1. An ARTICLE on MRP Presented By : Group-09 (Section - G)
2. MATERIAL REQUIREMENTS PLANNING MRP is a systematic planning-and-control methodology for production and inventory. Specifically, it is a procedure for planning and controlling the raw material, purchased parts, and work in progress (WIP) inventories required in manufacturing a product.
3.
4.
5.
6.
7.
8.
9.
10.
11. Bill of material LEVEL PRODUCT LEAD TIME Level 0 Two -drawer file cabinet Level 1 Case (1) 2 weeks Level 2 Drawer slide (4) 3 weeks Formed case (1) 2 weeks Level 3 Sheet steel (1) 4 weeks Level 1 Drawers (2) 1 week Level 2 Formed drawer (1) 2 weeks Handle (1) 3 weeks Support rollers (2) 3 weeks Level 3 Sheet steel(1) 4 weeks