for mailing the same to Head office.

   – Checking all the records fortnightly viz. stores inflow, outflow, vehicle
     logbooks, and HR records.

   – To focus on all areas where chances of cost overrun exist by ensuring
     regular monitoring.

   – Maintaining employee morale under all situations.


                         info@consultconstruction.com
                         www.consultconstruction.com
Reconciliation – FIM & Principal Material
•   Standard Consumption norms to be defined for every item in the WO.
    For e.g. – For 1 CUM of M20 - concrete production –
    Cement – 140 Kg, Sand – 875 Kgs, Agg – 1100 Kgs

•   Physical verification of Steel, Sand and Aggregate on the same day on which reco is
    prepared.
•   Material scattered at various locations
•   Consumption for unbilled extra items to be excluded.
•   Stock records to be updated regularly.

•   Shuttering Repetitions.

    If material consumption levels are found in excess of standards appropriate action
    needs to be taken for further control and identification of sub-contractor
    responsible for the same to enforce timely recovery.
                              info@consultconstruction.com
                              www.consultconstruction.com
Materials Usage Standard
• Theoretical Qty * (1 + Normal Wastage Norms)
  – Qty is derived from design and drawings
  – Normal Wastage Norms also change from Project to
    Project depending on nature of work, method of
    application
  – However Wastage from following is not a normal
    wastage
     •   Using Non-Standard Material
     •   Excess Purchase
     •   Wastage in Transportation
     •   Improper Storage

                      info@consultconstruction.com
                      www.consultconstruction.com
Billing Engineer
A. Client & Sub Contractor billing and Certification:
– Same Billing period for both client & sub contractor
     • Match the Quantities
     • Facilitate preparation of MIS
     • Identification of Extra Items

– DPR should be generated.

– RA bill preparation on Time as any delay
   • Affects Fund management
   • MIS




                       info@consultconstruction.com
                       www.consultconstruction.com
Sub Contractor Work Order:
Sub Contractor work orders should be prepared:
   - Item code and language should as per client work order
   - Project Manager and Project commercial head / Project Director
     approval signs or mail required.

For example:
Item     As per       Item description                              UOM Rate
Code
1234     Client       Providing reinforcement including cutting, MT        4500
                      bending, binding, fixing in position including the
                      cost of channels, bars (Binding Wire is in your
                      scope)

FIM or Raw Material shall be provided to contractor for work by Company:
1234-A Contractor Reinforcement Cutting                               MT    700
1234-B Contractor Reinforcement Bending                               MT    800
1234-C   Contractor Reinforcement Fixing                              MT   1200
         Contractor Total Rate of item code-1234 is ---->             MT   2700


                               info@consultconstruction.com
                               www.consultconstruction.com
• Engineering MIS




           info@consultconstruction.com
           www.consultconstruction.com
[Project Completion]




    info@consultconstruction.com
    www.consultconstruction.com
Project Completion
• Checklist for Project Completion
   –   Final bill preparation and certification
   –   FIM and Raw Material Reconciliation with bill and balance qty.
   –   Fulfillment of client work completion procedure
   –   Receivable & Liability status & Clearance
   –   Statutory compliances
   –   Demobilization
   –   Delayed in project completion
   –   Work completion certificate




                         info@consultconstruction.com
                         www.consultconstruction.com
Project Completion – cont….

Final bill preparation and certification:
 • Cumulative Executed Quantity.
 • All pending extra item claims should be included, if pending.
 • Necessary follow up for W.O amendment if Actual Qty > WO Qty.
 • Release of Qty on Hold for want of various reasons.
 • Fight for the incentive clause.
 • If any company asset is given on rental / hire basis to other party as
   per instruction from client, the same should be claimed in final bill .
 • If resources like equipment / manpower have remained ideal due to
   non availability of front, it should be claimed in the final bill.
 • NOC shall have to be obtained from various departments of the client



                         info@consultconstruction.com
                         www.consultconstruction.com
Project Completion – cont….
FIM and Raw Material Reconciliation with bill and balance qty.:

Formula:
• Total Material Inward
• Less: Material Returned / Transferred
• Less: Standard Consumption
• = Balance Quantity at Site / Store

•   In case this quantity is not available at site / store, there are following possibilities:
     – Excess consumption as compared to standard
     – Theft / Pilferage during the project

•   In case of excess consumption, some portion can be recovered from measurement contractor if
    not recovered till date.
•   Proper justifications are required from project manager and appropriate action should be
    taken in case of abnormal difference between actual balance and standard balance
•   Balance FIM material started to returning and take its documents with receiving sign and
    stamp from client.

                                      info@consultconstruction.com
                                      www.consultconstruction.com
Project Completion – cont….

 Fulfillment of client work completion procedure:
    In case of project completion client have checklist for same so you have to ask same from client
    and compile each point.


 Receivable & Liability Status & Clearance:
    Get status of project liability with break up of nature of creditor and special remark for local
    creditors.
     – Follow up for payment receivable from client after bill certification
     – Clear local liabilities to avoid any demobilization harassment from them.


 Statutory compliance:
    Follow up and get pending WCT & TDS receivable certificates from client.
     – Give all necessary details for VAT return filing to local sales tax consultant and other
         details, if any required for audit.
     – Get any pending forms like C & F from the department, also reconcile with the forms
         issued till date.
     – Clear o/s local pending liabilities like Road tax, Entry Tax, Employee Professional Tax etc.


                                 info@consultconstruction.com
                                 www.consultconstruction.com
Reasons for Delay in preparation of Final RA Bill
S. N.   Points                                                     Corrective Action

1       Non updation of FIM data with stores.                      Physical verification of FIM with stores
                                                                   records
2       Reconciliation of FIM                                      Required with each RA Bill
3       Work order Amendment                                       Little foresightedness
                                                                   Strong Followup
4       Change in Project Manager / Billing Engg.                  Documentation-JMR/BBS/Stores
                                                                   Good Back up at HO
                                                                   Handing over Checklist
5       Proper compilation of Hard and soft copies of all the      Data Control and Regular Audit
        Running Bills
6       Insistence to satisfy requirements of Labour Inspector –   Clarity in Work Order Terms
        If you are under EPC
7       Quality compliance after defect liability                  You should argue that it is client responsibility

8       Idling Claims depending on locations like Orissa /         Record / Emails to client on regular basis
        Kerela - Local problems
9       Direct Payments by the client                              Documentary Evidence

                                         info@consultconstruction.com
                                         www.consultconstruction.com
Project Completion – cont….

 Work completion certificate:

 •     Don’t forget to collect the work completion certificate from the client



 Demobilization:

 •     Dehire all types of equipment and machinery.
 •     Make proper plan for shifting of own material to other sites / Central Stores.
 •     Proper plan to shift staff.
 •     Dehire idle camp / mess and do not forget to recover the rent deposit or set off deposit against
       rent.
 •     Check, get and release Bank Guarantee from client after defect liability period is over




     Planning - Lalu

                                     info@consultconstruction.com
                                     www.consultconstruction.com
Release of Retention Money
• Checklist compliance
  –   Certification of Final bill
  –   Completion of work upto Defect liability period
  –   No local liability
  –   Site and area clearance
  –   Return of all FIM

  – Premature Release Against Bank Gaurantee Till Defect
    Liability


                     info@consultconstruction.com
                     www.consultconstruction.com
Commercial Procurement
i) Goods and ii) Services.




            info@consultconstruction.com
            www.consultconstruction.com
Normally in a manufacturing set up we divide the material as :-
a. Repetitive Items
     Raw Materials
     Stores
b. Non – Repetitive Items
     Capital Goods
     Major Repairs


   Primary purpose of classification is to Control:-
   - Quality - Cost - Timely Supply

   But how do we classify in the construction sector ?

                     info@consultconstruction.com
                     www.consultconstruction.com
The most comonly used classification is ABC Analysis.

But prerequisite is that the project should have a standardized bill of materials
listing the physical quantities, unit rate and total cost for each item.

1. Identify the material required for the Project
2. Determine Usage Value by multiplying the Qty required and its Unit rate.
3. Calculate the percentage usage value with respect to the total material
   cost for the project.
4. Arrange the Items in descending order of usage value
5. Give Red Colour till 70% and thereafter Green Colour till 90%.
6. Mark A class for Red Coloured Items / B Class for Green Colour and C Class
   for the balance.

Lets see a small excel sheet on this.


                         info@consultconstruction.com
                         www.consultconstruction.com
Use of ABC to Develop Policy Guidelines
Policy              “A”                 “B”                 “C”
Consideration
Degree of Control   Strict              Moderate            Loose
Forecast Accuracy   Accurate            Approximate         Rough
Authority of        Senior Level        Middle Level        At Site
Ordering
Purchases
Suppliers to be     Maximum             3 to 5 Reliable     2 to 3 Local
contacted                                                   suppliers
Safety Stock        Low                 Moderate            Adequate
Order Frequency     When Required       EOQ                 Bulk
Follow up           Maximum             Moderate            When Neccesary
Monitoring          Weekly              Monthly             May not be
Material                                                    required
Movement
MIS Reports         Weekly              Monthly             Random
                             info@consultconstruction.com
                             www.consultconstruction.com
Inventory Planning
• The construction material Inventory Plan
  aims at evolving materials stock-holding
  levels to meet project execution plan, with
  minimum investment on inventory.

• In typical project from Inventory point of
  view , we may classify the materials as
  follows:-
                info@consultconstruction.com
                www.consultconstruction.com
• Take the case of stocking of cement at the site :-

   –   Site Requirement – 500 Bags / Month for 12 Months
   –   Order Cost – Rs. 500 per order
   –   Carrying Cost – 10% of unit rate
   –   Transport Capacity – 100 Bags
   –   Lead Time – 5 Days
   –   Safety Stock – 100 Bags
   –   Material Life – 2 Months
   –   Unit Rate - Rs. 250 per bag


                      info@consultconstruction.com
                      www.consultconstruction.com
• EOQ –
  1 / Unit Rate *
  {Square Root of (2*Order Cost*Unit
  Rate*Site Requirement/Inventory Carrying
  Cost)}

 1/250 *   {Square root of (2*500*250*6000/0.1)}
 = 500 Bags



                 info@consultconstruction.com
                 www.consultconstruction.com
• Reorder Level =
  – Minimum Stock + (Lead Time * Daily Usage)
  – 100 + (5 * 20)
  – 200 Bags




                info@consultconstruction.com
                www.consultconstruction.com
Commercial Procurement
i) Goods cont…
  Goods:

   Define a Purchase Policy
      Purchases to be sourced by Head office.
      Purchases to be sourced locally with approval from Head office.
      Purchases to be sourced locally with the approval from Project Manager.

   Material required for Project:
      Project Manager to calculate total project material requirement through
       Bill of Quantity (BOQ).
      This would be categorized as FIM , Raw / Principle Material,
       Consumable / Hardware / Tools Material, Capital goods - Plant /
       Machinery / Equipment
      Monthly Requirement

                         info@consultconstruction.com
                         www.consultconstruction.com
Commercial Procurement
i) Goods cont…

 Placement of Order (PO): - Purchase order being the last document of
  procurement process, so it is necessary to take care before placing the order.
 Certain details which need to be mentioned
    Serially numbered
    Time & Place of Delivery
    Material Quality Description and specifications
    UOM
    Manufacturing date should be latest and not more than two months in
      case of certain items like Conplast / Admixture (To get maximum time of
      its utilization)




                            info@consultconstruction.com
                            www.consultconstruction.com
Commercial Procurement
i) Goods cont…

 Materials Indents:
    Authorized person should be allowed to raise an indent. The status
     about present level of stock should also be given.

 Market Survey / Enquiry / Quotation:
    Relevant journals, yellow pages, market directories etc.
    Company can ask quotation / price list with detailed terms and
     conditions with its validity from various vendors.
    Purchase department can take right decision after comparison and
     analysis of rate, quality, terms & conditions with price escalation
     terms and service condition


                         info@consultconstruction.com
                         www.consultconstruction.com
Stores Related Controls - Material Issue /
Receipt / Reconciliation Methods / Physical
              Verification Plan
           At a Construction Site




                info@consultconstruction.com
                www.consultconstruction.com
Store Team with Experience
• Store manpower depends on size of project, volume of
  material and stock movement and logistics.

• For a small site following if the ideal team
          – Store Incharge 1 = Master Degree / Specialization of store course and
                                 5 years work Experience
          – Store Assistant 2 = B. Com / 12th passed and 2years work Experience
                                 (Material Chaser)
          – Data Entry 1       = Bachelor / Certified Computer Course degree and
                                 2 years work Experience
          – Helpers 5           = Material loading & Un loading, Cleaning &
                        maintenance

            Computer literate with basic knowledge of
            identification of item, UOM & inward / outward
            procedures

                          info@consultconstruction.com
                          www.consultconstruction.com
Well Defined work Area
• Store personnel at Site should not be used
  for other works like
  – Sourcing of Vendor
  – Market survey
  – Creditor payment
  – Any other site functions like HR / Admin
    activity / Cash Mgmt / Taking measurements


                info@consultconstruction.com
                www.consultconstruction.com
Store Cycle




              info@consultconstruction.com
              www.consultconstruction.com
Stores Premises
• Stores Premises–
  –   GI Sheets / PCC Structure properly covered
  –   Door and Window for Lights & Ventilation
  –   House keeping (cleanliness)
  –   Fire extinguisher
  –   Rack for stacking of material
  –   Weight machine (Capacity least 100kg)
  –   Power connection
  –   Computer system with Printer & UPS
  –   Security guards at various points of store locations
      across the site
                    info@consultconstruction.com
                    www.consultconstruction.com
Setup of Stores
• It is suitable for proper control and supervision that stores
  should be near to
   •   Batching plant,
   •   Steel Yard,
   •   Contractor office
   •   Client store for best logistics


• Store Location should have adequate space to facilitate
  material storage and physical verification.

• Also open space near stores is required to park
  Equipments and Vehicles (JCB, TM, Tractor, etc.)

                           info@consultconstruction.com
                           www.consultconstruction.com
Stacking & Labeling
• Stacking of Material: -
  - Material not to be kept directly on ground (1ft above surface) - Rain
  - Liquid Items should be tightly covered in order to avoid wastage
   - Cement / Wooden Items need to be covered by Tarpoline for safety
  against rains
  - Arrangement on the basis of frequency of usage and in order of
  priority
  - Single item to be put at single place instead of multiple locations
  - Easily countable (Proper policy for Bulk Items)
• Safety to be ensured:-
  - Heavy material on surface / lower height & light weighted material in
  rack


• Label should be affixed on rack on each items with Material code
  (Additionally item description would be preferable)
                           info@consultconstruction.com
                           www.consultconstruction.com
Inventory Level & Local Procurement

• Inventory minimum and maximum level
  should be defined as per monthly Budget
  quantity, mainly for A Class Items.

• Store not to procure the material under normal
  cases .

• All local procurement department after
  approval from HO and as per defined policy.

                  info@consultconstruction.com
                  www.consultconstruction.com
Relationship with supplier

• Mgmt to ensure and check from time to time the
  relationship of store personnel with supplier –

      – If Frequent visits to supplier premises
      – Material Inwards to be checked by Site Engineer on
        Surprise basis
      – Material Receipt in day time
      – Quantity should not be left blank in supplier challan



                      info@consultconstruction.com
Non-Shrink            www.consultconstruction.com
Security Agency / Guard
• Stores should be backed by security personnel
   – Deployment of Guards as per requirement with proper
      uniform, stick, whistle & torch at store in two shifts.
   – Duty register / Card duly signed by store Incharge
   – Incident register (In case of theft)
   – Surprised visit should be carried out by HR incharge, specially
      during night
   – Surprised visit report required with monthly bill of external
      agency.




                       info@consultconstruction.com
                       www.consultconstruction.com
Material Inward
• I) FIM Material Inward–
   A) Steel :
   – Challan should have our indent number / date / quantity with
     weight slip.
   – Weight should be carried out at the time of material unloading.
   – Qty should always be mentioned as per dia and as per no.s and it
     should be kept dia wise in steel yard. Dia wise steel record and no.s
     measurement will also help in cross verification of weight as per
     defined ISI standard
   – Dia wise record will facilitate FIM reco
   – Client should inform about the dispatch of FIM in advance




                         info@consultconstruction.com
                         www.consultconstruction.com
Material Inward                                 Continue..
 B) Cement :   (FIM Material)

 – Inward should be on weight and challan also have quantity in
   numbers of bag.
 – Weight should be carried out at the time of unloading (Powder
   form).
 – This net weight quantity should be mentioned as received with
   mention of damaged bags in challan and the same should be
   conveyed to client / supplier store.
 – Also in case of rain/fog, if material is received without proper
   cover, the fact needs to be mentioned on the challan
 – Store should verify no. of cement bags and ensure proper stacking
   at time of unloading itself.
 – Control on Empty bags is required


                      info@consultconstruction.com
                      www.consultconstruction.com
Material Inward                                 Continue..
 C) RMC (Ready Mix Concrete):           (FIM Material)


 – Client may give RMC instead of cement
 – Physical received and challan / slip quantity should be the same
 – Any difference needs to be communicated to the client on a regular
   basis. This is the case when client has outsourced RMC production.
 – Further monthly reconciliation should be done to resolve the
   dispute, if any.
 – Special Precautions required if multiple agencies are working at the
   client location.




                      info@consultconstruction.com
                      www.consultconstruction.com
Material Inward                   Continue..
• II) Procured Material Inward:

  Sand & Aggregate / Boulder & Ruble:
  – Sand & Aggregate preferably to be purchased on CFT basis. Also
    advisable in rainy season.
  – CFT basis material should be measured every time by three point of
    vehicle and considered average area and this quantity mentioned
    as received in challan
  – Boulder / Rubble on MT basis due to voids
  – These items should be delivered by supplier with proper intimation
  – Materials would be delivered during day time
  – Location of Weigh Bridge
  – In rainy season stock would be store of Sand & Aggregate for any
    short fall and avoid to pay more cost
  – Royalty slips
                      info@consultconstruction.com
                      www.consultconstruction.com
Material Inward                                Continue..
• II) Procured Material Inward:

   – Binding Wire should always be weighed at the time of inward and
     its thickness should be matched as per order. No. of Bundles should
     also be mentioned in the challan.

   – Conplast / Admixture - Inwards with manufacturing & expiry date
     and number of drum and the same should be visible on each drum

   – Wooden material:
       • Plywood = This should be as per specification given in PO like
         thickness, weight per sheet, regular or water proof, size, qty. in
         numbers and sq.ft.
       • Batten = Batten size should be as per specification of PO like thickness
         & length, Abnormal damage & short length pieces should not be
         allowed and the qty should be mentioned in CFT in challan


                          info@consultconstruction.com
                          www.consultconstruction.com
Material Inward                              Continue..

• III) Returnable Material Entry:
• If any material, equipment or items are to be sent out, client
  procedure and documents should be followed with all records
  to avoid any delay in project completion.
   – Material entry gate pass
   – Inward stamp with date and time and sign of authorized
   – Material description with quantity etc..


• Any improper inward could prove costly for the company in
  future.



                         info@consultconstruction.com
                         www.consultconstruction.com
Material Inward                            Continue..

IV) Loan Transaction:
• This happens, where more than one contractor work in the same
  client premises.
   – This type of transactions should be done by site Project Manager in
     emergency case only and with approval from his higher authority.
   – This is returnable basis so the same should not be outstanding for
     more than specified days and should not be a routine practise.
   – Quantitative document should be generated and kept in record




                       info@consultconstruction.com
                       www.consultconstruction.com
Material Inward                                    Continue..

• V) Basic documents at the time of Material Inward :

   – Documents - Challan / Packing list / Inter-site Transfer Memo / Excise
     Gate pass / LR / Weight slip / Royalty Challan / Test certificates / PO
     copy or PO references / Tax Invoice / Statutory forms (If any).
   – Authorized sign required if overwriting available.
   – Mention of Short quantity & unmatched specification
   – Material inward stamp & Entry in material inward register / system &
     Unique inward number on documents
   – No material shall be dumped without pre intimation to store and
     presence of store person.
   – Rejection Policy


                         info@consultconstruction.com
                         www.consultconstruction.com
Material Outward
•   Codification of materials
            • Divide the materials into Capital Goods / Construction Materials / Consumables
              and Tools.
            • Codes as per class of material.
•   Material Issue Slip
     – Duplicate
     – Authorised from Site Engg.
     – Basis of Computer Entry
     – Watch on Missing serial numbers
•   Steel, Sand, Agg., etc consumption entry should atleast be passed as per RA Bills certified
    quantity.
•   In case of emergency /break down of batching plant if RMC procured from other sources,
    then FIM Cement can be issued to supplier and rate should be excluding cement.
•   Returnable register to be kept separately. Material required in same form from receiver
•   Computer System to have Alternate UOM provision – E.g. Wooden Items, Sand, Aggregate.
•   Free And Chargeable Materials List with stores.


                                info@consultconstruction.com
                                www.consultconstruction.com
Non Moving material
• Store should not allow those material which are not required
or
• excess quantity compare to required at site

• Disadvantage of non movement items –
   – Staff engagment
   – Cost of logistics & Inventory carrying cost
   – Space usage of store
   – Problem to Handling / Take care




                        info@consultconstruction.com
                        www.consultconstruction.com
Site visit by Store personal
• Store personal should visit site on every day
  for following purposes:
    – Idle material
    – Damage & Scattered material
    – Ensure that no material is lying in mud or in
      excavated holes, before back filing (Especially
      scaffolding material like coupler, pipes &
      shuttering plate etc..)

Lemon
                   info@consultconstruction.com
                   www.consultconstruction.com
Physical Stock Verification
                                                                   • Compliance to
    • A Class                                                        routine audit
      verification every                                             queries.
      quarter and                                                  • System report
    • other categories                                               should not contain
      every six months.                                              any negative items.
                                                                   • System report
                                            System Print             should be clear like
                               A-B-C                                 Bills received but
                                            after Updated
                           Identification                            goods not received
                                             Data entry.



                                             Ensure that
                                               material
                           Physical count    movement is
                            challenges        restricted
                                            before taking
    • Scaffolding /                         physical stock.
      Shuttering –                                            • Proper Stacking
      Rough Idea                                                and labelling
    • Steel, Sand, Agg –
      Expert estimate
    • Multiple
      locations
                                info@consultconstruction.com
                                www.consultconstruction.com
Control over Fuel Consumption
Following points need to be taken care for Equipments - JCB, Miller, and
Crane / Vehicles:-

•   Store should have resources like –
      – Fuel pipe, Filter & pump to fill fuel from one to another can,
      – Two standard size Barrels of 200Ltrs capacity,
      – Fuel small Can of 1ltr, 5Lts, 10Ltrs
      – Scale to measure balance stock of fuel (Rod)
•   Lock and key - Fuel tank
•   All vehicle and equipment Meters should be in working condition.
•   MRN containing authorisation from Project Manager & HR Incharge for fuel issue
    with vehicle & equipment number.
•   Physical meter reading should be verified and mentioned in log sheet at time of fuel
    issue.
•   If vehicle permanently work at single location, name of location is compulsory.
•   Vehicle Report - MIS.
•   Tracking fuel given on chargeable / Free issue basis.
                              info@consultconstruction.com
                              www.consultconstruction.com
BTN
• Whether such system exists at the client
  place




               info@consultconstruction.com
               www.consultconstruction.com
Other Areas -
                       Scrap Yard


                          Items in Scrap yard should be
                            properly segregated as per
                         nature and length to enable re-
                                       use.




                           Frequent Disposal of scrap
                                Items required.




                           Distribution of Scrap wood
                                 amongst labour




                info@consultconstruction.com
                www.consultconstruction.com
MIS
• MIS report, its format and period should be defined.

Following reports required fom store:
   –   Material Movement for the period
   –   Intersite Material Movement
   –    Fuel Transaction report with party wise
   –   Safety material movement
   –   Chargeable Material / Debit Note
   –   RMC Production & Principle items consumption
   –   Physical Stock
   –   Non Moving Material

                     info@consultconstruction.com
                     www.consultconstruction.com
Human Resource




         info@consultconstruction.com
         www.consultconstruction.com
HR Related Controls - Labour Colony / Mess /
     Attendance / Vehicle Management




                 info@consultconstruction.com
                 www.consultconstruction.com
• Sub – Contractor Management
  – Sub-contractor Data bank on the basis of skill
    set and past performance.
  – Incentive scheme for time bound completion




                 info@consultconstruction.com
                 www.consultconstruction.com
Human Resource – cont….

      Master Details of Sub Contractor:
         • Two passport size color photograph
         • Name with firm name
         • Copy of PAN card without which TDS liability shall be @ 20% in
           place of regular rate
         • Identity poof
         • Address proof (Election Card, Latest light bill or Panchayat
           certified letter)
         • Communication details (Like, Landline / mobile with contact
           person & Fax number, mail ID, Web site)
         • Bank name, Branch address, Account type, Account number and
           RTGS No., cancelled cheque or declaration letter from the bank
         • Specimen signature of authorized person in absence of the
           main sub contractor .
                          info@consultconstruction.com
                          www.consultconstruction.com
Human Resource – cont….

Labour Over time:
 There should be proper system to record the duty hours in the labour
   card:-
 • Contractor name and labour name
 • In time and out time
 • Company supervisor sign for allowing OT who shall also be responsible
   to reply why OT was allowed.
 • Track of supervisor sanctioning highest OT
 • Labour / sub contractor sign is required

 Daily report & Control – Labour:
 • HO must ask for manpower report and work progress report from Site
   on a daily basis to assess the work performance.

                          info@consultconstruction.com
                          www.consultconstruction.com
Human Resource – cont….
 Gate Pass (GP) / Entry Card:
 •   Company must issue Gate Pass (GP) / Entry card for control and security purpose to sub contractors
     and all employees and labours. The same can be cross checked with daily manpower report to catch
     discrepancy if any.

 •   Following details are required in the gate pass:
      – Unique serial number and area / Period wise color if any
      – Name of labour
      – Sub Contractor name
      – Type of skill (Helper, Carpenter, Mason, Fitter)
      – Date of GP issued and validity (Validity would be three months)
      – Blood Group
      – Color photograph through Web cam and color printer
      – Company may charge some nominal amount for GP
      – Sign required of HR and sub contractor on Gate Pass
      – HR should have details of gate passes issued in the manual register where GP receiver sign is
          required. HR should have GP wise status (Active, Cancel, Expired)
      – Penalty should be charged If Gate pass is lost, expired but not renewed or not returned at time
          of leaving the job
      – All Gate Passes should be destroyed which have been returned by workers / sub contractors
          after proper entry in manual register or system
                                   info@consultconstruction.com
                                   www.consultconstruction.com
Human Resource – cont….
 PF Records and Liability payment:
 • If the sub-contractor is well organized, then he can pay PF and keep proper records and
    just deliver paid challan with its break up for your record.
 • But where Sub contractor is unorganized, it is necessary to get sub contractor wise
    wages sheet to calculate PF liability and pay.

 Labour Colony / Water & Power supply:
 • Labours are asset for the company and it should take care of their basic needs.

 •   This should be the responsibility of HRD
      – to visit labour colony at fixed interval to find out if their living conditions are proper
      – Basic aspects like PCC in flooring of room,
      – Drinking & routine use Water,
      – proper toilets and bath rooms,
      – power supply, cleaning around labour colony to ensure it hygienic, monthly medical
          check up etc.

      This will result in improved performance in the labour output.
                                  info@consultconstruction.com
                                  www.consultconstruction.com
Human Resource – cont….
      – Employees
 Salary Structure & Letter of Appointment:
 •   Salary Structure: Say
      – Basic – 40% of total salary
      – Other Allowances 60% of total Salary, like:
             • HRA Allowance
             • Uniform
             • PF
             • Bonus
             • Medical Allowance or Group Mediclaim policy
             • Transportation Allowance
             • Telephone / Conveyance Reimbursement
             • Child Allowance
             • Education Allowance
      – Deductions:
             • PF employee contribution – 12% of Basic
             • Professional Tax – Employee, as per salary slab
             • Tax Deduction at Source (TDS) as per Government rules on taxable salary
             • Staff Welfare Fund as per Government rules
             • If any bond amount decided, to deduct from salary on monthly basis
                                   info@consultconstruction.com
                                   www.consultconstruction.com
Human Resource – cont….



 • Master Form - Employee:

 • Branch / Site Transfer Letter:
    – Salary Structure
    – O/s Advances and Loans
    – o/s Salary Dues with present days of last working days at
      previous site




                          info@consultconstruction.com
                          www.consultconstruction.com
Human Resource – cont….

 Daily Attendance - Staff:
 • Daily attendance can be marked by manual records like - Register or Daily
    Sheet or Card or by Auto systems like Punch card, Thumb or Finger impression
    or based on any other online software,

 Over Time:
 • There should be well structured Policy to regulate and monitor the over time
    payment.

 •   There are two options to maintain OT records
      – a) Out time to be mentioned in Daily manual attendance sheet
      – b) Separate Sheet to be maintained for OT

      HR needs to take sign from Project Manager on daily OT sheet or Daily
      attendance sheet. At the end of the month, OT hours shall be calculated on the
      basis of this record.
                             info@consultconstruction.com
                             www.consultconstruction.com
Human Resource – cont….
Leave Policy:
•   Leave policy needs to be defined
     – Various types of leave and their number
     – Carry forward or lapse in the year end
     – Encashment
     – Maximum accumulation etc.

     Further employee needs to fill a leave application form containing following details:
          • Leave application vs. Daily / Monthly Attendance sheet
          • Leave period and number of days
          • Applicant signature required on form
          • Approving authority depending on number of days leave applied
          • Leave utilized mentioning clearly against which category (i.e. Paid Leave - PL, Casual
             Leave - CL & Sick Leave - SL) on application
          • Status of leave balance category wise as per rules
          • To avoid misuse of sick leave, medical certificate must be required on return from
             leave if the leave is more than say one or two days
          • Absent should be marked for extension of leave beyond sanctioned
          • HR should verify perfectly about leave balance before action on application

                                   info@consultconstruction.com
                                   www.consultconstruction.com
Human Resource – cont….

 •   Hired Camp
      – Lease Agreement
      – Distance from the Site
      – Proper Planning to avoid Hotel Expenditure

 •   Mess - Staff:
      – Self vs Contracted
      – Fixed Payment to employees
      – Policy should also be defined for other facilities of stay and in house entertainment by
        way of TV, reading materials, sports and club activities etc.

 •   Group Employee Health Insurance Policy:
      – HRD needs to evaluate group medical policy v/s medical allowance. It is advisable to go
        for mediclaim Insurance for which policy should be well defined.
      – Accordingly all concerned employees and officers should be covered as per policy which
        should be taken from General Insurance Company with full negotiation.
      – There should be one officer in charge for claim settlement in time so as to get the benefit
        of the Insurance.


                                  info@consultconstruction.com
                                  www.consultconstruction.com
Human Resource – cont….
•   Vehicle Report

•   Admin Assets & Control
          •   Laptop
          •   Data Card
          •   CUG Mobile connections – SIM card
          •   Mobile Instrument
          •   Camp / Guest House & Mess, Vehicles, Equipment etc.

          HR should have master data of details of all admin assets and this should be updated on
            regular basis
          (Monthly / Quarterly / Half yearly) like
               – Name of asset
               – Asset user name
               – Location
               – Insurance period and Service provider, if applicable

•   Company can take undertaking from employee against asset given for use. There should be
    well designed policy in place about entitlement to regulate the use of such assets.


                                 info@consultconstruction.com
                                 www.consultconstruction.com
Human Resource – cont….




• HR – MIS




   Level of Perfection
                          info@consultconstruction.com
                          www.consultconstruction.com
Statutory Compliances required at the
                Construction Site

 Labour Law Requirements
            Labour License – Minimum Wages
            PF / ESI
            Workmen Compensation
            Worker’s cess
           Minimum Wages
            Professional Tax
 VAT Provisions
           Documentary Requirements
            Difference between VAT and WCT
            What is Entry Tax?
            Check Post Related Issues
            CST Provisions
 Service Tax Provisions
                        info@consultconstruction.com
                        www.consultconstruction.com
Labour License
• Two authorities to be approached – Centre / State
• Any unit belongs to Central Govt, then license to applied to
  Central Government
• Form No. 4 to be applied for before commencement of
  work.
• It is applicable on client to client basis.
• After Initial Declaration, there is a provision to increase the
  number, but no provision to decrease.
• Security Deposit for Gujarat Govt is Rs. 270/- per worker
  and Centre is Rs. 90/- per worker.
• On completion of work – Taken Work Compl. Cert from
  Client and submit to License Authority
                      info@consultconstruction.com
                      www.consultconstruction.com
EPF Act
• Applicability i) Every establishment in which 20
  or more persons are employed and

• But Across India, there is only one EPF Number.
  For ease of administration you may ask for a sub-
  code.

• No. of Labour on which EPF is paid should not be
  more than sanction as per Labour License



                  info@consultconstruction.com
                  www.consultconstruction.com
Eligibility
• Any person who is employed for work of an
  establishment or employed through
  contractor in or in connection with the work
  of an establishment.
• Basic Salary more than Rs. 6,500/- not
  covered.



               info@consultconstruction.com
               www.consultconstruction.com
ESI Act
• provides for certain benefits to employees in case
  of sickness, maternity and employment injury.
• It applies to all factories (including Government
  factories but excluding seasonal factories)
  employing ten or more persons and carrying on a
  manufacturing process with the aid of power or
  employing 20 or more persons and carrying on a
  manufacturing process without the aid of power


                  info@consultconstruction.com
                  www.consultconstruction.com
Coverage and contribution
• The existing wage-limit for coverage under
  the Act, is Rs.15,000/- per month

• Currently, the employee’s contribution rate
  (w.e.f. 1.1.97) is 1.75% of the wages and that
  of employer’s is 4.75% of the wages
  paid/payable in respect of the employees in
  every wage period
                info@consultconstruction.com
                www.consultconstruction.com
• Construction Sites – ESI does not apply
• But Insurance by way of WC Policy is
  advisable.




           info@consultconstruction.com
           www.consultconstruction.com
Workmen’s compensation Act, 1923

• The Workmen’s Compensation Act, aims to
  provide workmen and/or their dependents
  some relief in case of accidents arising out
  of and in the course of employment and
  causing either death or disablement of
  workmen.
• It provides for payment by certain classes of
  employers to their workmen compensation
  for injury by accident.

                info@consultconstruction.com
                www.consultconstruction.com
Employer’s liability
• The employer of any establishment covered under
  this Act, is required to compensate an employee :

• Who has suffered an accident arising out of and in
  the course of his employment, resulting into (i)
  death, (ii) permanent total disablement, (iii)
  permanent partial disablement, or (iv) temporary
  disablement whether total or partial, or
  Who has contracted an occupational disease

                  info@consultconstruction.com
                  www.consultconstruction.com
THE EMPLOYER SHALL NOT BE LIABLE
•       In respect of any injury which does not result in the total
        or partial disablement of the workmen for a period not
        exceeding three days;

•       In respect of any injury not resulting in death, caused by
        an accident which is directly attributable to-
    –      Place of occurrence is outside site premises and not in connection with
           the works
           Further two more issues need to be kept in mind subject to certification
           from the authority

    –      the workmen having been at the time thereof under the influence or
           drugs, or

    –      the willful disobedience of the workman to an order expressly given, or
           to a rule expressly framed, for the purpose of securing the safety of
           workmen
                            info@consultconstruction.com
                            www.consultconstruction.com
Building and Other
Construction Workers' Welfare Cess Act,1996
LEVY AND COLLECTION OF CESS. -

(1) There shall be levied and collected a cess for the
purposes of the Building and Other Construction Workers'
(Regulation of Employment and Conditions of Service) Act,
1996, at such rate not exceeding two per cent but not less
than one per cent of the cost of construction incurred by an
employer
It is applicable to all contractors – working for state or for
private sector.
Enforcement in the private sector is very poor.
                     info@consultconstruction.com
                     www.consultconstruction.com
Minimum wages Act, 1948
• Wages for Centre ( –or
• Wages for State (Unskilled – Rs. 135.40)

• Whichever is higher


• Every 6 Months, the govt declares special allowance which
  needs to be added
• Same Rate for Male and Female



                    info@consultconstruction.com
                    www.consultconstruction.com
Professional Tax
•   Corporation Level Subject
•   Registration required for all the branches
•   Whether Construction Site is a Branch?
•   Payroll Generated from Head office
•   For Casual Workers the provision does not
    apply


                 info@consultconstruction.com
                 www.consultconstruction.com
Shop and Establishment
• Does not apply to construction site
• But it applies to establishment




                info@consultconstruction.com
                www.consultconstruction.com
VAT
•   Composition
•   Format of Invoice / Charge of Taxation
•   Input Tax Credit
•   Check Post Related Issues
•   TDS
•   Forms from Department
•   Inter-State Movement

                 info@consultconstruction.com
                 www.consultconstruction.com
Types of composition
• For complete contract
   – within 30 days of commencement of Work
• For Complete year
   – Application within 30 days before to commencement of year
• For New Registered Dealer
   – Within 90 Days from the effective date of registration

   No condonation of delay – Matter Pending before Tribunal
   Non receipt is assumed as granted




                        info@consultconstruction.com
                        www.consultconstruction.com
Format of Invoice
• Under Composition
• Retail Invoice
• Tax Invoice




              info@consultconstruction.com
              www.consultconstruction.com
VAT – Input Tax Credit
• ITC available on all inputs used in works contract other than composition method
  subject to fulfilment of conditions

• Broad Restrictions on ITC:
 ‒   CST purchases
 ‒   Capital goods used in works contract – Some of the States
 ‒   Lease goods
 ‒   Goods purchased from Lump sum dealer
 ‒   Goods not connected with business
 ‒   Vehicles, equipments, accessories or spare parts
 ‒   Fuel used in motor vehicles
 ‒   Goods used as fuel in generation of electrical energy



                             info@consultconstruction.com
                             www.consultconstruction.com
Entry Tax related issues under VAT
Inward Movement

1.   Cement / Raw Steel / Motor Vehicle are liable to entry tax.
2.   Authenticated Form 403 is required.
3.   Invoice / delivery challan / LR to be made available at checkpost
4.   For normal Items, Form 403 without authentication is required.
5.   Scaffolding Pipes are not covered.

Outward Movement

1. Branch Transfers – Work Order / Declaration Form / Form 402.
2. Relevance of F Form – Ambika Steel.
3. Having registration / Work order from other state.

Any checkpost related issues ?


                               info@consultconstruction.com
                               www.consultconstruction.com
C Form / Way Bill / Entry Tax
• Transfer of materials from one state to
  another.
• Multi State VAT Compliance




                info@consultconstruction.com
                www.consultconstruction.com
TDS Rate under GVAT

     Person responsible for payment exceeding Rupees 1 crore for
     works contract is responsible for deduction of tax at prescribed rates

    TDS Rate : 0.6% in case of construction contract and 2% in case of others

    Works Contractor is mandatorily required to obtain TDN No. from Commercial Tax
    Department. Application in Form 706 to get TDN No. within 30 days of agreement.




    TDS to be claimed in the year in which same is deducted and not in which the same is


?
    paid.
    Form 702 under Gujarat VAT to be attached with Invoice for lesser deduction.




                             info@consultconstruction.com
                             www.consultconstruction.com
Inter-State Movement of Material

•   Movement of Raw Material
•   Movement of Finished Goods
•   Use in Works Contract
•   Payment of CST / VAT




                info@consultconstruction.com
                www.consultconstruction.com
Service Tax
•    Concept of Centralised Registration
•    Method to be opted
•    Cenvat Credit
•    Invoice Related Issues
•    Service Tax vs VAT
•    Point of Taxation



    Smart CA
                    info@consultconstruction.com
                    www.consultconstruction.com
info@consultconstruction.com
www.consultconstruction.com
Control Points for Equipments

               Own vs Hire


 Transit Miller            Scaffolding Pipes
 Batching Plant            Shuttering Material
 Concrete Pump             Walkway Jali
 Crane                     Clamps
 Excavator                 Other support structures
 Tractor Trolley


                    info@consultconstruction.com
                    www.consultconstruction.com
Commercial Procurement
i) Services

Equipment / Machinery / Plant / Tools provide by Client:

• Condition of equipment – Third party can be appointed
• Maintenance scope
• Operation of Equipment
• Round the clock Availability
• Advisable to clear the commercial aspects for supplies beyond the
  scope as this might result in recovery from the contractor.
• Transportation point for FIM & Transit risk within the site.




                       info@consultconstruction.com
                       www.consultconstruction.com
Equipments - Purchased
Advantages of buying -
• No dependence on others.
• Company’s status & capacity as a contractor will be rated high .
• Equipment can be moved from place to place as per requirement.
• Bigger jobs can be obtained.

Disadvantages of buying –
• Working capital gets blocked.
• Repayment in time is big a responsibility.
• Resell value shall be negligible in case the same is not required
• Maintenance cost and expertise will be required to run the equipment
   smoothly.

                        info@consultconstruction.com
                        www.consultconstruction.com
Equipment - Hired
  Hiring Agreement: The user pays fixed hire charges on daily or monthly basis as long as the
     equipment is held by him,
•    Hire the equipment & machinery
• Minimum average commitment required in case of Vehicle and equipment & machinery
• Rate should be on hours basis excluding lunch / dinner hours to avoid OT over head.

Advantages -
• Need not to invest the FUND
• Claim as expense for Income Tax purpose
• If service, maintenance and operational cost is in supplier scope, no any handling issue and
   cost and that means peace of mind
• In case of business close down, no headache except to return the equipment

Disadvantages -
• Company totally dependent on others
• Hired equipment does not enhance company’s status
• In case of under utilization, it will result in big loss
• Company will depend for Service / repair & maintenance on supplier
• Without supplier’s permission, equipment can not be moved to other site
                                info@consultconstruction.com
                                www.consultconstruction.com
Buying or Hiring
• Buy – Value * 4 Times should be the
  turnover.
• Future Planning – Residential / Commercial
  / Industrial / Power
• Debt : Equity ratio should not be more than
  2:1.
• Buy – Own O&M Team, Driver

               info@consultconstruction.com
               www.consultconstruction.com
Cost of owning an Equipment
• Depreciation
• Cost of Capital
• Equipment Operating Cost




              info@consultconstruction.com
              www.consultconstruction.com
Hired Equipment Controls
• Equipment Chart




              info@consultconstruction.com
              www.consultconstruction.com
Transit Mixture on Hire
Equipment control points in case of Hired:
Transit Mixture

• 1 Make, Size / Capacity & other specification if any
  Example: a) Make - Schwing Setter, b) Capacity - 6 M3,
• 2 Age of equipment In Good working condition and less
  than 5years
• 3 Team - Qualified Operator / Driver, Crew member &
  Maintenance team Team: Qualified Operator / Driver - 1,
  Helper - 1 & Mechanic for Maintenance - 2

                    info@consultconstruction.com
                    www.consultconstruction.com
Transit Mixture on Hire
• 4 Testing / Calibration / Commission certificate - Required
  from third party whose Govt. approved person / agency?
  No, But Water Pump should be in working condition with
  water tank.

• 5 Insurance of Equipment / Chassis / Vehicle / Operational
  team & Third party YES

• 6 Guidelines / Manual for user with Equipment YES,
  Optional

                     info@consultconstruction.com
                     www.consultconstruction.com
Transit Mixture on Hire
• 7 Self certified photocopies of RTO documents of
  Equipment YES

• 8 GPS System Recommendatory, However required if more
  than two millers at the site with wide area.

• 9 Equipment with Basic things Hours & Kms meters in
  working condition, Proper number Plate / identification
  mark, Front, Break lights in working condition with
  Mirrors, night radium plate / colors, First aid, Tools &
  tackles
                    info@consultconstruction.com
                    www.consultconstruction.com
Transit Mixture on Hire
• 10 Minimum Expected Output per month Needs to be decided for each
  and every project - Suggestible Qty - 2000 CUM
• 11 Hiring approx. amount. Monthly Basis - Rs.1.25 Lacs (Excluding
  Fuel)
• 12 Minimum Working Duration in a month Flexible 260hrs in a month
  (Note 3)
• 13 Fuel & Power, Oil & Lubricants a) Its advisable to ask the supplier
  to quote his rate with Fuel. Oil and Lubricant should always be in
  supplier scope. b) If fuel is in our scope then avg consumption norms
  may be fixed. Fuel consumption per hour as per site experience.




                        info@consultconstruction.com
                        www.consultconstruction.com
Transit Mixture on Hire
• 14 Daily Log Book / Records Supplier to maintain
  daily log book / records with sign of both -
  operator and Company authorized person.

• 15 Lock & key & Daily Records custody? If fuel is
  in the scope of company, Fuel Tank Key and
  Records should lie with the company.



                  info@consultconstruction.com
                  www.consultconstruction.com
Transit Mixture on Hire
• 16 Minimum Output performance clause of equipment Depends on
  batching plant setup & destination of structure.

  For e.g.           18 M3 casting per hour

  If TM takes 20min for one trip. Then 3 trips in one hour
  = 6 M3 per TM x 3 trip in one hour. 17 Attendance The operating team
  should be available at the site during the working days. The bill shall be
  reduced proportionately in case of absence. (Monthly Billing Amt / 26 *
  Absent Days). 18 Overtime clause OT shall start after expiry of flexible
  hours limit in the month and shall be calculated on pro rata basis
  (Monthly Rate / 260 Hours).


                         info@consultconstruction.com
                         www.consultconstruction.com
Transit Mixture on Hire
• 19 Incentive clause Volume based and other points like - lower break
  down, Safety during the work etc.

•   20 Equipment maintenance / Break down clause Permission for
    maintenance on any 4 half days in a month or as and when it is free
    after discussion with site PM.

• 21 Staff / Team Accommodation & Fooding clause Staff / team
  accommodation shall be provided by us But Food shall be in your scope

• 22 De Hiring Notice Period 7days on both sides to avoid any dispute.



                          info@consultconstruction.com
                          www.consultconstruction.com
Transit Mixture on Hire
• III ) Billing & Payment:
  23 Mobilization & Demobilization clause
        a) Mobilization = i) Within 10days from date of WO
  (mail or hardcopy) with all required resources. ii) One
  month mobilization advance to be recovered in six equal
  monthly installment.
       b) De Mob. Cost = If Contract is more than six months
  than in lessor's scope. 24 Billing & Certification cycle




                     info@consultconstruction.com
                     www.consultconstruction.com
Transit Mixture on Hire
• 24 Bill Submission = Billing on monthly basis. to site PM within
  5days of previous month with sign, stamp & inward date from
  company. In case of failure to get inward stamp or received sign,
  Accounts shall not accept the same.
  b) Bill / Supporting = Main bill in triplicate copy with company
  name, address & site, WO number, Bill date, period, name & make of
  equipment. All statutory numbers, break up of taxes, OT with proper
  calculation, incentive if any. Original Log sheet (Duplicate copy must for
  your records).




                          info@consultconstruction.com
                          www.consultconstruction.com
Transit Mixture on Hire
c) Bill Certification = Bill shall certified within a week from the date of invoice /
    inward with stamp and authorized sign & name by company. 25 Payment cycle
    Payment shall be made within 20days from the date of bill certification 26
    Debit / Recovery clause in case of break down or non performance / Any other
    damage Normally at time of certification or separately if issued by any other
    department or client for any non-compliance. 27 Local / RTO tax in scope of
    supplier All statutory (local / RTO etc.) liabilities in your scope, inclusive of
    rate. Service tax shall be paid extra. 28 TDS & any other Statutory deduction if
    any TDS or any other statutory deductions as applicable shall be deducted.
 D) Safety: 29 Clearance and data for Gate / Entry Pass Requirement of the
    principal client may be mentioned here. 30 Safety rules & regulation, violence
    & Penalty Requirement of the principal client may be mentioned here with the
    penal clauses, if any.
IV ) Legal: 31 Clause - Child labour Strict Compliance 32 Clause - Termination of
    Contract In case of non compliance of any condition and delay in work
    performance, contract shall be terminated immediately without any cost. 33
    Jurisdiction Jurisdiction is Ahmedabad only
                             info@consultconstruction.com
                             www.consultconstruction.com
Role of Site Accounts and Co-ordination with
                        Head Office




Changing Def’n - Democracy

                             info@consultconstruction.com
                             www.consultconstruction.com
Model of Accounting – Branch / Centralized
•   The model most prevalent, provided you have good team of accountants with
    you is the HO and Branch Model.

•   Branches maintain accounts at the construction site itself. Because if we have a
    smart accountant at the site that would serve as the best internal control
    measure.

•   Integration of accounts and Inventory would then be possible.

•   Complexity involved is you then need a perfect co-ordination between HO and
    Branches. Reconciliation between the two is required on a regular basis. As
    many a times HO would directly be making payment to Branch’s creditors
    without routing the same through the branch.

•   In case of centralised accounting the certification systems have to be perfect.
    You would need all the documents to be certified by the Site Incharge and
    respective area incharge before booking the same in accounts.


                            info@consultconstruction.com
                            www.consultconstruction.com
Role of Site Accounts
               • Preparation of cash vouchers and entry into the system.
               • Maintaining Bank book with not more than one day
                 transaction lag.
               • Documentation of purchase bills after comparison with
                 P.O and entry into the system.
               • Entry of subcontractor bills – Co-ordination with the
                 engineering dept.
               • Working out weekly cash requirements
               • Entry of debit notes in contractor accounts: -
 Executory       • Debit notes from Stores.
                 • Debit notes from H.R
Functions: -     • Debit notes from Engineering Dept.
               • Periodic entry and payment of statutory dues
                 • TDS – self-assessment and monthly payment.
                 • PF – Payment in co-ordination with H.R
                 • Service Tax – Preparation of input credit details


                 info@consultconstruction.com
                 www.consultconstruction.com
Role of Site Accounts – cont….
                       • All vouchers need to be authenticated by the
                         accountant.
                       • Vouchers carrying amount more than Rs.10K need to be
                         authorized by PM.
                       • Comparison of sub-contractor bills with Work orders.
                       • Ensuring that Full and final payments are made to the
                         contractors and employees only after getting a
                         completely filled Work Termination Form.
                       • Making payments against bills only after getting them
                         pre-audited.
   Control             • Ensuring that Subcontractor Master details are available
                         before his first bill is entered in the system.
 Functions: -          • Sending backups to HO on a weekly basis.
                       • Ensuring periodic reconciliations in the following
                         manner :-
                         • Intersite – Reco on a fortnightly basis.
                         • Bank – Reco on a monthly basis.
                         • Supplier – Reco on a monthly basis.


                         info@consultconstruction.com
                         www.consultconstruction.com
Role of Site Accounts – cont….
                 • Preparation of Labour supply bills.
                 • Preparation of documents/letters as required.
                 • Submission of bills to the client.
                 • Sending Original Work orders / LOI / amendments to HO after keeping
Administrative     copies.
                 • Ensuring original TDS certificates are sent to Head office.
 Functions : -
                 • Other site Co-ordination.




                 • Monthly profit centre performance reports.- 20 days
                 • Weekly Cash & Bank summaries.- 2 days
                 • Monthly liability statement. – 20 days
                 • Monthly vehicle reports.- 5 days
                 • Report on TDS deduction every month. – 25 days
  Reporting      • Quarterly Service Tax input credit details. – 10 days
 Functions: -    • Pending sub-contractor bills on a fortnightly basis for the previous months
                   duly authenticated by the project manager. – 2 days



                              info@consultconstruction.com
                              www.consultconstruction.com
Role of Site Accounts – cont….


 • Accounts MIS




                      info@consultconstruction.com
                      www.consultconstruction.com
Role of Site Accounts – cont….

 • Onsite Integration Model for a Construction Site

     Using cloud servers, access can be given to multiple locations
      without buying any software / hardware.
     Stores Material Receipt entry can be passed from the site provided
      there is a proper internet connectivity.
     When the purchase Invoices are received the same are certified by
      the stores department and the printed MIN is then attached behind
      the invoices.
     Accounts then enters the rates of materials picking up the tracking
      number. Any deviations are settled by way of Debit / Credit Note.
     Materials are then issued by way of Delivery Note to either the
      client / sub-contractors.


                        info@consultconstruction.com
                        www.consultconstruction.com
•           Payment Advice Format

                                                                                                   Site :_____________ Date :________________
                                              B) Supplier of Capital                               D) Rent ( Labour Colony / Room         E) Vehicle Hire / Petroleum
Sr.No.           A) Supplier of Material             Goods                C) Sub-Contractors                   / House )                           Suppliers
         1           Purchase Order              Purchase Order               Work Order                   Rent Agreement                          Log sheet

         2             Tax Invoice             Tax/Retail Invoice              RA Bill                 L.C. visiting Reports - HR           Auth.-Commercial/H.R.
                                               Authorization from         Authorization from
         3     Authorization from Site EIC      Project Director          Commercial Dept.            Authorization from H.R.    Authorization from Site Incharge
               Authorization from Project      Authorization from         Authorization from       Authorization from Commercial   Authorization from Project
         4              Director               Commercial Dept.            Project Director                     Dept.                        Director

                                               Stamp of Quality &                                                                       Bill Entry in books of accounts
           Authorization from Commercial      Installation from Site    Authorization from Site       Authorization from Project        with Deduction (maintenance
         5              Dept.                        Incharge                 Incharge                        Director                          /spare parts... )
                                              Bill Entry in books of     Debit notes receive &
                                                accounts with all        entered from Stores
                 Stamp of Quality & Qty.     deduction (TDS / VAT &       (Safety material) &       Bill Entry in books of accounts       Bill / Voucher / Supporting
         6       verification from stores             Other)                 H.R.D. (G.P.'s)             with Deduction (TDS )                    Proper filing
                                                                         Bill Entry in books of
                                                                           accounts with all
                Reconciliation of Material      Bill / Voucher /           deduction (TDS /           Bill / Voucher / Supporting          Monthly Vehicle Report of
         7        against Client Billing     Supporting Proper filing         Retention ….)                   Proper filing                    payment month
           Bill Entry in books of accounts
           with all deduction (TDS/VAT &         Receive party's       Bill / Voucher /
         8              Other)               Confirmation Statement Supporting Proper filing             Supplier master form                   Supplier master form

              Receive party's Confirmation                              Client vs. Subcontractor     Authorization from Internal          Authorization from Internal
         9       Statement with Reco.         Status of excise credit              Qty.                       Auditor                              Auditor
                                          Whether Against "C"           EIC Performance Report
     10 Whether Against "C" Form                 Form                         for the site
     13 Remarks required if On Account or Advance: -
             Amount Released                                info@consultconstruction.com
For H. Details of Payment (chq no. etc.)                    www.consultconstruction.com
O. use Remarks
Banking – Whether centralized or Branch wise
•   We are presently in a world where banks are all connected, so we may opt for a
    Centralized banking system, but then if you have a HO and the Branch Model,
    you need perfect controls in place before the HO releases funds.

•   Payment Authorization Vouchers – A system that can be implemented, similar to
    controls that we have in SAP.

•   Further if we have to plan the funds and ensure that funds generated from a
    particular site are available for only that site after HO takes out its share of profit,
    then it is advisable to have separate accounts for the branches.




                             info@consultconstruction.com
                             www.consultconstruction.com
Managing the Financing Needs of the business
•   Limits with the Bank – Fund Based / Non-Fund based.

•   Non-Fund based Limits are of great importance in the construction sector, as for
    any Project that is about to begin, the client is willing to give Mobilisation
    Advances against Bank Gaurantees.

•   Hence as a consultant you can fight hard with the bank to secure best terms in
    the Non-fund based limits. With a good order book you can get away by giving
    25-30% collateral to some of the private banks in the market.




                            info@consultconstruction.com
                            www.consultconstruction.com
[Internal Audit]




•   Trust


              info@consultconstruction.com
              www.consultconstruction.com
Lets have a look at an Internal Audit Report




            info@consultconstruction.com
            www.consultconstruction.com

More Related Content

What's hot

Managing Cash Flows On Construction Projects
Managing Cash Flows On Construction ProjectsManaging Cash Flows On Construction Projects
Managing Cash Flows On Construction ProjectsAGC of California
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
Lecture 10, chap 16, Chapter 16, Auditing Inventories and property, plant an...
Lecture 10,  chap 16, Chapter 16, Auditing Inventories and property, plant an...Lecture 10,  chap 16, Chapter 16, Auditing Inventories and property, plant an...
Lecture 10, chap 16, Chapter 16, Auditing Inventories and property, plant an...Sazzad Hossain, ITP, MBA, CSCA™
 
Appointment, Removal Resignation of auditors
Appointment, Removal Resignation of auditorsAppointment, Removal Resignation of auditors
Appointment, Removal Resignation of auditorsManjunath Ganesh
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in WorksDr K M SONI
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Schedulingakashpadole
 
Property, Plant & Equipment IAS 16
Property, Plant & Equipment   IAS 16 Property, Plant & Equipment   IAS 16
Property, Plant & Equipment IAS 16 Md. Moazzem Hossain
 
Internal financial control
Internal financial controlInternal financial control
Internal financial controlMitesh Katira
 
AS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party TransactionsAS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party TransactionsPrakhar Jain
 
Chapter 3 -Audit evidence
Chapter   3 -Audit evidenceChapter   3 -Audit evidence
Chapter 3 -Audit evidenceSaidiBuyera
 
Business Combinations & Consolidations
Business Combinations & ConsolidationsBusiness Combinations & Consolidations
Business Combinations & Consolidationsbduratti
 
Fast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.pptFast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.pptJo Balucanag - Bitonio
 

What's hot (20)

Cost management
Cost managementCost management
Cost management
 
Managing Cash Flows On Construction Projects
Managing Cash Flows On Construction ProjectsManaging Cash Flows On Construction Projects
Managing Cash Flows On Construction Projects
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Lecture 10, chap 16, Chapter 16, Auditing Inventories and property, plant an...
Lecture 10,  chap 16, Chapter 16, Auditing Inventories and property, plant an...Lecture 10,  chap 16, Chapter 16, Auditing Inventories and property, plant an...
Lecture 10, chap 16, Chapter 16, Auditing Inventories and property, plant an...
 
Appointment, Removal Resignation of auditors
Appointment, Removal Resignation of auditorsAppointment, Removal Resignation of auditors
Appointment, Removal Resignation of auditors
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
 
Ind as 2 ppt
Ind as 2 pptInd as 2 ppt
Ind as 2 ppt
 
Ias 37
Ias 37Ias 37
Ias 37
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
Property, Plant & Equipment IAS 16
Property, Plant & Equipment   IAS 16 Property, Plant & Equipment   IAS 16
Property, Plant & Equipment IAS 16
 
Internal financial control
Internal financial controlInternal financial control
Internal financial control
 
Risk management
Risk managementRisk management
Risk management
 
AS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party TransactionsAS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party Transactions
 
Chapter 3 -Audit evidence
Chapter   3 -Audit evidenceChapter   3 -Audit evidence
Chapter 3 -Audit evidence
 
Tax[1]
Tax[1]Tax[1]
Tax[1]
 
Business Combinations & Consolidations
Business Combinations & ConsolidationsBusiness Combinations & Consolidations
Business Combinations & Consolidations
 
Ind as 19
Ind as 19Ind as 19
Ind as 19
 
Fast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.pptFast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.ppt
 
Auditing and assurance standards
Auditing and assurance standardsAuditing and assurance standards
Auditing and assurance standards
 
Value for money audit
Value for money auditValue for money audit
Value for money audit
 

Similar to Here are some key points to consider for labour mobilisation:- Identify areas where required type/skill of labour is readily available to minimize mobilization time and cost. - Estimate initial cost of mobilization including transportation, advance payment, tools/equipment, accommodation etc. - Arrange for labour contracts and ensure all statutory compliances like registration, insurance, wages as per local laws.- Set up basic facilities like drinking water, temporary shelters, toilets before labour arrival to avoid delays. - Mobilize in phases linked to project schedule to avoid underutilization of labour.- Train labour on safety, quality norms and work processes to start productive work promptly.- Maintain

Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Bhalindra Bath - projects & M&A law
 
Sanjeewa_CV updated on 16.05.2014
Sanjeewa_CV  updated on 16.05.2014Sanjeewa_CV  updated on 16.05.2014
Sanjeewa_CV updated on 16.05.2014Sanjeewa Mahawedage
 
Quantity Surveyor
Quantity Surveyor Quantity Surveyor
Quantity Surveyor Danger Riyas
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Antonio Coladarce
 
Construction - Accounting and Tax Aspects
Construction - Accounting and Tax AspectsConstruction - Accounting and Tax Aspects
Construction - Accounting and Tax Aspectssandesh mundra
 
THE GLOBAL ENGINEERING PROCUREMENT & CONSTRUCTION PROJECT MANAGEMENT FOR THE ...
THE GLOBAL ENGINEERING PROCUREMENT & CONSTRUCTION PROJECT MANAGEMENT FOR THE ...THE GLOBAL ENGINEERING PROCUREMENT & CONSTRUCTION PROJECT MANAGEMENT FOR THE ...
THE GLOBAL ENGINEERING PROCUREMENT & CONSTRUCTION PROJECT MANAGEMENT FOR THE ...Lenka Larson
 
Global EPC Project Management Forum 20-21 APRIL 2017 AMSTERDAM
Global EPC Project Management Forum 20-21 APRIL 2017 AMSTERDAM Global EPC Project Management Forum 20-21 APRIL 2017 AMSTERDAM
Global EPC Project Management Forum 20-21 APRIL 2017 AMSTERDAM Lenka Larson
 
Disputes ans Arbitration..
Disputes ans Arbitration..Disputes ans Arbitration..
Disputes ans Arbitration..Rajesh Prasad
 
New update cv-qs- aboobaker
New update cv-qs- aboobakerNew update cv-qs- aboobaker
New update cv-qs- aboobakerSiyam Aboobukar
 
Abdul Ghafoor (SQS) ( )
Abdul Ghafoor (SQS) ( )Abdul Ghafoor (SQS) ( )
Abdul Ghafoor (SQS) ( )Ghafoor Butt
 
Commercial aspects of civil construction
Commercial aspects of civil constructionCommercial aspects of civil construction
Commercial aspects of civil constructionsandesh mundra
 
Christy_McKinzie_Resume_2015
Christy_McKinzie_Resume_2015Christy_McKinzie_Resume_2015
Christy_McKinzie_Resume_2015Christy McKinzie
 
Resume_mahim
Resume_mahimResume_mahim
Resume_mahimmahim_lal
 
Procedure to start small scale industries
Procedure to start small scale industriesProcedure to start small scale industries
Procedure to start small scale industrieszeeshanabdullateef
 
Quantity Surveyor - Riyas AM
Quantity Surveyor - Riyas AMQuantity Surveyor - Riyas AM
Quantity Surveyor - Riyas AMMohamed Riyaz
 
Sanjeewa_CV updated on 23.02.2016
Sanjeewa_CV  updated on 23.02.2016Sanjeewa_CV  updated on 23.02.2016
Sanjeewa_CV updated on 23.02.2016Sanjeewa Mahawedage
 
RV Resume updated Mar'16
RV Resume updated Mar'16RV Resume updated Mar'16
RV Resume updated Mar'16Rahul Vadgama
 

Similar to Here are some key points to consider for labour mobilisation:- Identify areas where required type/skill of labour is readily available to minimize mobilization time and cost. - Estimate initial cost of mobilization including transportation, advance payment, tools/equipment, accommodation etc. - Arrange for labour contracts and ensure all statutory compliances like registration, insurance, wages as per local laws.- Set up basic facilities like drinking water, temporary shelters, toilets before labour arrival to avoid delays. - Mobilize in phases linked to project schedule to avoid underutilization of labour.- Train labour on safety, quality norms and work processes to start productive work promptly.- Maintain (20)

Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...
 
Sanjeewa_CV updated on 16.05.2014
Sanjeewa_CV  updated on 16.05.2014Sanjeewa_CV  updated on 16.05.2014
Sanjeewa_CV updated on 16.05.2014
 
Contract mgt stc
Contract mgt stcContract mgt stc
Contract mgt stc
 
Quantity Surveyor
Quantity Surveyor Quantity Surveyor
Quantity Surveyor
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
Construction - Accounting and Tax Aspects
Construction - Accounting and Tax AspectsConstruction - Accounting and Tax Aspects
Construction - Accounting and Tax Aspects
 
THE GLOBAL ENGINEERING PROCUREMENT & CONSTRUCTION PROJECT MANAGEMENT FOR THE ...
THE GLOBAL ENGINEERING PROCUREMENT & CONSTRUCTION PROJECT MANAGEMENT FOR THE ...THE GLOBAL ENGINEERING PROCUREMENT & CONSTRUCTION PROJECT MANAGEMENT FOR THE ...
THE GLOBAL ENGINEERING PROCUREMENT & CONSTRUCTION PROJECT MANAGEMENT FOR THE ...
 
Global EPC Project Management Forum 20-21 APRIL 2017 AMSTERDAM
Global EPC Project Management Forum 20-21 APRIL 2017 AMSTERDAM Global EPC Project Management Forum 20-21 APRIL 2017 AMSTERDAM
Global EPC Project Management Forum 20-21 APRIL 2017 AMSTERDAM
 
Disputes ans Arbitration..
Disputes ans Arbitration..Disputes ans Arbitration..
Disputes ans Arbitration..
 
ppt of time.ppt
ppt of time.pptppt of time.ppt
ppt of time.ppt
 
New update cv-qs- aboobaker
New update cv-qs- aboobakerNew update cv-qs- aboobaker
New update cv-qs- aboobaker
 
Abdul Ghafoor (SQS) ( )
Abdul Ghafoor (SQS) ( )Abdul Ghafoor (SQS) ( )
Abdul Ghafoor (SQS) ( )
 
Commercial aspects of civil construction
Commercial aspects of civil constructionCommercial aspects of civil construction
Commercial aspects of civil construction
 
Christy_McKinzie_Resume_2015
Christy_McKinzie_Resume_2015Christy_McKinzie_Resume_2015
Christy_McKinzie_Resume_2015
 
Resume_mahim
Resume_mahimResume_mahim
Resume_mahim
 
Procedure to start small scale industries
Procedure to start small scale industriesProcedure to start small scale industries
Procedure to start small scale industries
 
Quantity Surveyor - Riyas AM
Quantity Surveyor - Riyas AMQuantity Surveyor - Riyas AM
Quantity Surveyor - Riyas AM
 
Inhouse Training
Inhouse TrainingInhouse Training
Inhouse Training
 
Sanjeewa_CV updated on 23.02.2016
Sanjeewa_CV  updated on 23.02.2016Sanjeewa_CV  updated on 23.02.2016
Sanjeewa_CV updated on 23.02.2016
 
RV Resume updated Mar'16
RV Resume updated Mar'16RV Resume updated Mar'16
RV Resume updated Mar'16
 

More from sandesh mundra

GSTR 9C Annual Return with example
GSTR 9C Annual Return with exampleGSTR 9C Annual Return with example
GSTR 9C Annual Return with examplesandesh mundra
 
Critical issues under hira
Critical issues under hiraCritical issues under hira
Critical issues under hirasandesh mundra
 
Presentation on gst impact and effect
Presentation on gst impact and effectPresentation on gst impact and effect
Presentation on gst impact and effectsandesh mundra
 
Form 5 & Case Studies in rera
Form 5 & Case Studies in reraForm 5 & Case Studies in rera
Form 5 & Case Studies in rerasandesh mundra
 
Complications of GST for Real-Estate and Developers
Complications of GST for Real-Estate and DevelopersComplications of GST for Real-Estate and Developers
Complications of GST for Real-Estate and Developerssandesh mundra
 
RERA- Certification and issues in Alteration
RERA- Certification and issues in AlterationRERA- Certification and issues in Alteration
RERA- Certification and issues in Alterationsandesh mundra
 
GST - Audit, Accounts and Returns
GST - Audit, Accounts and ReturnsGST - Audit, Accounts and Returns
GST - Audit, Accounts and Returnssandesh mundra
 
Affordable Housing under GST
Affordable Housing under GSTAffordable Housing under GST
Affordable Housing under GSTsandesh mundra
 
Recent Trends in Corporate Restructuring
Recent Trends in Corporate RestructuringRecent Trends in Corporate Restructuring
Recent Trends in Corporate Restructuringsandesh mundra
 
Rotary Club of Ahmedabad West - Lets Connect to the Future
Rotary Club of Ahmedabad West - Lets Connect to the FutureRotary Club of Ahmedabad West - Lets Connect to the Future
Rotary Club of Ahmedabad West - Lets Connect to the Futuresandesh mundra
 
Rotary Club of Ahmedabad West - Future Aspiration
Rotary Club of Ahmedabad West - Future AspirationRotary Club of Ahmedabad West - Future Aspiration
Rotary Club of Ahmedabad West - Future Aspirationsandesh mundra
 
Effect of GST on existing contracts
Effect of GST on existing contractsEffect of GST on existing contracts
Effect of GST on existing contractssandesh mundra
 
Issues faced by Realtors and works contractors
Issues faced by Realtors and works contractorsIssues faced by Realtors and works contractors
Issues faced by Realtors and works contractorssandesh mundra
 
Judicial Pronouncements in GST till date
Judicial Pronouncements in GST till dateJudicial Pronouncements in GST till date
Judicial Pronouncements in GST till datesandesh mundra
 
Concept of HSN and Tax free exports
Concept of HSN and Tax free exportsConcept of HSN and Tax free exports
Concept of HSN and Tax free exportssandesh mundra
 
GST - Impact, Development and Compliances
GST - Impact, Development and CompliancesGST - Impact, Development and Compliances
GST - Impact, Development and Compliancessandesh mundra
 

More from sandesh mundra (20)

PPT on GSTR 9C
PPT on GSTR 9CPPT on GSTR 9C
PPT on GSTR 9C
 
GSTR 9C template
GSTR  9C templateGSTR  9C template
GSTR 9C template
 
GSTR 9C Annual Return with example
GSTR 9C Annual Return with exampleGSTR 9C Annual Return with example
GSTR 9C Annual Return with example
 
GST Audit
GST AuditGST Audit
GST Audit
 
Affordable housing
Affordable housing Affordable housing
Affordable housing
 
Critical issues under hira
Critical issues under hiraCritical issues under hira
Critical issues under hira
 
Presentation on gst impact and effect
Presentation on gst impact and effectPresentation on gst impact and effect
Presentation on gst impact and effect
 
Form 5 & Case Studies in rera
Form 5 & Case Studies in reraForm 5 & Case Studies in rera
Form 5 & Case Studies in rera
 
Complications of GST for Real-Estate and Developers
Complications of GST for Real-Estate and DevelopersComplications of GST for Real-Estate and Developers
Complications of GST for Real-Estate and Developers
 
RERA- Certification and issues in Alteration
RERA- Certification and issues in AlterationRERA- Certification and issues in Alteration
RERA- Certification and issues in Alteration
 
GST - Audit, Accounts and Returns
GST - Audit, Accounts and ReturnsGST - Audit, Accounts and Returns
GST - Audit, Accounts and Returns
 
Affordable Housing under GST
Affordable Housing under GSTAffordable Housing under GST
Affordable Housing under GST
 
Recent Trends in Corporate Restructuring
Recent Trends in Corporate RestructuringRecent Trends in Corporate Restructuring
Recent Trends in Corporate Restructuring
 
Rotary Club of Ahmedabad West - Lets Connect to the Future
Rotary Club of Ahmedabad West - Lets Connect to the FutureRotary Club of Ahmedabad West - Lets Connect to the Future
Rotary Club of Ahmedabad West - Lets Connect to the Future
 
Rotary Club of Ahmedabad West - Future Aspiration
Rotary Club of Ahmedabad West - Future AspirationRotary Club of Ahmedabad West - Future Aspiration
Rotary Club of Ahmedabad West - Future Aspiration
 
Effect of GST on existing contracts
Effect of GST on existing contractsEffect of GST on existing contracts
Effect of GST on existing contracts
 
Issues faced by Realtors and works contractors
Issues faced by Realtors and works contractorsIssues faced by Realtors and works contractors
Issues faced by Realtors and works contractors
 
Judicial Pronouncements in GST till date
Judicial Pronouncements in GST till dateJudicial Pronouncements in GST till date
Judicial Pronouncements in GST till date
 
Concept of HSN and Tax free exports
Concept of HSN and Tax free exportsConcept of HSN and Tax free exports
Concept of HSN and Tax free exports
 
GST - Impact, Development and Compliances
GST - Impact, Development and CompliancesGST - Impact, Development and Compliances
GST - Impact, Development and Compliances
 

Recently uploaded

Stock Market Brief Deck for 4/24/24 .pdf
Stock Market Brief Deck for 4/24/24 .pdfStock Market Brief Deck for 4/24/24 .pdf
Stock Market Brief Deck for 4/24/24 .pdfMichael Silva
 
Tenets of Physiocracy History of Economic
Tenets of Physiocracy History of EconomicTenets of Physiocracy History of Economic
Tenets of Physiocracy History of Economiccinemoviesu
 
AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...
AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...
AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...yordanosyohannes2
 
call girls in Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in  Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in  Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Governor Olli Rehn: Dialling back monetary restraint
Governor Olli Rehn: Dialling back monetary restraintGovernor Olli Rehn: Dialling back monetary restraint
Governor Olli Rehn: Dialling back monetary restraintSuomen Pankki
 
Stock Market Brief Deck for "this does not happen often".pdf
Stock Market Brief Deck for "this does not happen often".pdfStock Market Brief Deck for "this does not happen often".pdf
Stock Market Brief Deck for "this does not happen often".pdfMichael Silva
 
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...Henry Tapper
 
government_intervention_in_business_ownership[1].pdf
government_intervention_in_business_ownership[1].pdfgovernment_intervention_in_business_ownership[1].pdf
government_intervention_in_business_ownership[1].pdfshaunmashale756
 
Call Girls Near Delhi Pride Hotel, New Delhi|9873777170
Call Girls Near Delhi Pride Hotel, New Delhi|9873777170Call Girls Near Delhi Pride Hotel, New Delhi|9873777170
Call Girls Near Delhi Pride Hotel, New Delhi|9873777170Sonam Pathan
 
(办理学位证)加拿大萨省大学毕业证成绩单原版一比一
(办理学位证)加拿大萨省大学毕业证成绩单原版一比一(办理学位证)加拿大萨省大学毕业证成绩单原版一比一
(办理学位证)加拿大萨省大学毕业证成绩单原版一比一S SDS
 
NO1 Certified Ilam kala Jadu Specialist Expert In Bahawalpur, Sargodha, Sialk...
NO1 Certified Ilam kala Jadu Specialist Expert In Bahawalpur, Sargodha, Sialk...NO1 Certified Ilam kala Jadu Specialist Expert In Bahawalpur, Sargodha, Sialk...
NO1 Certified Ilam kala Jadu Specialist Expert In Bahawalpur, Sargodha, Sialk...Amil Baba Dawood bangali
 
PMFBY , Pradhan Mantri Fasal bima yojna
PMFBY , Pradhan Mantri  Fasal bima yojnaPMFBY , Pradhan Mantri  Fasal bima yojna
PMFBY , Pradhan Mantri Fasal bima yojnaDharmendra Kumar
 
Bladex 1Q24 Earning Results Presentation
Bladex 1Q24 Earning Results PresentationBladex 1Q24 Earning Results Presentation
Bladex 1Q24 Earning Results PresentationBladex
 
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACT
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACTGOODSANDSERVICETAX IN INDIAN ECONOMY IMPACT
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACTharshitverma1762
 
2024 Q1 Crypto Industry Report | CoinGecko
2024 Q1 Crypto Industry Report | CoinGecko2024 Q1 Crypto Industry Report | CoinGecko
2024 Q1 Crypto Industry Report | CoinGeckoCoinGecko
 
Stock Market Brief Deck FOR 4/17 video.pdf
Stock Market Brief Deck FOR 4/17 video.pdfStock Market Brief Deck FOR 4/17 video.pdf
Stock Market Brief Deck FOR 4/17 video.pdfMichael Silva
 
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办fqiuho152
 
Classical Theory of Macroeconomics by Adam Smith
Classical Theory of Macroeconomics by Adam SmithClassical Theory of Macroeconomics by Adam Smith
Classical Theory of Macroeconomics by Adam SmithAdamYassin2
 
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdf
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdfBPPG response - Options for Defined Benefit schemes - 19Apr24.pdf
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdfHenry Tapper
 

Recently uploaded (20)

Stock Market Brief Deck for 4/24/24 .pdf
Stock Market Brief Deck for 4/24/24 .pdfStock Market Brief Deck for 4/24/24 .pdf
Stock Market Brief Deck for 4/24/24 .pdf
 
Tenets of Physiocracy History of Economic
Tenets of Physiocracy History of EconomicTenets of Physiocracy History of Economic
Tenets of Physiocracy History of Economic
 
AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...
AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...
AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...
 
call girls in Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in  Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in  Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Governor Olli Rehn: Dialling back monetary restraint
Governor Olli Rehn: Dialling back monetary restraintGovernor Olli Rehn: Dialling back monetary restraint
Governor Olli Rehn: Dialling back monetary restraint
 
Stock Market Brief Deck for "this does not happen often".pdf
Stock Market Brief Deck for "this does not happen often".pdfStock Market Brief Deck for "this does not happen often".pdf
Stock Market Brief Deck for "this does not happen often".pdf
 
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
letter-from-the-chair-to-the-fca-relating-to-british-steel-pensions-scheme-15...
 
Monthly Economic Monitoring of Ukraine No 231, April 2024
Monthly Economic Monitoring of Ukraine No 231, April 2024Monthly Economic Monitoring of Ukraine No 231, April 2024
Monthly Economic Monitoring of Ukraine No 231, April 2024
 
government_intervention_in_business_ownership[1].pdf
government_intervention_in_business_ownership[1].pdfgovernment_intervention_in_business_ownership[1].pdf
government_intervention_in_business_ownership[1].pdf
 
Call Girls Near Delhi Pride Hotel, New Delhi|9873777170
Call Girls Near Delhi Pride Hotel, New Delhi|9873777170Call Girls Near Delhi Pride Hotel, New Delhi|9873777170
Call Girls Near Delhi Pride Hotel, New Delhi|9873777170
 
(办理学位证)加拿大萨省大学毕业证成绩单原版一比一
(办理学位证)加拿大萨省大学毕业证成绩单原版一比一(办理学位证)加拿大萨省大学毕业证成绩单原版一比一
(办理学位证)加拿大萨省大学毕业证成绩单原版一比一
 
NO1 Certified Ilam kala Jadu Specialist Expert In Bahawalpur, Sargodha, Sialk...
NO1 Certified Ilam kala Jadu Specialist Expert In Bahawalpur, Sargodha, Sialk...NO1 Certified Ilam kala Jadu Specialist Expert In Bahawalpur, Sargodha, Sialk...
NO1 Certified Ilam kala Jadu Specialist Expert In Bahawalpur, Sargodha, Sialk...
 
PMFBY , Pradhan Mantri Fasal bima yojna
PMFBY , Pradhan Mantri  Fasal bima yojnaPMFBY , Pradhan Mantri  Fasal bima yojna
PMFBY , Pradhan Mantri Fasal bima yojna
 
Bladex 1Q24 Earning Results Presentation
Bladex 1Q24 Earning Results PresentationBladex 1Q24 Earning Results Presentation
Bladex 1Q24 Earning Results Presentation
 
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACT
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACTGOODSANDSERVICETAX IN INDIAN ECONOMY IMPACT
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACT
 
2024 Q1 Crypto Industry Report | CoinGecko
2024 Q1 Crypto Industry Report | CoinGecko2024 Q1 Crypto Industry Report | CoinGecko
2024 Q1 Crypto Industry Report | CoinGecko
 
Stock Market Brief Deck FOR 4/17 video.pdf
Stock Market Brief Deck FOR 4/17 video.pdfStock Market Brief Deck FOR 4/17 video.pdf
Stock Market Brief Deck FOR 4/17 video.pdf
 
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办
(办理原版一样)QUT毕业证昆士兰科技大学毕业证学位证留信学历认证成绩单补办
 
Classical Theory of Macroeconomics by Adam Smith
Classical Theory of Macroeconomics by Adam SmithClassical Theory of Macroeconomics by Adam Smith
Classical Theory of Macroeconomics by Adam Smith
 
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdf
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdfBPPG response - Options for Defined Benefit schemes - 19Apr24.pdf
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdf
 

Here are some key points to consider for labour mobilisation:- Identify areas where required type/skill of labour is readily available to minimize mobilization time and cost. - Estimate initial cost of mobilization including transportation, advance payment, tools/equipment, accommodation etc. - Arrange for labour contracts and ensure all statutory compliances like registration, insurance, wages as per local laws.- Set up basic facilities like drinking water, temporary shelters, toilets before labour arrival to avoid delays. - Mobilize in phases linked to project schedule to avoid underutilization of labour.- Train labour on safety, quality norms and work processes to start productive work promptly.- Maintain

  • 1. Internal Controls at the Construction Site 7th Jan, 2012, Hotel Inder Residency, Ellisbridge, Ahmedabad From To Topic 10.00 am 10.25 am Registration and Breakfast 10.25 am 10.30 am MOC Overview and Relevance of Internal Controls at the Construction Site and Role of a Project Manager Statutory Compliances required at the 10.30 am 12.00 am Construction Site under Labour Laws / VAT Laws / Other local requirements Control Points for Various Equipments like Transit Miller / Batching Plant / Concrete Pump / Crane / Excavator Understanding of Material & Labour Procurement Related 12.15 pm 1.30 pm Controls required at the Construction Site 01.30 pm 02.00 am Lunch HR Related Controls - Labour Colony / Mess / Attendance / Vehicle Management Stores Related Controls - Material Issue / Receipt / 02.00 pm 03.30 pm Reconciliation Methods / Physical Verification Plan 03.30 pm 03.45 pm Tea Break Basics of MIS Preparation for various Departments - Engineering / Stores / Accounts / HR / Safety Role of Site Accounts and Co-ordination with Head Office 03.45 pm 05.15 pm info@consultconstruction.com www.consultconstruction.com
  • 2. Overview and Relevance of Internal Controls at the Construction Site and Role of a Project Manager Tendering  Budgeting  Site Mobilisation  Role of a Project Manager  Role of a Billing Engineer  Material Reconciliation  Project Completion  Release of Retention Money info@consultconstruction.com www.consultconstruction.com
  • 4. Lets see how to approach the job Of :- • Study of Tender Terms • Planning – Budgets, Funds, Project Timeline through PERT, CPM • Lining up various functions • Engineering • Stores • HR • Accounts • Safety and Quality info@consultconstruction.com www.consultconstruction.com
  • 5. Understanding the conditions of the tender S. Details sought for Catch N 1 Work order Value? Qty Variation not more than 25-30%. Incentive / Penalty (0.5-5%)Clause. 1a Physical visit of the work locations Material Rates / Terrain for Equipments / Labour colony area / Distance from city. 2 FIM - RMC / Cement / Steel? Wastage Norms, Debit Rates, Location of Client Stores (From Loading / Unloading perspective) 3 Work completion period Subject to drawings, front, resources 4 Facilities from the Client - Labour colony, Land, Power & Free or Chargeable. Single / Multiple point Water supply. at site / At Labour Colony Mobilisation Advance and Time Limit % given and recovery rate 5 Adhoc Payment against uncertified bills (75%) and Strict committment from client status of remaining bill. 6 Check whether any prescribed format for client bill? Compliance with local laws 7 Whether the job is new or left over one? Investigation required if it’s a left over job – Impact of Margins 8 Safety / Quality Norms info@consultconstruction.com on Time and Money Impact Formatting system of FQP www.consultconstruction.com
  • 6. Cont... S.N Details sought for Catch 9 What are the requirements with each RA bill? Third Party Physical Certification Reconciliation Statement of FIM 10 What are the rates of principal items (like Higher Margin in items to be executed Excavation, RMC supply, Shuttering etc.) first Apart from FIM, what are other items are kept in client scope (e.g. False Ceiling, Roofing, Aluminium Doors and Windows) 11 What deductions shall be made by client from Only those agreed as per WO RA bill 12 Service tax / VAT / WCT extra or inclusive? Exemptions – Paper Work 13 Whether running plant expansion or If in running plant – Scarce area / construction of new plant building? Pollution – Impact on Labour. 15 Internal Logistics Location - Porta Cabin / Client office / Labour Colony / Batching Plant / Store 16 Bank Guarantee Amt / Performance / Time Validity 17 Always cry in front of the client, don’t give any inputs about high margin items 18 Statutory Compliance Insurance / PF / CAR - Who’s scope? So proper Site Investigation Reports needs to be prepared at Tender Stage info@consultconstruction.com www.consultconstruction.com
  • 7. You have received a tender from the Client / consultant M/s XYZ for making a 500 MW Thermal Power Plant in Gujarat. info@consultconstruction.com www.consultconstruction.com
  • 9. • Lets now come back to Planning info@consultconstruction.com www.consultconstruction.com
  • 11. • Cost Oriented Planning – Convincing the EIC to prepare the Budgets is the biggest task. Because the forces are so dynamic, actual scenario is expected to be different from the work orders, hence he is not in a position to do so. Most of the times he would argue that because of delay in submission of drawings by the client, planning is not very easy. But to meet the Project Deadline / it is in the best interests of the client to break the work order quantities into monthly quantities. Further an overall cap is required to be kept on the total quantities to be consumed for the project. Monthly requirements can then be prepared on the basis of monthly budgets. info@consultconstruction.com www.consultconstruction.com
  • 12. Congrats! You have got a work order from M/s XYZ Cement & Steel in the state of shall be FIM Gujarat. You have to mobilise 500 Value of the labourers in job is 20 Days from Rs.100cr today. Time deadline is 15 Months info@consultconstruction.com www.consultconstruction.com
  • 13. • Manual for Compliance Verification – Whenever a new site is about to begin:- info@consultconstruction.com www.consultconstruction.com
  • 14. Budgeting • Lets see a sample budget … info@consultconstruction.com www.consultconstruction.com
  • 15. Different types of contracts – Item rate – Lumpsum contract – Cost-plus contract – Turnkey contract – engineering, inspections, erection, electrical. info@consultconstruction.com www.consultconstruction.com
  • 16. [Mobilisation and Role of Engg Dept] info@consultconstruction.com www.consultconstruction.com
  • 17. Mobilisation Checklist • Statutory registration numbers / Good Local consultants • Resource Mobilisation – Equipments – JCB & Loader, Batching plant capacity, Miller, Crane, etc. – Vehicles – Staff Bus, Sumo, Utility, Trailer, Tractor & Dumper, Bike etc. – IT – Computers/Printer/Scanner/Copier/Internet/Telecom Network – Functional Heads – PM / Store / HR / Accounts – Office Stationery – Reports / Registers / Blank Slips – From client – Power / FIM / Drawings / Work Front • Staff Accomodation / Mess / Guest House • Onsite office set up • Lining up the labour • Logistics – Movement to site from various locations • Local Survey – Materials and Services info@consultconstruction.com www.consultconstruction.com
  • 18. Labour mobilisation Issues • Special Points to be kept in mind for labour mobilisation – Areas where labour is available – Initial cost of mobilisation – Stay Arrangements – Facilities offered by competitors – Watch for the sudden movement of labour info@consultconstruction.com www.consultconstruction.com
  • 19. • The site is now mobilised and you have to commence the work. info@consultconstruction.com www.consultconstruction.com
  • 20. Role of Project Manager – Work Planning Daily / Weekly / Monthly: When we plan for work – we need to keep in mind client priority, availability of resources, availability of drawing & front, weather, Funds etc. – Pre planning for FIM / Own Material: Pre planning (system and procedure) is required for FIM and Own material so as to make it available in time. – Complete responsibility to ensure compliance of the functions by all the Dept.: Engineering, HR & Admin, Stores, Accounts – Sub Contractor Work Order: Sub Contractor work order should be prepared on time with their acceptance. – Timely submission of bills with due verification from QSD at HO, if any . If delay reasons need to be submitted to HO. – Subcontractor bills are prepared in due time and are paid after pre-audit at HO. info@consultconstruction.com www.consultconstruction.com
  • 21. Role of Project Manager – cont… – Understanding of Site Performance both in terms of actual execution and profitability and submitting regular MIS to head office. – Ensuring proper back up in case if any employee leaves the organization. – Weekly meetings with the Core team and ensuring due preparation of minutes for mailing the same to Head office. – Checking all the records fortnightly viz. stores inflow, outflow, vehicle logbooks, and HR records. – To focus on all areas where chances of cost overrun exist by ensuring regular monitoring. – Maintaining employee morale under all situations. info@consultconstruction.com www.consultconstruction.com
  • 22. Reconciliation – FIM & Principal Material • Standard Consumption norms to be defined for every item in the WO. For e.g. – For 1 CUM of M20 - concrete production – Cement – 140 Kg, Sand – 875 Kgs, Agg – 1100 Kgs • Physical verification of Steel, Sand and Aggregate on the same day on which reco is prepared. • Material scattered at various locations • Consumption for unbilled extra items to be excluded. • Stock records to be updated regularly. • Shuttering Repetitions. If material consumption levels are found in excess of standards appropriate action needs to be taken for further control and identification of sub-contractor responsible for the same to enforce timely recovery. info@consultconstruction.com www.consultconstruction.com
  • 23. Materials Usage Standard • Theoretical Qty * (1 + Normal Wastage Norms) – Qty is derived from design and drawings – Normal Wastage Norms also change from Project to Project depending on nature of work, method of application – However Wastage from following is not a normal wastage • Using Non-Standard Material • Excess Purchase • Wastage in Transportation • Improper Storage info@consultconstruction.com www.consultconstruction.com
  • 24. Billing Engineer A. Client & Sub Contractor billing and Certification: – Same Billing period for both client & sub contractor • Match the Quantities • Facilitate preparation of MIS • Identification of Extra Items – DPR should be generated. – RA bill preparation on Time as any delay • Affects Fund management • MIS info@consultconstruction.com www.consultconstruction.com
  • 25. Sub Contractor Work Order: Sub Contractor work orders should be prepared: - Item code and language should as per client work order - Project Manager and Project commercial head / Project Director approval signs or mail required. For example: Item As per Item description UOM Rate Code 1234 Client Providing reinforcement including cutting, MT 4500 bending, binding, fixing in position including the cost of channels, bars (Binding Wire is in your scope) FIM or Raw Material shall be provided to contractor for work by Company: 1234-A Contractor Reinforcement Cutting MT 700 1234-B Contractor Reinforcement Bending MT 800 1234-C Contractor Reinforcement Fixing MT 1200 Contractor Total Rate of item code-1234 is ----> MT 2700 info@consultconstruction.com www.consultconstruction.com
  • 26. • Engineering MIS info@consultconstruction.com www.consultconstruction.com
  • 27. [Project Completion] info@consultconstruction.com www.consultconstruction.com
  • 28. Project Completion • Checklist for Project Completion – Final bill preparation and certification – FIM and Raw Material Reconciliation with bill and balance qty. – Fulfillment of client work completion procedure – Receivable & Liability status & Clearance – Statutory compliances – Demobilization – Delayed in project completion – Work completion certificate info@consultconstruction.com www.consultconstruction.com
  • 29. Project Completion – cont…. Final bill preparation and certification: • Cumulative Executed Quantity. • All pending extra item claims should be included, if pending. • Necessary follow up for W.O amendment if Actual Qty > WO Qty. • Release of Qty on Hold for want of various reasons. • Fight for the incentive clause. • If any company asset is given on rental / hire basis to other party as per instruction from client, the same should be claimed in final bill . • If resources like equipment / manpower have remained ideal due to non availability of front, it should be claimed in the final bill. • NOC shall have to be obtained from various departments of the client info@consultconstruction.com www.consultconstruction.com
  • 30. Project Completion – cont…. FIM and Raw Material Reconciliation with bill and balance qty.: Formula: • Total Material Inward • Less: Material Returned / Transferred • Less: Standard Consumption • = Balance Quantity at Site / Store • In case this quantity is not available at site / store, there are following possibilities: – Excess consumption as compared to standard – Theft / Pilferage during the project • In case of excess consumption, some portion can be recovered from measurement contractor if not recovered till date. • Proper justifications are required from project manager and appropriate action should be taken in case of abnormal difference between actual balance and standard balance • Balance FIM material started to returning and take its documents with receiving sign and stamp from client. info@consultconstruction.com www.consultconstruction.com
  • 31. Project Completion – cont…. Fulfillment of client work completion procedure: In case of project completion client have checklist for same so you have to ask same from client and compile each point. Receivable & Liability Status & Clearance: Get status of project liability with break up of nature of creditor and special remark for local creditors. – Follow up for payment receivable from client after bill certification – Clear local liabilities to avoid any demobilization harassment from them. Statutory compliance: Follow up and get pending WCT & TDS receivable certificates from client. – Give all necessary details for VAT return filing to local sales tax consultant and other details, if any required for audit. – Get any pending forms like C & F from the department, also reconcile with the forms issued till date. – Clear o/s local pending liabilities like Road tax, Entry Tax, Employee Professional Tax etc. info@consultconstruction.com www.consultconstruction.com
  • 32. Reasons for Delay in preparation of Final RA Bill S. N. Points Corrective Action 1 Non updation of FIM data with stores. Physical verification of FIM with stores records 2 Reconciliation of FIM Required with each RA Bill 3 Work order Amendment Little foresightedness Strong Followup 4 Change in Project Manager / Billing Engg. Documentation-JMR/BBS/Stores Good Back up at HO Handing over Checklist 5 Proper compilation of Hard and soft copies of all the Data Control and Regular Audit Running Bills 6 Insistence to satisfy requirements of Labour Inspector – Clarity in Work Order Terms If you are under EPC 7 Quality compliance after defect liability You should argue that it is client responsibility 8 Idling Claims depending on locations like Orissa / Record / Emails to client on regular basis Kerela - Local problems 9 Direct Payments by the client Documentary Evidence info@consultconstruction.com www.consultconstruction.com
  • 33. Project Completion – cont…. Work completion certificate: • Don’t forget to collect the work completion certificate from the client Demobilization: • Dehire all types of equipment and machinery. • Make proper plan for shifting of own material to other sites / Central Stores. • Proper plan to shift staff. • Dehire idle camp / mess and do not forget to recover the rent deposit or set off deposit against rent. • Check, get and release Bank Guarantee from client after defect liability period is over Planning - Lalu info@consultconstruction.com www.consultconstruction.com
  • 34. Release of Retention Money • Checklist compliance – Certification of Final bill – Completion of work upto Defect liability period – No local liability – Site and area clearance – Return of all FIM – Premature Release Against Bank Gaurantee Till Defect Liability info@consultconstruction.com www.consultconstruction.com
  • 35. Commercial Procurement i) Goods and ii) Services. info@consultconstruction.com www.consultconstruction.com
  • 36. Normally in a manufacturing set up we divide the material as :- a. Repetitive Items  Raw Materials  Stores b. Non – Repetitive Items  Capital Goods  Major Repairs Primary purpose of classification is to Control:- - Quality - Cost - Timely Supply But how do we classify in the construction sector ? info@consultconstruction.com www.consultconstruction.com
  • 37. The most comonly used classification is ABC Analysis. But prerequisite is that the project should have a standardized bill of materials listing the physical quantities, unit rate and total cost for each item. 1. Identify the material required for the Project 2. Determine Usage Value by multiplying the Qty required and its Unit rate. 3. Calculate the percentage usage value with respect to the total material cost for the project. 4. Arrange the Items in descending order of usage value 5. Give Red Colour till 70% and thereafter Green Colour till 90%. 6. Mark A class for Red Coloured Items / B Class for Green Colour and C Class for the balance. Lets see a small excel sheet on this. info@consultconstruction.com www.consultconstruction.com
  • 38. Use of ABC to Develop Policy Guidelines Policy “A” “B” “C” Consideration Degree of Control Strict Moderate Loose Forecast Accuracy Accurate Approximate Rough Authority of Senior Level Middle Level At Site Ordering Purchases Suppliers to be Maximum 3 to 5 Reliable 2 to 3 Local contacted suppliers Safety Stock Low Moderate Adequate Order Frequency When Required EOQ Bulk Follow up Maximum Moderate When Neccesary Monitoring Weekly Monthly May not be Material required Movement MIS Reports Weekly Monthly Random info@consultconstruction.com www.consultconstruction.com
  • 39. Inventory Planning • The construction material Inventory Plan aims at evolving materials stock-holding levels to meet project execution plan, with minimum investment on inventory. • In typical project from Inventory point of view , we may classify the materials as follows:- info@consultconstruction.com www.consultconstruction.com
  • 40. • Take the case of stocking of cement at the site :- – Site Requirement – 500 Bags / Month for 12 Months – Order Cost – Rs. 500 per order – Carrying Cost – 10% of unit rate – Transport Capacity – 100 Bags – Lead Time – 5 Days – Safety Stock – 100 Bags – Material Life – 2 Months – Unit Rate - Rs. 250 per bag info@consultconstruction.com www.consultconstruction.com
  • 41. • EOQ – 1 / Unit Rate * {Square Root of (2*Order Cost*Unit Rate*Site Requirement/Inventory Carrying Cost)} 1/250 * {Square root of (2*500*250*6000/0.1)} = 500 Bags info@consultconstruction.com www.consultconstruction.com
  • 42. • Reorder Level = – Minimum Stock + (Lead Time * Daily Usage) – 100 + (5 * 20) – 200 Bags info@consultconstruction.com www.consultconstruction.com
  • 43. Commercial Procurement i) Goods cont… Goods:  Define a Purchase Policy  Purchases to be sourced by Head office.  Purchases to be sourced locally with approval from Head office.  Purchases to be sourced locally with the approval from Project Manager.  Material required for Project:  Project Manager to calculate total project material requirement through Bill of Quantity (BOQ).  This would be categorized as FIM , Raw / Principle Material, Consumable / Hardware / Tools Material, Capital goods - Plant / Machinery / Equipment  Monthly Requirement info@consultconstruction.com www.consultconstruction.com
  • 44. Commercial Procurement i) Goods cont…  Placement of Order (PO): - Purchase order being the last document of procurement process, so it is necessary to take care before placing the order.  Certain details which need to be mentioned  Serially numbered  Time & Place of Delivery  Material Quality Description and specifications  UOM  Manufacturing date should be latest and not more than two months in case of certain items like Conplast / Admixture (To get maximum time of its utilization) info@consultconstruction.com www.consultconstruction.com
  • 45. Commercial Procurement i) Goods cont…  Materials Indents:  Authorized person should be allowed to raise an indent. The status about present level of stock should also be given.  Market Survey / Enquiry / Quotation:  Relevant journals, yellow pages, market directories etc.  Company can ask quotation / price list with detailed terms and conditions with its validity from various vendors.  Purchase department can take right decision after comparison and analysis of rate, quality, terms & conditions with price escalation terms and service condition info@consultconstruction.com www.consultconstruction.com
  • 46. Stores Related Controls - Material Issue / Receipt / Reconciliation Methods / Physical Verification Plan At a Construction Site info@consultconstruction.com www.consultconstruction.com
  • 47. Store Team with Experience • Store manpower depends on size of project, volume of material and stock movement and logistics. • For a small site following if the ideal team – Store Incharge 1 = Master Degree / Specialization of store course and 5 years work Experience – Store Assistant 2 = B. Com / 12th passed and 2years work Experience (Material Chaser) – Data Entry 1 = Bachelor / Certified Computer Course degree and 2 years work Experience – Helpers 5 = Material loading & Un loading, Cleaning & maintenance Computer literate with basic knowledge of identification of item, UOM & inward / outward procedures info@consultconstruction.com www.consultconstruction.com
  • 48. Well Defined work Area • Store personnel at Site should not be used for other works like – Sourcing of Vendor – Market survey – Creditor payment – Any other site functions like HR / Admin activity / Cash Mgmt / Taking measurements info@consultconstruction.com www.consultconstruction.com
  • 49. Store Cycle info@consultconstruction.com www.consultconstruction.com
  • 50. Stores Premises • Stores Premises– – GI Sheets / PCC Structure properly covered – Door and Window for Lights & Ventilation – House keeping (cleanliness) – Fire extinguisher – Rack for stacking of material – Weight machine (Capacity least 100kg) – Power connection – Computer system with Printer & UPS – Security guards at various points of store locations across the site info@consultconstruction.com www.consultconstruction.com
  • 51. Setup of Stores • It is suitable for proper control and supervision that stores should be near to • Batching plant, • Steel Yard, • Contractor office • Client store for best logistics • Store Location should have adequate space to facilitate material storage and physical verification. • Also open space near stores is required to park Equipments and Vehicles (JCB, TM, Tractor, etc.) info@consultconstruction.com www.consultconstruction.com
  • 52. Stacking & Labeling • Stacking of Material: - - Material not to be kept directly on ground (1ft above surface) - Rain - Liquid Items should be tightly covered in order to avoid wastage - Cement / Wooden Items need to be covered by Tarpoline for safety against rains - Arrangement on the basis of frequency of usage and in order of priority - Single item to be put at single place instead of multiple locations - Easily countable (Proper policy for Bulk Items) • Safety to be ensured:- - Heavy material on surface / lower height & light weighted material in rack • Label should be affixed on rack on each items with Material code (Additionally item description would be preferable) info@consultconstruction.com www.consultconstruction.com
  • 53. Inventory Level & Local Procurement • Inventory minimum and maximum level should be defined as per monthly Budget quantity, mainly for A Class Items. • Store not to procure the material under normal cases . • All local procurement department after approval from HO and as per defined policy. info@consultconstruction.com www.consultconstruction.com
  • 54. Relationship with supplier • Mgmt to ensure and check from time to time the relationship of store personnel with supplier – – If Frequent visits to supplier premises – Material Inwards to be checked by Site Engineer on Surprise basis – Material Receipt in day time – Quantity should not be left blank in supplier challan info@consultconstruction.com Non-Shrink www.consultconstruction.com
  • 55. Security Agency / Guard • Stores should be backed by security personnel – Deployment of Guards as per requirement with proper uniform, stick, whistle & torch at store in two shifts. – Duty register / Card duly signed by store Incharge – Incident register (In case of theft) – Surprised visit should be carried out by HR incharge, specially during night – Surprised visit report required with monthly bill of external agency. info@consultconstruction.com www.consultconstruction.com
  • 56. Material Inward • I) FIM Material Inward– A) Steel : – Challan should have our indent number / date / quantity with weight slip. – Weight should be carried out at the time of material unloading. – Qty should always be mentioned as per dia and as per no.s and it should be kept dia wise in steel yard. Dia wise steel record and no.s measurement will also help in cross verification of weight as per defined ISI standard – Dia wise record will facilitate FIM reco – Client should inform about the dispatch of FIM in advance info@consultconstruction.com www.consultconstruction.com
  • 57. Material Inward Continue.. B) Cement : (FIM Material) – Inward should be on weight and challan also have quantity in numbers of bag. – Weight should be carried out at the time of unloading (Powder form). – This net weight quantity should be mentioned as received with mention of damaged bags in challan and the same should be conveyed to client / supplier store. – Also in case of rain/fog, if material is received without proper cover, the fact needs to be mentioned on the challan – Store should verify no. of cement bags and ensure proper stacking at time of unloading itself. – Control on Empty bags is required info@consultconstruction.com www.consultconstruction.com
  • 58. Material Inward Continue.. C) RMC (Ready Mix Concrete): (FIM Material) – Client may give RMC instead of cement – Physical received and challan / slip quantity should be the same – Any difference needs to be communicated to the client on a regular basis. This is the case when client has outsourced RMC production. – Further monthly reconciliation should be done to resolve the dispute, if any. – Special Precautions required if multiple agencies are working at the client location. info@consultconstruction.com www.consultconstruction.com
  • 59. Material Inward Continue.. • II) Procured Material Inward: Sand & Aggregate / Boulder & Ruble: – Sand & Aggregate preferably to be purchased on CFT basis. Also advisable in rainy season. – CFT basis material should be measured every time by three point of vehicle and considered average area and this quantity mentioned as received in challan – Boulder / Rubble on MT basis due to voids – These items should be delivered by supplier with proper intimation – Materials would be delivered during day time – Location of Weigh Bridge – In rainy season stock would be store of Sand & Aggregate for any short fall and avoid to pay more cost – Royalty slips info@consultconstruction.com www.consultconstruction.com
  • 60. Material Inward Continue.. • II) Procured Material Inward: – Binding Wire should always be weighed at the time of inward and its thickness should be matched as per order. No. of Bundles should also be mentioned in the challan. – Conplast / Admixture - Inwards with manufacturing & expiry date and number of drum and the same should be visible on each drum – Wooden material: • Plywood = This should be as per specification given in PO like thickness, weight per sheet, regular or water proof, size, qty. in numbers and sq.ft. • Batten = Batten size should be as per specification of PO like thickness & length, Abnormal damage & short length pieces should not be allowed and the qty should be mentioned in CFT in challan info@consultconstruction.com www.consultconstruction.com
  • 61. Material Inward Continue.. • III) Returnable Material Entry: • If any material, equipment or items are to be sent out, client procedure and documents should be followed with all records to avoid any delay in project completion. – Material entry gate pass – Inward stamp with date and time and sign of authorized – Material description with quantity etc.. • Any improper inward could prove costly for the company in future. info@consultconstruction.com www.consultconstruction.com
  • 62. Material Inward Continue.. IV) Loan Transaction: • This happens, where more than one contractor work in the same client premises. – This type of transactions should be done by site Project Manager in emergency case only and with approval from his higher authority. – This is returnable basis so the same should not be outstanding for more than specified days and should not be a routine practise. – Quantitative document should be generated and kept in record info@consultconstruction.com www.consultconstruction.com
  • 63. Material Inward Continue.. • V) Basic documents at the time of Material Inward : – Documents - Challan / Packing list / Inter-site Transfer Memo / Excise Gate pass / LR / Weight slip / Royalty Challan / Test certificates / PO copy or PO references / Tax Invoice / Statutory forms (If any). – Authorized sign required if overwriting available. – Mention of Short quantity & unmatched specification – Material inward stamp & Entry in material inward register / system & Unique inward number on documents – No material shall be dumped without pre intimation to store and presence of store person. – Rejection Policy info@consultconstruction.com www.consultconstruction.com
  • 64. Material Outward • Codification of materials • Divide the materials into Capital Goods / Construction Materials / Consumables and Tools. • Codes as per class of material. • Material Issue Slip – Duplicate – Authorised from Site Engg. – Basis of Computer Entry – Watch on Missing serial numbers • Steel, Sand, Agg., etc consumption entry should atleast be passed as per RA Bills certified quantity. • In case of emergency /break down of batching plant if RMC procured from other sources, then FIM Cement can be issued to supplier and rate should be excluding cement. • Returnable register to be kept separately. Material required in same form from receiver • Computer System to have Alternate UOM provision – E.g. Wooden Items, Sand, Aggregate. • Free And Chargeable Materials List with stores. info@consultconstruction.com www.consultconstruction.com
  • 65. Non Moving material • Store should not allow those material which are not required or • excess quantity compare to required at site • Disadvantage of non movement items – – Staff engagment – Cost of logistics & Inventory carrying cost – Space usage of store – Problem to Handling / Take care info@consultconstruction.com www.consultconstruction.com
  • 66. Site visit by Store personal • Store personal should visit site on every day for following purposes: – Idle material – Damage & Scattered material – Ensure that no material is lying in mud or in excavated holes, before back filing (Especially scaffolding material like coupler, pipes & shuttering plate etc..) Lemon info@consultconstruction.com www.consultconstruction.com
  • 67. Physical Stock Verification • Compliance to • A Class routine audit verification every queries. quarter and • System report • other categories should not contain every six months. any negative items. • System report System Print should be clear like A-B-C Bills received but after Updated Identification goods not received Data entry. Ensure that material Physical count movement is challenges restricted before taking • Scaffolding / physical stock. Shuttering – • Proper Stacking Rough Idea and labelling • Steel, Sand, Agg – Expert estimate • Multiple locations info@consultconstruction.com www.consultconstruction.com
  • 68. Control over Fuel Consumption Following points need to be taken care for Equipments - JCB, Miller, and Crane / Vehicles:- • Store should have resources like – – Fuel pipe, Filter & pump to fill fuel from one to another can, – Two standard size Barrels of 200Ltrs capacity, – Fuel small Can of 1ltr, 5Lts, 10Ltrs – Scale to measure balance stock of fuel (Rod) • Lock and key - Fuel tank • All vehicle and equipment Meters should be in working condition. • MRN containing authorisation from Project Manager & HR Incharge for fuel issue with vehicle & equipment number. • Physical meter reading should be verified and mentioned in log sheet at time of fuel issue. • If vehicle permanently work at single location, name of location is compulsory. • Vehicle Report - MIS. • Tracking fuel given on chargeable / Free issue basis. info@consultconstruction.com www.consultconstruction.com
  • 69. BTN • Whether such system exists at the client place info@consultconstruction.com www.consultconstruction.com
  • 70. Other Areas - Scrap Yard Items in Scrap yard should be properly segregated as per nature and length to enable re- use. Frequent Disposal of scrap Items required. Distribution of Scrap wood amongst labour info@consultconstruction.com www.consultconstruction.com
  • 71. MIS • MIS report, its format and period should be defined. Following reports required fom store: – Material Movement for the period – Intersite Material Movement – Fuel Transaction report with party wise – Safety material movement – Chargeable Material / Debit Note – RMC Production & Principle items consumption – Physical Stock – Non Moving Material info@consultconstruction.com www.consultconstruction.com
  • 72. Human Resource info@consultconstruction.com www.consultconstruction.com
  • 73. HR Related Controls - Labour Colony / Mess / Attendance / Vehicle Management info@consultconstruction.com www.consultconstruction.com
  • 74. • Sub – Contractor Management – Sub-contractor Data bank on the basis of skill set and past performance. – Incentive scheme for time bound completion info@consultconstruction.com www.consultconstruction.com
  • 75. Human Resource – cont…. Master Details of Sub Contractor: • Two passport size color photograph • Name with firm name • Copy of PAN card without which TDS liability shall be @ 20% in place of regular rate • Identity poof • Address proof (Election Card, Latest light bill or Panchayat certified letter) • Communication details (Like, Landline / mobile with contact person & Fax number, mail ID, Web site) • Bank name, Branch address, Account type, Account number and RTGS No., cancelled cheque or declaration letter from the bank • Specimen signature of authorized person in absence of the main sub contractor . info@consultconstruction.com www.consultconstruction.com
  • 76. Human Resource – cont…. Labour Over time: There should be proper system to record the duty hours in the labour card:- • Contractor name and labour name • In time and out time • Company supervisor sign for allowing OT who shall also be responsible to reply why OT was allowed. • Track of supervisor sanctioning highest OT • Labour / sub contractor sign is required Daily report & Control – Labour: • HO must ask for manpower report and work progress report from Site on a daily basis to assess the work performance. info@consultconstruction.com www.consultconstruction.com
  • 77. Human Resource – cont…. Gate Pass (GP) / Entry Card: • Company must issue Gate Pass (GP) / Entry card for control and security purpose to sub contractors and all employees and labours. The same can be cross checked with daily manpower report to catch discrepancy if any. • Following details are required in the gate pass: – Unique serial number and area / Period wise color if any – Name of labour – Sub Contractor name – Type of skill (Helper, Carpenter, Mason, Fitter) – Date of GP issued and validity (Validity would be three months) – Blood Group – Color photograph through Web cam and color printer – Company may charge some nominal amount for GP – Sign required of HR and sub contractor on Gate Pass – HR should have details of gate passes issued in the manual register where GP receiver sign is required. HR should have GP wise status (Active, Cancel, Expired) – Penalty should be charged If Gate pass is lost, expired but not renewed or not returned at time of leaving the job – All Gate Passes should be destroyed which have been returned by workers / sub contractors after proper entry in manual register or system info@consultconstruction.com www.consultconstruction.com
  • 78. Human Resource – cont…. PF Records and Liability payment: • If the sub-contractor is well organized, then he can pay PF and keep proper records and just deliver paid challan with its break up for your record. • But where Sub contractor is unorganized, it is necessary to get sub contractor wise wages sheet to calculate PF liability and pay. Labour Colony / Water & Power supply: • Labours are asset for the company and it should take care of their basic needs. • This should be the responsibility of HRD – to visit labour colony at fixed interval to find out if their living conditions are proper – Basic aspects like PCC in flooring of room, – Drinking & routine use Water, – proper toilets and bath rooms, – power supply, cleaning around labour colony to ensure it hygienic, monthly medical check up etc. This will result in improved performance in the labour output. info@consultconstruction.com www.consultconstruction.com
  • 79. Human Resource – cont…. – Employees Salary Structure & Letter of Appointment: • Salary Structure: Say – Basic – 40% of total salary – Other Allowances 60% of total Salary, like: • HRA Allowance • Uniform • PF • Bonus • Medical Allowance or Group Mediclaim policy • Transportation Allowance • Telephone / Conveyance Reimbursement • Child Allowance • Education Allowance – Deductions: • PF employee contribution – 12% of Basic • Professional Tax – Employee, as per salary slab • Tax Deduction at Source (TDS) as per Government rules on taxable salary • Staff Welfare Fund as per Government rules • If any bond amount decided, to deduct from salary on monthly basis info@consultconstruction.com www.consultconstruction.com
  • 80. Human Resource – cont…. • Master Form - Employee: • Branch / Site Transfer Letter: – Salary Structure – O/s Advances and Loans – o/s Salary Dues with present days of last working days at previous site info@consultconstruction.com www.consultconstruction.com
  • 81. Human Resource – cont…. Daily Attendance - Staff: • Daily attendance can be marked by manual records like - Register or Daily Sheet or Card or by Auto systems like Punch card, Thumb or Finger impression or based on any other online software, Over Time: • There should be well structured Policy to regulate and monitor the over time payment. • There are two options to maintain OT records – a) Out time to be mentioned in Daily manual attendance sheet – b) Separate Sheet to be maintained for OT HR needs to take sign from Project Manager on daily OT sheet or Daily attendance sheet. At the end of the month, OT hours shall be calculated on the basis of this record. info@consultconstruction.com www.consultconstruction.com
  • 82. Human Resource – cont…. Leave Policy: • Leave policy needs to be defined – Various types of leave and their number – Carry forward or lapse in the year end – Encashment – Maximum accumulation etc. Further employee needs to fill a leave application form containing following details: • Leave application vs. Daily / Monthly Attendance sheet • Leave period and number of days • Applicant signature required on form • Approving authority depending on number of days leave applied • Leave utilized mentioning clearly against which category (i.e. Paid Leave - PL, Casual Leave - CL & Sick Leave - SL) on application • Status of leave balance category wise as per rules • To avoid misuse of sick leave, medical certificate must be required on return from leave if the leave is more than say one or two days • Absent should be marked for extension of leave beyond sanctioned • HR should verify perfectly about leave balance before action on application info@consultconstruction.com www.consultconstruction.com
  • 83. Human Resource – cont…. • Hired Camp – Lease Agreement – Distance from the Site – Proper Planning to avoid Hotel Expenditure • Mess - Staff: – Self vs Contracted – Fixed Payment to employees – Policy should also be defined for other facilities of stay and in house entertainment by way of TV, reading materials, sports and club activities etc. • Group Employee Health Insurance Policy: – HRD needs to evaluate group medical policy v/s medical allowance. It is advisable to go for mediclaim Insurance for which policy should be well defined. – Accordingly all concerned employees and officers should be covered as per policy which should be taken from General Insurance Company with full negotiation. – There should be one officer in charge for claim settlement in time so as to get the benefit of the Insurance. info@consultconstruction.com www.consultconstruction.com
  • 84. Human Resource – cont…. • Vehicle Report • Admin Assets & Control • Laptop • Data Card • CUG Mobile connections – SIM card • Mobile Instrument • Camp / Guest House & Mess, Vehicles, Equipment etc. HR should have master data of details of all admin assets and this should be updated on regular basis (Monthly / Quarterly / Half yearly) like – Name of asset – Asset user name – Location – Insurance period and Service provider, if applicable • Company can take undertaking from employee against asset given for use. There should be well designed policy in place about entitlement to regulate the use of such assets. info@consultconstruction.com www.consultconstruction.com
  • 85. Human Resource – cont…. • HR – MIS Level of Perfection info@consultconstruction.com www.consultconstruction.com
  • 86. Statutory Compliances required at the Construction Site  Labour Law Requirements  Labour License – Minimum Wages  PF / ESI  Workmen Compensation  Worker’s cess Minimum Wages  Professional Tax  VAT Provisions Documentary Requirements  Difference between VAT and WCT  What is Entry Tax?  Check Post Related Issues  CST Provisions  Service Tax Provisions info@consultconstruction.com www.consultconstruction.com
  • 87. Labour License • Two authorities to be approached – Centre / State • Any unit belongs to Central Govt, then license to applied to Central Government • Form No. 4 to be applied for before commencement of work. • It is applicable on client to client basis. • After Initial Declaration, there is a provision to increase the number, but no provision to decrease. • Security Deposit for Gujarat Govt is Rs. 270/- per worker and Centre is Rs. 90/- per worker. • On completion of work – Taken Work Compl. Cert from Client and submit to License Authority info@consultconstruction.com www.consultconstruction.com
  • 88. EPF Act • Applicability i) Every establishment in which 20 or more persons are employed and • But Across India, there is only one EPF Number. For ease of administration you may ask for a sub- code. • No. of Labour on which EPF is paid should not be more than sanction as per Labour License info@consultconstruction.com www.consultconstruction.com
  • 89. Eligibility • Any person who is employed for work of an establishment or employed through contractor in or in connection with the work of an establishment. • Basic Salary more than Rs. 6,500/- not covered. info@consultconstruction.com www.consultconstruction.com
  • 90. ESI Act • provides for certain benefits to employees in case of sickness, maternity and employment injury. • It applies to all factories (including Government factories but excluding seasonal factories) employing ten or more persons and carrying on a manufacturing process with the aid of power or employing 20 or more persons and carrying on a manufacturing process without the aid of power info@consultconstruction.com www.consultconstruction.com
  • 91. Coverage and contribution • The existing wage-limit for coverage under the Act, is Rs.15,000/- per month • Currently, the employee’s contribution rate (w.e.f. 1.1.97) is 1.75% of the wages and that of employer’s is 4.75% of the wages paid/payable in respect of the employees in every wage period info@consultconstruction.com www.consultconstruction.com
  • 92. • Construction Sites – ESI does not apply • But Insurance by way of WC Policy is advisable. info@consultconstruction.com www.consultconstruction.com
  • 93. Workmen’s compensation Act, 1923 • The Workmen’s Compensation Act, aims to provide workmen and/or their dependents some relief in case of accidents arising out of and in the course of employment and causing either death or disablement of workmen. • It provides for payment by certain classes of employers to their workmen compensation for injury by accident. info@consultconstruction.com www.consultconstruction.com
  • 94. Employer’s liability • The employer of any establishment covered under this Act, is required to compensate an employee : • Who has suffered an accident arising out of and in the course of his employment, resulting into (i) death, (ii) permanent total disablement, (iii) permanent partial disablement, or (iv) temporary disablement whether total or partial, or Who has contracted an occupational disease info@consultconstruction.com www.consultconstruction.com
  • 95. THE EMPLOYER SHALL NOT BE LIABLE • In respect of any injury which does not result in the total or partial disablement of the workmen for a period not exceeding three days; • In respect of any injury not resulting in death, caused by an accident which is directly attributable to- – Place of occurrence is outside site premises and not in connection with the works Further two more issues need to be kept in mind subject to certification from the authority – the workmen having been at the time thereof under the influence or drugs, or – the willful disobedience of the workman to an order expressly given, or to a rule expressly framed, for the purpose of securing the safety of workmen info@consultconstruction.com www.consultconstruction.com
  • 96. Building and Other Construction Workers' Welfare Cess Act,1996 LEVY AND COLLECTION OF CESS. - (1) There shall be levied and collected a cess for the purposes of the Building and Other Construction Workers' (Regulation of Employment and Conditions of Service) Act, 1996, at such rate not exceeding two per cent but not less than one per cent of the cost of construction incurred by an employer It is applicable to all contractors – working for state or for private sector. Enforcement in the private sector is very poor. info@consultconstruction.com www.consultconstruction.com
  • 97. Minimum wages Act, 1948 • Wages for Centre ( –or • Wages for State (Unskilled – Rs. 135.40) • Whichever is higher • Every 6 Months, the govt declares special allowance which needs to be added • Same Rate for Male and Female info@consultconstruction.com www.consultconstruction.com
  • 98. Professional Tax • Corporation Level Subject • Registration required for all the branches • Whether Construction Site is a Branch? • Payroll Generated from Head office • For Casual Workers the provision does not apply info@consultconstruction.com www.consultconstruction.com
  • 99. Shop and Establishment • Does not apply to construction site • But it applies to establishment info@consultconstruction.com www.consultconstruction.com
  • 100. VAT • Composition • Format of Invoice / Charge of Taxation • Input Tax Credit • Check Post Related Issues • TDS • Forms from Department • Inter-State Movement info@consultconstruction.com www.consultconstruction.com
  • 101. Types of composition • For complete contract – within 30 days of commencement of Work • For Complete year – Application within 30 days before to commencement of year • For New Registered Dealer – Within 90 Days from the effective date of registration No condonation of delay – Matter Pending before Tribunal Non receipt is assumed as granted info@consultconstruction.com www.consultconstruction.com
  • 102. Format of Invoice • Under Composition • Retail Invoice • Tax Invoice info@consultconstruction.com www.consultconstruction.com
  • 103. VAT – Input Tax Credit • ITC available on all inputs used in works contract other than composition method subject to fulfilment of conditions • Broad Restrictions on ITC: ‒ CST purchases ‒ Capital goods used in works contract – Some of the States ‒ Lease goods ‒ Goods purchased from Lump sum dealer ‒ Goods not connected with business ‒ Vehicles, equipments, accessories or spare parts ‒ Fuel used in motor vehicles ‒ Goods used as fuel in generation of electrical energy info@consultconstruction.com www.consultconstruction.com
  • 104. Entry Tax related issues under VAT Inward Movement 1. Cement / Raw Steel / Motor Vehicle are liable to entry tax. 2. Authenticated Form 403 is required. 3. Invoice / delivery challan / LR to be made available at checkpost 4. For normal Items, Form 403 without authentication is required. 5. Scaffolding Pipes are not covered. Outward Movement 1. Branch Transfers – Work Order / Declaration Form / Form 402. 2. Relevance of F Form – Ambika Steel. 3. Having registration / Work order from other state. Any checkpost related issues ? info@consultconstruction.com www.consultconstruction.com
  • 105. C Form / Way Bill / Entry Tax • Transfer of materials from one state to another. • Multi State VAT Compliance info@consultconstruction.com www.consultconstruction.com
  • 106. TDS Rate under GVAT Person responsible for payment exceeding Rupees 1 crore for works contract is responsible for deduction of tax at prescribed rates TDS Rate : 0.6% in case of construction contract and 2% in case of others Works Contractor is mandatorily required to obtain TDN No. from Commercial Tax Department. Application in Form 706 to get TDN No. within 30 days of agreement. TDS to be claimed in the year in which same is deducted and not in which the same is ? paid. Form 702 under Gujarat VAT to be attached with Invoice for lesser deduction. info@consultconstruction.com www.consultconstruction.com
  • 107. Inter-State Movement of Material • Movement of Raw Material • Movement of Finished Goods • Use in Works Contract • Payment of CST / VAT info@consultconstruction.com www.consultconstruction.com
  • 108. Service Tax • Concept of Centralised Registration • Method to be opted • Cenvat Credit • Invoice Related Issues • Service Tax vs VAT • Point of Taxation Smart CA info@consultconstruction.com www.consultconstruction.com
  • 110. Control Points for Equipments Own vs Hire  Transit Miller  Scaffolding Pipes  Batching Plant  Shuttering Material  Concrete Pump  Walkway Jali  Crane  Clamps  Excavator  Other support structures  Tractor Trolley info@consultconstruction.com www.consultconstruction.com
  • 111. Commercial Procurement i) Services Equipment / Machinery / Plant / Tools provide by Client: • Condition of equipment – Third party can be appointed • Maintenance scope • Operation of Equipment • Round the clock Availability • Advisable to clear the commercial aspects for supplies beyond the scope as this might result in recovery from the contractor. • Transportation point for FIM & Transit risk within the site. info@consultconstruction.com www.consultconstruction.com
  • 112. Equipments - Purchased Advantages of buying - • No dependence on others. • Company’s status & capacity as a contractor will be rated high . • Equipment can be moved from place to place as per requirement. • Bigger jobs can be obtained. Disadvantages of buying – • Working capital gets blocked. • Repayment in time is big a responsibility. • Resell value shall be negligible in case the same is not required • Maintenance cost and expertise will be required to run the equipment smoothly. info@consultconstruction.com www.consultconstruction.com
  • 113. Equipment - Hired Hiring Agreement: The user pays fixed hire charges on daily or monthly basis as long as the equipment is held by him, • Hire the equipment & machinery • Minimum average commitment required in case of Vehicle and equipment & machinery • Rate should be on hours basis excluding lunch / dinner hours to avoid OT over head. Advantages - • Need not to invest the FUND • Claim as expense for Income Tax purpose • If service, maintenance and operational cost is in supplier scope, no any handling issue and cost and that means peace of mind • In case of business close down, no headache except to return the equipment Disadvantages - • Company totally dependent on others • Hired equipment does not enhance company’s status • In case of under utilization, it will result in big loss • Company will depend for Service / repair & maintenance on supplier • Without supplier’s permission, equipment can not be moved to other site info@consultconstruction.com www.consultconstruction.com
  • 114. Buying or Hiring • Buy – Value * 4 Times should be the turnover. • Future Planning – Residential / Commercial / Industrial / Power • Debt : Equity ratio should not be more than 2:1. • Buy – Own O&M Team, Driver info@consultconstruction.com www.consultconstruction.com
  • 115. Cost of owning an Equipment • Depreciation • Cost of Capital • Equipment Operating Cost info@consultconstruction.com www.consultconstruction.com
  • 116. Hired Equipment Controls • Equipment Chart info@consultconstruction.com www.consultconstruction.com
  • 117. Transit Mixture on Hire Equipment control points in case of Hired: Transit Mixture • 1 Make, Size / Capacity & other specification if any Example: a) Make - Schwing Setter, b) Capacity - 6 M3, • 2 Age of equipment In Good working condition and less than 5years • 3 Team - Qualified Operator / Driver, Crew member & Maintenance team Team: Qualified Operator / Driver - 1, Helper - 1 & Mechanic for Maintenance - 2 info@consultconstruction.com www.consultconstruction.com
  • 118. Transit Mixture on Hire • 4 Testing / Calibration / Commission certificate - Required from third party whose Govt. approved person / agency? No, But Water Pump should be in working condition with water tank. • 5 Insurance of Equipment / Chassis / Vehicle / Operational team & Third party YES • 6 Guidelines / Manual for user with Equipment YES, Optional info@consultconstruction.com www.consultconstruction.com
  • 119. Transit Mixture on Hire • 7 Self certified photocopies of RTO documents of Equipment YES • 8 GPS System Recommendatory, However required if more than two millers at the site with wide area. • 9 Equipment with Basic things Hours & Kms meters in working condition, Proper number Plate / identification mark, Front, Break lights in working condition with Mirrors, night radium plate / colors, First aid, Tools & tackles info@consultconstruction.com www.consultconstruction.com
  • 120. Transit Mixture on Hire • 10 Minimum Expected Output per month Needs to be decided for each and every project - Suggestible Qty - 2000 CUM • 11 Hiring approx. amount. Monthly Basis - Rs.1.25 Lacs (Excluding Fuel) • 12 Minimum Working Duration in a month Flexible 260hrs in a month (Note 3) • 13 Fuel & Power, Oil & Lubricants a) Its advisable to ask the supplier to quote his rate with Fuel. Oil and Lubricant should always be in supplier scope. b) If fuel is in our scope then avg consumption norms may be fixed. Fuel consumption per hour as per site experience. info@consultconstruction.com www.consultconstruction.com
  • 121. Transit Mixture on Hire • 14 Daily Log Book / Records Supplier to maintain daily log book / records with sign of both - operator and Company authorized person. • 15 Lock & key & Daily Records custody? If fuel is in the scope of company, Fuel Tank Key and Records should lie with the company. info@consultconstruction.com www.consultconstruction.com
  • 122. Transit Mixture on Hire • 16 Minimum Output performance clause of equipment Depends on batching plant setup & destination of structure. For e.g. 18 M3 casting per hour If TM takes 20min for one trip. Then 3 trips in one hour = 6 M3 per TM x 3 trip in one hour. 17 Attendance The operating team should be available at the site during the working days. The bill shall be reduced proportionately in case of absence. (Monthly Billing Amt / 26 * Absent Days). 18 Overtime clause OT shall start after expiry of flexible hours limit in the month and shall be calculated on pro rata basis (Monthly Rate / 260 Hours). info@consultconstruction.com www.consultconstruction.com
  • 123. Transit Mixture on Hire • 19 Incentive clause Volume based and other points like - lower break down, Safety during the work etc. • 20 Equipment maintenance / Break down clause Permission for maintenance on any 4 half days in a month or as and when it is free after discussion with site PM. • 21 Staff / Team Accommodation & Fooding clause Staff / team accommodation shall be provided by us But Food shall be in your scope • 22 De Hiring Notice Period 7days on both sides to avoid any dispute. info@consultconstruction.com www.consultconstruction.com
  • 124. Transit Mixture on Hire • III ) Billing & Payment: 23 Mobilization & Demobilization clause a) Mobilization = i) Within 10days from date of WO (mail or hardcopy) with all required resources. ii) One month mobilization advance to be recovered in six equal monthly installment. b) De Mob. Cost = If Contract is more than six months than in lessor's scope. 24 Billing & Certification cycle info@consultconstruction.com www.consultconstruction.com
  • 125. Transit Mixture on Hire • 24 Bill Submission = Billing on monthly basis. to site PM within 5days of previous month with sign, stamp & inward date from company. In case of failure to get inward stamp or received sign, Accounts shall not accept the same. b) Bill / Supporting = Main bill in triplicate copy with company name, address & site, WO number, Bill date, period, name & make of equipment. All statutory numbers, break up of taxes, OT with proper calculation, incentive if any. Original Log sheet (Duplicate copy must for your records). info@consultconstruction.com www.consultconstruction.com
  • 126. Transit Mixture on Hire c) Bill Certification = Bill shall certified within a week from the date of invoice / inward with stamp and authorized sign & name by company. 25 Payment cycle Payment shall be made within 20days from the date of bill certification 26 Debit / Recovery clause in case of break down or non performance / Any other damage Normally at time of certification or separately if issued by any other department or client for any non-compliance. 27 Local / RTO tax in scope of supplier All statutory (local / RTO etc.) liabilities in your scope, inclusive of rate. Service tax shall be paid extra. 28 TDS & any other Statutory deduction if any TDS or any other statutory deductions as applicable shall be deducted. D) Safety: 29 Clearance and data for Gate / Entry Pass Requirement of the principal client may be mentioned here. 30 Safety rules & regulation, violence & Penalty Requirement of the principal client may be mentioned here with the penal clauses, if any. IV ) Legal: 31 Clause - Child labour Strict Compliance 32 Clause - Termination of Contract In case of non compliance of any condition and delay in work performance, contract shall be terminated immediately without any cost. 33 Jurisdiction Jurisdiction is Ahmedabad only info@consultconstruction.com www.consultconstruction.com
  • 127. Role of Site Accounts and Co-ordination with Head Office Changing Def’n - Democracy info@consultconstruction.com www.consultconstruction.com
  • 128. Model of Accounting – Branch / Centralized • The model most prevalent, provided you have good team of accountants with you is the HO and Branch Model. • Branches maintain accounts at the construction site itself. Because if we have a smart accountant at the site that would serve as the best internal control measure. • Integration of accounts and Inventory would then be possible. • Complexity involved is you then need a perfect co-ordination between HO and Branches. Reconciliation between the two is required on a regular basis. As many a times HO would directly be making payment to Branch’s creditors without routing the same through the branch. • In case of centralised accounting the certification systems have to be perfect. You would need all the documents to be certified by the Site Incharge and respective area incharge before booking the same in accounts. info@consultconstruction.com www.consultconstruction.com
  • 129. Role of Site Accounts • Preparation of cash vouchers and entry into the system. • Maintaining Bank book with not more than one day transaction lag. • Documentation of purchase bills after comparison with P.O and entry into the system. • Entry of subcontractor bills – Co-ordination with the engineering dept. • Working out weekly cash requirements • Entry of debit notes in contractor accounts: - Executory • Debit notes from Stores. • Debit notes from H.R Functions: - • Debit notes from Engineering Dept. • Periodic entry and payment of statutory dues • TDS – self-assessment and monthly payment. • PF – Payment in co-ordination with H.R • Service Tax – Preparation of input credit details info@consultconstruction.com www.consultconstruction.com
  • 130. Role of Site Accounts – cont…. • All vouchers need to be authenticated by the accountant. • Vouchers carrying amount more than Rs.10K need to be authorized by PM. • Comparison of sub-contractor bills with Work orders. • Ensuring that Full and final payments are made to the contractors and employees only after getting a completely filled Work Termination Form. • Making payments against bills only after getting them pre-audited. Control • Ensuring that Subcontractor Master details are available before his first bill is entered in the system. Functions: - • Sending backups to HO on a weekly basis. • Ensuring periodic reconciliations in the following manner :- • Intersite – Reco on a fortnightly basis. • Bank – Reco on a monthly basis. • Supplier – Reco on a monthly basis. info@consultconstruction.com www.consultconstruction.com
  • 131. Role of Site Accounts – cont…. • Preparation of Labour supply bills. • Preparation of documents/letters as required. • Submission of bills to the client. • Sending Original Work orders / LOI / amendments to HO after keeping Administrative copies. • Ensuring original TDS certificates are sent to Head office. Functions : - • Other site Co-ordination. • Monthly profit centre performance reports.- 20 days • Weekly Cash & Bank summaries.- 2 days • Monthly liability statement. – 20 days • Monthly vehicle reports.- 5 days • Report on TDS deduction every month. – 25 days Reporting • Quarterly Service Tax input credit details. – 10 days Functions: - • Pending sub-contractor bills on a fortnightly basis for the previous months duly authenticated by the project manager. – 2 days info@consultconstruction.com www.consultconstruction.com
  • 132. Role of Site Accounts – cont…. • Accounts MIS info@consultconstruction.com www.consultconstruction.com
  • 133. Role of Site Accounts – cont…. • Onsite Integration Model for a Construction Site  Using cloud servers, access can be given to multiple locations without buying any software / hardware.  Stores Material Receipt entry can be passed from the site provided there is a proper internet connectivity.  When the purchase Invoices are received the same are certified by the stores department and the printed MIN is then attached behind the invoices.  Accounts then enters the rates of materials picking up the tracking number. Any deviations are settled by way of Debit / Credit Note.  Materials are then issued by way of Delivery Note to either the client / sub-contractors. info@consultconstruction.com www.consultconstruction.com
  • 134. Payment Advice Format Site :_____________ Date :________________ B) Supplier of Capital D) Rent ( Labour Colony / Room E) Vehicle Hire / Petroleum Sr.No. A) Supplier of Material Goods C) Sub-Contractors / House ) Suppliers 1 Purchase Order Purchase Order Work Order Rent Agreement Log sheet 2 Tax Invoice Tax/Retail Invoice RA Bill L.C. visiting Reports - HR Auth.-Commercial/H.R. Authorization from Authorization from 3 Authorization from Site EIC Project Director Commercial Dept. Authorization from H.R. Authorization from Site Incharge Authorization from Project Authorization from Authorization from Authorization from Commercial Authorization from Project 4 Director Commercial Dept. Project Director Dept. Director Stamp of Quality & Bill Entry in books of accounts Authorization from Commercial Installation from Site Authorization from Site Authorization from Project with Deduction (maintenance 5 Dept. Incharge Incharge Director /spare parts... ) Bill Entry in books of Debit notes receive & accounts with all entered from Stores Stamp of Quality & Qty. deduction (TDS / VAT & (Safety material) & Bill Entry in books of accounts Bill / Voucher / Supporting 6 verification from stores Other) H.R.D. (G.P.'s) with Deduction (TDS ) Proper filing Bill Entry in books of accounts with all Reconciliation of Material Bill / Voucher / deduction (TDS / Bill / Voucher / Supporting Monthly Vehicle Report of 7 against Client Billing Supporting Proper filing Retention ….) Proper filing payment month Bill Entry in books of accounts with all deduction (TDS/VAT & Receive party's Bill / Voucher / 8 Other) Confirmation Statement Supporting Proper filing Supplier master form Supplier master form Receive party's Confirmation Client vs. Subcontractor Authorization from Internal Authorization from Internal 9 Statement with Reco. Status of excise credit Qty. Auditor Auditor Whether Against "C" EIC Performance Report 10 Whether Against "C" Form Form for the site 13 Remarks required if On Account or Advance: - Amount Released info@consultconstruction.com For H. Details of Payment (chq no. etc.) www.consultconstruction.com O. use Remarks
  • 135. Banking – Whether centralized or Branch wise • We are presently in a world where banks are all connected, so we may opt for a Centralized banking system, but then if you have a HO and the Branch Model, you need perfect controls in place before the HO releases funds. • Payment Authorization Vouchers – A system that can be implemented, similar to controls that we have in SAP. • Further if we have to plan the funds and ensure that funds generated from a particular site are available for only that site after HO takes out its share of profit, then it is advisable to have separate accounts for the branches. info@consultconstruction.com www.consultconstruction.com
  • 136. Managing the Financing Needs of the business • Limits with the Bank – Fund Based / Non-Fund based. • Non-Fund based Limits are of great importance in the construction sector, as for any Project that is about to begin, the client is willing to give Mobilisation Advances against Bank Gaurantees. • Hence as a consultant you can fight hard with the bank to secure best terms in the Non-fund based limits. With a good order book you can get away by giving 25-30% collateral to some of the private banks in the market. info@consultconstruction.com www.consultconstruction.com
  • 137. [Internal Audit] • Trust info@consultconstruction.com www.consultconstruction.com
  • 138. Lets have a look at an Internal Audit Report info@consultconstruction.com www.consultconstruction.com