2. Project Scope Management The processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully Why Do We Manage Scope? Can’t manage schedule and budget if scope is out of control (Triple Constraint) Scope docs are used to manage expectations
3. Scope Management Key Points What is scope management Checking to ensure that one is completing work Saying No to additional work not in the charter Preventing extra work Work Breakdown Structure (WBS) Foundation of the project, all planning and controlling is based on the WBS Identifies all work to be performed, if it is not in the WBS it does not need to be done Graphical picture of work
5. How Do We Manage Scope? Five processes Scope Planning Scope Definition Create WBS Scope Verification Scope Control Scope Planning Scope Definition Create WBS Scope Verification Scope Control
46. Why Time Management?Part of triple constraint, can’t manage one without the others (scope, time, and quality) Second hardest section on the test behind integration
57. Planning componentOrganizational Process Assets Activity List Project Scope Statement Activity Attributes Work Breakdown Structure Milestone List WBS Dictionary Requested Changes Project Management Plan
58.
59. Planning Component – WBS items that cannot be broken down into work packages are put in a:
60. Control Account – High level planning dates for the scope to be defined
107. Schedule modelInputs Schedule Management Plan Performance measurements Outputs Requested changes Schedule Baseline Recommended corrective actions Performance reports Organizational process assets updates Approved Change Requests Activity list updates Activity attribute updates Project Management Plan updates
108.
109. Free Slack – Available delay time without impacting start of successor
110. Total Slack – Amount of time a task can be delayed without delaying project completion date
111. Project Slack – Amount of time a project can be delayed without impacting completion dates imposed by client
112. Crashing – Adding resources to critical path items to shorten schedule
113. Fast Tracking – Performing critical path tasks in parallel rather than series
114.
115. Basic Principles of Cost Management Most members of an executive board have a better understanding and are more interested in financial terms than IT terms, so IT project managers must speak their language. Profits are revenues minus expenses. Life cycle costing considers the total cost of ownership, or development plus support costs, for a project. Cash flow analysis determines the estimated annual costs and benefits for a project and the resulting annual cash flow. Tangible costs or benefits are those costs or benefits that an organization can easily measure in dollars. Intangible costs or benefits are costs or benefits that are difficult to measure in monetary terms. Direct costs are costs that can be directly related to producing the products and services of the project. Indirect costs are costs that are not directly related to the products or services of the project, but are indirectly related to performing the project. Sunk cost is money that has been spent in the past; when deciding what projects to invest in or continue, you should not include sunk costs.
116. Earned value Management The earned value Management involves developing these key values for each schedule activity, work package, or control account: Planned value (PV). PV is the budgeted cost for the work scheduled to be completed on an activity or WBS component up to a given point in time. Earned value (EV). EV is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period. Actual cost (AC). AC is the total cost incurred in accomplishing work on the schedule activity or WBS component during a given time period. This AC must correspond in definition and coverage to whatever was budgeted for the PV and the EV (e.g., direct hours only, direct costs only, or all costs including indirect costs). Cost variance (CV). CV equals earned value (EV) minus actual cost (AC). The cost variance at the end of the project will be the difference between the budget at completion (BAC) and the actual amount spent. Formula: CV= EV - AC Schedule variance (SV). SV equals earned value (EV) minus planned value (PV). Schedule variance will ultimately equal zero when the project is completed because all of the planned values will have been earned. Formula: SV = EV - PV These two values, the CV and SV, can be converted to efficiency indicators to reflect the cost and schedule performance of any project. Cost performance index (CPI). A CPI value less than 1.0 indicates a cost overrun of the estimates. A CPI value greater than 1.0 indicates a cost underrun of the estimates. CPI equals the ratio of the EV to the AC. The CPI is the most commonly used cost-efficiency indicator. Formula: CPI = EV/AC Schedule performance index (SPI). The SPI is used, in addition to the schedule status to predict the completion date and is sometimes used in conjunction with the CPI to forecast the project completion estimates. SPI equals the ratio of the EV to the PV. Formula: SPI = EV/PV