2. LUPITERTECHNOLOHIES
3D
A model with objects having three-
dimensional properties. Such models are
always to be considered to be dynamic, as
they will be made up of 'model files' that
are 'reference' files
3. 4D
It is a process to the intelligent linking of a
3D digital model with time or schedule
related information. It provides precise
and useful construction project
information for teams.
LUPITERTECHNOLOGIES
4. 5D
It is a term used in the CAD and
construction industries, and refers to the
intelligent linking of individual 3D CAD
components or assemblies with time
schedule (4D BIM) constraints and then
with cost-related information. 5D = 3D +
TIME SCHEDULE + COST.
LUPITERTECHNOLOGIES
5. 6D
It is a phrase extensively used in the AEC
industry and refers to the intellectual
linking of all the individual 3D CAD
components or assemblies with all
aspects of project life-cycle management
information
LUPITERTECHNOLOGIES
6. 7D
7D-BIM (seventh-dimensional building
information modelling) is used by
managers in the operation and
maintenance of the facility throughout its
life cycle. ... IntegratingBIM with 7D CAD
simulation models optimizes asset
management from design to demolition.
LUPITERTECHNOLOGIES
10. BIM EXECUTION
PLAN (BEP)
A developing strategy prepared
by suppliers that comprises a pre-
contractBIM execution and then a post-
contract BIM execution plan
LUPITERTECHNOLOGIES
11. BIM MATURITY
LEVELS
The levels of complexity
and collaborationthat building
information modelling can take
LUPITERTECHNOLOGIES
12. BIM PROTOCOL
A supplementary legal agreement that
can be incorporated
into professional servicesappointments, c
onstruction contracts, sub
contracts and novation agreements
LUPITERTECHNOLOGIES
13. BS 1192
Collaborative production of
architectural, engineering and construction
information. Code of practice.
LUPITERTECHNOLOGIES
16. CIC BIM PROTOCOL
The Construction Industry Council Building
Information
Modelling Protocol: Standardprotocol for
use in projects using Building Information
Models
LUPITERTECHNOLOGIES
18. COMMON DATA
ENVIRONMENT (CDE)
The single source of information for
the project, used to collect, manage and
disseminate documentation, the
graphical model and non-graphical data for
the whole project team
LUPITERTECHNOLOGIES
22. EMPLOYER'S
INFORMATION
REQUIREMENTS(EIR)
Set out the information required by
the employer aligned to key decision
points or project stages, enabling suppliers to
produce an initial BIM execution plan from which
their proposed approach, capability and capacity
can be evaluated
LUPITERTECHNOLOGIES
24. GOVERNMENT SOFT
LANDINGS (GSL)
The process of aligning the interests of those
who design and construct an assetwith the
interests of those who use and manage it. GSL sits
alongside BIM, as BIMfeeds into Computer
Aided Facility Management (CAFM) systems, and
helps enable future alterations to
completed buildings
LUPITERTECHNOLOGIES
27. LEVEL 0 BIM
Unmanaged computer aided design (CAD)
including 2D drawings, and text with paper-based
or electronic exchange of information but without
common standardsand processes
LUPITERTECHNOLOGIES
28. LEVEL 1 BIM
Managed CAD, with the increasing introduction of
spatial coordination, standardised structures and
formats as it moves towards Level 2 BIM
LUPITERTECHNOLOGIES
29. LEVEL 2 BIM
Managed 3D environment with dataattached, but
created in separate discipline-based models
LUPITERTECHNOLOGIES
30. LEVEL 3 BIM
A single collaborative,
online, projectmodel with construction sequencing
(4D), cost (5D) and project lifecycle information
(6D). This is sometimes referred to as 'iBIM'
(integrated BIM)
LUPITERTECHNOLOGIES
31. LEVEL OF DEFINITION
Overall term describing the level of model
detail and the level of information detail
LUPITERTECHNOLOGIES
36. PROJECT EXECUTION
PLAN (PEP)
Sets out the overall strategy for managing
a project, describing the policies, procedures and
priorities that will be adopted
LUPITERTECHNOLOGIES
37. PROJECT
IMPLEMENTATION
PLAN (PIP)
A statement relating to the suppliers' IT and human
resources capability to deliver the Employer's
Information Requirementssubmitted as part of
the pre-contract BIM Execution Plan by each
organisation bidding for a project
LUPITERTECHNOLOGIES