SlideShare a Scribd company logo
1 of 53
CONSTRUCTION CLAIMS, DISPUTES
AND PROJECT CLOSURE
By
T . Srinivasa Rao
 During the execution of a project, several issues
arise that cannot be resolved among project
participants.
 Such issues typically involve contractor requesting
for either time extension or reimbursement of an
additional cost, or sometimes both.
 Such requests by the contractor are referred to as
‘claim’.
 f the owner accedes to the claim of contractor and
grants him extension of time or reimbursement of
additional cost, or both, the issue is sorted out.
 if the owner does not agree to the claim put out by
contractor and there are differences in the
interpretations, the issue takes the form of a
dispute.
 Claims are becoming an inevitable and unavoidable
burden in modern projects involving new
technologies, specifications and high expectations
from the owner.
 The claim mentioned above can also be put up by
the owner.
 It is, therefore, imperative for all the parties to be
fully acquainted with the procedures and systems,
including recourse to certain preventive actions as
found necessary and required.
SOURCES OF CLAIMS
 As mentioned, the claim may arise due to the
owner or the contractor. The claim may be on
account of any one of the following causes:
 There may be defects and loopholes in the contract
document. For example, the contract document may not
be clear, may have dual meanings at different places, or
may not have sufficient details.
 There may be delay in release of areas as per contract.
Besides, site conditions differ to a large extent from
those described in the contract document.
 The owner may desire to get the work done at a faster
pace than is required by the contract document.
 There may be delay in supply of power, water and other
materials from the owner.
 There may be hold on works due to delay in release of
drawings and other inputs.
 There may be delay in release of payments to the
contractor.
 The scope of work may be substantially modified by the
owner.
 There may be levy of liquidated damages (LD) on the
contractor. Other recoveries from bills may also lead to
contractor raising the claim.
 There may be delay on the part of contractor in
completion of works due to inadequate mobilization of
labour, material and plant.
 There may be loss of profit and investment to the owner
due to delays caused by the contractor.
 Construction claims can also arise on account of
inclement weather.
CLAIM MANAGEMENT
 The major issues in claims and disputes are
identification of issues and the party responsible for
the claim, and ascertaining the time and cost
impact of the claim.
 The party raising the claim has to notify the claims once
they have been identified.
 it is the responsibility of the party raising the claim to
substantiate the facts.
 Depending on the decision of the other party against
which the claim is made, the claim may be settled
amicably or it may take the form of a dispute.
CLAIM NOTIFICATION
 After it is established by the contractor that it is an
extra work, the contractor is required to inform the
engineer within the time frame stipulated and clarify
his intention to claim extra rates for the same. This
is very important because failure on contractor’s
part regarding this shall entail its rejection by the
engineer.
CLAIM SUBSTANTIATION
 The contractor has to fully establish the claim including his
entitlement under the contract, giving reference to the
relevant clauses.
 The claim is supported by necessary backup calculations.
 Backup documents like letters, vouchers and drawings
are also enclosed.
 For period-related claims such as extended stay costs
and interest on delayed payments, it is required to
revalidate the claim at periodic intervals and submit the
same to the engineer until the end of the relevant period.
DECISION OF ENGINEER/OWNER
 The owner/engineer is supposed to convey his
decision on the claim to the contractor within a time
frame specified in the contract.
 If the claim is not allowed, the same needs to be
stated along with reasons.
FURTHER ACTION BY CONTRACTOR
 The contractor has to refer the claim for
adjudication if provided, within a specific time frame
after receiving the decision from the engineer, if the
same is being disallowed.
 The adjudication process is carried out as per the
provisions set out in the contract.
GUIDELINES TO PREPARE THE CLAIMS
 It is always preferable to link the claim to
contractual provisions.
 Prepare the base for its establishment.
 Indicate intention and submit it within the time
frame provided in the contract.
 Submit with all backup documents, calculations,
etc.
 Be fair in projecting the figures and do not inflate.
DISPUTE
 Because of the uncertainties involved in a
construction project and the magnitude of funds
involved, it is only natural to have disagreements
between parties.
 most of such day-to-day differences are resolved
in an amicable manner
 However, it is some times not possible to resolve
disputes in such fashion.
 In such situation construction and legal laws
become helpful for resolving disputes.
“Technically, a dispute implies assertion of a
claim by one party and repudiation thereof by
another.”
 Thus, neither a mere claim without repudiation, nor
a pair of claim and counterclaim, can be called a
dispute.
CAUSES OF DISPUTES
 The geneses of many disputes often lie in the contract
document itself.
 It is often observed that tenders are hastily made and
sufficient attention is not paid to ensure that
 all the required information and details are appropriately
incorporated in the tender document
 the documents are internally consistent, i.e., there is no
contradiction in the provisions of general conditions, special
conditions and drawings
 specifications, where required, are available
 incompleteness, inaccuracy and inconsistency of
information are only part of the reasons for disputes in a
construction project.
CAUSES OF DISPUTES
 Incorrect Ground Data:
 Such data includes information about ground conditions,
depth of groundwater table, rainfall and temperature
data, availability of power and water, etc.
 The estimates of a contractor are based on the ground
data provided with the tender documents
 Any difference between the ground reality during
execution and the conditions provided in the contract
could easily be the reason for disputes
 Use of Faulty and Ambiguous Provisions and/or
Language in Contracts:
 The language of the contract should be clear and such that
it is not open to different interpretations.
 Use of ambiguous language and/or provisions could open
a floodgate of avoidable litigation.
 It is also important that the contract clearly lays down
specific procedures that are to be adopted in the event of
contingencies.
 absence of appropriate provisions to handle technical
inspections by the client or owner, or third parties, could
become a source for litigation
 ill-defined or a vaguely defined hierarchy of documents
that will be deemed to prevail in the event of a dispute
could be a cause for dispute
 Deviations
 The contract should be so designed that there are as
few extra items and/or deviations as possible.
 the scope of work in any contract should be
unambiguously defined
 Unreasonable Attitudes
 It should be borne in mind that in order to complete the work
professionally, it is important that the parties involved resort
to unilateral action to preserve an environment of mutual
trust.
 both the client and the contractor need to have a
professional approach to the project, including areas where
there could be disagreement on interpretation, etc.
 Measures such as suspension of the contract or invoking of
clauses related to imposition of liquidated damages should
be resorted to only in the most extreme cases.
 Delays in payment of bills should also be avoided to ensure
that the contractor does not get cash-strapped, which will
obviously affect his ability to perform.
 Contractor Being of Poor Means
 It is important that the contractor identified to do a job
possesses the required human, financial and technical
resources.
 In the absence of any of these, it is very likely that the
contractor will look for an escape route for leaving the
project, and may try to force a suspension or
determination (termination) of the contract, or take the
matter into arbitration/litigation to cut his losses.
 Unfair Distribution of Risk
 This could be a major reason for not only avoidable
litigation but also increase in the cost of the project.
 Indian contracts typically are heavily loaded against the
contractor, who obviously tries to cover the risks he is
‘forced’ to take by either hiking the rates, or taking an
approach of ‘crossing the bridge when we come to it’,
DISPUTE AVOIDANCE VS DISPUTE
RESOLUTION
 an appropriate strategy for dispute avoidance and
dispute resolution needs to be drafted, and put in
place even before the onset of works in a project.
 Given that the client or the owner usually takes the
lead in drafting contracts, the onus is largely on him
to ensure that both dispute avoidance and
dispute resolution are adequately addressed in the
contract.
 the important reasons as listed above are
appropriately taken care of, the possibility of
disputes can be largely minimized.
 Contracts need to be drawn up with a professional
mindset, and a fair distribution of risk between the
contractor and the owner.
 Special care needs to be taken in drafting dispute-prone
clauses and identifying potential neutral agencies, which
could be called upon to mediate any dispute.
 It may be considered advisable to provide for a binding
mechanism for alternate dispute resolution (ADR), which
could include constitution of dispute review board (DRB),
comprising persons drawn from the contractor’s and the
owner’s sides, which should meet periodically to review
any pending or potential dispute.
MECHANISMS OF DISPUTE RESOLUTION
 Apart from the normal legal process, emphasis here
is on the alternative dispute resolution mechanisms
generally available in construction contracts.
 Such mechanisms could include
 Negotiation
 Mediation
 Conciliation
 Arbitration
 Negotiation
 This could refer to a focused discussion on the dispute
among the engineers from all interested parties, with the
intention of resolving differences without the
involvement of third parties,
 this is an informal process in the legal sense
 if an agreement is reached through the process, it may
have the usual legal significance
 The negotiation process is fast and does not involve
additional expenses
 The discussions are held between the parties across
the table in a cordial and peaceful atmosphere.
 Mediation and Conciliation
 Mediation and conciliation are essentially an informal
process in which the parties are assisted by one or more
neutral third parties in their efforts towards settlement.
 These mediators do not sit in judgement but try to advise
and consult impartially with the parties with the object of
assisting in bringing about a mutually agreeable solution to
the problem.
 They have no power to impose an outcome on disputing
parties.
 Mediation and conciliation are voluntary in the sense that
the parties participate of their own free will, and a neutral
third party simply assists them in reaching a settlement.
 The process is private, confidential and conducted
without prejudice to any legal proceedings.
 The process is non-binding unless an agreement is
reached
 once an agreement is reached, and the parties have
signed it, the document (or the understanding) is as
binding as any other agreement would be.
 Although the process is largely informal, the following
could be identified as parts or stages in a mediation
process.
 In the pre-mediation stage, there has to be a basic
agreement among the parties to the mediation process,
including the identification of a mediator
 Mediation could be direct or indirect, and could involve
meeting(s) with parties, presentation(s) being made by
them, putting together of facts, negotiations and a
settlement
 mediation is an informal process, it has certain inherent
advantages over the more formal and legal process.
 it could be a lot less time-consuming
 involve lesser costs
 the outcome could be more satisfying to the parties
 It also opens channels of communication, and could
contribute greatly to preserving or enhancing a
professional relationship.
 Arbitration
 Arbitration is perhaps the most commonly used
mechanism for settlement of technical disputes in a
construction project.
 It is a quasi-judicial process to the extent that legal
protocol is largely observed
 In India, the Arbitration and Conciliation Act, 1996,
provides the legal framework for the arbitration process.
 In principle, collection and interpretation of evidence,
examination and cross-examination of witnesses, etc.,
are some examples of essentially legal matters
 Arbitrator should be able to guide and provide a
direction to the proceedings.
 As far as the number of arbitrators is concerned, much
like the judicial system, technical disputes can also be
resolved by single arbitrators, or a panel of several
arbitrators, and though the parties are free to determine
the number of arbitrators, it should be ensured that the
number is odd, so that a situation of a ‘tie’ in an award is
preempted.
 Often, one arbitrator each is nominated by the
contractor and the owner, and these individuals together
choose a third colleague (brother) arbitrator, to complete
the constitution of a bench of arbitrators.
CAUSES LEADING TO ARBITRATION
 Incorrect ground data
 Contracts containing faulty and ambiguous provisions
 Faulty administration of contract
 Deviations
 Suspension of works
 Contractor being of poor means
 Default by contractor
 No publicity involved
 Unreasonable attitude adopted by contractor
 Overpayment
 Levy of compensation for delay
 Delay in payment of bills
 Observation arising out of technical examination of works
ADVANTAGES OF ADR OVER LEGAL PROCEEDINGS
IN A COURT
 Alternative dispute resolution (ADR) has clear merits over
formal legal proceedings in a court of law, and is often
preferred over the latter.
 the process is less formal and quasi judicial which allows a
certain degree of flexibility and ease to the parties
 the arbitrator works on a lesser number of cases at any given
time, the settlement of cases is quicker and less expensive.
 place of a hearing are fixed based on the mutual convenience
of parties.
 Since the hearings are not open to the public, the overall
relationships are less affected.
 This aspect is important considering the fact that the parties
often want to avoid needless publicity as it adversely affects
their professional standing and relationships.
SOME DOS AND DON’TS TO AVOID DISPUTE
 When contractors are faced with lack of work and idle
overheads, they tend to under-quote and take up jobs at
cutthroat rates, which often land them in a soup. Thus, it
may be said that ‘contractors are so afraid of dying that
they commit suicide.’
 Good claims-management practice means:
 eliminating risks to the extent possible before entering into
contract, and
 during the course of work, to have variation orders settled
without elevating them to the status of claims.
 ‘Be careful how the law of the land interprets ‘no
damages clause’ in favour of the owner.’
 ‘Don’t throw good money after bad money in pursuing
bad claims.’
 ‘Don’t set up ego barriers in settling disputes during the
course of work.’
 Negotiated contracts have fewer claims than lump-sum
contracts. Most owners’ engineers tend to assume that
the contractors have covered all risks while quoting.
Highlight the areas not covered in the quotation.
 Study contract conditions and local laws thoroughly.
 Educate and train staff to act early at the lower level so
that disputes do not escalate and rise to the highest
decision-making level.
 Do not pile up claims to the end, which result in the
owner’s engineer also getting hemmed in. Settle them
early, before the amount looks big.
 Provide analysis and documentation early, and not at the end.
 Relate every claim to the project schedule drawn up in the
beginning. The base plan should be prepared right at the
beginning of the contract, and this should not be lost sight of
either mentally or physically. Keep a copy of the original schedule
in your cash box or bank locker so that it is not lost.
 Concurrent delays cannot be seen from bar chart. It is better to
use CPM network so that the floats are known. Do the CPM
network right in the beginning of the project. ‘You can build a
project without CPM but you cannot build delay-claim without it.’
Update the CPM network through periodical monitoring so that
you can prove delays, as the onus of proof is on the contractor.
 Claim is a three-legged table:
 Liability, which means contractual facts
 Causation, which means connection
 Damages, which means claims presented
 Submission of claims should be subject to IRAC test as follows:
 Issue—Are you entitled to recovery?
 Review—Contractual and factual right to recover
 Analysis—If necessary, get expert opinion and judgements available
 Chronology—Perspective to be drawn up
 Submissions should be understandable by the arbitrator. If available,
enclose periodical progress photographs, which can speak volumes.
 Do not lose credibility by submitting untenable or exorbitant claims.
 Have the submissions examined by your own people, or experts. ‘You
never have a second chance to make the first impression.’
 Have your claims settled during the course of execution when you have
leverage.
 While negotiating international contracts, suggest a formula from outside
the country, preferably a neutral country, to settle the disputes.
 Suggest a mediator from a neutral country to advise during the course of
contract
PROJECT CLOSURE
 This is the last phase of a construction project and
is as important as any other phase in the project.
 This is a process of completing and documenting all
the construction tasks required to complete the
project.
 A poor project closure (or close-out, as it is referred
to sometimes) leaves the client unsatisfied and may
prove to be a cause for not getting repeat business.
 Thus, project closure should be meticulously
planned.
 Project closure consists of a number of tasks.
 the project closure phase can be divided into the
following broad headings:
 Construction closure
 Financial closure
 Contract closure
 Project manager’s closure
 Lessons learned from the project
CONSTRUCTION CLOSURE
 This involves preparation of the project punch list,
which is a list of deficiencies identified during the
combined inspection of constructed facilities by the
representatives of client, contractor, consultant and
architect.
 During the regular inspection also, deficiencies are
reported to the contractor by the architect, the
consultant, and the client’s representative.
 The punch list is prepared usually towards the end
of the project when all major construction activities
are completed.
 The punch list is formally handed over to the
contractor, who takes steps to rectify the
deficiencies thus pointed out.
 There may be a situation in which some of the
deficiencies pointed out in the punch list may not be
part of the contract, and the contractor in such
cases usually asks the owner for extra payment.
 Certificate of Substantial Completion
 For a contractor, obtaining the certificate of substantial
completion is an important milestone event as it ends
the contractor’s liability for liquidated damages (LD).
 Substantial completion refers to a situation in which
the project is sufficiently completed.
 In other words, even though some minor deficiencies
may be present (all the deficiencies pointed out in the
punch list may not have been attended to), the
constructed facility can now be used for its intended
function.
 Certificate of Occupancy
 This is usually issued by the municipality under whose
jurisdiction the project location falls.
 It indicates that the constructed facility complies with the
entire codal requirement and is safe to be occupied.
 Fire- and elevator-related inspection by municipal
authorities is required before the certificate of
occupancy is issued.
 Demobilization or Release of Resources
 This consists of demobilization (release) of resources
such as staff and workers, and is as important as their
mobilization.
 The closure of office, removal of unused materials lying
in store, and disconnecting water, electricity and
sewerage lines are all part of the demobilization process
FINANCIAL CLOSURE
 Financial closure consists of writing applications for final
payment, release of various bank guarantees, and
settlement of any change order issued by the client.
 Final Payment
 The contractor has to apply for the release of final payment
after he has attended to all the deficiencies pointed out in the
punch list. The request for release of retention money is also
made.
 Release of Various Bank Guarantees
 During the course of execution of project, the contractor
submits a number of bank guarantees to the owner. A written
request is made to the client to release the bank guarantees.
CONTRACT CLOSURE
 Construction contract usually specifies the
requirement of contract closure and, thus, the
contractor should prepare a list of requirements for
contract closure as per the contract between him
and the owner.
 Submission of As-built Drawings
 During the project execution process, due to site
constraint there might be some changes in the as-built
facility from that as specified in the contract drawings.
 it is very important to prepare the as-built drawings by
estimating the actual dimension and condition of the
constructed facility.
 The as-built drawings of all the trades such as civil,
electrical and mechanical disciplines should be
compiled and submitted to the owner.
 Submission of Operation and Maintenance
Manual
 Modern projects involve a number of mechanical and
electrical appliances—for example, elevator, cooling
tower, air-handling unit and diesel-generator set.
 The manufacturers of these appliances provide
operation and maintenance manual associated with
these appliances
 These should be handed over to the owner.
 Submission of Warranties
 It is the duty of the contractor to collect all the
warranties and guarantees from vendors,
subcontractors and suppliers, and submit these to the
owner.
 Submission of Test Reports
 During the execution of project, a number of tests are
conducted on materials, appliances and systems that
are installed in the project.
 The test records need to be compiled and submitted to
the owner for future reference.
PROJECT MANAGER’S CLOSURE
 This includes tasks such as preparation of an as-
built estimate, analysis of actual cost versus
estimated cost, analysis of items where cost
overrun was high etc.
 conduct of meetings with external agencies such as
client, architect and consultants for understanding
their feedback on various project management
aspects.
 Meetings with own staff and subcontractor should
also be held to get their feedback on various
issues.
LESSONS LEARNED FROM THE PROJECT
 This involves collection and compilation of all records
associated with the project, and preparing archives of
important project records.
 It also involves documenting the important issues faced in the
project and their resolution.
 This helps in planning for such type of issues in the early
stages of other projects.
 This helps in planning for such type of issues in the early
stages of other projects.
 Did the project meet its requirements and objectives?
 Was the customer satisfied?
 Was the project schedule met? Was the project completed within
the stipulated cost?
 Was the level of achieved quality acceptable?
 Were the risks identified and appropriately mitigated?
 What better ways can be employed to improve project execution
and its management?
 THANKYOU

More Related Content

What's hot

Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes managementMohammed Tanbouz
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESPundlik Rathod
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contractsDr K M SONI
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16Arvind Solanki
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contractsAnil Kumar(6)
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction ManagementShahin MB
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
Civil tenders and contracts spce
Civil tenders and contracts spceCivil tenders and contracts spce
Civil tenders and contracts spceirkportal
 
Construction management
Construction managementConstruction management
Construction managementUsama Khalid
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.Aszahari Aie
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project ManagementAravind Samala
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Fidic contract
Fidic contract Fidic contract
Fidic contract Yash Patel
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFrancis Ho
 

What's hot (20)

Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Contracts
ContractsContracts
Contracts
 
Construction contracts
Construction contractsConstruction contracts
Construction contracts
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes management
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Construction process
Construction processConstruction process
Construction process
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Civil tenders and contracts spce
Civil tenders and contracts spceCivil tenders and contracts spce
Civil tenders and contracts spce
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
Construction management
Construction managementConstruction management
Construction management
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Construction contract
Construction contract Construction contract
Construction contract
 
Fidic contract
Fidic contract Fidic contract
Fidic contract
 
WORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-IWORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-I
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
 

Similar to Construction claims, disputes and project closure

"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"Abhishek Shah
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentationelliotfus
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management ContractSAJJAD KHUDHUR ABBAS
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation Lin Hui
 
How To Protect Your Construction Business and Legal Interests
How To Protect Your Construction Business and Legal InterestsHow To Protect Your Construction Business and Legal Interests
How To Protect Your Construction Business and Legal InterestsPalecek & Palecek, PLLC
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Tahir B Mirza
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of timeJoseph Sangpang
 
Construction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of ResidencesConstruction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of ResidencesConstruction Cicerone
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Melvin Lim
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction ContractSarah Fox
 
Extra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractExtra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractSHKLaw
 
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدالمحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدEgyptian Engineers Association
 

Similar to Construction claims, disputes and project closure (20)

"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 
TOPIC7.pdf
TOPIC7.pdfTOPIC7.pdf
TOPIC7.pdf
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management Contract
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
 
How To Protect Your Construction Business and Legal Interests
How To Protect Your Construction Business and Legal InterestsHow To Protect Your Construction Business and Legal Interests
How To Protect Your Construction Business and Legal Interests
 
TE&A news
TE&A newsTE&A news
TE&A news
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
 
Construction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of ResidencesConstruction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of Residences
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
 
Extra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractExtra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the Contract
 
The pathway to documenting successful contract claims..
The pathway to documenting successful contract claims..The pathway to documenting successful contract claims..
The pathway to documenting successful contract claims..
 
Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
 
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدالمحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
 
Against all odds
Against all odds Against all odds
Against all odds
 

More from srinivas2036

Fundamental operations
Fundamental operationsFundamental operations
Fundamental operationssrinivas2036
 
Data collection and input overview
Data collection and input overviewData collection and input overview
Data collection and input overviewsrinivas2036
 
Theoretical framework for gis
Theoretical framework for gisTheoretical framework for gis
Theoretical framework for gissrinivas2036
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Managementsrinivas2036
 
Mechanized construction
Mechanized constructionMechanized construction
Mechanized constructionsrinivas2036
 
Fire protection in construction
Fire protection in constructionFire protection in construction
Fire protection in constructionsrinivas2036
 
Environment at site – construction management
Environment at site – construction managementEnvironment at site – construction management
Environment at site – construction managementsrinivas2036
 
Electrical safety in construction
Electrical safety in constructionElectrical safety in construction
Electrical safety in constructionsrinivas2036
 
Personal safety in construction
Personal safety in constructionPersonal safety in construction
Personal safety in constructionsrinivas2036
 
Startup india action plan – who are eligible
Startup india action plan – who are eligibleStartup india action plan – who are eligible
Startup india action plan – who are eligiblesrinivas2036
 
Introduction to aerial photography and photogrammetry.ppt
Introduction to aerial photography and photogrammetry.pptIntroduction to aerial photography and photogrammetry.ppt
Introduction to aerial photography and photogrammetry.pptsrinivas2036
 
Topic stereoscopy, Parallax, Relief displacement
Topic  stereoscopy, Parallax, Relief displacementTopic  stereoscopy, Parallax, Relief displacement
Topic stereoscopy, Parallax, Relief displacementsrinivas2036
 
Principle of aerial photography and types.ppt
Principle of aerial photography and types.pptPrinciple of aerial photography and types.ppt
Principle of aerial photography and types.pptsrinivas2036
 
GATE Syllabus Civil engineering
GATE Syllabus Civil engineeringGATE Syllabus Civil engineering
GATE Syllabus Civil engineeringsrinivas2036
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 
Airport apron and holding bays
Airport apron and holding baysAirport apron and holding bays
Airport apron and holding bayssrinivas2036
 
Pavement Materials Bitumen
Pavement Materials  BitumenPavement Materials  Bitumen
Pavement Materials Bitumensrinivas2036
 

More from srinivas2036 (20)

Fundamental operations
Fundamental operationsFundamental operations
Fundamental operations
 
Data collection and input overview
Data collection and input overviewData collection and input overview
Data collection and input overview
 
Theoretical framework for gis
Theoretical framework for gisTheoretical framework for gis
Theoretical framework for gis
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Mechanized construction
Mechanized constructionMechanized construction
Mechanized construction
 
Fire protection in construction
Fire protection in constructionFire protection in construction
Fire protection in construction
 
Environment at site – construction management
Environment at site – construction managementEnvironment at site – construction management
Environment at site – construction management
 
Electrical safety in construction
Electrical safety in constructionElectrical safety in construction
Electrical safety in construction
 
Personal safety in construction
Personal safety in constructionPersonal safety in construction
Personal safety in construction
 
Startup india action plan – who are eligible
Startup india action plan – who are eligibleStartup india action plan – who are eligible
Startup india action plan – who are eligible
 
Introduction to aerial photography and photogrammetry.ppt
Introduction to aerial photography and photogrammetry.pptIntroduction to aerial photography and photogrammetry.ppt
Introduction to aerial photography and photogrammetry.ppt
 
Topic stereoscopy, Parallax, Relief displacement
Topic  stereoscopy, Parallax, Relief displacementTopic  stereoscopy, Parallax, Relief displacement
Topic stereoscopy, Parallax, Relief displacement
 
Principle of aerial photography and types.ppt
Principle of aerial photography and types.pptPrinciple of aerial photography and types.ppt
Principle of aerial photography and types.ppt
 
GATE Syllabus Civil engineering
GATE Syllabus Civil engineeringGATE Syllabus Civil engineering
GATE Syllabus Civil engineering
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Valuation
ValuationValuation
Valuation
 
Airport lighting
Airport lightingAirport lighting
Airport lighting
 
Airport marking
Airport markingAirport marking
Airport marking
 
Airport apron and holding bays
Airport apron and holding baysAirport apron and holding bays
Airport apron and holding bays
 
Pavement Materials Bitumen
Pavement Materials  BitumenPavement Materials  Bitumen
Pavement Materials Bitumen
 

Recently uploaded

Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
The SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsThe SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsDILIPKUMARMONDAL6
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Steel Structures - Building technology.pptx
Steel Structures - Building technology.pptxSteel Structures - Building technology.pptx
Steel Structures - Building technology.pptxNikhil Raut
 

Recently uploaded (20)

Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
The SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsThe SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teams
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Steel Structures - Building technology.pptx
Steel Structures - Building technology.pptxSteel Structures - Building technology.pptx
Steel Structures - Building technology.pptx
 

Construction claims, disputes and project closure

  • 1. CONSTRUCTION CLAIMS, DISPUTES AND PROJECT CLOSURE By T . Srinivasa Rao
  • 2.  During the execution of a project, several issues arise that cannot be resolved among project participants.  Such issues typically involve contractor requesting for either time extension or reimbursement of an additional cost, or sometimes both.  Such requests by the contractor are referred to as ‘claim’.  f the owner accedes to the claim of contractor and grants him extension of time or reimbursement of additional cost, or both, the issue is sorted out.
  • 3.  if the owner does not agree to the claim put out by contractor and there are differences in the interpretations, the issue takes the form of a dispute.  Claims are becoming an inevitable and unavoidable burden in modern projects involving new technologies, specifications and high expectations from the owner.  The claim mentioned above can also be put up by the owner.
  • 4.  It is, therefore, imperative for all the parties to be fully acquainted with the procedures and systems, including recourse to certain preventive actions as found necessary and required.
  • 5. SOURCES OF CLAIMS  As mentioned, the claim may arise due to the owner or the contractor. The claim may be on account of any one of the following causes:  There may be defects and loopholes in the contract document. For example, the contract document may not be clear, may have dual meanings at different places, or may not have sufficient details.  There may be delay in release of areas as per contract. Besides, site conditions differ to a large extent from those described in the contract document.  The owner may desire to get the work done at a faster pace than is required by the contract document.
  • 6.  There may be delay in supply of power, water and other materials from the owner.  There may be hold on works due to delay in release of drawings and other inputs.  There may be delay in release of payments to the contractor.  The scope of work may be substantially modified by the owner.  There may be levy of liquidated damages (LD) on the contractor. Other recoveries from bills may also lead to contractor raising the claim.
  • 7.  There may be delay on the part of contractor in completion of works due to inadequate mobilization of labour, material and plant.  There may be loss of profit and investment to the owner due to delays caused by the contractor.  Construction claims can also arise on account of inclement weather.
  • 8. CLAIM MANAGEMENT  The major issues in claims and disputes are identification of issues and the party responsible for the claim, and ascertaining the time and cost impact of the claim.  The party raising the claim has to notify the claims once they have been identified.  it is the responsibility of the party raising the claim to substantiate the facts.  Depending on the decision of the other party against which the claim is made, the claim may be settled amicably or it may take the form of a dispute.
  • 9. CLAIM NOTIFICATION  After it is established by the contractor that it is an extra work, the contractor is required to inform the engineer within the time frame stipulated and clarify his intention to claim extra rates for the same. This is very important because failure on contractor’s part regarding this shall entail its rejection by the engineer.
  • 10. CLAIM SUBSTANTIATION  The contractor has to fully establish the claim including his entitlement under the contract, giving reference to the relevant clauses.  The claim is supported by necessary backup calculations.  Backup documents like letters, vouchers and drawings are also enclosed.  For period-related claims such as extended stay costs and interest on delayed payments, it is required to revalidate the claim at periodic intervals and submit the same to the engineer until the end of the relevant period.
  • 11. DECISION OF ENGINEER/OWNER  The owner/engineer is supposed to convey his decision on the claim to the contractor within a time frame specified in the contract.  If the claim is not allowed, the same needs to be stated along with reasons.
  • 12. FURTHER ACTION BY CONTRACTOR  The contractor has to refer the claim for adjudication if provided, within a specific time frame after receiving the decision from the engineer, if the same is being disallowed.  The adjudication process is carried out as per the provisions set out in the contract.
  • 13. GUIDELINES TO PREPARE THE CLAIMS  It is always preferable to link the claim to contractual provisions.  Prepare the base for its establishment.  Indicate intention and submit it within the time frame provided in the contract.  Submit with all backup documents, calculations, etc.  Be fair in projecting the figures and do not inflate.
  • 15.  Because of the uncertainties involved in a construction project and the magnitude of funds involved, it is only natural to have disagreements between parties.  most of such day-to-day differences are resolved in an amicable manner  However, it is some times not possible to resolve disputes in such fashion.  In such situation construction and legal laws become helpful for resolving disputes.
  • 16. “Technically, a dispute implies assertion of a claim by one party and repudiation thereof by another.”  Thus, neither a mere claim without repudiation, nor a pair of claim and counterclaim, can be called a dispute.
  • 17. CAUSES OF DISPUTES  The geneses of many disputes often lie in the contract document itself.  It is often observed that tenders are hastily made and sufficient attention is not paid to ensure that  all the required information and details are appropriately incorporated in the tender document  the documents are internally consistent, i.e., there is no contradiction in the provisions of general conditions, special conditions and drawings  specifications, where required, are available  incompleteness, inaccuracy and inconsistency of information are only part of the reasons for disputes in a construction project.
  • 18. CAUSES OF DISPUTES  Incorrect Ground Data:  Such data includes information about ground conditions, depth of groundwater table, rainfall and temperature data, availability of power and water, etc.  The estimates of a contractor are based on the ground data provided with the tender documents  Any difference between the ground reality during execution and the conditions provided in the contract could easily be the reason for disputes
  • 19.  Use of Faulty and Ambiguous Provisions and/or Language in Contracts:  The language of the contract should be clear and such that it is not open to different interpretations.  Use of ambiguous language and/or provisions could open a floodgate of avoidable litigation.  It is also important that the contract clearly lays down specific procedures that are to be adopted in the event of contingencies.  absence of appropriate provisions to handle technical inspections by the client or owner, or third parties, could become a source for litigation  ill-defined or a vaguely defined hierarchy of documents that will be deemed to prevail in the event of a dispute could be a cause for dispute
  • 20.  Deviations  The contract should be so designed that there are as few extra items and/or deviations as possible.  the scope of work in any contract should be unambiguously defined
  • 21.  Unreasonable Attitudes  It should be borne in mind that in order to complete the work professionally, it is important that the parties involved resort to unilateral action to preserve an environment of mutual trust.  both the client and the contractor need to have a professional approach to the project, including areas where there could be disagreement on interpretation, etc.  Measures such as suspension of the contract or invoking of clauses related to imposition of liquidated damages should be resorted to only in the most extreme cases.  Delays in payment of bills should also be avoided to ensure that the contractor does not get cash-strapped, which will obviously affect his ability to perform.
  • 22.  Contractor Being of Poor Means  It is important that the contractor identified to do a job possesses the required human, financial and technical resources.  In the absence of any of these, it is very likely that the contractor will look for an escape route for leaving the project, and may try to force a suspension or determination (termination) of the contract, or take the matter into arbitration/litigation to cut his losses.
  • 23.  Unfair Distribution of Risk  This could be a major reason for not only avoidable litigation but also increase in the cost of the project.  Indian contracts typically are heavily loaded against the contractor, who obviously tries to cover the risks he is ‘forced’ to take by either hiking the rates, or taking an approach of ‘crossing the bridge when we come to it’,
  • 24. DISPUTE AVOIDANCE VS DISPUTE RESOLUTION  an appropriate strategy for dispute avoidance and dispute resolution needs to be drafted, and put in place even before the onset of works in a project.  Given that the client or the owner usually takes the lead in drafting contracts, the onus is largely on him to ensure that both dispute avoidance and dispute resolution are adequately addressed in the contract.  the important reasons as listed above are appropriately taken care of, the possibility of disputes can be largely minimized.
  • 25.  Contracts need to be drawn up with a professional mindset, and a fair distribution of risk between the contractor and the owner.  Special care needs to be taken in drafting dispute-prone clauses and identifying potential neutral agencies, which could be called upon to mediate any dispute.  It may be considered advisable to provide for a binding mechanism for alternate dispute resolution (ADR), which could include constitution of dispute review board (DRB), comprising persons drawn from the contractor’s and the owner’s sides, which should meet periodically to review any pending or potential dispute.
  • 26. MECHANISMS OF DISPUTE RESOLUTION  Apart from the normal legal process, emphasis here is on the alternative dispute resolution mechanisms generally available in construction contracts.  Such mechanisms could include  Negotiation  Mediation  Conciliation  Arbitration
  • 27.  Negotiation  This could refer to a focused discussion on the dispute among the engineers from all interested parties, with the intention of resolving differences without the involvement of third parties,  this is an informal process in the legal sense  if an agreement is reached through the process, it may have the usual legal significance  The negotiation process is fast and does not involve additional expenses  The discussions are held between the parties across the table in a cordial and peaceful atmosphere.
  • 28.  Mediation and Conciliation  Mediation and conciliation are essentially an informal process in which the parties are assisted by one or more neutral third parties in their efforts towards settlement.  These mediators do not sit in judgement but try to advise and consult impartially with the parties with the object of assisting in bringing about a mutually agreeable solution to the problem.  They have no power to impose an outcome on disputing parties.  Mediation and conciliation are voluntary in the sense that the parties participate of their own free will, and a neutral third party simply assists them in reaching a settlement.
  • 29.  The process is private, confidential and conducted without prejudice to any legal proceedings.  The process is non-binding unless an agreement is reached  once an agreement is reached, and the parties have signed it, the document (or the understanding) is as binding as any other agreement would be.  Although the process is largely informal, the following could be identified as parts or stages in a mediation process.  In the pre-mediation stage, there has to be a basic agreement among the parties to the mediation process, including the identification of a mediator
  • 30.  Mediation could be direct or indirect, and could involve meeting(s) with parties, presentation(s) being made by them, putting together of facts, negotiations and a settlement  mediation is an informal process, it has certain inherent advantages over the more formal and legal process.  it could be a lot less time-consuming  involve lesser costs  the outcome could be more satisfying to the parties  It also opens channels of communication, and could contribute greatly to preserving or enhancing a professional relationship.
  • 31.  Arbitration  Arbitration is perhaps the most commonly used mechanism for settlement of technical disputes in a construction project.  It is a quasi-judicial process to the extent that legal protocol is largely observed  In India, the Arbitration and Conciliation Act, 1996, provides the legal framework for the arbitration process.  In principle, collection and interpretation of evidence, examination and cross-examination of witnesses, etc., are some examples of essentially legal matters
  • 32.  Arbitrator should be able to guide and provide a direction to the proceedings.  As far as the number of arbitrators is concerned, much like the judicial system, technical disputes can also be resolved by single arbitrators, or a panel of several arbitrators, and though the parties are free to determine the number of arbitrators, it should be ensured that the number is odd, so that a situation of a ‘tie’ in an award is preempted.  Often, one arbitrator each is nominated by the contractor and the owner, and these individuals together choose a third colleague (brother) arbitrator, to complete the constitution of a bench of arbitrators.
  • 33. CAUSES LEADING TO ARBITRATION  Incorrect ground data  Contracts containing faulty and ambiguous provisions  Faulty administration of contract  Deviations  Suspension of works  Contractor being of poor means  Default by contractor  No publicity involved  Unreasonable attitude adopted by contractor  Overpayment  Levy of compensation for delay  Delay in payment of bills  Observation arising out of technical examination of works
  • 34. ADVANTAGES OF ADR OVER LEGAL PROCEEDINGS IN A COURT  Alternative dispute resolution (ADR) has clear merits over formal legal proceedings in a court of law, and is often preferred over the latter.  the process is less formal and quasi judicial which allows a certain degree of flexibility and ease to the parties  the arbitrator works on a lesser number of cases at any given time, the settlement of cases is quicker and less expensive.  place of a hearing are fixed based on the mutual convenience of parties.  Since the hearings are not open to the public, the overall relationships are less affected.  This aspect is important considering the fact that the parties often want to avoid needless publicity as it adversely affects their professional standing and relationships.
  • 35. SOME DOS AND DON’TS TO AVOID DISPUTE  When contractors are faced with lack of work and idle overheads, they tend to under-quote and take up jobs at cutthroat rates, which often land them in a soup. Thus, it may be said that ‘contractors are so afraid of dying that they commit suicide.’  Good claims-management practice means:  eliminating risks to the extent possible before entering into contract, and  during the course of work, to have variation orders settled without elevating them to the status of claims.  ‘Be careful how the law of the land interprets ‘no damages clause’ in favour of the owner.’  ‘Don’t throw good money after bad money in pursuing bad claims.’
  • 36.  ‘Don’t set up ego barriers in settling disputes during the course of work.’  Negotiated contracts have fewer claims than lump-sum contracts. Most owners’ engineers tend to assume that the contractors have covered all risks while quoting. Highlight the areas not covered in the quotation.  Study contract conditions and local laws thoroughly.  Educate and train staff to act early at the lower level so that disputes do not escalate and rise to the highest decision-making level.  Do not pile up claims to the end, which result in the owner’s engineer also getting hemmed in. Settle them early, before the amount looks big.
  • 37.  Provide analysis and documentation early, and not at the end.  Relate every claim to the project schedule drawn up in the beginning. The base plan should be prepared right at the beginning of the contract, and this should not be lost sight of either mentally or physically. Keep a copy of the original schedule in your cash box or bank locker so that it is not lost.  Concurrent delays cannot be seen from bar chart. It is better to use CPM network so that the floats are known. Do the CPM network right in the beginning of the project. ‘You can build a project without CPM but you cannot build delay-claim without it.’ Update the CPM network through periodical monitoring so that you can prove delays, as the onus of proof is on the contractor.  Claim is a three-legged table:  Liability, which means contractual facts  Causation, which means connection  Damages, which means claims presented
  • 38.  Submission of claims should be subject to IRAC test as follows:  Issue—Are you entitled to recovery?  Review—Contractual and factual right to recover  Analysis—If necessary, get expert opinion and judgements available  Chronology—Perspective to be drawn up  Submissions should be understandable by the arbitrator. If available, enclose periodical progress photographs, which can speak volumes.  Do not lose credibility by submitting untenable or exorbitant claims.  Have the submissions examined by your own people, or experts. ‘You never have a second chance to make the first impression.’  Have your claims settled during the course of execution when you have leverage.  While negotiating international contracts, suggest a formula from outside the country, preferably a neutral country, to settle the disputes.  Suggest a mediator from a neutral country to advise during the course of contract
  • 40.  This is the last phase of a construction project and is as important as any other phase in the project.  This is a process of completing and documenting all the construction tasks required to complete the project.  A poor project closure (or close-out, as it is referred to sometimes) leaves the client unsatisfied and may prove to be a cause for not getting repeat business.  Thus, project closure should be meticulously planned.
  • 41.  Project closure consists of a number of tasks.  the project closure phase can be divided into the following broad headings:  Construction closure  Financial closure  Contract closure  Project manager’s closure  Lessons learned from the project
  • 42. CONSTRUCTION CLOSURE  This involves preparation of the project punch list, which is a list of deficiencies identified during the combined inspection of constructed facilities by the representatives of client, contractor, consultant and architect.  During the regular inspection also, deficiencies are reported to the contractor by the architect, the consultant, and the client’s representative.  The punch list is prepared usually towards the end of the project when all major construction activities are completed.
  • 43.  The punch list is formally handed over to the contractor, who takes steps to rectify the deficiencies thus pointed out.  There may be a situation in which some of the deficiencies pointed out in the punch list may not be part of the contract, and the contractor in such cases usually asks the owner for extra payment.
  • 44.  Certificate of Substantial Completion  For a contractor, obtaining the certificate of substantial completion is an important milestone event as it ends the contractor’s liability for liquidated damages (LD).  Substantial completion refers to a situation in which the project is sufficiently completed.  In other words, even though some minor deficiencies may be present (all the deficiencies pointed out in the punch list may not have been attended to), the constructed facility can now be used for its intended function.
  • 45.  Certificate of Occupancy  This is usually issued by the municipality under whose jurisdiction the project location falls.  It indicates that the constructed facility complies with the entire codal requirement and is safe to be occupied.  Fire- and elevator-related inspection by municipal authorities is required before the certificate of occupancy is issued.
  • 46.  Demobilization or Release of Resources  This consists of demobilization (release) of resources such as staff and workers, and is as important as their mobilization.  The closure of office, removal of unused materials lying in store, and disconnecting water, electricity and sewerage lines are all part of the demobilization process
  • 47. FINANCIAL CLOSURE  Financial closure consists of writing applications for final payment, release of various bank guarantees, and settlement of any change order issued by the client.  Final Payment  The contractor has to apply for the release of final payment after he has attended to all the deficiencies pointed out in the punch list. The request for release of retention money is also made.  Release of Various Bank Guarantees  During the course of execution of project, the contractor submits a number of bank guarantees to the owner. A written request is made to the client to release the bank guarantees.
  • 48. CONTRACT CLOSURE  Construction contract usually specifies the requirement of contract closure and, thus, the contractor should prepare a list of requirements for contract closure as per the contract between him and the owner.  Submission of As-built Drawings  During the project execution process, due to site constraint there might be some changes in the as-built facility from that as specified in the contract drawings.  it is very important to prepare the as-built drawings by estimating the actual dimension and condition of the constructed facility.
  • 49.  The as-built drawings of all the trades such as civil, electrical and mechanical disciplines should be compiled and submitted to the owner.  Submission of Operation and Maintenance Manual  Modern projects involve a number of mechanical and electrical appliances—for example, elevator, cooling tower, air-handling unit and diesel-generator set.  The manufacturers of these appliances provide operation and maintenance manual associated with these appliances  These should be handed over to the owner.
  • 50.  Submission of Warranties  It is the duty of the contractor to collect all the warranties and guarantees from vendors, subcontractors and suppliers, and submit these to the owner.  Submission of Test Reports  During the execution of project, a number of tests are conducted on materials, appliances and systems that are installed in the project.  The test records need to be compiled and submitted to the owner for future reference.
  • 51. PROJECT MANAGER’S CLOSURE  This includes tasks such as preparation of an as- built estimate, analysis of actual cost versus estimated cost, analysis of items where cost overrun was high etc.  conduct of meetings with external agencies such as client, architect and consultants for understanding their feedback on various project management aspects.  Meetings with own staff and subcontractor should also be held to get their feedback on various issues.
  • 52. LESSONS LEARNED FROM THE PROJECT  This involves collection and compilation of all records associated with the project, and preparing archives of important project records.  It also involves documenting the important issues faced in the project and their resolution.  This helps in planning for such type of issues in the early stages of other projects.  This helps in planning for such type of issues in the early stages of other projects.  Did the project meet its requirements and objectives?  Was the customer satisfied?  Was the project schedule met? Was the project completed within the stipulated cost?  Was the level of achieved quality acceptable?  Were the risks identified and appropriately mitigated?  What better ways can be employed to improve project execution and its management?