SOFTWARE TOOLS - I
UNDER GUIDANCE
PROF. XXXXXXX
PREPARED BY
NAEEM LASHKARWALA
XXXXXXXXXXX
ACADEMIC YEAR (2023-2025)
MASTER OF TECHNOLOGY (XXXXXXXXXXX)
MICROSOFT PROJECT
MICROSOFT
PROJECT
2016
BRIEF DETAILS OF PRESENTATION
IN THIS PRESENTATION WE WILL COVER FOLLOWING TOPICS
I. INTRODUCTION TO THE SCREEN / USER
INTERFACE
II. INITIAL SETTINGS SHOULD BE DONE BEFORE
STARTING
III. DIFFERENT OPRATIONS IN PROJECT
IV. FINDING CRITICAL PATH
V. FORMATING OF BAR
VI. PROJECT SUMMARY TASK
VII. ALL ABOUT CALENDER IN MS PROJECT
VIII. ADDING NEW COLUMNS
IX. ADDING RESOURCES AND RESOURCE’S
SHEET
X. ASSIGNING OF RESOURCES
INTRODUCTION OF THE SCREEN /
USER INTERFACE
1
Task Mode Has
Two Types
1. Manually
2. auto
Task Name is The
Activity Name
Ex.., Excavation,
PCC,ETC..
Duration is
Duration or Taken
Time By Activity
or Task
Task Or Activity
Start Date
Task or Activity
Finish Date
Predecessors
Contains main 4
Constraints That
Can Decide That
Which Activities
Will Start
Together or
Parallel.
INITIAL SETTINGS SHOULD BE DONE
BEFORE STARTING
2
I. Open MS Project 2016.
II. Before Start Using it, You Need to Set Certain Things on it for that Go to the
file menu on the right hand side upper corner.
III. You Get to See The Last Tab of Options There. Click on it.
IV. A Dialogue box will Prompt Up as Shown in Image.
Go To File
Menu
Click on
‘Options’
Prompt
Dialogue Box
GENERAL TAB
In General TAB You Need to Set the DATE & Time
Format From Any of The Options above but
Generally Use DD-MM-YY
DISPLAY TAB
In Display Tab Set Currency and Calendar According
to Your Project and Country.
SCHEDULE TAB
In Schedule TAB Set Your Work Timing and Change
Assignment Unit Percentage to Decimal and Change
Task Mode to Manually to Auto for Ease of Work.
ADVANCED TAB
In Advanced TAB, There are Chances of make
mistakes in entries, to overcome that we can undo
them by CTRL+Z, But There an Option in this TAB by
which you can increase this Undo Level, By Default
it is 20. You Can Changed this Level According to
Your Work.
DIFFERENT OPRATIONS IN PROJECT
/ PRACTICAL EXAMPLE
3
Task Mode Has
Two Types
1. Manually
2. auto
Task Name is The
Activity Name
Ex.., Excavation,
PCC,ETC..
Duration is
Duration or Taken
Time By Activity
or Task
Task Or Activity
Start Date
Task or Activity
Finish Date
Predecessors
Contains main 4
Constraints That
Can Decide That
Which Activities
Will Start
Together or
Parallel.
FINDING CRITICAL PATH
4
Find Critical Path
of Network By
Clicking on
Critical Path
Option
After Clicking
Critical Activity
Option You Can
See The Change
of Color of Chart
Blue to Red.
Task Bar
Format
Menu
Critical
Path
FORMATING OF BAR
5
I. So You Can See That The Critical Path Has Been Highlighted by Red Bars.
II. Now If You Look at the Bars The Only Gives the Duration of Activity as Bar, No
Other Information Can be Obtained By Them.
III. To do we need to Format the Bars.
Format
Menu
Format Bar Style
TEXT TAB
• Go to the Text TAB on the right side corner as
shown, you will have the things.
• You Need to change it. So in the Text TAB just
change & Write Followings.
1. Left-
’Start’
2. Right-
’Finish’
3. Top-
‘Name’
4. Bottom-
‘Duration’
PROJECT SUMMARY TASK
6
Project Summary Task
• It is Used to Determine total Summary or total
duration of entire project.
• To do the same, select the whole project data
from last corner of Screen..
Format Menu
Upper Left
Corner
Chk. Mark to
Project Summary
Task Button
After Clicking
Project Summary
Task Button You
will See..
Total Duration of
Project
CALENDER IN MS PROJECT
7
How to Create New Calendar
• First go to Project Menu and after go to Change
Working Time Then Create New Calendar.
• Default you get standard Calendar you can copy
standard calendar and after making copy of calendar.
Changes Make According to your Project and Time and
Days and Week-offs.
Project Menu
Change
Working Time
Create New
Calendar
Changed Calendar
Made By Project
Planner During
Project Planning
and Scheduling
Create New
Calendar By
Clicking Create
New Calendar.
Apply New Project Calendar
• It Won’t Work or Apply Your Calendar Until & Unless
you Changed it.
• To Do So..
Project Menu
Project
Information
Change
Calendar
Change New
Calendar made by
You According to
Your
Requirements.
After Changing
Calendar Press
OK.
Yearly Exception
• Let us take example of 15th August That Occurs as Holiday
in Calendar Every Year.
• So You don’t need to add exception every year manually.
• To do so 1st Create the Exception of Independence Day for
Current Year & Double Click on It.
Project Menu
Change
Working Time
Select The
Calendar
Exception
[Details]
2023 Calendar
Weekly Exception
• Let us Take any Company that has alternate Saturday or
Sunday holiday.
• To do So Create an Exception..
Project
Menu
Change
Working
Time
Select The
Calendar
Work Weeks
[Details]
2023 Calendar
Monthly Exception
• Let us Take any Company that has Saturday or Sunday
holiday.
• To do So Create an Exception..
Project
Menu
Change
Working
Time
Select The
Calendar
Exception
[Details]
2023 Calendar
Adding New Columns
8
New Columns (Responsibility)
• Let Us Take You want to Add Responsible Person For Any
Activity or Task You Have to Add New Column for it..
• To Do So
Add New Column
[Right Click]
Column Fields
Rename TEXT 1
[Responsibilities]
Custom
Attributes
Look Up Add Value
Add Description /
Name
Assigning Responsibilities
Adding Resources and Sheet
9
Resource Sheet
• In Resource Sheet We Add All Resources Who’s Needed
During an Overall Project.
• To Do So
Task Menu
Gantt Bar
Chart
[Dropdown]
Resource
Sheet
Resource Name
Resource Rate
Max Resource
During Project
Type of Resource
1. Work
2. Material
3. Cost
Resource Assigning
10
Resource Assign
• Now We Assign The Resources According to Work Type
and Requirements.
• To Do So
Go To Gantt
Chart
Add
Resources
Column
Assign
Resources
Different
Resources
Assigned
Resources
Mastering Project Planning with Microsoft Project 2016.pptx

More Related Content

Similar to Mastering Project Planning with Microsoft Project 2016.pptx

MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docxMS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
rosemarybdodson23141
 
SCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docx
SCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docxSCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docx
SCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docx
bagotjesusa
 
Generic project proposal template
Generic project proposal templateGeneric project proposal template
Generic project proposal template
Esther Njiro
 
Burnsheet Tool Description
Burnsheet Tool DescriptionBurnsheet Tool Description
Burnsheet Tool Description
DEEPANSHU GUPTA
 
Project management by MS Project 2010
Project management by MS Project 2010Project management by MS Project 2010
Project management by MS Project 2010
Wadhwani Foundation
 
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docxMS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
rosemarybdodson23141
 

Similar to Mastering Project Planning with Microsoft Project 2016.pptx (20)

Primavera P6 Notes for Beginners
Primavera P6 Notes for Beginners Primavera P6 Notes for Beginners
Primavera P6 Notes for Beginners
 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorial
 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iit
 
Getting started with MS Project 2010
Getting started with MS Project 2010Getting started with MS Project 2010
Getting started with MS Project 2010
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptx
 
MS Project Guide.pdf
MS Project Guide.pdfMS Project Guide.pdf
MS Project Guide.pdf
 
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docxMS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
MS Project - Lesson #1A - Basics of Project Scheduling - Part 1O.docx
 
Projects Better Faster Cheaper
Projects Better Faster CheaperProjects Better Faster Cheaper
Projects Better Faster Cheaper
 
Odoo 13 project management
Odoo 13 project managementOdoo 13 project management
Odoo 13 project management
 
Generic_Project_Proposal_Template
Generic_Project_Proposal_TemplateGeneric_Project_Proposal_Template
Generic_Project_Proposal_Template
 
SCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docx
SCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docxSCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docx
SCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docx
 
Generic project proposal template
Generic project proposal templateGeneric project proposal template
Generic project proposal template
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
How to change working days and time in MS Project?
How to change working days and time in MS Project?How to change working days and time in MS Project?
How to change working days and time in MS Project?
 
Burnsheet Tool Description
Burnsheet Tool DescriptionBurnsheet Tool Description
Burnsheet Tool Description
 
Project Management Quick Reference Guide for Microsoft Project 2007
Project Management Quick Reference Guide for Microsoft Project 2007Project Management Quick Reference Guide for Microsoft Project 2007
Project Management Quick Reference Guide for Microsoft Project 2007
 
Project management by MS Project 2010
Project management by MS Project 2010Project management by MS Project 2010
Project management by MS Project 2010
 
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docxMS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
 
MSP JANVI_KAIVALYA.pptx
MSP JANVI_KAIVALYA.pptxMSP JANVI_KAIVALYA.pptx
MSP JANVI_KAIVALYA.pptx
 
BhadaniS Microsoft Project Manual Training
BhadaniS Microsoft Project Manual TrainingBhadaniS Microsoft Project Manual Training
BhadaniS Microsoft Project Manual Training
 

Recently uploaded

Abortion Pill Prices Jane Furse ](+27832195400*)[🏥Women's Abortion Clinic in ...
Abortion Pill Prices Jane Furse ](+27832195400*)[🏥Women's Abortion Clinic in ...Abortion Pill Prices Jane Furse ](+27832195400*)[🏥Women's Abortion Clinic in ...
Abortion Pill Prices Jane Furse ](+27832195400*)[🏥Women's Abortion Clinic in ...
Medical / Health Care (+971588192166) Mifepristone and Misoprostol tablets 200mg
 
Abortion Pills For Sale WhatsApp[[+27737758557]] In Birch Acres, Abortion Pil...
Abortion Pills For Sale WhatsApp[[+27737758557]] In Birch Acres, Abortion Pil...Abortion Pills For Sale WhatsApp[[+27737758557]] In Birch Acres, Abortion Pil...
Abortion Pills For Sale WhatsApp[[+27737758557]] In Birch Acres, Abortion Pil...
drm1699
 

Recently uploaded (20)

Workshop - Architecting Innovative Graph Applications- GraphSummit Milan
Workshop -  Architecting Innovative Graph Applications- GraphSummit MilanWorkshop -  Architecting Innovative Graph Applications- GraphSummit Milan
Workshop - Architecting Innovative Graph Applications- GraphSummit Milan
 
Community is Just as Important as Code by Andrea Goulet
Community is Just as Important as Code by Andrea GouletCommunity is Just as Important as Code by Andrea Goulet
Community is Just as Important as Code by Andrea Goulet
 
Weeding your micro service landscape.pdf
Weeding your micro service landscape.pdfWeeding your micro service landscape.pdf
Weeding your micro service landscape.pdf
 
Workshop: Enabling GenAI Breakthroughs with Knowledge Graphs - GraphSummit Milan
Workshop: Enabling GenAI Breakthroughs with Knowledge Graphs - GraphSummit MilanWorkshop: Enabling GenAI Breakthroughs with Knowledge Graphs - GraphSummit Milan
Workshop: Enabling GenAI Breakthroughs with Knowledge Graphs - GraphSummit Milan
 
[GRCPP] Introduction to concepts (C++20)
[GRCPP] Introduction to concepts (C++20)[GRCPP] Introduction to concepts (C++20)
[GRCPP] Introduction to concepts (C++20)
 
Encryption Recap: A Refresher on Key Concepts
Encryption Recap: A Refresher on Key ConceptsEncryption Recap: A Refresher on Key Concepts
Encryption Recap: A Refresher on Key Concepts
 
A Deep Dive into Secure Product Development Frameworks.pdf
A Deep Dive into Secure Product Development Frameworks.pdfA Deep Dive into Secure Product Development Frameworks.pdf
A Deep Dive into Secure Product Development Frameworks.pdf
 
BusinessGPT - Security and Governance for Generative AI
BusinessGPT  - Security and Governance for Generative AIBusinessGPT  - Security and Governance for Generative AI
BusinessGPT - Security and Governance for Generative AI
 
CERVED e Neo4j su una nuvola, migrazione ed evoluzione di un grafo mission cr...
CERVED e Neo4j su una nuvola, migrazione ed evoluzione di un grafo mission cr...CERVED e Neo4j su una nuvola, migrazione ed evoluzione di un grafo mission cr...
CERVED e Neo4j su una nuvola, migrazione ed evoluzione di un grafo mission cr...
 
Abortion Pill Prices Jane Furse ](+27832195400*)[🏥Women's Abortion Clinic in ...
Abortion Pill Prices Jane Furse ](+27832195400*)[🏥Women's Abortion Clinic in ...Abortion Pill Prices Jane Furse ](+27832195400*)[🏥Women's Abortion Clinic in ...
Abortion Pill Prices Jane Furse ](+27832195400*)[🏥Women's Abortion Clinic in ...
 
UNI DI NAPOLI FEDERICO II - Il ruolo dei grafi nell'AI Conversazionale Ibrida
UNI DI NAPOLI FEDERICO II - Il ruolo dei grafi nell'AI Conversazionale IbridaUNI DI NAPOLI FEDERICO II - Il ruolo dei grafi nell'AI Conversazionale Ibrida
UNI DI NAPOLI FEDERICO II - Il ruolo dei grafi nell'AI Conversazionale Ibrida
 
Abortion Pill Prices Aliwal North ](+27832195400*)[ 🏥 Women's Abortion Clinic...
Abortion Pill Prices Aliwal North ](+27832195400*)[ 🏥 Women's Abortion Clinic...Abortion Pill Prices Aliwal North ](+27832195400*)[ 🏥 Women's Abortion Clinic...
Abortion Pill Prices Aliwal North ](+27832195400*)[ 🏥 Women's Abortion Clinic...
 
[GeeCON2024] How I learned to stop worrying and love the dark silicon apocalypse
[GeeCON2024] How I learned to stop worrying and love the dark silicon apocalypse[GeeCON2024] How I learned to stop worrying and love the dark silicon apocalypse
[GeeCON2024] How I learned to stop worrying and love the dark silicon apocalypse
 
Abortion Pills For Sale WhatsApp[[+27737758557]] In Birch Acres, Abortion Pil...
Abortion Pills For Sale WhatsApp[[+27737758557]] In Birch Acres, Abortion Pil...Abortion Pills For Sale WhatsApp[[+27737758557]] In Birch Acres, Abortion Pil...
Abortion Pills For Sale WhatsApp[[+27737758557]] In Birch Acres, Abortion Pil...
 
Wired_2.0_CREATE YOUR ULTIMATE LEARNING ENVIRONMENT_JCON_16052024
Wired_2.0_CREATE YOUR ULTIMATE LEARNING ENVIRONMENT_JCON_16052024Wired_2.0_CREATE YOUR ULTIMATE LEARNING ENVIRONMENT_JCON_16052024
Wired_2.0_CREATE YOUR ULTIMATE LEARNING ENVIRONMENT_JCON_16052024
 
Anypoint Code Builder - Munich MuleSoft Meetup - 16th May 2024
Anypoint Code Builder - Munich MuleSoft Meetup - 16th May 2024Anypoint Code Builder - Munich MuleSoft Meetup - 16th May 2024
Anypoint Code Builder - Munich MuleSoft Meetup - 16th May 2024
 
Abortion Clinic In Pongola ](+27832195400*)[ 🏥 Safe Abortion Pills In Pongola...
Abortion Clinic In Pongola ](+27832195400*)[ 🏥 Safe Abortion Pills In Pongola...Abortion Clinic In Pongola ](+27832195400*)[ 🏥 Safe Abortion Pills In Pongola...
Abortion Clinic In Pongola ](+27832195400*)[ 🏥 Safe Abortion Pills In Pongola...
 
Prompt Engineering - an Art, a Science, or your next Job Title?
Prompt Engineering - an Art, a Science, or your next Job Title?Prompt Engineering - an Art, a Science, or your next Job Title?
Prompt Engineering - an Art, a Science, or your next Job Title?
 
Artyushina_Guest lecture_YorkU CS May 2024.pptx
Artyushina_Guest lecture_YorkU CS May 2024.pptxArtyushina_Guest lecture_YorkU CS May 2024.pptx
Artyushina_Guest lecture_YorkU CS May 2024.pptx
 
Transformer Neural Network Use Cases with Links
Transformer Neural Network Use Cases with LinksTransformer Neural Network Use Cases with Links
Transformer Neural Network Use Cases with Links
 

Mastering Project Planning with Microsoft Project 2016.pptx

  • 1. SOFTWARE TOOLS - I UNDER GUIDANCE PROF. XXXXXXX PREPARED BY NAEEM LASHKARWALA XXXXXXXXXXX ACADEMIC YEAR (2023-2025) MASTER OF TECHNOLOGY (XXXXXXXXXXX) MICROSOFT PROJECT
  • 3. BRIEF DETAILS OF PRESENTATION IN THIS PRESENTATION WE WILL COVER FOLLOWING TOPICS I. INTRODUCTION TO THE SCREEN / USER INTERFACE II. INITIAL SETTINGS SHOULD BE DONE BEFORE STARTING III. DIFFERENT OPRATIONS IN PROJECT IV. FINDING CRITICAL PATH V. FORMATING OF BAR VI. PROJECT SUMMARY TASK VII. ALL ABOUT CALENDER IN MS PROJECT VIII. ADDING NEW COLUMNS IX. ADDING RESOURCES AND RESOURCE’S SHEET X. ASSIGNING OF RESOURCES
  • 4. INTRODUCTION OF THE SCREEN / USER INTERFACE 1
  • 5. Task Mode Has Two Types 1. Manually 2. auto Task Name is The Activity Name Ex.., Excavation, PCC,ETC.. Duration is Duration or Taken Time By Activity or Task Task Or Activity Start Date Task or Activity Finish Date Predecessors Contains main 4 Constraints That Can Decide That Which Activities Will Start Together or Parallel.
  • 6. INITIAL SETTINGS SHOULD BE DONE BEFORE STARTING 2
  • 7. I. Open MS Project 2016. II. Before Start Using it, You Need to Set Certain Things on it for that Go to the file menu on the right hand side upper corner. III. You Get to See The Last Tab of Options There. Click on it. IV. A Dialogue box will Prompt Up as Shown in Image. Go To File Menu Click on ‘Options’ Prompt Dialogue Box
  • 8.
  • 9. GENERAL TAB In General TAB You Need to Set the DATE & Time Format From Any of The Options above but Generally Use DD-MM-YY
  • 10.
  • 11. DISPLAY TAB In Display Tab Set Currency and Calendar According to Your Project and Country.
  • 12.
  • 13. SCHEDULE TAB In Schedule TAB Set Your Work Timing and Change Assignment Unit Percentage to Decimal and Change Task Mode to Manually to Auto for Ease of Work.
  • 14.
  • 15. ADVANCED TAB In Advanced TAB, There are Chances of make mistakes in entries, to overcome that we can undo them by CTRL+Z, But There an Option in this TAB by which you can increase this Undo Level, By Default it is 20. You Can Changed this Level According to Your Work.
  • 16.
  • 17. DIFFERENT OPRATIONS IN PROJECT / PRACTICAL EXAMPLE 3
  • 18. Task Mode Has Two Types 1. Manually 2. auto Task Name is The Activity Name Ex.., Excavation, PCC,ETC.. Duration is Duration or Taken Time By Activity or Task Task Or Activity Start Date Task or Activity Finish Date Predecessors Contains main 4 Constraints That Can Decide That Which Activities Will Start Together or Parallel.
  • 20. Find Critical Path of Network By Clicking on Critical Path Option After Clicking Critical Activity Option You Can See The Change of Color of Chart Blue to Red. Task Bar Format Menu Critical Path
  • 22. I. So You Can See That The Critical Path Has Been Highlighted by Red Bars. II. Now If You Look at the Bars The Only Gives the Duration of Activity as Bar, No Other Information Can be Obtained By Them. III. To do we need to Format the Bars. Format Menu Format Bar Style
  • 23.
  • 24. TEXT TAB • Go to the Text TAB on the right side corner as shown, you will have the things. • You Need to change it. So in the Text TAB just change & Write Followings. 1. Left- ’Start’ 2. Right- ’Finish’ 3. Top- ‘Name’ 4. Bottom- ‘Duration’
  • 25.
  • 26.
  • 28. Project Summary Task • It is Used to Determine total Summary or total duration of entire project. • To do the same, select the whole project data from last corner of Screen.. Format Menu Upper Left Corner Chk. Mark to Project Summary Task Button
  • 29.
  • 30. After Clicking Project Summary Task Button You will See.. Total Duration of Project
  • 31. CALENDER IN MS PROJECT 7
  • 32. How to Create New Calendar • First go to Project Menu and after go to Change Working Time Then Create New Calendar. • Default you get standard Calendar you can copy standard calendar and after making copy of calendar. Changes Make According to your Project and Time and Days and Week-offs. Project Menu Change Working Time Create New Calendar
  • 33. Changed Calendar Made By Project Planner During Project Planning and Scheduling Create New Calendar By Clicking Create New Calendar.
  • 34. Apply New Project Calendar • It Won’t Work or Apply Your Calendar Until & Unless you Changed it. • To Do So.. Project Menu Project Information Change Calendar
  • 35. Change New Calendar made by You According to Your Requirements. After Changing Calendar Press OK.
  • 36. Yearly Exception • Let us take example of 15th August That Occurs as Holiday in Calendar Every Year. • So You don’t need to add exception every year manually. • To do so 1st Create the Exception of Independence Day for Current Year & Double Click on It. Project Menu Change Working Time Select The Calendar Exception [Details]
  • 38. Weekly Exception • Let us Take any Company that has alternate Saturday or Sunday holiday. • To do So Create an Exception.. Project Menu Change Working Time Select The Calendar Work Weeks [Details]
  • 40. Monthly Exception • Let us Take any Company that has Saturday or Sunday holiday. • To do So Create an Exception.. Project Menu Change Working Time Select The Calendar Exception [Details]
  • 43. New Columns (Responsibility) • Let Us Take You want to Add Responsible Person For Any Activity or Task You Have to Add New Column for it.. • To Do So Add New Column [Right Click] Column Fields Rename TEXT 1 [Responsibilities] Custom Attributes Look Up Add Value Add Description / Name
  • 44.
  • 47. Resource Sheet • In Resource Sheet We Add All Resources Who’s Needed During an Overall Project. • To Do So Task Menu Gantt Bar Chart [Dropdown] Resource Sheet
  • 49. Max Resource During Project Type of Resource 1. Work 2. Material 3. Cost
  • 51. Resource Assign • Now We Assign The Resources According to Work Type and Requirements. • To Do So Go To Gantt Chart Add Resources Column Assign Resources