SlideShare a Scribd company logo
1 of 26
Municipal Wetland Management:
Overview of the CBJ process and
the real life applications of the
Juneau Wetlands Mgmt Plan

        Watershed Forum Presentation
                       March 8, 2012
                            Presented by:
              Teri Camery, Senior Planner
             Nicole Jones, Planner I, CFM
Juneau Wetlands Management Plan—Purpose

• Classify wetlands into high-value (A
  and B), low-value (C and D), and
  Enhancement Potential based on
  ranked environmental functions
  according to the Adamus wetland
  methodology
• Provide for reasoned, scientifically-
  supported decisions regarding
  protection and development of
  wetlands
• Increase predictability for property
  owners
Juneau Wetlands Management Plan—History

Two stages of development:

3)    1980s wetland surveys
      and wetland functional
      analysis report

2)    1992 final Juneau
      Wetlands Management
      Plan, with policies,
      regulations, and
      implementation
      guidelines
Juneau Wetlands Management Plan—History

  More recent
  versions of the plan
  —1997 and 2008—
  still use the original
  studies and study
  area.

  CBJ will begin the
  first phase of a
  four-year plan to
  update the JWMP
  this year.
Juneau Wetlands Management Plan—Components



• Wetland Categories—A, B, C, D, and EP
• 140 different wetland units, each with its
  own functional analysis of 15 different
  wetland functions
• Freshwater wetlands only, not estuarine
• Wetland surveys, not wetland delineations
Shoreline Corridor Rule

    Highest wetland category adjacent to streams
Residential Road Corridor Rule

       Lower wetland category within 100-feet
                 of some major roads
Juneau Wetlands Management Plan—Components

• Individual
  management
  regulations for each
  wetland category
• CBJ Land Use Code
  wetland regulations
  implemented through
  CBJ Building and
  Zoning permits
• Regulations allow
  consideration of new
  scientific evidence
Juneau Wetlands Management Plan—Components




Establishment of CBJ Wetlands Review Board
• Volunteer Scientific Advisory Board appointed by the CBJ Assembly
• General Permit Authority from Army Corps for low-value Category C
   and D wetlands
• Board has an advisory role over projects that impact wetlands and
   salmon streams
CBJ Wetland Permitting Process
Wetlands Fill Permit—Process

• Wetland Delineation
• Application submittal
   – Fees $350-$1,600
• Staff Review
• Wetlands Review Board
   – Conditions of approval
• Wetland Permit Issued
   – Approximately 8-12 weeks
• Applicant applies for a
  Building permit
   – Fees $50-??
Wetland Permit Case Study




                            WET2000 - 00001
Juneau Wetland Management Plan
Partial Wetland Functional Analysis of J7 Wetland
Unit

 • Add wetland functions of this wetland unit
Wetlands   Site Plan Pre-Wetland Fill
Proposed Wetland Fill


  ±800 cu yards of fill—category B(r)C




±1,400 cu yards of fill—category B(r)C
   wetlands
Wetland Fill Permit—Conditions


Notice of Decision—see handout
• 1,500 cubic yards of wetland fill was
  approved to allow for a new church with
  a parking area
    – 5,200 cubic yards of overburden was
      approved to be removed
•   11 conditions of approval were applied to
    the wetland permit.
JWMP Challenges and Update
Juneau Wetland Management Plan—Challenges

• Wetland maps are surveys, not formal
  delineations. Delineations are valid for only 5
  years.
• Studies, maps, and regulations are outdated.
  Developed area of the Borough has expanded.
• The majority of low-value C and D wetlands
  have been filled (an indicator of success);
  General Permit authority has lapsed
• Poor enforcement of permit conditions
Juneau Wetlands Management Plan Update


• Four year project funded by
  federal CIAP which includes
  LiDAR, infrared imagery, and
  stream and wetland mapping
  and classification
• New wetland methodology
• New wetland categories and
  analysis, freshwater and
  estuarine
Juneau Wetlands Management Plan Update

• Update existing surveys and classifications and
  expand into developing areas
Juneau Wetlands Management Plan Update


Includes Land Use Code regulatory revisions
  for compatibility with:
• Corps 2008 Mitigation Rule
• other local mitigation programs such as
  SEALTrust fee-in-lieu; and
• new General Permit authority (with Corps
  approval) for low-value wetlands
Juneau Wetlands Management Plan Resources
• Juneau Wetlands Management Plan
  http://www.juneau.org/cddftp/plansstudies.php
• Wetlands Permit Application


  http://www.juneau.org/cddftp/documents/Wetlands_Applicati
• CBJ Land Use Code Title 49


  http://library.municode.com/index.aspx?clientId=13307&state
Teri Camery teri_camery@ci.juneau.ak.us 586-0755
Nicole Jones nicole_jones@ci.juneau.ak.us 586-0218
Questions?

More Related Content

What's hot

Tete bayou openhousemeeting_021215
Tete bayou openhousemeeting_021215Tete bayou openhousemeeting_021215
Tete bayou openhousemeeting_021215Justin Shaw
 
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015Carl Greenstreet
 
Dhi uk 2015 - marine - a new approach to modelling long-term shoreline evolut...
Dhi uk 2015 - marine - a new approach to modelling long-term shoreline evolut...Dhi uk 2015 - marine - a new approach to modelling long-term shoreline evolut...
Dhi uk 2015 - marine - a new approach to modelling long-term shoreline evolut...Stephen Flood
 
Reducing Wastewater Pollution: Upgrades and Sewer Extensions
Reducing Wastewater Pollution: Upgrades and Sewer ExtensionsReducing Wastewater Pollution: Upgrades and Sewer Extensions
Reducing Wastewater Pollution: Upgrades and Sewer ExtensionsChesapeake Bay Foundation
 
Soil management at metrolinx
Soil management at metrolinx Soil management at metrolinx
Soil management at metrolinx ONEIA
 
ONEIA Excess Soil Session, September 9, 2014 - Presentation by MOECC
ONEIA Excess Soil Session, September 9, 2014 - Presentation by MOECCONEIA Excess Soil Session, September 9, 2014 - Presentation by MOECC
ONEIA Excess Soil Session, September 9, 2014 - Presentation by MOECCONEIA
 
AIPG Michigan Section Technical Workshop - Presentation - June 2017
AIPG Michigan Section Technical Workshop - Presentation - June 2017AIPG Michigan Section Technical Workshop - Presentation - June 2017
AIPG Michigan Section Technical Workshop - Presentation - June 2017Envirologic Technologies, Inc
 
Presentation on expertise services
Presentation on expertise servicesPresentation on expertise services
Presentation on expertise servicesWATER HARVESTERS
 
Water Board Update to Moffett RAB
Water Board Update to Moffett RABWater Board Update to Moffett RAB
Water Board Update to Moffett RABSteve Williams
 
Intertidal habitat creation as compensation for the impacts of dredging assoc...
Intertidal habitat creation as compensation for the impacts of dredging assoc...Intertidal habitat creation as compensation for the impacts of dredging assoc...
Intertidal habitat creation as compensation for the impacts of dredging assoc...Tristan Wiggill
 
#4/9 Monitoring red throated diver distribution Liverpool Bay - DONG Energy
#4/9 Monitoring red throated diver distribution Liverpool Bay - DONG Energy#4/9 Monitoring red throated diver distribution Liverpool Bay - DONG Energy
#4/9 Monitoring red throated diver distribution Liverpool Bay - DONG EnergyNaturalEngland
 
Lid Stormwater Approach: Overcoming Barriers to Implementation
Lid Stormwater Approach: Overcoming Barriers to ImplementationLid Stormwater Approach: Overcoming Barriers to Implementation
Lid Stormwater Approach: Overcoming Barriers to Implementationabroadsword
 
Oneia excess soils session, September 9, 2014
Oneia excess soils session, September 9, 2014Oneia excess soils session, September 9, 2014
Oneia excess soils session, September 9, 2014ONEIA
 
Water presentation port of corpus christi
Water presentation port of corpus christiWater presentation port of corpus christi
Water presentation port of corpus christijeshaml10
 
EPA Steering Committee Meeting slides, Dec, 8, 2020
EPA Steering Committee Meeting slides, Dec, 8, 2020EPA Steering Committee Meeting slides, Dec, 8, 2020
EPA Steering Committee Meeting slides, Dec, 8, 2020Mark Healy
 
Sharing Experiences of Flood Modelling Using MIKE 21
Sharing Experiences of Flood Modelling Using MIKE 21Sharing Experiences of Flood Modelling Using MIKE 21
Sharing Experiences of Flood Modelling Using MIKE 21Stephen Flood
 

What's hot (20)

Tete bayou openhousemeeting_021215
Tete bayou openhousemeeting_021215Tete bayou openhousemeeting_021215
Tete bayou openhousemeeting_021215
 
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
Greenstreet CW - Cooper Basin Unconventional Resources APPEA 2015
 
Dhi uk 2015 - marine - a new approach to modelling long-term shoreline evolut...
Dhi uk 2015 - marine - a new approach to modelling long-term shoreline evolut...Dhi uk 2015 - marine - a new approach to modelling long-term shoreline evolut...
Dhi uk 2015 - marine - a new approach to modelling long-term shoreline evolut...
 
Water balance & management
Water balance & managementWater balance & management
Water balance & management
 
Reducing Wastewater Pollution: Upgrades and Sewer Extensions
Reducing Wastewater Pollution: Upgrades and Sewer ExtensionsReducing Wastewater Pollution: Upgrades and Sewer Extensions
Reducing Wastewater Pollution: Upgrades and Sewer Extensions
 
Soil management at metrolinx
Soil management at metrolinx Soil management at metrolinx
Soil management at metrolinx
 
ONEIA Excess Soil Session, September 9, 2014 - Presentation by MOECC
ONEIA Excess Soil Session, September 9, 2014 - Presentation by MOECCONEIA Excess Soil Session, September 9, 2014 - Presentation by MOECC
ONEIA Excess Soil Session, September 9, 2014 - Presentation by MOECC
 
AIPG Michigan Section Technical Workshop - Presentation - June 2017
AIPG Michigan Section Technical Workshop - Presentation - June 2017AIPG Michigan Section Technical Workshop - Presentation - June 2017
AIPG Michigan Section Technical Workshop - Presentation - June 2017
 
Minorca final
Minorca finalMinorca final
Minorca final
 
Presentation on expertise services
Presentation on expertise servicesPresentation on expertise services
Presentation on expertise services
 
Water Board Update to Moffett RAB
Water Board Update to Moffett RABWater Board Update to Moffett RAB
Water Board Update to Moffett RAB
 
Intertidal habitat creation as compensation for the impacts of dredging assoc...
Intertidal habitat creation as compensation for the impacts of dredging assoc...Intertidal habitat creation as compensation for the impacts of dredging assoc...
Intertidal habitat creation as compensation for the impacts of dredging assoc...
 
#4/9 Monitoring red throated diver distribution Liverpool Bay - DONG Energy
#4/9 Monitoring red throated diver distribution Liverpool Bay - DONG Energy#4/9 Monitoring red throated diver distribution Liverpool Bay - DONG Energy
#4/9 Monitoring red throated diver distribution Liverpool Bay - DONG Energy
 
Lid Stormwater Approach: Overcoming Barriers to Implementation
Lid Stormwater Approach: Overcoming Barriers to ImplementationLid Stormwater Approach: Overcoming Barriers to Implementation
Lid Stormwater Approach: Overcoming Barriers to Implementation
 
Delivering Mitigation Solutions for Natural Resource Extraction Projects: Ins...
Delivering Mitigation Solutions for Natural Resource Extraction Projects: Ins...Delivering Mitigation Solutions for Natural Resource Extraction Projects: Ins...
Delivering Mitigation Solutions for Natural Resource Extraction Projects: Ins...
 
Oneia excess soils session, September 9, 2014
Oneia excess soils session, September 9, 2014Oneia excess soils session, September 9, 2014
Oneia excess soils session, September 9, 2014
 
Water presentation port of corpus christi
Water presentation port of corpus christiWater presentation port of corpus christi
Water presentation port of corpus christi
 
EPA Steering Committee Meeting slides, Dec, 8, 2020
EPA Steering Committee Meeting slides, Dec, 8, 2020EPA Steering Committee Meeting slides, Dec, 8, 2020
EPA Steering Committee Meeting slides, Dec, 8, 2020
 
test.pptx
test.pptxtest.pptx
test.pptx
 
Sharing Experiences of Flood Modelling Using MIKE 21
Sharing Experiences of Flood Modelling Using MIKE 21Sharing Experiences of Flood Modelling Using MIKE 21
Sharing Experiences of Flood Modelling Using MIKE 21
 

Viewers also liked

Partnering with the Forest Service: Lessons Learned by Sheila Jacobson
Partnering with the Forest Service: Lessons Learned by Sheila JacobsonPartnering with the Forest Service: Lessons Learned by Sheila Jacobson
Partnering with the Forest Service: Lessons Learned by Sheila JacobsonSoutheast Alaska Watershed Coalition
 
Building strategic partnerships with the Forest Service by Angela Coleman
Building strategic partnerships with the Forest Service by Angela ColemanBuilding strategic partnerships with the Forest Service by Angela Coleman
Building strategic partnerships with the Forest Service by Angela ColemanSoutheast Alaska Watershed Coalition
 
Wetland Mitigation Programs by Steve Sego (Southeast Alaska Watershed Coalition)
Wetland Mitigation Programs by Steve Sego (Southeast Alaska Watershed Coalition)Wetland Mitigation Programs by Steve Sego (Southeast Alaska Watershed Coalition)
Wetland Mitigation Programs by Steve Sego (Southeast Alaska Watershed Coalition)Southeast Alaska Watershed Coalition
 

Viewers also liked (20)

Southeast yritwc
Southeast yritwcSoutheast yritwc
Southeast yritwc
 
Compensatory Mitigation by Matthew LaCroix
Compensatory Mitigation by Matthew LaCroix Compensatory Mitigation by Matthew LaCroix
Compensatory Mitigation by Matthew LaCroix
 
Partnering with the Forest Service: Lessons Learned by Sheila Jacobson
Partnering with the Forest Service: Lessons Learned by Sheila JacobsonPartnering with the Forest Service: Lessons Learned by Sheila Jacobson
Partnering with the Forest Service: Lessons Learned by Sheila Jacobson
 
Wetland MItigation by Jessica Kayser
 Wetland MItigation by Jessica Kayser Wetland MItigation by Jessica Kayser
Wetland MItigation by Jessica Kayser
 
Watershed Partnerships and Collaboration by Sue Mauger
Watershed Partnerships and Collaboration by Sue MaugerWatershed Partnerships and Collaboration by Sue Mauger
Watershed Partnerships and Collaboration by Sue Mauger
 
Watershed Restoration by Neil Stichert
Watershed Restoration by Neil Stichert Watershed Restoration by Neil Stichert
Watershed Restoration by Neil Stichert
 
Mitigation Site Identification in Southeast Alaska.
Mitigation Site Identification in Southeast Alaska. Mitigation Site Identification in Southeast Alaska.
Mitigation Site Identification in Southeast Alaska.
 
Building strategic partnerships with the Forest Service by Angela Coleman
Building strategic partnerships with the Forest Service by Angela ColemanBuilding strategic partnerships with the Forest Service by Angela Coleman
Building strategic partnerships with the Forest Service by Angela Coleman
 
Wetland Permitting in WA by Francis Naglich
Wetland Permitting in WA by Francis NaglichWetland Permitting in WA by Francis Naglich
Wetland Permitting in WA by Francis Naglich
 
Wetland Mitigation Programs by Steve Sego (Southeast Alaska Watershed Coalition)
Wetland Mitigation Programs by Steve Sego (Southeast Alaska Watershed Coalition)Wetland Mitigation Programs by Steve Sego (Southeast Alaska Watershed Coalition)
Wetland Mitigation Programs by Steve Sego (Southeast Alaska Watershed Coalition)
 
Community Based Wetland and Watershed Management
Community Based Wetland and Watershed ManagementCommunity Based Wetland and Watershed Management
Community Based Wetland and Watershed Management
 
Municipal Wetland Initiatives by Frankie Barker
Municipal Wetland Initiatives by Frankie BarkerMunicipal Wetland Initiatives by Frankie Barker
Municipal Wetland Initiatives by Frankie Barker
 
Biomass Photo Slideshow, Karen Petersen, UAF CES
Biomass Photo Slideshow, Karen Petersen, UAF CESBiomass Photo Slideshow, Karen Petersen, UAF CES
Biomass Photo Slideshow, Karen Petersen, UAF CES
 
Watershed Education and Outreach by Pam Randles
Watershed Education and Outreach by Pam RandlesWatershed Education and Outreach by Pam Randles
Watershed Education and Outreach by Pam Randles
 
Restoration: Education and Regulation by Bill Lucey
Restoration: Education and Regulation by Bill LuceyRestoration: Education and Regulation by Bill Lucey
Restoration: Education and Regulation by Bill Lucey
 
Restoration Project Analysis in Juneau Alaska by John Hudson
Restoration Project Analysis in Juneau Alaska by John HudsonRestoration Project Analysis in Juneau Alaska by John Hudson
Restoration Project Analysis in Juneau Alaska by John Hudson
 
In-Lieu Fee Programs by Michael Murphy
In-Lieu Fee Programs by Michael MurphyIn-Lieu Fee Programs by Michael Murphy
In-Lieu Fee Programs by Michael Murphy
 
The Southeast Alaska Mitigation Fund
The Southeast Alaska Mitigation FundThe Southeast Alaska Mitigation Fund
The Southeast Alaska Mitigation Fund
 
Planning for Watershed Restoration by Neil Stichert
Planning for Watershed Restoration by Neil StichertPlanning for Watershed Restoration by Neil Stichert
Planning for Watershed Restoration by Neil Stichert
 
Watershed Assessments by John Hudson
Watershed Assessments by John HudsonWatershed Assessments by John Hudson
Watershed Assessments by John Hudson
 

Similar to Juneau Wetland Management Plan by Teri Camery and Nicole Jones

2013 06 bristol deep sea container terminal - jerry stanford
2013   06 bristol deep sea container terminal - jerry stanford2013   06 bristol deep sea container terminal - jerry stanford
2013 06 bristol deep sea container terminal - jerry stanfordSevernEstuary
 
Regulations, timetable, challenges and key issues for Water Framework Directi...
Regulations, timetable, challenges and key issues for Water Framework Directi...Regulations, timetable, challenges and key issues for Water Framework Directi...
Regulations, timetable, challenges and key issues for Water Framework Directi...Environmental Protection Agency, Ireland
 
Dcr swm pgm rollout regional meetings 1
Dcr swm pgm rollout regional meetings 1Dcr swm pgm rollout regional meetings 1
Dcr swm pgm rollout regional meetings 1NSVRC
 
Fall 2023 JBTF presentation on Additional HRE project areas. .pptx
Fall 2023 JBTF presentation on Additional HRE project areas. .pptxFall 2023 JBTF presentation on Additional HRE project areas. .pptx
Fall 2023 JBTF presentation on Additional HRE project areas. .pptxecowatchers
 
DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...
DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...
DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...Deltares
 
Stormwater Webinar 11 14 12 Final
Stormwater Webinar 11 14 12 FinalStormwater Webinar 11 14 12 Final
Stormwater Webinar 11 14 12 Finalaearles
 
Water Wednesday 2009 July Mike Young as Robyn McLeod
Water Wednesday 2009 July Mike Young as Robyn McLeodWater Wednesday 2009 July Mike Young as Robyn McLeod
Water Wednesday 2009 July Mike Young as Robyn McLeodUniversity of Adelaide
 
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Toronto Public Consultation Unit
 
Future Watershed by Frank M. Piorko , Dir., Div. of Watershed Stewardship, DE...
Future Watershed by Frank M. Piorko , Dir., Div. of Watershed Stewardship, DE...Future Watershed by Frank M. Piorko , Dir., Div. of Watershed Stewardship, DE...
Future Watershed by Frank M. Piorko , Dir., Div. of Watershed Stewardship, DE...Kim Beidler
 
120509 Iasi RESTORE - Toni Scarr
120509 Iasi  RESTORE - Toni Scarr120509 Iasi  RESTORE - Toni Scarr
120509 Iasi RESTORE - Toni ScarrRESTORE
 
Central Pollution Control Board India
Central Pollution Control Board IndiaCentral Pollution Control Board India
Central Pollution Control Board IndiaKULDEEP VYAS
 
Mitigation symposium - Andre Corbould
Mitigation symposium - Andre CorbouldMitigation symposium - Andre Corbould
Mitigation symposium - Andre CorbouldYourAlberta
 
central pollution control board
central pollution control boardcentral pollution control board
central pollution control boardSruthi Tangirala
 
Presentation - Workshop 2: The implementation of the Polluter Pays Principle,...
Presentation - Workshop 2: The implementation of the Polluter Pays Principle,...Presentation - Workshop 2: The implementation of the Polluter Pays Principle,...
Presentation - Workshop 2: The implementation of the Polluter Pays Principle,...OECD Environment
 
6.0 Bhutan Open NAP Cas Case Study
6.0 Bhutan Open NAP Cas  Case Study6.0 Bhutan Open NAP Cas  Case Study
6.0 Bhutan Open NAP Cas Case StudyNAP Events
 

Similar to Juneau Wetland Management Plan by Teri Camery and Nicole Jones (20)

2013 06 bristol deep sea container terminal - jerry stanford
2013   06 bristol deep sea container terminal - jerry stanford2013   06 bristol deep sea container terminal - jerry stanford
2013 06 bristol deep sea container terminal - jerry stanford
 
Regulations, timetable, challenges and key issues for Water Framework Directi...
Regulations, timetable, challenges and key issues for Water Framework Directi...Regulations, timetable, challenges and key issues for Water Framework Directi...
Regulations, timetable, challenges and key issues for Water Framework Directi...
 
Dcr swm pgm rollout regional meetings 1
Dcr swm pgm rollout regional meetings 1Dcr swm pgm rollout regional meetings 1
Dcr swm pgm rollout regional meetings 1
 
Act basin priority project
Act basin priority projectAct basin priority project
Act basin priority project
 
Fall 2023 JBTF presentation on Additional HRE project areas. .pptx
Fall 2023 JBTF presentation on Additional HRE project areas. .pptxFall 2023 JBTF presentation on Additional HRE project areas. .pptx
Fall 2023 JBTF presentation on Additional HRE project areas. .pptx
 
DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...
DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...
DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...
 
Stormwater Webinar 11 14 12 Final
Stormwater Webinar 11 14 12 FinalStormwater Webinar 11 14 12 Final
Stormwater Webinar 11 14 12 Final
 
Water Wednesday 2009 July Mike Young as Robyn McLeod
Water Wednesday 2009 July Mike Young as Robyn McLeodWater Wednesday 2009 July Mike Young as Robyn McLeod
Water Wednesday 2009 July Mike Young as Robyn McLeod
 
2. 2nd Cycle Draft River Basin Management Plan - Colin Byrne
2. 2nd Cycle Draft River Basin Management Plan - Colin Byrne2. 2nd Cycle Draft River Basin Management Plan - Colin Byrne
2. 2nd Cycle Draft River Basin Management Plan - Colin Byrne
 
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
 
Future Watershed by Frank M. Piorko , Dir., Div. of Watershed Stewardship, DE...
Future Watershed by Frank M. Piorko , Dir., Div. of Watershed Stewardship, DE...Future Watershed by Frank M. Piorko , Dir., Div. of Watershed Stewardship, DE...
Future Watershed by Frank M. Piorko , Dir., Div. of Watershed Stewardship, DE...
 
Moore
MooreMoore
Moore
 
120509 Iasi RESTORE - Toni Scarr
120509 Iasi  RESTORE - Toni Scarr120509 Iasi  RESTORE - Toni Scarr
120509 Iasi RESTORE - Toni Scarr
 
Central Pollution Control Board India
Central Pollution Control Board IndiaCentral Pollution Control Board India
Central Pollution Control Board India
 
Mitigation symposium - Andre Corbould
Mitigation symposium - Andre CorbouldMitigation symposium - Andre Corbould
Mitigation symposium - Andre Corbould
 
central pollution control board
central pollution control boardcentral pollution control board
central pollution control board
 
Presentation - Workshop 2: The implementation of the Polluter Pays Principle,...
Presentation - Workshop 2: The implementation of the Polluter Pays Principle,...Presentation - Workshop 2: The implementation of the Polluter Pays Principle,...
Presentation - Workshop 2: The implementation of the Polluter Pays Principle,...
 
6.0 Bhutan Open NAP Cas Case Study
6.0 Bhutan Open NAP Cas  Case Study6.0 Bhutan Open NAP Cas  Case Study
6.0 Bhutan Open NAP Cas Case Study
 
3 WUL appendices
3 WUL appendices 3 WUL appendices
3 WUL appendices
 
Progress at Southwestern Travis County GCD
Progress at Southwestern Travis County GCD Progress at Southwestern Travis County GCD
Progress at Southwestern Travis County GCD
 

More from Southeast Alaska Watershed Coalition

Biofuels presentation, Karen Petersen UAF Cooperative Extension Service
Biofuels presentation, Karen Petersen UAF Cooperative Extension ServiceBiofuels presentation, Karen Petersen UAF Cooperative Extension Service
Biofuels presentation, Karen Petersen UAF Cooperative Extension ServiceSoutheast Alaska Watershed Coalition
 
Wetland Ecosystem Service Protocol for Southeast Alaska by Dr. Paul Adamus
Wetland Ecosystem Service Protocol for Southeast Alaska by Dr. Paul AdamusWetland Ecosystem Service Protocol for Southeast Alaska by Dr. Paul Adamus
Wetland Ecosystem Service Protocol for Southeast Alaska by Dr. Paul AdamusSoutheast Alaska Watershed Coalition
 

More from Southeast Alaska Watershed Coalition (13)

Stewardship Contracting by Keith Rush of The Nature Conservancy
Stewardship Contracting by Keith Rush of The Nature ConservancyStewardship Contracting by Keith Rush of The Nature Conservancy
Stewardship Contracting by Keith Rush of The Nature Conservancy
 
Biofuels presentation, Karen Petersen UAF Cooperative Extension Service
Biofuels presentation, Karen Petersen UAF Cooperative Extension ServiceBiofuels presentation, Karen Petersen UAF Cooperative Extension Service
Biofuels presentation, Karen Petersen UAF Cooperative Extension Service
 
WESPAK-SE: Wetland Functional Assessment by Paul Adamus
WESPAK-SE: Wetland Functional Assessment by Paul AdamusWESPAK-SE: Wetland Functional Assessment by Paul Adamus
WESPAK-SE: Wetland Functional Assessment by Paul Adamus
 
Watershed Condition Frameworks by Angela Coleman
Watershed Condition Frameworks by Angela ColemanWatershed Condition Frameworks by Angela Coleman
Watershed Condition Frameworks by Angela Coleman
 
Watershed Assessments by John Hudson
Watershed Assessments by John HudsonWatershed Assessments by John Hudson
Watershed Assessments by John Hudson
 
Federal Programs for Watershed Restoration by John Hudson
Federal Programs for Watershed Restoration by John HudsonFederal Programs for Watershed Restoration by John Hudson
Federal Programs for Watershed Restoration by John Hudson
 
Wetland Ecosystem Service Protocol for Southeast Alaska by Dr. Paul Adamus
Wetland Ecosystem Service Protocol for Southeast Alaska by Dr. Paul AdamusWetland Ecosystem Service Protocol for Southeast Alaska by Dr. Paul Adamus
Wetland Ecosystem Service Protocol for Southeast Alaska by Dr. Paul Adamus
 
Writing a Successful Project Proposal by Kathleen Dowd-Gailey
Writing a Successful Project Proposal by Kathleen Dowd-GaileyWriting a Successful Project Proposal by Kathleen Dowd-Gailey
Writing a Successful Project Proposal by Kathleen Dowd-Gailey
 
Southeast Alaska Watershed Coalition by Jessica Kayser
Southeast Alaska Watershed Coalition by Jessica KayserSoutheast Alaska Watershed Coalition by Jessica Kayser
Southeast Alaska Watershed Coalition by Jessica Kayser
 
Watershed Collaboration on the Yukon River by Ryan Toohey
Watershed Collaboration on the Yukon River by Ryan Toohey Watershed Collaboration on the Yukon River by Ryan Toohey
Watershed Collaboration on the Yukon River by Ryan Toohey
 
Restoration Partnerships: Lessons Learned by Scott Harris
Restoration Partnerships: Lessons Learned by Scott HarrisRestoration Partnerships: Lessons Learned by Scott Harris
Restoration Partnerships: Lessons Learned by Scott Harris
 
The Watershed Approach by Matthew Lacroix
The Watershed Approach by Matthew Lacroix The Watershed Approach by Matthew Lacroix
The Watershed Approach by Matthew Lacroix
 
Municipal Wetland Mapping by Mike Gracz
Municipal Wetland Mapping by Mike GraczMunicipal Wetland Mapping by Mike Gracz
Municipal Wetland Mapping by Mike Gracz
 

Recently uploaded

The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenHervé Boutemy
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Scott Keck-Warren
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piececharlottematthew16
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteDianaGray10
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxNavinnSomaal
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clashcharlottematthew16
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Manik S Magar
 
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostLeverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostZilliz
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 

Recently uploaded (20)

The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache Maven
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piece
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test Suite
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptx
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clash
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostLeverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 

Juneau Wetland Management Plan by Teri Camery and Nicole Jones

  • 1. Municipal Wetland Management: Overview of the CBJ process and the real life applications of the Juneau Wetlands Mgmt Plan Watershed Forum Presentation March 8, 2012 Presented by: Teri Camery, Senior Planner Nicole Jones, Planner I, CFM
  • 2. Juneau Wetlands Management Plan—Purpose • Classify wetlands into high-value (A and B), low-value (C and D), and Enhancement Potential based on ranked environmental functions according to the Adamus wetland methodology • Provide for reasoned, scientifically- supported decisions regarding protection and development of wetlands • Increase predictability for property owners
  • 3. Juneau Wetlands Management Plan—History Two stages of development: 3) 1980s wetland surveys and wetland functional analysis report 2) 1992 final Juneau Wetlands Management Plan, with policies, regulations, and implementation guidelines
  • 4. Juneau Wetlands Management Plan—History More recent versions of the plan —1997 and 2008— still use the original studies and study area. CBJ will begin the first phase of a four-year plan to update the JWMP this year.
  • 5.
  • 6.
  • 7. Juneau Wetlands Management Plan—Components • Wetland Categories—A, B, C, D, and EP • 140 different wetland units, each with its own functional analysis of 15 different wetland functions • Freshwater wetlands only, not estuarine • Wetland surveys, not wetland delineations
  • 8. Shoreline Corridor Rule Highest wetland category adjacent to streams
  • 9. Residential Road Corridor Rule Lower wetland category within 100-feet of some major roads
  • 10. Juneau Wetlands Management Plan—Components • Individual management regulations for each wetland category • CBJ Land Use Code wetland regulations implemented through CBJ Building and Zoning permits • Regulations allow consideration of new scientific evidence
  • 11. Juneau Wetlands Management Plan—Components Establishment of CBJ Wetlands Review Board • Volunteer Scientific Advisory Board appointed by the CBJ Assembly • General Permit Authority from Army Corps for low-value Category C and D wetlands • Board has an advisory role over projects that impact wetlands and salmon streams
  • 13. Wetlands Fill Permit—Process • Wetland Delineation • Application submittal – Fees $350-$1,600 • Staff Review • Wetlands Review Board – Conditions of approval • Wetland Permit Issued – Approximately 8-12 weeks • Applicant applies for a Building permit – Fees $50-??
  • 14. Wetland Permit Case Study WET2000 - 00001
  • 16. Partial Wetland Functional Analysis of J7 Wetland Unit • Add wetland functions of this wetland unit
  • 17. Wetlands Site Plan Pre-Wetland Fill
  • 18. Proposed Wetland Fill ±800 cu yards of fill—category B(r)C ±1,400 cu yards of fill—category B(r)C wetlands
  • 19. Wetland Fill Permit—Conditions Notice of Decision—see handout • 1,500 cubic yards of wetland fill was approved to allow for a new church with a parking area – 5,200 cubic yards of overburden was approved to be removed • 11 conditions of approval were applied to the wetland permit.
  • 21. Juneau Wetland Management Plan—Challenges • Wetland maps are surveys, not formal delineations. Delineations are valid for only 5 years. • Studies, maps, and regulations are outdated. Developed area of the Borough has expanded. • The majority of low-value C and D wetlands have been filled (an indicator of success); General Permit authority has lapsed • Poor enforcement of permit conditions
  • 22. Juneau Wetlands Management Plan Update • Four year project funded by federal CIAP which includes LiDAR, infrared imagery, and stream and wetland mapping and classification • New wetland methodology • New wetland categories and analysis, freshwater and estuarine
  • 23. Juneau Wetlands Management Plan Update • Update existing surveys and classifications and expand into developing areas
  • 24. Juneau Wetlands Management Plan Update Includes Land Use Code regulatory revisions for compatibility with: • Corps 2008 Mitigation Rule • other local mitigation programs such as SEALTrust fee-in-lieu; and • new General Permit authority (with Corps approval) for low-value wetlands
  • 25. Juneau Wetlands Management Plan Resources • Juneau Wetlands Management Plan http://www.juneau.org/cddftp/plansstudies.php • Wetlands Permit Application http://www.juneau.org/cddftp/documents/Wetlands_Applicati • CBJ Land Use Code Title 49 http://library.municode.com/index.aspx?clientId=13307&state Teri Camery teri_camery@ci.juneau.ak.us 586-0755 Nicole Jones nicole_jones@ci.juneau.ak.us 586-0218