We discussed some techniques to help prioritise (or serialise) the work. Some techniques can be combined, some are better for teams, some help create consensus...
26. No priority (finish at end)
Feature Duration Value Cost of delay
Performance
review of team -
A
4 weeks 1500€ 23 x 1500
LinkedIn
Campaign - B
2 weeks 2000€ 23 X 2000
Reorganize team
- C
10 weeks 8500€ 23 X 8500
Create training
plan - D
7 weeks 6000€ 23 X 6000
TOTAL 23 weeks 18000€ 414,000€
27. Based on Duration
Feature Duration Value Cost of delay
LinkedIn
Campaign - B
2 weeks 2000€ 2 x 2000 =
4000€
Performance
review of team -
A
4 weeks 1500€ (4+2) x 1500 =
9000€
Create training
plan - D
7 weeks 6000€ (7+6) x 6000 =
78000€
Reorganize team
- C
10 weeks 8500€ (10+13) x 8500 =
195500
TOTAL 286,500€
28. Based on Value
Feature Duration Value Cost of delay
Reorganize team
- C
10 weeks 8500€ 10 x 8500 =
85000€
Create training
plan - D
7 weeks 6000€ (7+10) x 6000 =
102000€
LinkedIn
Campaign - B
2 weeks 2000€ (2+17) x 2000 =
38000€
Performance
review of team -
A
4 weeks 1500€ (4+19) x 1500 =
34500€
TOTAL 259,500€
30. Calculate the CD3
Feature Duration Value CD3
Performance
review of team -
A
4 weeks 1500€ (1500/4)/1000 =
0.375
LinkedIn
Campaign - B
2 weeks 2000€ (2000/2)/1000 =
1
Reorganize team
- C
10 weeks 8500€ (8500/10)/1000 =
0.85
Create training
plan - D
7 weeks 6000€ (6000/7)/1000 =
0.857
TOTAL 23 weeks 18000€
31. Based on CD3 (highest first)
Feature Duration Value CD3 Cost
LinkedIn
Campaign - B
2 weeks 2000€ 1 2 x 2000 =
4000€
Create
training plan
- D
7 weeks 6000€ 0.857 (7 + 2) x 6000 =
54000€
Reorganize
team - C
10 weeks 8500€ 0.85 (10 + 9) x 8500 =
161500€
Performance
review of
team - A
4 weeks 1500€ 0.375 (4 + 19) x 1500 =
34500€
TOTAL 23 weeks 18000€ 254,000€