SlideShare a Scribd company logo
1 of 19
Download to read offline
Selection of Powered Roof Supports
         for Longwall Face


         U Siva Sankar, U.Mgr
   Project and Planning Department
       SCCL, ANDHRA PRADESH




       Layout of Longwall Face




                          Sectional view along x-x
   x




   x          Plan view




                                                     1
Close View of Longwall Face




Purpose of Powered Roof Support in Longwall Face:
  To ensure the Safety of face Crew
  To ensure Controlled Roof Caving
  To Prevent flushing of Goaf material into the face, and
 To facilitate Smooth Functioning of Longwall face

 Face length decides the number of supports to be
 installed in the face
 Cost of Supports is nearly 70% of longwall package cost
 and this cost increases or decreases w.r.t. face length.




                                                            2
The success of a longwall face depends to a large extent on the
Type and Capacity of the Powered Roof Supports.
In India, different types of Powered Roof Supports of various
capacities were tried earlier, but 4 leg chock shields have been
the most widely used.
Several mines in India like Kottadih, Churcha and Dhemomain
had experienced catastrophic failures of long wall faces due to
ground control problems and inadequate capacity and design of
powered roof supports.
A case study summarizing the experiences of working Longwall
faces with IFS, 4-leg chock shields under varying contact roofs,
viz; coal and sand stone roofs were analyzed.




               Types of Powered Roof Supports


                                                             4 - Leg
                                                             Shield



     Lt: Chock,1950 Rt: Frame, 1951




                                      6 - Leg Chock Shield


                                                             2 - Leg
                                                             Shield
     4- Leg Chock Shield (1962)




                                                                       3
Powered Roof Supports - Design


                                       Complete Canopy
                                          Assembly




                      Complete Rear
                     Shield Assembly




                                                         Complete Base
                                                           Assembly

Earlier Caliper Canopy design was replaced with lemniscate
design to maintain uniform tip to face distance
Rigid canopy are replaced with extensible canopy to control
friable roof geologies




          Powered Roof Support Canopy Designs




                                                                         4
Caliper Shield Support




      4 legged Chock Lemniscate Shield Support ,
                   Legs –V orientation




                                                   5
4x410 Tonne ,I.F.S , Chock Shield with rigid roof bar




4x410 Tonne ,I.F.S , Chock Shield with articulated
forward bar




                                                         6
Conventional                                      IFS




 Name of the Project       Make           Support Capacity     Working       Depth of
                                          (tonnes) & Type     Range (m)     Working(m)
BCCL
Moonidih               Dowty, UK        4x280, Chock          1.24 - 1.82      400
Moonidih               Kopex, Poland    6x 240, Chock         1.25 - 1.98      400
Moonidih               Dowty, UK        4x280, Chock          1.49 - 2.90      400
Moonidih               MAMC, Dowty      4x325, Chock Shield   1.90 - 3.20      400
Moonidih               MAMC, Dowty      4x400, Shield         1.27 - 2.40      400
Moonidih               Jessop/Gullick   4x400, Chock Shield   0.70 - 1.65      400
Moonidih               Kopex, Poland    4x400, Chock Shield   2.00 - 3.50      400
ECL
Sheetalpur             Gullick, UK      4x240 Chock Shield    1.40 - 2.09   420 - 450
Dhemomain              Gullick, UK      4x360 Chock Shield    2.02 - 3.20     300
Dhemomain & Jhanjra    Jessop/Gullick   4x550, Chock Shield   1.70 - 3.05   40 - 100
Jhanjra                KM -130,USSR     2x320, Chock          2.50 - 4.10    40 - 90
Churcha & Jhanjra,     Joy              4x680 Chock Shield    1.65 - 3.60   90 - 200
Kottadih,              CDFI, France     2x470 Shield          2.20 - 4.70   180 - 220
Pathakera,             MAMC, Dowty      6x240 Chock           1.11 - 1.74     110
SECL
Balrampur              CMEI&E,China     4x650, Chock Shield   1.40 - 2.70    45 - 55
New Kumda              CMEI&E,China     4x450, Chock Shield   1.40 - 2.70    45 - 55
Rajendra               CMEI&E,China     4x450, Chock Shield   1.70 - 3.10    50 - 90
SCCL
GDK 7 & 9              Gullick, UK      4x360, Chock Shield   2.10 - 3.21   100 - 350
JK5                    Gullick, UK      4x450, Chock Shield    2.0 - 3.20   138 - 265
VK 7                   Gullick          4x360, Chock Shield    2.0 - 3.20    93-272
VK 7                   Gullick          4x450, Chock Shield    2.0 - 3.20    38-382
GDK-11A                Gullick, UK      4x430, Chock Shield   1.50 - 3.00   70 - 200
GDK-11A                MECO&Gullick     4x450, Chock Shield   1.50 - 3.00   70 - 200
GDK-10A                MAMC             4x750, Chock Shield   1.65 - 3.60     240
GDK-9 Extn.            MECO             4x800, Chock Shield   1.65 - 3.60     225
PVK & GDK 9            CME, China       4x760, Chock Shield   2.20 - 3.40   54 - 297


List of Powered Roof Supports deployed in India.




                                                                                         7
Historical overview of increasing shield
                       capacities




                               SCCL




   Powered roof supports of 1750 tonnes was also Manufactured by Joy
   International, and DBT Bucyrus, 2008
   World’s biggest powered roof supports used at Anglo Coal’s
   Moranbah North mine in Queensland, Australia, 2008




Capacity: 2x1750 tonnes
Weight: 62 tonnes
Range: 2.40 to 5.0m
Leg Dia: 480mm
Life: 90,000 cycles




           World’s Biggest and Highest Rated Roof Support




                                                                       8
Longwall supports used in Australia (Source: Cram,2007)




       Factors Affecting Support Selection



Thickness and Strength of immediate roof above the
supports (easily caving or massive)
Upper      Main        Strata    Competency         (including
strong/massive units) – thickness and strength of upper
roof, especially information on any units that may bridge
Floor strength
Support Design and Capacity to prevent spalling of the
face or weakness of roof between tip to face area
Alignment of jointing or cleating in the face area
Cutting height




                                                                 9
CLASSIFICATION OF LONGWALL ROOF STRATA




   Vertical Stress Distribution in Longwall
          Panel & Immediate Roof




                   Vertical stress Distribution in Immediate
                                       roof




                                                               10
Vertical Stress Distribution Immediate Roof



When the load in the front leg is higher, the vertical stress
distribution on the front portion of the canopy is the
largest and the horizontal force acts towards the face.
As a result, there is no tensile stress in the immediate roof
of unsupported area between the canopy tip and face line
and consequently the roof will be stable.
 Conversely, when the load in the front leg is smaller, the
 vertical stress distribution on the front portion of the
 canopy is also smaller
 The horizontal force acts towards the gob resulting in
 development of tensile stress in the immediate roof of
 unsupported area, causing roof failure.




   Magnitude and type of Horizontal stress in
   Immediate Roof




                             Load Ratio = Rear leg to Front leg




                       (After Peng, et. al.,1988)




                                                                  11
Main Roof




       Case-1                                     Case-2
1. Massive Main roof with Weak Immediate Roof
  Caving and bulking up of immediate roof supports main roof
  leads to less weighting on face
  In the above higher capacity support is not required
2. Massive Main Roof with Strong Immediate Roof
  Does not cave properly and does not support upper strata
  quickly leads to intense loading of longwall face
  In the above higher capacity support is required
  Under massive roof conditions, Supports having resistance
  of 120 tonnes/Sq.m., are desirable under above conditions
  based on Australian’s Experience.




      METHODS USED FOR SUPPORT CAPACITY
               DETERMINATION


Detached Block theory (Wilson, 1975)
Empirical Nomograph based method (Peng, Hsiung and Jiang,
1987)
Load cycle analysis (Park et al, 1992, Peng 1998)
Neural networks (Chen, 1998, Deb)
Various Numerical models (Gale, 2001, Klenowski et al, 1992,
UK Singh, G. Benerjee, Deb)
Ground response curves (Medhurst, 2003)
Convergence Vis–a-Vis Support Resistance (CMRI Approach)
Roof Separation Index, After U.K.Singh, e.t.al.
Plate Theory Proposed by Quan Ming Gao(1989)




                                                               12
INSITU STRESS
                                                   SUPPORT CAPACITY
                                                        Bigger the Better �
                                                        Fig. Ground Reaction
                                                        Curve and support
                                                        response.




                                                        Fig. Impact of shield
                                                        capacities (setting
                                                        pressures) on
                                                        convergence.



Pressure Arch Concept




         Performance of Shields under Unstable or
               Poor or weak Roof Conditions




                           After Barczak T.M., (1992)

 With inclined legs, 2 leg shields create compressive forces in the
 immediate roof with which the roof is held in place.
 Thus the stability of the roof can be maintained and support
 efficacy can be improved under weak roof conditions
 Positive setting of legs is not advisable in 4 leg chock shields
 under weak roof conditions




                                                                                13
Operational characteristics
              2 Leg and 4 Leg shields
        Parameter                 2- Leg shield             4-Leg Chock shield
 Canopy ratio            optimum at approx. 2 : 1         > 2:1
 Canopy length           short and compact                longer canopy design
 Supporting force into   minimum distance to the          due to construction
 the roof                coal face                        larger distance
 Range of adjustment     up to approx. 3 : 1              <3:1
 Travelling route        in front of / behind the props   between the props
 Handling                very easy and quick              more complicated
 Possibility of faulty                                    insufficient setting of
                         extremely low
 operation                                                the rear props
 Cycle time              < 12 sec                         > 15 sec
 Requirement of
                         relatively small                 larger
 hydraulics
 Toe loading             High                              Low
 (Ground Pressure)

Floor penetration can be overcome with the use of Base lifting
device with solid base or with use of split base




          Powered Roof Supports - Longwall




  The illusion of chock shields helps in inducing
  caving of goaf was ruled out with numerical
  modelling studies.
  There is an increasing trend of usage of 2 leg
  shields all over the world.
  The life of the PRS was also increased from
  earlier 10,000 cycles to nearly 70,000 to 1 Lakh
  cycles based on manufacturer and cost of
  longwall package.




                                                                                    14
SCCL GEO MINING CONDITIONS



1. EXTRACTION THICKENESS: 1.70 to 4.50 m (>4.50m WITH LTCC)
2. IMMEDIATE ROOF:
  SHALY COAL OR SAND STONE
3. IMMEDIATE FLOOR:
  SHALY COAL OR SAND STONE
4. COMPETENCY OF MAIN ROOF: Fg to Cg Sand stone
  MASSIVE IN NATURE, with less Strength values
  THICKNESS RANGE: 12 to20 m
  MODERATELY CAVABLE to CAVABLE WITH DIFFICULTY
   CAVING HEIGHT is 30 to 45m, i.e., 10 times of Height of Extraction




                 SCCL GEO MINING CONDITIONS




Geo Engineering properties of roof and floor strata of ALP (SCCL, 2007)




                                                                          15
CASE STUDY


                                                          Panel 1A




                                                               Panel 21




Layout of Longwall Panels in Top seam of PVK 5 Incline




   Salient features of Longwall Panels under Study


                           Panel 1A            Panel 21
                                  Panel - A             Panel - B
Dimensions (m x m)         62.5 x 500            150 x 420
Height of extraction (m)   3.0                   3.0
Depth of workings (m)      48.0 Minimum          206 Minimum
                           85.0 Maximum          239 Maximum
Face Gradient              1 in 8.9              1 in 8.9
Support capacity           4 x 760 t             4 x 760 t
No. of Supports at face    43                    102
Contact Roof               Shaley coal           Partially stone &
                                                 partially Shaley coal
Contact Floor              Shaley coal           Shaley coal
Setting pressure (Mpa)     25                    28
Status of Underlying       Depillared            Depillared
seam, i.e., Middle Seam




                                                                          16
Specifications of Chock Shield of PVK


                                                   Support Range                                                                          2.20 to 3.40m
                                                   Support width                                                                          1.50 m
                                                   Support length                                                                         3.87m
                                                   Canopy ratio                                                                           2.50
                                                   Roof coverage                                                                          6.30 Sq.m
                                                   Yield load                                                                             760 tonnes
                                                   Support density                                                                        110 t/sq.m
                                                   Floor specific pressure                                                                3.10 MPa
                                                   Force to advance conveyor                                                              360KN
                                                   Force to advance support                                                               633 KN
                                                   Support weight                                                                         20.50 tonnes




                                  Pressure Distribution between Front and Rear legs
                             27
                                       Front

                             25        Rear                                                                                            Average          pressure
                                                                                                                                       distribution     between
        Leg pressure (MPa)




                             23
                                                                                                                                       front and rear legs under
                             21
                                                                                                                                       shaly coal roof (Panel
                             19                                                                                                        No.1) – shallow short
                             17                                                                                                        longwall panel
                             15
                                  34          95      145         212        279              355         429         498
                                                             Average face progress (m )




                             32
                                                                                                                            F ro n t
                                                                                                                            R ear
                             30


                             28                                                                                                        Average           pressure
                                                                                                                                       distribution between front
Leg Pressure(MPa)




                             26


                             24
                                                                                                                                       and rear legs under stone
                                                                                                                                       roof conditions (Panel
                             22
                                                                                                                                       No.21)
                             20
                                                    Stone Roof                                      Coal Roof
                             18
                                  0        50        100        150        200          250         300         350     400

                                                            D is t a n c e F r o m   B a r r ie r ( m )




                                                                                                                                                                    17
Performance of 4-leg Chock Shield at PVK
      mine under varying roof conditions
        Parameter                              Coal Roof       Stone Roof

        Compressive Strength (MPa)             9.3 to 11 MPa   16 to 21 MPa

        Setting Pressure (% of Yield           65%             75%
        Pressure)
        Main Weighting Exposure (Sq.m)         8000 to 12500   7000

        Periodic Weighting Interval (m)        15 to 25        10 to 12

        Cavities                               Frequent        Moderate
                                               (crumbled)
        Weighting Intensity                    Moderate        Intense

        Load Ratio Rear to Front               0.70 to 0.76    0.90 to 1.00

        Capacity utilization (MMLD/RMLD)       60 to 65%       80 to 85%


MMLD: Measured Mean Load Density          RMLD: Rated Mean Load Density




  Conclusions


 The desirable type and capacity of the powered roof support must
 be selected based on the site specific geo-mining conditions.
 While deploying longwall technology with foreign collaborations,
 sufficient scientific study regarding suitability of powered roof
 support under existing geo-mining conditions should be done.
 Under immediate weak and strong roof conditions, containing
 overlain massive sandstone beds, high capacity 2- leg shields of
 same capacity are desirable over 4-leg chock shields.
 Numerical modeling studies are to be conducted for better
 understanding of the interaction between the shield and the
 strata.
 Faster rate of extraction and continuous monitoring of the shields
 are the sine-qua-non for effectively combating strata control
 problems.




                                                                              18
THANK YOU




            19

More Related Content

What's hot

Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELALongwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELAIndrajeetKumar110
 
Bord and pillar working with LHD/SDL
Bord and pillar working with LHD/SDLBord and pillar working with LHD/SDL
Bord and pillar working with LHD/SDLAnkit Narain
 
Development and depillaring with continuous miner
Development and depillaring with continuous minerDevelopment and depillaring with continuous miner
Development and depillaring with continuous minerSafdar Ali
 
LHD Load haul dump ppt
LHD Load haul dump pptLHD Load haul dump ppt
LHD Load haul dump pptguru brahmam
 
Criteria for selection of Board and pillar for multiple seams
Criteria for selection of Board and pillar for multiple seamsCriteria for selection of Board and pillar for multiple seams
Criteria for selection of Board and pillar for multiple seamsAsim kumar Satapathy
 
TYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W Z
TYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W ZTYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W Z
TYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W ZANIL KUMAR KUDIRE
 
Differnt technologies in oc mines
Differnt technologies in oc minesDiffernt technologies in oc mines
Differnt technologies in oc minesSATYANARAYANA I
 

What's hot (20)

Blasting Gallery Method
Blasting Gallery MethodBlasting Gallery Method
Blasting Gallery Method
 
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELALongwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
 
Bord and pillar working with LHD/SDL
Bord and pillar working with LHD/SDLBord and pillar working with LHD/SDL
Bord and pillar working with LHD/SDL
 
Development and depillaring with continuous miner
Development and depillaring with continuous minerDevelopment and depillaring with continuous miner
Development and depillaring with continuous miner
 
Pillar design in coal mines
Pillar design in coal minesPillar design in coal mines
Pillar design in coal mines
 
LHD Load haul dump ppt
LHD Load haul dump pptLHD Load haul dump ppt
LHD Load haul dump ppt
 
Continuous miner
Continuous minerContinuous miner
Continuous miner
 
Roof supports in coal mines
Roof supports in coal minesRoof supports in coal mines
Roof supports in coal mines
 
Subsidence in coal mines
Subsidence in coal minesSubsidence in coal mines
Subsidence in coal mines
 
Longwall machinery
Longwall  machineryLongwall  machinery
Longwall machinery
 
Applicability of hydraulic mining
Applicability of hydraulic miningApplicability of hydraulic mining
Applicability of hydraulic mining
 
Oc mechanical excavation
Oc mechanical excavationOc mechanical excavation
Oc mechanical excavation
 
Highwall mining – a new approach in india
Highwall mining – a new approach in indiaHighwall mining – a new approach in india
Highwall mining – a new approach in india
 
High Wall Mining
High Wall MiningHigh Wall Mining
High Wall Mining
 
Highwall mining
Highwall miningHighwall mining
Highwall mining
 
Road Header and Bolter Miner
Road Header and Bolter MinerRoad Header and Bolter Miner
Road Header and Bolter Miner
 
Criteria for selection of Board and pillar for multiple seams
Criteria for selection of Board and pillar for multiple seamsCriteria for selection of Board and pillar for multiple seams
Criteria for selection of Board and pillar for multiple seams
 
TYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W Z
TYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W ZTYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W Z
TYPES OF VENTILATION SYSTEMS IN MINES - CENTRAL BOUNDARY U W Z
 
Subsidence
SubsidenceSubsidence
Subsidence
 
Differnt technologies in oc mines
Differnt technologies in oc minesDiffernt technologies in oc mines
Differnt technologies in oc mines
 

Similar to Selection of longwall powered roof support

Selection of powered roof supports – 2 leg shields vis-à-vis
Selection of powered roof supports – 2 leg shields vis-à-visSelection of powered roof supports – 2 leg shields vis-à-vis
Selection of powered roof supports – 2 leg shields vis-à-visUlimella Siva Sankar
 
Deep foundations sheet pile
Deep foundations   sheet pileDeep foundations   sheet pile
Deep foundations sheet pileRakesh Reddy
 
Barrette foundation
Barrette foundationBarrette foundation
Barrette foundationHassnAlaa
 
Anchored excavations
Anchored excavationsAnchored excavations
Anchored excavationsDeniz Kurt
 
Powered suppport_sk1.pdf
Powered suppport_sk1.pdfPowered suppport_sk1.pdf
Powered suppport_sk1.pdfKumarSurya7
 
Universal marine global aquaculture
Universal marine global aquacultureUniversal marine global aquaculture
Universal marine global aquacultureuniversalnets
 
PROJECT REPORT ON SOIL REINFORCEMENT RETAINING STRUCTURES
PROJECT REPORT ON SOIL REINFORCEMENT RETAINING STRUCTURESPROJECT REPORT ON SOIL REINFORCEMENT RETAINING STRUCTURES
PROJECT REPORT ON SOIL REINFORCEMENT RETAINING STRUCTURESIndrajit Sardar
 
2015 Recent Developments in ACIP and DD Piling (NeSmith)
2015 Recent Developments in ACIP and DD Piling (NeSmith)2015 Recent Developments in ACIP and DD Piling (NeSmith)
2015 Recent Developments in ACIP and DD Piling (NeSmith)Ryan Coggins, P.E.
 
Transocean offshore operation 2
Transocean   offshore operation 2Transocean   offshore operation 2
Transocean offshore operation 2Steffones K
 
The Road to Saqqara ( Jack-up units and Move )
The Road to Saqqara ( Jack-up units and Move )The Road to Saqqara ( Jack-up units and Move )
The Road to Saqqara ( Jack-up units and Move )Kamel Elsayed
 
seismic control of structure
seismic control of structureseismic control of structure
seismic control of structurefazalrahman rang
 

Similar to Selection of longwall powered roof support (20)

2leg vs4leg
2leg vs4leg2leg vs4leg
2leg vs4leg
 
Selection of powered roof supports – 2 leg shields vis-à-vis
Selection of powered roof supports – 2 leg shields vis-à-visSelection of powered roof supports – 2 leg shields vis-à-vis
Selection of powered roof supports – 2 leg shields vis-à-vis
 
Deep foundations sheet pile
Deep foundations   sheet pileDeep foundations   sheet pile
Deep foundations sheet pile
 
Barrette foundation
Barrette foundationBarrette foundation
Barrette foundation
 
Anchored excavations
Anchored excavationsAnchored excavations
Anchored excavations
 
Powered suppport_sk1.pdf
Powered suppport_sk1.pdfPowered suppport_sk1.pdf
Powered suppport_sk1.pdf
 
Confinement of Reinforcement Concrete Using High Strength Concrete
Confinement of Reinforcement Concrete Using High Strength Concrete Confinement of Reinforcement Concrete Using High Strength Concrete
Confinement of Reinforcement Concrete Using High Strength Concrete
 
Universal marine global aquaculture
Universal marine global aquacultureUniversal marine global aquaculture
Universal marine global aquaculture
 
FinalReport
FinalReportFinalReport
FinalReport
 
Pilefoundation
PilefoundationPilefoundation
Pilefoundation
 
PROJECT REPORT ON SOIL REINFORCEMENT RETAINING STRUCTURES
PROJECT REPORT ON SOIL REINFORCEMENT RETAINING STRUCTURESPROJECT REPORT ON SOIL REINFORCEMENT RETAINING STRUCTURES
PROJECT REPORT ON SOIL REINFORCEMENT RETAINING STRUCTURES
 
16WCEE_Ferguson_Chadwell_Gershfeld
16WCEE_Ferguson_Chadwell_Gershfeld16WCEE_Ferguson_Chadwell_Gershfeld
16WCEE_Ferguson_Chadwell_Gershfeld
 
2015 Recent Developments in ACIP and DD Piling (NeSmith)
2015 Recent Developments in ACIP and DD Piling (NeSmith)2015 Recent Developments in ACIP and DD Piling (NeSmith)
2015 Recent Developments in ACIP and DD Piling (NeSmith)
 
Transocean offshore operation 2
Transocean   offshore operation 2Transocean   offshore operation 2
Transocean offshore operation 2
 
Lecture-04 Piles.pptx
Lecture-04 Piles.pptxLecture-04 Piles.pptx
Lecture-04 Piles.pptx
 
Final thesis presentation.
Final thesis presentation.Final thesis presentation.
Final thesis presentation.
 
The Road to Saqqara ( Jack-up units and Move )
The Road to Saqqara ( Jack-up units and Move )The Road to Saqqara ( Jack-up units and Move )
The Road to Saqqara ( Jack-up units and Move )
 
Print_Reduced
Print_ReducedPrint_Reduced
Print_Reduced
 
Pilework
PileworkPilework
Pilework
 
seismic control of structure
seismic control of structureseismic control of structure
seismic control of structure
 

More from Ulimella Siva Sankar

Safety Management of Deep Mechanised Longwall Mine
Safety Management of Deep Mechanised Longwall MineSafety Management of Deep Mechanised Longwall Mine
Safety Management of Deep Mechanised Longwall MineUlimella Siva Sankar
 
Theories of interaction of rock cutting tools
Theories of interaction of rock cutting toolsTheories of interaction of rock cutting tools
Theories of interaction of rock cutting toolsUlimella Siva Sankar
 
Ground control in undergound mines
Ground control in undergound minesGround control in undergound mines
Ground control in undergound minesUlimella Siva Sankar
 
Rock mass classification or rock mass rating of rock materials in civil and m...
Rock mass classification or rock mass rating of rock materials in civil and m...Rock mass classification or rock mass rating of rock materials in civil and m...
Rock mass classification or rock mass rating of rock materials in civil and m...Ulimella Siva Sankar
 
Physico-Mechanical properties of rock materials
Physico-Mechanical properties of rock materialsPhysico-Mechanical properties of rock materials
Physico-Mechanical properties of rock materialsUlimella Siva Sankar
 
Numerical modelling in Geo mechanics
Numerical modelling in Geo mechanicsNumerical modelling in Geo mechanics
Numerical modelling in Geo mechanicsUlimella Siva Sankar
 
Numerical modelling in Geomechanics
Numerical modelling in GeomechanicsNumerical modelling in Geomechanics
Numerical modelling in GeomechanicsUlimella Siva Sankar
 
Longwall technology in india, SCCL
Longwall technology in india, SCCLLongwall technology in india, SCCL
Longwall technology in india, SCCLUlimella Siva Sankar
 

More from Ulimella Siva Sankar (20)

Tube bundle gas monitoring system
Tube bundle gas monitoring systemTube bundle gas monitoring system
Tube bundle gas monitoring system
 
Aircooling underground coal mine
 Aircooling underground coal mine Aircooling underground coal mine
Aircooling underground coal mine
 
Adriyala longwall paper
Adriyala  longwall  paperAdriyala  longwall  paper
Adriyala longwall paper
 
Safety Management of Deep Mechanised Longwall Mine
Safety Management of Deep Mechanised Longwall MineSafety Management of Deep Mechanised Longwall Mine
Safety Management of Deep Mechanised Longwall Mine
 
Pneumoconiosis
PneumoconiosisPneumoconiosis
Pneumoconiosis
 
insitu Horizontal stress
insitu Horizontal stressinsitu Horizontal stress
insitu Horizontal stress
 
Ug mechanical excavation
Ug mechanical excavationUg mechanical excavation
Ug mechanical excavation
 
Theories of interaction of rock cutting tools
Theories of interaction of rock cutting toolsTheories of interaction of rock cutting tools
Theories of interaction of rock cutting tools
 
Design of openings
Design of openingsDesign of openings
Design of openings
 
Slopestability
SlopestabilitySlopestability
Slopestability
 
strata monitoring Instrumentation
strata monitoring Instrumentationstrata monitoring Instrumentation
strata monitoring Instrumentation
 
Insitu stresses and measurement
Insitu stresses and measurementInsitu stresses and measurement
Insitu stresses and measurement
 
Ground control in undergound mines
Ground control in undergound minesGround control in undergound mines
Ground control in undergound mines
 
Strike dip rise longwall panels
Strike dip rise longwall panelsStrike dip rise longwall panels
Strike dip rise longwall panels
 
Selection of viable ug technology
Selection of viable ug technologySelection of viable ug technology
Selection of viable ug technology
 
Rock mass classification or rock mass rating of rock materials in civil and m...
Rock mass classification or rock mass rating of rock materials in civil and m...Rock mass classification or rock mass rating of rock materials in civil and m...
Rock mass classification or rock mass rating of rock materials in civil and m...
 
Physico-Mechanical properties of rock materials
Physico-Mechanical properties of rock materialsPhysico-Mechanical properties of rock materials
Physico-Mechanical properties of rock materials
 
Numerical modelling in Geo mechanics
Numerical modelling in Geo mechanicsNumerical modelling in Geo mechanics
Numerical modelling in Geo mechanics
 
Numerical modelling in Geomechanics
Numerical modelling in GeomechanicsNumerical modelling in Geomechanics
Numerical modelling in Geomechanics
 
Longwall technology in india, SCCL
Longwall technology in india, SCCLLongwall technology in india, SCCL
Longwall technology in india, SCCL
 

Recently uploaded

TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...Nguyen Thanh Tu Collection
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxAreebaZafar22
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxRamakrishna Reddy Bijjam
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.christianmathematics
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Shubhangi Sonawane
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.pptRamjanShidvankar
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfChris Hunter
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesEnergy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesShubhangi Sonawane
 
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIFood Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIShubhangi Sonawane
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxVishalSingh1417
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 

Recently uploaded (20)

TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesEnergy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
 
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIFood Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 

Selection of longwall powered roof support

  • 1. Selection of Powered Roof Supports for Longwall Face U Siva Sankar, U.Mgr Project and Planning Department SCCL, ANDHRA PRADESH Layout of Longwall Face Sectional view along x-x x x Plan view 1
  • 2. Close View of Longwall Face Purpose of Powered Roof Support in Longwall Face: To ensure the Safety of face Crew To ensure Controlled Roof Caving To Prevent flushing of Goaf material into the face, and To facilitate Smooth Functioning of Longwall face Face length decides the number of supports to be installed in the face Cost of Supports is nearly 70% of longwall package cost and this cost increases or decreases w.r.t. face length. 2
  • 3. The success of a longwall face depends to a large extent on the Type and Capacity of the Powered Roof Supports. In India, different types of Powered Roof Supports of various capacities were tried earlier, but 4 leg chock shields have been the most widely used. Several mines in India like Kottadih, Churcha and Dhemomain had experienced catastrophic failures of long wall faces due to ground control problems and inadequate capacity and design of powered roof supports. A case study summarizing the experiences of working Longwall faces with IFS, 4-leg chock shields under varying contact roofs, viz; coal and sand stone roofs were analyzed. Types of Powered Roof Supports 4 - Leg Shield Lt: Chock,1950 Rt: Frame, 1951 6 - Leg Chock Shield 2 - Leg Shield 4- Leg Chock Shield (1962) 3
  • 4. Powered Roof Supports - Design Complete Canopy Assembly Complete Rear Shield Assembly Complete Base Assembly Earlier Caliper Canopy design was replaced with lemniscate design to maintain uniform tip to face distance Rigid canopy are replaced with extensible canopy to control friable roof geologies Powered Roof Support Canopy Designs 4
  • 5. Caliper Shield Support 4 legged Chock Lemniscate Shield Support , Legs –V orientation 5
  • 6. 4x410 Tonne ,I.F.S , Chock Shield with rigid roof bar 4x410 Tonne ,I.F.S , Chock Shield with articulated forward bar 6
  • 7. Conventional IFS Name of the Project Make Support Capacity Working Depth of (tonnes) & Type Range (m) Working(m) BCCL Moonidih Dowty, UK 4x280, Chock 1.24 - 1.82 400 Moonidih Kopex, Poland 6x 240, Chock 1.25 - 1.98 400 Moonidih Dowty, UK 4x280, Chock 1.49 - 2.90 400 Moonidih MAMC, Dowty 4x325, Chock Shield 1.90 - 3.20 400 Moonidih MAMC, Dowty 4x400, Shield 1.27 - 2.40 400 Moonidih Jessop/Gullick 4x400, Chock Shield 0.70 - 1.65 400 Moonidih Kopex, Poland 4x400, Chock Shield 2.00 - 3.50 400 ECL Sheetalpur Gullick, UK 4x240 Chock Shield 1.40 - 2.09 420 - 450 Dhemomain Gullick, UK 4x360 Chock Shield 2.02 - 3.20 300 Dhemomain & Jhanjra Jessop/Gullick 4x550, Chock Shield 1.70 - 3.05 40 - 100 Jhanjra KM -130,USSR 2x320, Chock 2.50 - 4.10 40 - 90 Churcha & Jhanjra, Joy 4x680 Chock Shield 1.65 - 3.60 90 - 200 Kottadih, CDFI, France 2x470 Shield 2.20 - 4.70 180 - 220 Pathakera, MAMC, Dowty 6x240 Chock 1.11 - 1.74 110 SECL Balrampur CMEI&E,China 4x650, Chock Shield 1.40 - 2.70 45 - 55 New Kumda CMEI&E,China 4x450, Chock Shield 1.40 - 2.70 45 - 55 Rajendra CMEI&E,China 4x450, Chock Shield 1.70 - 3.10 50 - 90 SCCL GDK 7 & 9 Gullick, UK 4x360, Chock Shield 2.10 - 3.21 100 - 350 JK5 Gullick, UK 4x450, Chock Shield 2.0 - 3.20 138 - 265 VK 7 Gullick 4x360, Chock Shield 2.0 - 3.20 93-272 VK 7 Gullick 4x450, Chock Shield 2.0 - 3.20 38-382 GDK-11A Gullick, UK 4x430, Chock Shield 1.50 - 3.00 70 - 200 GDK-11A MECO&Gullick 4x450, Chock Shield 1.50 - 3.00 70 - 200 GDK-10A MAMC 4x750, Chock Shield 1.65 - 3.60 240 GDK-9 Extn. MECO 4x800, Chock Shield 1.65 - 3.60 225 PVK & GDK 9 CME, China 4x760, Chock Shield 2.20 - 3.40 54 - 297 List of Powered Roof Supports deployed in India. 7
  • 8. Historical overview of increasing shield capacities SCCL Powered roof supports of 1750 tonnes was also Manufactured by Joy International, and DBT Bucyrus, 2008 World’s biggest powered roof supports used at Anglo Coal’s Moranbah North mine in Queensland, Australia, 2008 Capacity: 2x1750 tonnes Weight: 62 tonnes Range: 2.40 to 5.0m Leg Dia: 480mm Life: 90,000 cycles World’s Biggest and Highest Rated Roof Support 8
  • 9. Longwall supports used in Australia (Source: Cram,2007) Factors Affecting Support Selection Thickness and Strength of immediate roof above the supports (easily caving or massive) Upper Main Strata Competency (including strong/massive units) – thickness and strength of upper roof, especially information on any units that may bridge Floor strength Support Design and Capacity to prevent spalling of the face or weakness of roof between tip to face area Alignment of jointing or cleating in the face area Cutting height 9
  • 10. CLASSIFICATION OF LONGWALL ROOF STRATA Vertical Stress Distribution in Longwall Panel & Immediate Roof Vertical stress Distribution in Immediate roof 10
  • 11. Vertical Stress Distribution Immediate Roof When the load in the front leg is higher, the vertical stress distribution on the front portion of the canopy is the largest and the horizontal force acts towards the face. As a result, there is no tensile stress in the immediate roof of unsupported area between the canopy tip and face line and consequently the roof will be stable. Conversely, when the load in the front leg is smaller, the vertical stress distribution on the front portion of the canopy is also smaller The horizontal force acts towards the gob resulting in development of tensile stress in the immediate roof of unsupported area, causing roof failure. Magnitude and type of Horizontal stress in Immediate Roof Load Ratio = Rear leg to Front leg (After Peng, et. al.,1988) 11
  • 12. Main Roof Case-1 Case-2 1. Massive Main roof with Weak Immediate Roof Caving and bulking up of immediate roof supports main roof leads to less weighting on face In the above higher capacity support is not required 2. Massive Main Roof with Strong Immediate Roof Does not cave properly and does not support upper strata quickly leads to intense loading of longwall face In the above higher capacity support is required Under massive roof conditions, Supports having resistance of 120 tonnes/Sq.m., are desirable under above conditions based on Australian’s Experience. METHODS USED FOR SUPPORT CAPACITY DETERMINATION Detached Block theory (Wilson, 1975) Empirical Nomograph based method (Peng, Hsiung and Jiang, 1987) Load cycle analysis (Park et al, 1992, Peng 1998) Neural networks (Chen, 1998, Deb) Various Numerical models (Gale, 2001, Klenowski et al, 1992, UK Singh, G. Benerjee, Deb) Ground response curves (Medhurst, 2003) Convergence Vis–a-Vis Support Resistance (CMRI Approach) Roof Separation Index, After U.K.Singh, e.t.al. Plate Theory Proposed by Quan Ming Gao(1989) 12
  • 13. INSITU STRESS SUPPORT CAPACITY Bigger the Better � Fig. Ground Reaction Curve and support response. Fig. Impact of shield capacities (setting pressures) on convergence. Pressure Arch Concept Performance of Shields under Unstable or Poor or weak Roof Conditions After Barczak T.M., (1992) With inclined legs, 2 leg shields create compressive forces in the immediate roof with which the roof is held in place. Thus the stability of the roof can be maintained and support efficacy can be improved under weak roof conditions Positive setting of legs is not advisable in 4 leg chock shields under weak roof conditions 13
  • 14. Operational characteristics 2 Leg and 4 Leg shields Parameter 2- Leg shield 4-Leg Chock shield Canopy ratio optimum at approx. 2 : 1 > 2:1 Canopy length short and compact longer canopy design Supporting force into minimum distance to the due to construction the roof coal face larger distance Range of adjustment up to approx. 3 : 1 <3:1 Travelling route in front of / behind the props between the props Handling very easy and quick more complicated Possibility of faulty insufficient setting of extremely low operation the rear props Cycle time < 12 sec > 15 sec Requirement of relatively small larger hydraulics Toe loading High Low (Ground Pressure) Floor penetration can be overcome with the use of Base lifting device with solid base or with use of split base Powered Roof Supports - Longwall The illusion of chock shields helps in inducing caving of goaf was ruled out with numerical modelling studies. There is an increasing trend of usage of 2 leg shields all over the world. The life of the PRS was also increased from earlier 10,000 cycles to nearly 70,000 to 1 Lakh cycles based on manufacturer and cost of longwall package. 14
  • 15. SCCL GEO MINING CONDITIONS 1. EXTRACTION THICKENESS: 1.70 to 4.50 m (>4.50m WITH LTCC) 2. IMMEDIATE ROOF: SHALY COAL OR SAND STONE 3. IMMEDIATE FLOOR: SHALY COAL OR SAND STONE 4. COMPETENCY OF MAIN ROOF: Fg to Cg Sand stone MASSIVE IN NATURE, with less Strength values THICKNESS RANGE: 12 to20 m MODERATELY CAVABLE to CAVABLE WITH DIFFICULTY CAVING HEIGHT is 30 to 45m, i.e., 10 times of Height of Extraction SCCL GEO MINING CONDITIONS Geo Engineering properties of roof and floor strata of ALP (SCCL, 2007) 15
  • 16. CASE STUDY Panel 1A Panel 21 Layout of Longwall Panels in Top seam of PVK 5 Incline Salient features of Longwall Panels under Study Panel 1A Panel 21 Panel - A Panel - B Dimensions (m x m) 62.5 x 500 150 x 420 Height of extraction (m) 3.0 3.0 Depth of workings (m) 48.0 Minimum 206 Minimum 85.0 Maximum 239 Maximum Face Gradient 1 in 8.9 1 in 8.9 Support capacity 4 x 760 t 4 x 760 t No. of Supports at face 43 102 Contact Roof Shaley coal Partially stone & partially Shaley coal Contact Floor Shaley coal Shaley coal Setting pressure (Mpa) 25 28 Status of Underlying Depillared Depillared seam, i.e., Middle Seam 16
  • 17. Specifications of Chock Shield of PVK Support Range 2.20 to 3.40m Support width 1.50 m Support length 3.87m Canopy ratio 2.50 Roof coverage 6.30 Sq.m Yield load 760 tonnes Support density 110 t/sq.m Floor specific pressure 3.10 MPa Force to advance conveyor 360KN Force to advance support 633 KN Support weight 20.50 tonnes Pressure Distribution between Front and Rear legs 27 Front 25 Rear Average pressure distribution between Leg pressure (MPa) 23 front and rear legs under 21 shaly coal roof (Panel 19 No.1) – shallow short 17 longwall panel 15 34 95 145 212 279 355 429 498 Average face progress (m ) 32 F ro n t R ear 30 28 Average pressure distribution between front Leg Pressure(MPa) 26 24 and rear legs under stone roof conditions (Panel 22 No.21) 20 Stone Roof Coal Roof 18 0 50 100 150 200 250 300 350 400 D is t a n c e F r o m B a r r ie r ( m ) 17
  • 18. Performance of 4-leg Chock Shield at PVK mine under varying roof conditions Parameter Coal Roof Stone Roof Compressive Strength (MPa) 9.3 to 11 MPa 16 to 21 MPa Setting Pressure (% of Yield 65% 75% Pressure) Main Weighting Exposure (Sq.m) 8000 to 12500 7000 Periodic Weighting Interval (m) 15 to 25 10 to 12 Cavities Frequent Moderate (crumbled) Weighting Intensity Moderate Intense Load Ratio Rear to Front 0.70 to 0.76 0.90 to 1.00 Capacity utilization (MMLD/RMLD) 60 to 65% 80 to 85% MMLD: Measured Mean Load Density RMLD: Rated Mean Load Density Conclusions The desirable type and capacity of the powered roof support must be selected based on the site specific geo-mining conditions. While deploying longwall technology with foreign collaborations, sufficient scientific study regarding suitability of powered roof support under existing geo-mining conditions should be done. Under immediate weak and strong roof conditions, containing overlain massive sandstone beds, high capacity 2- leg shields of same capacity are desirable over 4-leg chock shields. Numerical modeling studies are to be conducted for better understanding of the interaction between the shield and the strata. Faster rate of extraction and continuous monitoring of the shields are the sine-qua-non for effectively combating strata control problems. 18
  • 19. THANK YOU 19