SlideShare a Scribd company logo
1 of 33
Department of Electrical Engg.SIET,Dhenkanal.
Synergy Institute of Engineering &
Technology,Dhenkanal
Seminar on
Power Grid Design
Submitted by
Susanta Das
7th Semester B.Tech
Reg.No-0901230234
Seminar Guide Mr. A. Panda
Department of Electrical
Engg.SIET,Dhenkanal. 2
Outline of Presentation
 Introduction
 Need of Power Grids
 Selection Site
 Layout Design
1.Busbar Schemes
2.Electrical Layout Drawing
3.Bill of Material
 Safety Clearance in Grid
 Design of Earth Mat
 Control Room
 Switch/Relay Room
 Grid Equipments
 Conclusion
 Reference
Department of Electrical Engg.SIET,Dhenkanal.
INTRODUCTION
 An electrical grid is an
interconnected network for
delivering electricity from
suppliers to consumers. It
consists of three main
components; 1) power
station that produce
electricity from combustible
fuels or non-combustible
fuels; 2) transmission
lines that carry electricity
from power plants to
demand centers; and
3) transformers that reduce
voltage so distribution lines
carry power for final
delivery.
Department of Electrical Engg.SIET,Dhenkanal.
WHY WE NEED GRID?
 Improvement of
Reliability
 Improvement of
economics
 Improvement of
efficiency
 Imrovement of power
quality
 Improvement of security
& safety
 Controller of entire power
system
Department of Electrical Engg.SIET,Dhenkanal.
SELECTION OF SITE
 Selection of site for construction of a Grid Sub Station is the first
and important activity. This needs meticulous planning, fore-sight,
skillful observation and handling so that the selected site is
technically, environmentally, economically and socially optimal
and is the best suited to the requirements
The site should be:-
 As near the load centre as possible.
 Easily accessible to the public road to facilitate transport of
material
 Above highest flood level (HFL) so that there is no water logging.
 Sufficiently away from areas where police and military rifle
practices are held.
 Free from master plans / layouts or future development activities
to have free line
 The should be far away from Airport
Department of Electrical Engg.SIET,Dhenkanal.
REQUIREMENT OF LAND / AREA:-
 The site should have sufficient area to properly accommodate
the Sub Station buildings, structures, equipments, etc. and
should have the sufficient area for future extension of the
buildings and / or switchyard.
 The requirement of land for construction of Sub Station including
staff colony is as under:
S.No. Voltage Class of GSS Required Area
1 400 20.0 Hectare
2 220 6.0 Hectare
3 132 3.5 Hectare
Department of Electrical Engg.SIET,Dhenkanal.
Layout Design-Bus bar Schemes
The commonly used
bus bar schemes at
Sub Stations are:
 Single bus bar.
 Main and Auxiliary
bus bar.
 Double bus bar.
 Double Main and
Auxiliary bus bar
 One and a half
breaker scheme.
Department of Electrical Engg.SIET,Dhenkanal.
Single bus bar:-
 This is the simplest switching scheme
in which each circuit is provided with
one circuit breaker.
 This arrangement offers little security
against bus bar faults .
 The entire Sub Station is lost in case
of a fault on the bus bar.
 In case of maintenance of circuit
breaker, the associated feeder has
also to be shutdown.
Main and Auxiliary bus
Bar:-
 This is technically a single bus bar
arrangement with an additional
bus bar called “Auxiliary bus”.
 As in the case of single bus
arrangement, due to the fault the
entire substation is lost.
 This bus arrangement has been
extensively used in 132 kV Sub
Stations.
Department of Electrical Engg.SIET,Dhenkanal.
Double Bus Bar
 In this scheme, a double bus bar
arrangement is provided. Each circuit
can be connected to either one of these
bus bars through respective bus bar
isolator.
 Bus coupler breaker is also provided so
that the circuits can be switched on from
one bus to the other on load.
 This scheme suffers from the
disadvantage that when any circuit
breaker is taken out for maintenance, the
associated feeder has to be shutdown
 This Bus bar arrangement was generally
used in earlier 220 kV sub stations.
DOUBLE MAIN AND
AUXILIARY BUS BAR
ARRANGEMENT
 The limitation of double bus bar
scheme can be overcome by using
additional Auxiliary bus,.
 The feeder is transferred to the
Auxiliary bus during maintenance of its
controlling circuit breaker without
affecting the other ckt.
Department of Electrical Engg.SIET,Dhenkanal.
One & A Half Breaker Arrangement
 In this scheme, three circuit breakers
are used for controlling two circuits
which are connected between two bus
bars. Normally, both the bus bars are
in service.
 A fault on any one of the bus bars is
cleared by opening of the associated
circuit breakers connected to the faulty
bus bar without affecting continuity of
supply. Similarly any circuit breaker
can be taken out for maintenance
without causing interruption.
 Load transfer is achieved through the
breakers and, therefore, the operation
is simple.
 The breaker and a half scheme is best
for those substations which handle
large quantities of power and where
the orientation of out going.
 This scheme has been used in the
400 kV substations.
Department of Electrical Engg.SIET,Dhenkanal.
Electrical Layout Drawing
Department of Electrical Engg.SIET,Dhenkanal.
Department of Electrical Engg.SIET,Dhenkanal.
List of Material The lists of material are only typical and cover the general requirement. Any
other
 equipment / structure / material which may be required for construction of
Sub Station as
 per layout and other requirements and not included in the above typical lists
of
Department of Electrical Engg.SIET,Dhenkanal.
Department of Electrical Engg.SIET,Dhenkanal.
Safety Clearance The various equipments and associated / required facilities have to be so arranged within the substation that
specified minimum clearances are always available from the point of view of the system reliability and safety
of operating personnel. These include the minimum clearances from live parts to earth, between live parts of
adjacent phases and sectional clearance between live parts of adjacent circuits / bays. It must be ensured
that sufficient clearance to ground is also available within the Sub Station so as to ensure safety of the
personnel moving about within the switchyard.
 As per Rule 64 (2) of the Indian Electricity Rules, 1956, the following safety working
 clearances shall be maintained for the bare conductors and live parts of any apparatus in any
 Sub Stations, excluding over head lines of HV and EHV installations:
Nominal
system
Voltage
in (kv)
Highes
t
Syste
m
Voltag
e in(kv)
Lightin
g
impulse
Level(K
Vp)
Switching
Implulse
Voltage in
(KVp)
Minm
Clearance
Betn Phase
&Earth(mm)
Minm
clearanc
e Betn
Phases
(in mm)
Safety
Clearan
ce(mm)
Grou
nd
Clear
ance(
mm)
11 12 70 ---- 178 229 2600 3700
33 36 170 ---- 320 320 2800 3700
132 145 550
650
---- 1100
1300
1100
1300
3700
3800
4600
4600
220 245 950
1050
---- 1900
2100
1900
2100
4300
4600
5500
5500
400 420 1425 1050(Ph-
E)
3400
----
----
4200
6400 8000
Earth Mat Design
 Provision of adequate earthing system
in a Sub Station is extremely important
for the safety of the operating
personnel as well as for proper system
operation and performance of the
protective devices.
 The primary requirements of a good
earthing system in a Sub Station are
a):-The impedance to ground should
be as low as possible but it should not
exceed 1.0 (ONE) Ohm.
b):- The Step Potential, which is the
maximum value of the potential
difference possible of being shunted by
a human body between two accessible
points on the ground separated by the
distance of one pace (which may be
assumed to be one metre), should be
within safe limits.
c):- Touch Potential, which is the
maximum value of potential difference
between a point on the ground and a
point on an object likely to carry fault
current such that the points can be
touched by a person, should also be
within safe limits.
Department of Electrical Engg.SIET,Dhenkanal.
Cont.
The details of the earthing material generally used in a
sub station are given below:
Design of Control Room
 The control room is the
main command centre of
the substation. The entire
operation of the site is
monitored and controlled
from this central location.
 A control room may range
from a small, seldom
manned, non-ventilated
room to a large, air
conditioned area containing
numerous staff members
and electronic equipment
(PCs, control
panels/consoles, electrical
and electronic switching
devices, under floor
cabling, etc.).
Department of Electrical Engg.SIET,Dhenkanal.
Design of battery Room
 The Battery Room houses lead acid or
nickel cadmium batteries for uninterrupted
power supply (UPS) to the substation.
 In power grid normally 110 no. of batteries
are present, having each capacity of 2.1V
to maintain 220V output & the specific
gravity of liquid is 1.835.
 Power House FCBC are designed to
supply continuous power to the DC load
and simultaneously charge the batteries
connected. Input supply form 415V. AC 3
Phase or 220V. AC 1 Ph. is converted to
regulated DC. The charger has two
independent systems.
 Normally the DC Power is supplied to he
load by the Float Charger. It also supplies
trickle current to the battery to keep it
healthy. If the charging current under Float
Mode exceeds a set level.Boost charger is
switched ON. It supplies Quick charging
current to the battery. On battery reaching
the set value the Boost Charger is switched
OFF.
Department of Electrical Engg.SIET,Dhenkanal.
Design of Switch/Relay Room
 The Switch Room
accommodates high density of
electronic equipment housed
in cabinets and automated
switch-gear. In-cabinet
equipment maintain the
primary functions of the facility
and form the switching
interface between the Control
Room and the field
equipment. The area may also
accommodate a significant
amount of metering and
logging equipment. Due to the
high volume of critical
electronic equipment, it is
essential that a fire event be
detected before the operation
of the plant is compromised.Department of Electrical Engg.SIET,Dhenkanal.
Grid Equipments
Lighting Arrestor
 It is an instrument that protect
vital equipments in the grid
 when a lightning strikes a
power transmission line, the
induced high voltage travels
along the line towards both
ends; this arrester will bypass
this high voltage to the ground
so that the nearby transformer
will not be damaged.
Line Volt.(KV) L.A.Rating(KV)
400 327
220 180
132 108
33 27
CVT:-
 It is that type tfr which is used to
measure potential
 It is the major advantage of PT, &
also used for carrier
communication, which replace the
coupling capacitor.
 At first for carrier communication a
coupling capacitor is used with a
PT, which is costlier than CVT.
 It act as a high pass filter.
Connection diagram of CVT
Potential
transformer:-
 Potential Transformer or Voltage
Transformer are used in electrical
power system for stepping down
the system voltage to a safe value
which can be fed to low ratings
meters and relays. Commercially
available relays and meters used
for protection and metering, are
designed for low voltage.
Current Transformer:-
 A current transformer is
used in high voltage
circuits where it is not
possible to measure
current directly.
 A CT is a step up
transformer with only one
turn in primary. There will
be as many cores based
on the purposes like
metering, protection etc.
 The secondary of a CT
should never be kept open
circuited because very high
flux will be developed in the
secondary and hence it
may be damaged.
Power TRANSFORMER
 It is a static device which
transforms electrical energy from
one ckt to another ckt without
change of frequency, but changing
voltage with the principle mutual
induction.
 Most of the power transformer are
in MVA ratings.
 It is the most costlier equipments
in the grid.
 INSULATOR:-
 Insulators are used to prevent
flow of current from
conducting material to non
conducting material.
 It should be mechanically
strong & high dielectric
strength.
 Each insulator rating is of
11kv to 16kv.
Wave Trap:-
It is the combination of inductance &
capacitance, which act as a low pass filter,
which passes low frequencies in to the
grid, & this frequency is used in the grid.
The Line trap offers high impedance to
the high frequency communication signals
thus obstructs the flow of these signals in
to the substation bus bars. If there were
not to be there, then signal loss is more
and communication will be
ineffective/probably impossible.
Circuit breaker:-
 It is protective equipments in the
grid.
 It is the automatic on load switch.
 There are of 5 medium type of
circuit breaker., but SF6 ckt
breaker is used for best.
Isolators:-
 This is an off load switching
device to used open or close for
flow of current or not to flow
respectively in the grid.
Conclusion:-
 Grid is the nodal point of the
entire power system.
 It has two objectives i.e.1: Supply
Quality Power, 2:Supply the power
from source to load with an
economic reasons.
 AS Grids are interconnected so,
there is an improvement of
reliability of can achieved.
 As grid is the nodal point, if it fails
to work, then entire power system
will fails.
 Grid efficiency is lower i.e. 50-
70%.
 As Grid has too many equipments
so, design of grid is too costlier.
Reference:-
 Construction Manual for substations by Shreemat Pandey Chairman &
Managing Director Jaipur Rajasthan Rajya Vidyut Prasaran Nigam Ltd.
 Albert, R., Albert, I., and Nakarado, G. L. (2004). Structural Vulnerability of
the North American Power Grid. Physical Review E 69 025103(R). 1-4 pgs.
 Grid Manual of OPTCL.
 http://www.powergridindia.com
33Dept of Electrical Engg.

More Related Content

What's hot

Flexible ac transmission system
Flexible ac transmission systemFlexible ac transmission system
Flexible ac transmission systemUday Wankar
 
220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training pptShubham Patel
 
Training report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substationTraining report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substationankesh kumar
 
400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohitMohit Awasthi
 
Introduction to power system analysis
Introduction to power system analysisIntroduction to power system analysis
Introduction to power system analysisRevathi Subramaniam
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design) SayanSarkar55
 
Control of hvdc system
Control of hvdc systemControl of hvdc system
Control of hvdc systemAazim Rasool
 
PPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppclPPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppclVISHAL VERMA
 
Power grid operation in India
Power grid operation in IndiaPower grid operation in India
Power grid operation in IndiaMahim Srivastava
 
Electric substation
Electric substation Electric substation
Electric substation ANNU KUMAR
 
Micro computer control of dc drive
Micro computer control of dc driveMicro computer control of dc drive
Micro computer control of dc driveraviarmugam
 
Hydrothermal scheduling
Hydrothermal schedulingHydrothermal scheduling
Hydrothermal schedulingASHIRBAD BARIK
 
PPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONPPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONRavi Phadtare
 
Three phase voltage source inverter
Three phase voltage source inverterThree phase voltage source inverter
Three phase voltage source invertertamilnesaner
 

What's hot (20)

Flexible ac transmission system
Flexible ac transmission systemFlexible ac transmission system
Flexible ac transmission system
 
220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt
 
Training report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substationTraining report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substation
 
400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit
 
Introduction to power system analysis
Introduction to power system analysisIntroduction to power system analysis
Introduction to power system analysis
 
33 kv substation vt report
33 kv substation vt report33 kv substation vt report
33 kv substation vt report
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design)
 
Control of hvdc system
Control of hvdc systemControl of hvdc system
Control of hvdc system
 
PPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppclPPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppcl
 
Power grid operation in India
Power grid operation in IndiaPower grid operation in India
Power grid operation in India
 
MTDC SYSTEMS
MTDC SYSTEMSMTDC SYSTEMS
MTDC SYSTEMS
 
Electric substation
Electric substation Electric substation
Electric substation
 
Micro computer control of dc drive
Micro computer control of dc driveMicro computer control of dc drive
Micro computer control of dc drive
 
132 kv
132 kv132 kv
132 kv
 
Single line diagram
Single line diagramSingle line diagram
Single line diagram
 
Hydrothermal scheduling
Hydrothermal schedulingHydrothermal scheduling
Hydrothermal scheduling
 
PPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONPPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATION
 
Corona in power system
Corona  in power systemCorona  in power system
Corona in power system
 
Underground cables vs overhead lines
Underground cables vs overhead linesUnderground cables vs overhead lines
Underground cables vs overhead lines
 
Three phase voltage source inverter
Three phase voltage source inverterThree phase voltage source inverter
Three phase voltage source inverter
 

Viewers also liked

Financial Analysis HINDALCO 2009
Financial Analysis HINDALCO 2009Financial Analysis HINDALCO 2009
Financial Analysis HINDALCO 2009Govind Kumar Rai
 
PPT POWER GRID CORPORATION OF INDIA LIMITED
PPT POWER GRID CORPORATION OF INDIA LIMITED PPT POWER GRID CORPORATION OF INDIA LIMITED
PPT POWER GRID CORPORATION OF INDIA LIMITED Aditya Shankar
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plantDr. Ramesh B
 
Best ppt onRenewable & hydropower
Best ppt onRenewable & hydropowerBest ppt onRenewable & hydropower
Best ppt onRenewable & hydropowerRonak Thakare
 
Hydro power-plant
Hydro power-plantHydro power-plant
Hydro power-plantpranavn007
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plantYuri Melliza
 
Anurag Arpan (PPT on AutoCAD )
Anurag Arpan (PPT on AutoCAD )Anurag Arpan (PPT on AutoCAD )
Anurag Arpan (PPT on AutoCAD )Anurag Arpan
 

Viewers also liked (11)

Financial Analysis HINDALCO 2009
Financial Analysis HINDALCO 2009Financial Analysis HINDALCO 2009
Financial Analysis HINDALCO 2009
 
PPT POWER GRID CORPORATION OF INDIA LIMITED
PPT POWER GRID CORPORATION OF INDIA LIMITED PPT POWER GRID CORPORATION OF INDIA LIMITED
PPT POWER GRID CORPORATION OF INDIA LIMITED
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Best ppt onRenewable & hydropower
Best ppt onRenewable & hydropowerBest ppt onRenewable & hydropower
Best ppt onRenewable & hydropower
 
Auto Cad Powerpoint
Auto Cad PowerpointAuto Cad Powerpoint
Auto Cad Powerpoint
 
Smart grid ppt
Smart grid pptSmart grid ppt
Smart grid ppt
 
Smart Grid Technology
Smart Grid TechnologySmart Grid Technology
Smart Grid Technology
 
Hydro power-plant
Hydro power-plantHydro power-plant
Hydro power-plant
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Anurag Arpan (PPT on AutoCAD )
Anurag Arpan (PPT on AutoCAD )Anurag Arpan (PPT on AutoCAD )
Anurag Arpan (PPT on AutoCAD )
 

Similar to Ppt power grid design

Universal Four Leg v4
Universal Four Leg v4Universal Four Leg v4
Universal Four Leg v4AxelDijksman
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at JassureShuvam Pathania
 
NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )AnandMohan271812
 
NTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship reportNTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship reportAneel-k Suthar
 
33016052 electric-traction-system
33016052 electric-traction-system33016052 electric-traction-system
33016052 electric-traction-systemMasterhead Jack
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentationRajashekar Gurrala
 
internship report of 220/132 kV substation
internship report of 220/132 kV substationinternship report of 220/132 kV substation
internship report of 220/132 kV substationShivamUpadhyay86734
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)IJERD Editor
 
Smart Wireless Battery Charger with Charging Monitor: A Review
Smart Wireless Battery Charger with Charging Monitor: A ReviewSmart Wireless Battery Charger with Charging Monitor: A Review
Smart Wireless Battery Charger with Charging Monitor: A ReviewIRJET Journal
 
Design of substation
Design of substationDesign of substation
Design of substationSayanSarkar55
 
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdfDesign_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdfEngnr Kami Zeb
 
Variable Frequency on Wireless Power Transfer for Pacemaker using Embedded Te...
Variable Frequency on Wireless Power Transfer for Pacemaker using Embedded Te...Variable Frequency on Wireless Power Transfer for Pacemaker using Embedded Te...
Variable Frequency on Wireless Power Transfer for Pacemaker using Embedded Te...IRJET Journal
 
33016052 electric-traction-system
33016052 electric-traction-system33016052 electric-traction-system
33016052 electric-traction-systembabu yadav
 
Green power zone
Green power zoneGreen power zone
Green power zoneCHESF
 
Internship doc 33 11 kv substation
Internship doc 33 11 kv substation  Internship doc 33 11 kv substation
Internship doc 33 11 kv substation Madeen Kumar
 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation Tejveer Choudhary
 
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfindustrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfDevesh54
 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptAshutosh Srivastava
 
Module 4 power generation & Economics - Substation vtu syllabus
Module 4 power generation & Economics - Substation vtu syllabusModule 4 power generation & Economics - Substation vtu syllabus
Module 4 power generation & Economics - Substation vtu syllabusDrCVMOHAN
 

Similar to Ppt power grid design (20)

Universal Four Leg v4
Universal Four Leg v4Universal Four Leg v4
Universal Four Leg v4
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
 
NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )
 
NTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship reportNTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship report
 
33016052 electric-traction-system
33016052 electric-traction-system33016052 electric-traction-system
33016052 electric-traction-system
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
 
internship report of 220/132 kV substation
internship report of 220/132 kV substationinternship report of 220/132 kV substation
internship report of 220/132 kV substation
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 
Smart Wireless Battery Charger with Charging Monitor: A Review
Smart Wireless Battery Charger with Charging Monitor: A ReviewSmart Wireless Battery Charger with Charging Monitor: A Review
Smart Wireless Battery Charger with Charging Monitor: A Review
 
Design of substation
Design of substationDesign of substation
Design of substation
 
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdfDesign_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
 
Variable Frequency on Wireless Power Transfer for Pacemaker using Embedded Te...
Variable Frequency on Wireless Power Transfer for Pacemaker using Embedded Te...Variable Frequency on Wireless Power Transfer for Pacemaker using Embedded Te...
Variable Frequency on Wireless Power Transfer for Pacemaker using Embedded Te...
 
33016052 electric-traction-system
33016052 electric-traction-system33016052 electric-traction-system
33016052 electric-traction-system
 
Green power zone
Green power zoneGreen power zone
Green power zone
 
Internship doc 33 11 kv substation
Internship doc 33 11 kv substation  Internship doc 33 11 kv substation
Internship doc 33 11 kv substation
 
bhuwnesh
bhuwneshbhuwnesh
bhuwnesh
 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation
 
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfindustrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation ppt
 
Module 4 power generation & Economics - Substation vtu syllabus
Module 4 power generation & Economics - Substation vtu syllabusModule 4 power generation & Economics - Substation vtu syllabus
Module 4 power generation & Economics - Substation vtu syllabus
 

Recently uploaded

Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 

Recently uploaded (20)

Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 

Ppt power grid design

  • 1. Department of Electrical Engg.SIET,Dhenkanal.
  • 2. Synergy Institute of Engineering & Technology,Dhenkanal Seminar on Power Grid Design Submitted by Susanta Das 7th Semester B.Tech Reg.No-0901230234 Seminar Guide Mr. A. Panda Department of Electrical Engg.SIET,Dhenkanal. 2
  • 3. Outline of Presentation  Introduction  Need of Power Grids  Selection Site  Layout Design 1.Busbar Schemes 2.Electrical Layout Drawing 3.Bill of Material  Safety Clearance in Grid  Design of Earth Mat  Control Room  Switch/Relay Room  Grid Equipments  Conclusion  Reference Department of Electrical Engg.SIET,Dhenkanal.
  • 4. INTRODUCTION  An electrical grid is an interconnected network for delivering electricity from suppliers to consumers. It consists of three main components; 1) power station that produce electricity from combustible fuels or non-combustible fuels; 2) transmission lines that carry electricity from power plants to demand centers; and 3) transformers that reduce voltage so distribution lines carry power for final delivery. Department of Electrical Engg.SIET,Dhenkanal.
  • 5. WHY WE NEED GRID?  Improvement of Reliability  Improvement of economics  Improvement of efficiency  Imrovement of power quality  Improvement of security & safety  Controller of entire power system Department of Electrical Engg.SIET,Dhenkanal.
  • 6. SELECTION OF SITE  Selection of site for construction of a Grid Sub Station is the first and important activity. This needs meticulous planning, fore-sight, skillful observation and handling so that the selected site is technically, environmentally, economically and socially optimal and is the best suited to the requirements The site should be:-  As near the load centre as possible.  Easily accessible to the public road to facilitate transport of material  Above highest flood level (HFL) so that there is no water logging.  Sufficiently away from areas where police and military rifle practices are held.  Free from master plans / layouts or future development activities to have free line  The should be far away from Airport Department of Electrical Engg.SIET,Dhenkanal.
  • 7. REQUIREMENT OF LAND / AREA:-  The site should have sufficient area to properly accommodate the Sub Station buildings, structures, equipments, etc. and should have the sufficient area for future extension of the buildings and / or switchyard.  The requirement of land for construction of Sub Station including staff colony is as under: S.No. Voltage Class of GSS Required Area 1 400 20.0 Hectare 2 220 6.0 Hectare 3 132 3.5 Hectare Department of Electrical Engg.SIET,Dhenkanal.
  • 8. Layout Design-Bus bar Schemes The commonly used bus bar schemes at Sub Stations are:  Single bus bar.  Main and Auxiliary bus bar.  Double bus bar.  Double Main and Auxiliary bus bar  One and a half breaker scheme. Department of Electrical Engg.SIET,Dhenkanal.
  • 9. Single bus bar:-  This is the simplest switching scheme in which each circuit is provided with one circuit breaker.  This arrangement offers little security against bus bar faults .  The entire Sub Station is lost in case of a fault on the bus bar.  In case of maintenance of circuit breaker, the associated feeder has also to be shutdown. Main and Auxiliary bus Bar:-  This is technically a single bus bar arrangement with an additional bus bar called “Auxiliary bus”.  As in the case of single bus arrangement, due to the fault the entire substation is lost.  This bus arrangement has been extensively used in 132 kV Sub Stations. Department of Electrical Engg.SIET,Dhenkanal.
  • 10. Double Bus Bar  In this scheme, a double bus bar arrangement is provided. Each circuit can be connected to either one of these bus bars through respective bus bar isolator.  Bus coupler breaker is also provided so that the circuits can be switched on from one bus to the other on load.  This scheme suffers from the disadvantage that when any circuit breaker is taken out for maintenance, the associated feeder has to be shutdown  This Bus bar arrangement was generally used in earlier 220 kV sub stations. DOUBLE MAIN AND AUXILIARY BUS BAR ARRANGEMENT  The limitation of double bus bar scheme can be overcome by using additional Auxiliary bus,.  The feeder is transferred to the Auxiliary bus during maintenance of its controlling circuit breaker without affecting the other ckt. Department of Electrical Engg.SIET,Dhenkanal.
  • 11. One & A Half Breaker Arrangement  In this scheme, three circuit breakers are used for controlling two circuits which are connected between two bus bars. Normally, both the bus bars are in service.  A fault on any one of the bus bars is cleared by opening of the associated circuit breakers connected to the faulty bus bar without affecting continuity of supply. Similarly any circuit breaker can be taken out for maintenance without causing interruption.  Load transfer is achieved through the breakers and, therefore, the operation is simple.  The breaker and a half scheme is best for those substations which handle large quantities of power and where the orientation of out going.  This scheme has been used in the 400 kV substations. Department of Electrical Engg.SIET,Dhenkanal.
  • 12. Electrical Layout Drawing Department of Electrical Engg.SIET,Dhenkanal.
  • 13. Department of Electrical Engg.SIET,Dhenkanal.
  • 14. List of Material The lists of material are only typical and cover the general requirement. Any other  equipment / structure / material which may be required for construction of Sub Station as  per layout and other requirements and not included in the above typical lists of Department of Electrical Engg.SIET,Dhenkanal.
  • 15. Department of Electrical Engg.SIET,Dhenkanal.
  • 16.
  • 17. Safety Clearance The various equipments and associated / required facilities have to be so arranged within the substation that specified minimum clearances are always available from the point of view of the system reliability and safety of operating personnel. These include the minimum clearances from live parts to earth, between live parts of adjacent phases and sectional clearance between live parts of adjacent circuits / bays. It must be ensured that sufficient clearance to ground is also available within the Sub Station so as to ensure safety of the personnel moving about within the switchyard.  As per Rule 64 (2) of the Indian Electricity Rules, 1956, the following safety working  clearances shall be maintained for the bare conductors and live parts of any apparatus in any  Sub Stations, excluding over head lines of HV and EHV installations: Nominal system Voltage in (kv) Highes t Syste m Voltag e in(kv) Lightin g impulse Level(K Vp) Switching Implulse Voltage in (KVp) Minm Clearance Betn Phase &Earth(mm) Minm clearanc e Betn Phases (in mm) Safety Clearan ce(mm) Grou nd Clear ance( mm) 11 12 70 ---- 178 229 2600 3700 33 36 170 ---- 320 320 2800 3700 132 145 550 650 ---- 1100 1300 1100 1300 3700 3800 4600 4600 220 245 950 1050 ---- 1900 2100 1900 2100 4300 4600 5500 5500 400 420 1425 1050(Ph- E) 3400 ---- ---- 4200 6400 8000
  • 18. Earth Mat Design  Provision of adequate earthing system in a Sub Station is extremely important for the safety of the operating personnel as well as for proper system operation and performance of the protective devices.  The primary requirements of a good earthing system in a Sub Station are a):-The impedance to ground should be as low as possible but it should not exceed 1.0 (ONE) Ohm. b):- The Step Potential, which is the maximum value of the potential difference possible of being shunted by a human body between two accessible points on the ground separated by the distance of one pace (which may be assumed to be one metre), should be within safe limits. c):- Touch Potential, which is the maximum value of potential difference between a point on the ground and a point on an object likely to carry fault current such that the points can be touched by a person, should also be within safe limits. Department of Electrical Engg.SIET,Dhenkanal.
  • 19. Cont. The details of the earthing material generally used in a sub station are given below:
  • 20. Design of Control Room  The control room is the main command centre of the substation. The entire operation of the site is monitored and controlled from this central location.  A control room may range from a small, seldom manned, non-ventilated room to a large, air conditioned area containing numerous staff members and electronic equipment (PCs, control panels/consoles, electrical and electronic switching devices, under floor cabling, etc.). Department of Electrical Engg.SIET,Dhenkanal.
  • 21. Design of battery Room  The Battery Room houses lead acid or nickel cadmium batteries for uninterrupted power supply (UPS) to the substation.  In power grid normally 110 no. of batteries are present, having each capacity of 2.1V to maintain 220V output & the specific gravity of liquid is 1.835.  Power House FCBC are designed to supply continuous power to the DC load and simultaneously charge the batteries connected. Input supply form 415V. AC 3 Phase or 220V. AC 1 Ph. is converted to regulated DC. The charger has two independent systems.  Normally the DC Power is supplied to he load by the Float Charger. It also supplies trickle current to the battery to keep it healthy. If the charging current under Float Mode exceeds a set level.Boost charger is switched ON. It supplies Quick charging current to the battery. On battery reaching the set value the Boost Charger is switched OFF. Department of Electrical Engg.SIET,Dhenkanal.
  • 22. Design of Switch/Relay Room  The Switch Room accommodates high density of electronic equipment housed in cabinets and automated switch-gear. In-cabinet equipment maintain the primary functions of the facility and form the switching interface between the Control Room and the field equipment. The area may also accommodate a significant amount of metering and logging equipment. Due to the high volume of critical electronic equipment, it is essential that a fire event be detected before the operation of the plant is compromised.Department of Electrical Engg.SIET,Dhenkanal.
  • 23. Grid Equipments Lighting Arrestor  It is an instrument that protect vital equipments in the grid  when a lightning strikes a power transmission line, the induced high voltage travels along the line towards both ends; this arrester will bypass this high voltage to the ground so that the nearby transformer will not be damaged. Line Volt.(KV) L.A.Rating(KV) 400 327 220 180 132 108 33 27
  • 24. CVT:-  It is that type tfr which is used to measure potential  It is the major advantage of PT, & also used for carrier communication, which replace the coupling capacitor.  At first for carrier communication a coupling capacitor is used with a PT, which is costlier than CVT.  It act as a high pass filter. Connection diagram of CVT
  • 25. Potential transformer:-  Potential Transformer or Voltage Transformer are used in electrical power system for stepping down the system voltage to a safe value which can be fed to low ratings meters and relays. Commercially available relays and meters used for protection and metering, are designed for low voltage.
  • 26. Current Transformer:-  A current transformer is used in high voltage circuits where it is not possible to measure current directly.  A CT is a step up transformer with only one turn in primary. There will be as many cores based on the purposes like metering, protection etc.  The secondary of a CT should never be kept open circuited because very high flux will be developed in the secondary and hence it may be damaged.
  • 27. Power TRANSFORMER  It is a static device which transforms electrical energy from one ckt to another ckt without change of frequency, but changing voltage with the principle mutual induction.  Most of the power transformer are in MVA ratings.  It is the most costlier equipments in the grid.
  • 28.  INSULATOR:-  Insulators are used to prevent flow of current from conducting material to non conducting material.  It should be mechanically strong & high dielectric strength.  Each insulator rating is of 11kv to 16kv. Wave Trap:- It is the combination of inductance & capacitance, which act as a low pass filter, which passes low frequencies in to the grid, & this frequency is used in the grid. The Line trap offers high impedance to the high frequency communication signals thus obstructs the flow of these signals in to the substation bus bars. If there were not to be there, then signal loss is more and communication will be ineffective/probably impossible.
  • 29. Circuit breaker:-  It is protective equipments in the grid.  It is the automatic on load switch.  There are of 5 medium type of circuit breaker., but SF6 ckt breaker is used for best. Isolators:-  This is an off load switching device to used open or close for flow of current or not to flow respectively in the grid.
  • 30. Conclusion:-  Grid is the nodal point of the entire power system.  It has two objectives i.e.1: Supply Quality Power, 2:Supply the power from source to load with an economic reasons.  AS Grids are interconnected so, there is an improvement of reliability of can achieved.  As grid is the nodal point, if it fails to work, then entire power system will fails.  Grid efficiency is lower i.e. 50- 70%.  As Grid has too many equipments so, design of grid is too costlier.
  • 31. Reference:-  Construction Manual for substations by Shreemat Pandey Chairman & Managing Director Jaipur Rajasthan Rajya Vidyut Prasaran Nigam Ltd.  Albert, R., Albert, I., and Nakarado, G. L. (2004). Structural Vulnerability of the North American Power Grid. Physical Review E 69 025103(R). 1-4 pgs.  Grid Manual of OPTCL.  http://www.powergridindia.com
  • 32.