1. AUD 1301 - INTERNAL
AUDITING PROJECT MANAGEMENT
Buildinga200sqmhouse
Alod, Joyce Alexandra A.
Dalisay, Katherine Meg C.
Lanzanas, Khristephen Kyle C.
Relos, Roy A.
Tamayo, Keziah D.
Section 4
5. TASK A
0 10
0 10
Dig
Foundation
TASK B
10 30
10
Build walls
TASK C
10 20
10 30
Build roof
TASK E
30 34
30 33
Install
fixtures
TASK D
30 32
30 33
Install
faucets
TASK F
30 33
30 33
Install
carpetings
33 33
33 33
Finished
building
house
Float = 0
Float = 0
Float =10
Float =1
Float =1
Float = 0
Float = 0
10 days
20 days
10 days
2 days
4 days
3 days
0 days
30
CRITICAL PATH CHART
Critical Path
Task A -> Task B -> Task F
Total Project Time:
33 Days
6. TASK A
0 10
0 10
Dig
Foundation
TASK B
10 30
10
Build walls
TASK F
30 33
30 33
Install
carpetings
33 33
33 33
Finished
building
house
Float = 0
Float = 0
Float = 0
Float = 0
10 days
20 days
3 days
0 days
30
CRITICAL PATH CHART
Critical Path
Task A -> Task B -> Task F
Total Project Time:
33 Days