SAP Plant Maintenance




                Presentation By:
          Mr. Subhrajyoti Bhattacharjee
B.E., P.G.D.M., PMP®, Certified SAP PM Solution
                   Consultant
Brief Background of Presenter
 Subhra works as SAP Systems Analyst at Iluka
 Resources Limited, Perth, Western Australia

 He has a Net experience of around 7.8 years with around
 6 years of SAP Consulting Experience in SAP PM &
 CS, MM modules. He has also has standard configuration
 knowledge of SAP PS, DMS and integration aspects of
 other SAP modules & applications

 He      has     worked        in      multiple   SAP
 Implementation, Upgrade, Support & Audit assignments in
 Australia, USA, India and Middle East and is an ex-
 employee of PwC India Ltd, T.C.S. Limited

 He also possesses Core Industry experience of 1.8 years
 in Maintenance & Inbound Logistics
ERP Systems: An Overview

          Plant Maintenance: An Overview


                 Organizational Structure



                     Master Data in SAP PM



                 Maintenance Processing: Objects


          Maintenance Processing: Scenarios


Advanced scenarios, Interfaces & Reports
Government
          & Authorities




Vendors   Organization    Customers




          Environment
External
  Vendors
                                                         Environment

                      Organizational ERP
                     System
                           Finance &
                            Controllin
                                g

               Purchasin
                                            Projects
                   g
                              Productio
                                  n
                              Planning
                HR &
                Payroll
                                            Sales &
                                           Distributio
                           Maintena             n
                             nce
Government &                                             Customers
 Authorities
ERP Systems: An Overview

          Plant Maintenance: An Overview


                 Organizational Structure



                     Master Data in SAP PM



                 Maintenance Processing: Objects


          Maintenance Processing: Scenarios


Advanced scenarios, Interfaces & Reports
 Maintenance is a Support Function within an Organization and Maintenance
costs generally constitute a part of Production overhead costs except when
Maintenance is carried out on Customer Assets to earn revenue.

 Primary Objective of Maintenance is to maintain a high level of
Availability, preventing degeneration and maintaining optimal utilization life of an
Organization’s Physical Assets.

 Physical Assets primarily comprise:
 Fixed assets such as Plant & Machinery, Buildings & Properties, Vehicles and
so on. Usually such assets have a Long useful life (usually > 1 year) over which
they are depreciated
 Operating Assets which may not be treated as Assets in Financial Module nor
depreciated, but having a long term utilization
 High valued current assets such as High valued spares/operating
supplies/machine parts which are subject to Refurbishments with their condition
based values maintained accurately

 Key Performance objectives in Maintenance include
 Maintaining a high level of OEE (Overall Equipment Effectiveness)
Maintaining and Optimal balance between Cost of Breakdown vs. Cost of
Prevention
Utilizing concepts such as TPM, RCM etc. to contribute in Lowering Operating
costs and minimize adverse effects on Equipment ,Operating resources and
ERP Systems: An Overview

          Plant Maintenance: An Overview


                 Organizational Structure



                     Master Data in SAP PM



                 Maintenance Processing: Objects


          Maintenance Processing: Scenarios


Advanced scenarios, Interfaces & Reports
Company
      Centralized         Code        De-centralized
      Planning                        Planning



        Maintenance                Maintenance
         Planning                   Planning
           Plant                      Plant



Maintenance         Maintenance    Maintenance
   Plant               Plant          Plant
ERP Systems: An Overview

          Plant Maintenance: An Overview


                 Organizational Structure



                     Master Data in SAP PM



                 Maintenance Processing: Objects


          Maintenance Processing: Scenarios


Advanced scenarios, Interfaces & Reports
Technical
           Objects




           SAP
 Work      PM:        Planning
Centres   Master      Objects
           Data



           Others
Work
                 Centre           Work Centre Hierarchy is a
                Hierarch          Grouping of Work centres
                   y              comprising Maintenance Task
                                  Force

                                  Work
Capacity
                                  Centre
           Capacity
           information
           includes:                       PM Work Centre
                                           Category “0005”




                                           Comprises: Basic
                                           data, Default
                                           values, Capacity
           Unit of capacity                view, Scheduling
           Start/End times                 view, HR
                                           Assignments, Costing
           Utilizations                    view
           Shift schedules etc.
Load
                Monitoring
  Capacity
  Planning



             Capacity
             Leveling




Capacity Functionalities
Functional Locations       Structured into Hierarchical
                             Levels using Structure
                             Indicators


       Equipment                       Serial Number




     Sub Equipment                      Material No




Equipment Bill of Material




Component material parts
Plan
Top Down                      Bottom up
planning                      planning




               Task List



           Maintenance item
• Single cycle Plans
           • Strategy Based Plans
  Plans    • Counter Based Plans (Single/Multi Counter)


           • General Task Lists
           • Functional Location Task Lists
Task Lists • Equipment Task Lists



           • Standard items
           • Strategy based items
  Items
Other Master
Data

                                 Measuring
                               Points/Counters




                 Class/
               Characteristi
                   cs



                                             Permits
ERP Systems: An Overview

          Plant Maintenance: An Overview


                 Organizational Structure



                     Master Data in SAP PM



                 Maintenance Processing: Objects


          Maintenance Processing: Scenarios


Advanced scenarios, Interfaces & Reports
Maintenance Notifications vs. Maintenance
Orders
 Maintenance                  Maintenance Orders
  Notifications are             are a complete record
  Reporting objects to          of:
  record:                      Operations performed
 Maintenance requirement      Components used
 Cause, Object                 (Stock/Non stock)
  Impacted, Tasks due &        Services hired
  Activities Performed         Time and costs posted
 Types: Maintenance
                               Settlements executed
  Request, Malfunction
  (Breakdown)                  Types: Breakdown
  Report, Activity              Orders, Planned
  Report, Service               Orders, Predictive
  Notifications                 Orders, Calibrations
                                Orders, Refurbishment
 Maintenance Notifications
                                Orders, Capital Work
ERP Systems: An Overview

          Plant Maintenance: An Overview


                 Organizational Structure



                     Master Data in SAP PM



                 Maintenance Processing: Objects


          Maintenance Processing: Scenarios


Advanced scenarios, Interfaces & Reports
Master Data
                                                                Functional                                           Material                      Work center
                                                                                        Equipment
                                                                 Location                                          (Stock parts)                   (PM & PP)


                      Production personnel                                 Permits (If                     Activity                  Service
                    follows up on work done
                         against existing
                                                                           applicable)                      Type                   Master record
                           Notification

                              Yes

                                                                                                    Further work done is
                                                                                                        recorded in
                                                                                                                                         SAP Notification mail to
                      Existing Notification                                                             Notification&
                                                                                                                                            initiator of work
                        (Report IW29)?                                                               Notification Tasks
                                                                                                   Technically completed
                                                  No

                                                                                                            No


                                                                  SAP Notification mail to                                        Notification user                                       PM Oredr
                                          Maintenance               designated Person                                            status changed to                                      Planning done
       Equipment breaks                                                                               Convert to PM                                                  Order (Type
                                        Notification (Type            responsible in                                       Yes       ALWD and                                            (Operation,
            down                                                                                         Order?                                                     PM01) created
                                         “M2”) created              Notification header                                              notification                                       Components,
                                                                                                                                      released                                         Service, Permits)




                                                                                                                                                                        Shop papers
                                                                                                                                                                        printed from
                                                                                                                                                                         PM order
                                    Goods receipt to Storage                                Issue stock part to Reservation No
                                           location                                               assigned to PM Order

                                              Stock part                                                   Yes


                                      Approved purchase                   Purchase
                                    requisitions converted to         requisition created                                                                       Order user status      Assigned permits if
                                                                                                       Is stock part               Is Stock part
                                        Purchase order                    (MM side)           No                           Yes                                 changed to PLND          any are issued by
                                                                                                        available?                   planned?
                                                                                                                                                               and order released      relevant personnel



                                                                                                                                          No

                                                                        Approved
                                                                        purchase                           Purchase
                                  Goods receipt against PO                                                requisition
                                                                       requisitions                                               Is Non – stock
                                  posts costs to associated            converted to                     created within     Yes
                                                                                                                                  part planned?
                                          PM order                    Purchase order                       PM order
                                                                                                                                     Y



Order settled to relevant                                                                                                                 No             Yes
settlement receiver (Cost
        Center)
                                                                         Approved
                                       Service acceptance                                                  Purchase
                                                                         purchase
                                      throughService entry                                                requisition                Is Extenal                Is further planning
                                                                        requisitions
                                    sheet against Service PO                                            created within                 service                      required?
                                                                        converted to
                                    posts costs to associated                                              PM order                  planned?
                                                                       Purchase order
                                            PM order


                                                                                                                                                       No

                                         Production
Settlement rule defined in                                                                        User status of
                                        personnel to              Time confirmation
order & Order Technically                                                                       Maintenance order
                                       confirm Order              for Manhours with                                               Is Maintenance
completed with details of                                                                      changed to MTCO –         Yes                                             No
                                       completion by               suitable Activity                                             work completed?
Malfunction end date/time                                                                         Completed by
                                       changing user                    Type
                                      status to PRCO
                                                                                                  Maintenance                                                                                  In SAP

                                                                                                                                                                                          Outside SAP
Master Data
                                            Functional                                        Material                    Work center                   Service
                                                                  Equipment
                                             Location                                       (Stock parts)                 (PM & PP)                   Master record

                                                                                                                                                       Counter (For
                                            Permits (If              Activity                Maintenance                   Maintenance
                                                                                                                                                      counter based
                                            applicable)               Type                    Task List                       Plan
                                                                                                                                                         plans)



                                      Measurement                                                                           Planned Due
                                   document posting                                                                        dates for order
                                   for Counter Based                                                                     creation are set in
                                         plans                                                                                 system




                                                                                                                                                                            Orders generated
                                   Maintenance Plan                                                                                                   Scheduling overview   for the periodare
                                                               Maintenance plan            Is next call object –           Preventive
                                    created (Single                                                                                                   report generated by    planned further
          Maintenance Task
                                    cycle/Strategy
                                                                  scheduled                Maintenance Order        Yes Maintenance order                maintenance
             List created                                      (Background job/                    due?                  (Type”PM02")                                          (Operation,
                                    based/Counter                                                                                                       personnel on a        Components,
                                                                   Manual)                                                  generated
                                        based)                                                                                                           periodic basis     Service, Permits)




                                                                                                                                                             Shop papers
                                                                                                                                                             printed from
                                                                                                                                                              PM order
                              Goods receipt to Storage                              Issue stock part to Reservation No
                                     location                                             assigned to PM Order

                                     Stock part                                                    Yes


                                Approved purchase                 Purchase
                              requisitions converted to       requisition created                                                                      Order user status    Assigned permits if
                                                                                               Is stock part                Is Stock part
                                  Purchase order                  (MM side)           No                           Yes                                changed to PLND        any are issued by
                                                                                                available?                    planned?
                                                                                                                                                      and order released    relevant personnel



                                                                                                                                  No

                                                                Approved
                                                                                                  Purchase
                                                                purchase
                             Goods receipt against PO                                            requisition
                                                               requisitions                                                Is Non – stock
                             posts costs to associated                                         created within      Yes
                                                               converted to                                                part planned?
                                     PM order                                                     PM order
                                                              Purchase order
                                                                                                                              Y



Order settled to relevant                                                                                                         No            Yes
settlement receiver (Cost
        Center)                                                  Approved
                                 Service acceptance              purchase                         Purchase
                                throughService entry            requisitions                     requisition                  Is Extenal              Is further planning
                              sheet against Service PO          converted to                   created within                   service                    required?
                              posts costs to associated        Purchase order                     PM order                    planned?
                                      PM order


                                                                                                                                               No

                                   Production
Settlement rule defined in                                                                User status of
                                  personnel to            Time confirmation
order & Order Technically                                                               Maintenance order
                                 confirm Order            for Manhours with                                                Is Maintenance
completed with details of                                                              changed to MTCO –        Yes                                          No
                                 completion by             suitable Activity                                              work completed?
   Start/end date/time                                                                    Completed by
                                 changing user                  Type
                                status to PRCO
                                                                                          Maintenance                                                                               In SAP

                                                                                                                                                                               Outside SAP
Master Data
                                               Functional                                        Material                    Work center                   Service
                                                                     Equipment
                                                Location                                       (Stock parts)                 (PM & PP)                   Master record

                                                                                                                                                          Counter (For
                                               Permits (If              Activity                Maintenance                   Maintenance
                                                                                                                                                         counter based
                                               applicable)               Type                    Task List                       Plan
                                                                                                                                                            plans)



                                         Measurement                                                                           Planned Due
                                      document posting                                                                        dates for order
                                      for Counter Based                                                                     creation are set in
                                            plans                                                                                 system




            Maintenance Task          Maintenance Plan                                                                                                   Scheduling overview    Calibration Orders auto
                                                                  Maintenance plan            Is next call object –           Preventive
               List created            created (Single                                                                                                   report generated by    generated and released
            (Inspection point          cycle/Strategy
                                                                     scheduled                Maintenance Order        Yes Maintenance order                maintenance               (Operation,
                                                                  (Background job/                    due?                  (Type”PM02")
               300, MIC’s              based/Counter                                                                                                       personnel on a        Components, Service,
                                                                      Manual)                                                  generated
                 entered)                  based)                                                                                                           periodic basis              Permits)



                                 Goods receipt to Storage                              Issue stock part to Reservation No
                                        location                                             assigned to PM Order

                                        Stock part                                                    Yes




                                                                                                                                                                Shop papers
                                                                                                                                                                printed from
                                                                                                                                                                 PM order
                                   Approved purchase                 Purchase
                                 requisitions converted to       requisition created                                                                                           Quality Inspection Lot
                                                                                                  Is stock part                Is Stock part
                                     Purchase order                  (MM side)           No                           Yes                                                           Generated
                                                                                                   available?                    planned?




 Order settled to relevant                                                                                                           No
settlement receiver (Quality
       Cost Center)                                                Approved
                                                                                                     Purchase
                                                                   purchase
                                Goods receipt against PO                                            requisition
                                                                  requisitions                                                Is Non – stock
                                posts costs to associated                                         created within      Yes
                                                                  converted to                                                part planned?
                                        PM order                                                     PM order
                                                                 Purchase order
                                                                                                                                 Y


                                                                                                                                     No            Yes

   Result recording done                                            Approved
against Inspection Lot, Order       Service acceptance              purchase                         Purchase
   Technically completed           throughService entry            requisitions                     requisition                  Is Extenal              Is further planning
                                 sheet against Service PO          converted to                   created within                   service                    required?
                                 posts costs to associated        Purchase order                     PM order                    planned?
                                         PM order


                                                                                                                                                  No


                                                             Time confirmation
                                                                for Internal
   Settlement rule set in                                                                                                     Is Maintenance
                                                              Manhours with                                        Yes                                          No
     Calibration order                                                                                                       work completed?
                                                              suitable Activity
                                                                   Type                                                                                                                 In SAP

                                                                                                                                                                                   Outside SAP
Master Data
                                                                Functional                                             Material                      Work center
                                                                                        Equipment
                                                                 Location                                            (Stock parts)                   (PM & PP)


                                                                           Permits (If                      Activity                   Service
                   Requestor checks on work
                          progress
                                                                           applicable)                       Type                    Master record


                              Yes

                                                                                                      Work detailed in
                                                                                                                                        SAP Notification mail to
                                                                                                    Notification and Tasks
                      Existing Notification                                                                                                initiator of work
                                                                                                    Technically completed
                        (Report IW29)?
                                                  No
                                                                                                             No


                                                                                                                                    Notification user                                    PM Oredr
     Scope for correction/                 Maintenance            SAP Notification mail to
                                                                                                                                   status changed to                                   Planning done
    predictive maintenance              Notification (Type          designated Person                  Convert to PM                                                Order (Type
                                                                                                                             Yes       ALWD and                                         (Operation,
    identified by Operator/             “M1” Maintenance              responsible in                      Order?                                                   PM01) created
                                                                                                                                       notification                                    Components,
     Maintenance person                  request) created           Notification header
                                                                                                                                        released                                      Service, Permits)




                                                                                                                                                                       Shop papers
                                                                                                                                                                       printed from
                                                                                                                                                                        PM order
                                    Goods receipt to Storage                                 Issue stock part to Reservation No
                                           location                                                assigned to PM Order

                                              Stock part                                                     Yes


                                      Approved purchase                   Purchase
                                    requisitions converted to         requisition created                                                                       Order user status     Assigned permits if
                                                                                                         Is stock part               Is Stock part
                                        Purchase order                    (MM side)            No                            Yes                               changed to PLND         any are issued by
                                                                                                          available?                   planned?
                                                                                                                                                               and order released     relevant personnel



                                                                                                                                           No

                                                                        Approved
                                                                                                            Purchase
                                                                        purchase
                                  Goods receipt against PO                                                 requisition
                                                                       requisitions                                                 Is Non – stock
                                  posts costs to associated                                              created within      Yes
                                                                       converted to                                                 part planned?
                                          PM order                                                          PM order
                                                                      Purchase order
                                                                                                                                       Y



Order settled to relevant                                                                                                                  No            Yes
settlement receiver (Cost
        Center)
                                                                         Approved
                                       Service acceptance                purchase                           Purchase
                                      throughService entry              requisitions                       requisition                 Is Extenal              Is further planning
                                    sheet against Service PO            converted to                     created within                  service                    required?
                                    posts costs to associated          Purchase order                       PM order                   planned?
                                            PM order


                                                                                                                                                        No

                                         Production
Settlement rule defined in                                                                         User status of
                                        personnel to              Time confirmation
order & Order Technically                                                                        Maintenance order
                                       confirm Order              for Manhours with                                                 Is Maintenance
completed with details of                                                                       changed to MTCO –         Yes                                           No
                                       completion by               suitable Activity                                               work completed?
   Start/ end date/time                                                                            Completed by
                                       changing user                    Type
                                      status to PRCO
                                                                                                   Maintenance                                                                                In SAP

                                                                                                                                                                                         Outside SAP
Master Data
                                                                                           Asset Master –
                                                               Functional                                                         Material                     Work center
                                                                                            AuC/FxA (As
                                                                Location                                                        (Stock parts)                  (PM & PP)
                                                                                             relevant)


                                                                    Permits (If                  Activity                 Service                         Equipment
                                                                    applicable)                   Type                  Master record                   (Associated to
                                                                                                                                                            FxA)


                                                Asset under                     Maintenance Team                             Functional Location (for asset
                                             construction created              intimated on the AuC                          build up created) as reference
                   New Asset buildup
                                              by Business SAP                         Number                                        Technical object
                                               Finance Team


        Capital work –
      New asset build up
       or Enhancement
                                                                                                                                                                                      Order Planning
                                                                                                                                                      Capital work Order (Type       done (Operation,
                                             Existing Equipment No (with
                                                                                                                                                       “PM06”) created – with          Components,
                    Asset Enhancement        assigned Fixed asset) would
                                                                                                                                                        relevant Maintenance         Service, Permits),
                                                     be identified
                                                                                                                                                        Activity type assigned        Settlement rule
                                                                                                                                                                                          defined




                                                                                                                                                                      Shop papers
                                                                                                                                                                      printed from
                                                                                                                                                                       PM order
                                   Goods receipt to Storage                                Issue stock part to Reservation No
                                          location                                               assigned to PM Order

                                                                                                          Yes
                                          Stock part


Functional Location Structure        Approved purchase                   Purchase
                                   requisitions converted to         requisition created              Is stock part                                                                  Assigned permits if
  completed with assigned                                                                   No                                      Is Stock part                 Capital order
                                       Purchase order                    (MM side)                     available?       Yes                                                           any are issued by
 Equipment tagged to FxA                                                                                                              planned?                     released
                                                                                                                                                                                     relevant personnel
           number


                                                                                                                                          No

                                                                       Approved
                                                                                                         Purchase
                                                                       purchase
     Maintenance Team             Goods receipt against PO                                              requisition
    intimated on the FxA
                                                                      requisitions                                                 Is Non – stock
                                  posts costs to associated                                           created within    Yes
                                                                      converted to                                                 part planned?
           Number                         PM order                                                       PM order
                                                                     Purchase order
                                                                                                                                      Y


                                                                                                                                          No             Yes


                                                                       Approved
                                      Service acceptance                                                 Purchase
In case of Asset buildup work,                                         purchase
                                     throughService entry                                               requisition                   Is Extenal               Is further planning
 Finance finally settles AuC to                                       requisitions
                                   sheet against Service PO                                           created within    Yes             service                     required?
       a FxA ( created)                                               converted to
                                   posts costs to associated                                             PM order                     planned?
                                                                     Purchase order
                                           PM order


                                                                                                                                                       No


                                                                                              Time confirmation
On completion of work Order                             Periodic settlement
                                                                                              for Manhours with                    Is Maintenance
 Technically completed with                             executed to relevant                                           Yes                                            No
                                                                                               suitable Activity                  work completed?
     necessary details                                  receiver (AuC/FxA)
                                                                                                    Type
                                                                                                                                                                                             In SAP

                                                                                                                                                                                        Outside SAP
Master Data
                                                        Ref. Material (with                                                                             PM Work center
                                                         valuation types                   Serial
                                                                                                                         Equipment                       (For Internal
                                                          C1, C2, C3)                     Number                                                        Refurbishment)


                                                        Batch Numbers for C1,                                                                          Asset No
                                                                                                Service                       Activity
                                                         C2, C3 states of Ref                                                                         (Tagged to
                                                               material                       Master record                    Type
                                                                                                                                                     Equipment ID)




                                                                                                                                                Refurbishment order type                          Order Planning done
                                                                                                                                               “PM04" created for Material                      (Operation – Internal or
                                                                                          Need for Refurbishment
                                                                                                                                                 No, to convert from C3 -                     External Services, Additional
                                                                                                 identified
                                                                                                                                                    Damaged to C2 -                               Components if any),
                                                                                                                                                   Refurbished state                            Settlement rule defined




                                                                                                                                                                               Shop papers
                                                                                                                                                                               printed from
                                                                                                                                                                                PM order
                                 Goods receipt to Storage                               Issue stock part to Reservation No
                                        location                                              assigned to PM Order

                                        Stock part                                                     Yes


                                   Approved purchase                  Purchase                                                 Additional
                                 requisitions converted to        requisition created                                                                      Damaged Material part
                                                                                                   Available in                Stock parts                                                          Order released
                                     Purchase order                   (MM side)          No                          Yes                                (valuation type C3) issued to
                                                                                                     stock?                     required/
                                                                                                                                                           reservation no. in order
                                                                                                                                planned?


                                                                                                                                    No

                                                                    Approved
                                                                                                     Purchase
                                                                    purchase
                                Goods receipt against PO                                            requisition
                                                                   requisitions                                               Is Non – stock
                                posts costs to associated                                         created within    Yes
                                                                   converted to                                               part planned?
                                        PM order                                                     PM order
                                                                  Purchase order
                                                                                                                                Y


                                                                                                                                    No            Yes


                                                                     Approved
                                    Service acceptance                                               Purchase
Settlement executed to settle                                        purchase                                                   Is Extenal
                                   throughService entry                                             requisition                                         Is further planning
order costs (As per business                                        requisitions                                              Refurbishment
                                 sheet against Service PO                                         created within                                             required?
     requirement to FxA)                                            converted to                                                  service
                                 posts costs to associated                                           PM order
                                                                   Purchase order                                               planned?
                                         PM order


                                                                                                                                                No

                                                                                          Time confirmation
                                                                                          for Manhours with
On completion of work Order                            Goods receipt of
                                                                                            suitable Activity                 Is Maintenance
 Technically completed with                       Refurbished part (val. Type                                      Yes                                         No
                                                                                          Type – In case of                  work completed?
     necessary details                                  “C2") to store
                                                                                           internal manhour
                                                                                               consumed
                                                                                                                                                                                                      In SAP

                                                                                                                                                                                                 Outside SAP
ERP Systems: An Overview

          Plant Maintenance: An Overview


                 Organizational Structure



                     Master Data in SAP PM



                 Maintenance Processing: Objects


          Maintenance Processing: Scenarios


Integrations, Advanced scenarios, Interfaces & Reports
Plant Maintenance                      Controlling
          QM Master                                                                                  Employe
          Equipments                                                                                    e
                                                                       Sender Cost        Activity
                       Functional                                                                    Planned
                                         Notification    PM Work         Center           Types
                        Location                                                                     Rates /hr
           Financial                                      Center
          Accounting                                                    Receiver
                                                                       Cost Center


                                         Maintenance        Order
  G/L        Fixed     Equipment            Plan           Header
Account      Asset                                                       Material Management
                                                         Operation
                                                          - Internal
                              Shutdown                   Operation
                                                         – Services         Service Master
            PP Work    BOM Spares                        Compone
            Center -                                          nt
            Machine                                                         Material Master
                                                           Costs
 PM - Customer Service Scenarios

 PM - Work Clearance Management

 PM – Fleet Management

 PM – Mobile Asset Management

 ** PM – Project Oriented Maintenance

** PM – Linear Asset Management

 ** PM – Rotables Subcontracting

 ** PM – Inspection Rounds

 ** PM – Take over- Hand over of Equipments

** Functionalities available only in ECC 6.0 and in specific EHP versions
SCADA                            SAP
                                 BW




         SAP Plant Maintenance




                                 Others
SAP MI
Maintenance Cost Analysis Report




                                   Wave- I




                                   Wave- II
Man hour Utilization Report




                              Wave- I




                              Wave- II
Downtime Analysis Report




                           Wave- I




                           Wave- II
MTTR/MTBF Report




                   Wave- I




                   Wave- II
Cause and Effect Analysis Report




                                   Wave- I




                                   Wave- II
Preventive Schedule Overview Report




                                      Wave- I




                                      Wave- II
Material Goods Movement/Consumption Report




                                             Wave- I




                                             Wave- II
Thank you !!

More Related Content

What's hot

SAP PM Master Data Training Guide
SAP PM Master Data Training GuideSAP PM Master Data Training Guide
SAP PM Master Data Training Guidesapdocs. info
 
SAP Plant Maintenance Training Material | www.sapdocs.info
SAP Plant Maintenance Training Material | www.sapdocs.infoSAP Plant Maintenance Training Material | www.sapdocs.info
SAP Plant Maintenance Training Material | www.sapdocs.infosapdocs. info
 
Sap S4 HANA PM Online training +918660816919
Sap S4 HANA PM Online training +918660816919Sap S4 HANA PM Online training +918660816919
Sap S4 HANA PM Online training +918660816919Senthil kumar
 
Pm key user presentation- Harith senarath/Janaka Pathmendra
Pm   key user presentation- Harith senarath/Janaka PathmendraPm   key user presentation- Harith senarath/Janaka Pathmendra
Pm key user presentation- Harith senarath/Janaka PathmendraJanaka Pathmendra
 
Pm overview comprehensive_1
Pm overview comprehensive_1Pm overview comprehensive_1
Pm overview comprehensive_1Venu Vemula
 
SAP ECC 6.0 PM Configuration Manual - www.sapdocs.info
SAP ECC 6.0 PM Configuration Manual - www.sapdocs.infoSAP ECC 6.0 PM Configuration Manual - www.sapdocs.info
SAP ECC 6.0 PM Configuration Manual - www.sapdocs.infosapdocs. info
 
Sap plant-maintenance-pm-business-blueprint-bbp2
Sap plant-maintenance-pm-business-blueprint-bbp2Sap plant-maintenance-pm-business-blueprint-bbp2
Sap plant-maintenance-pm-business-blueprint-bbp2gabrielsyst
 
Ps sap-pm maintenance-planning
Ps sap-pm maintenance-planningPs sap-pm maintenance-planning
Ps sap-pm maintenance-planningMansour Hineidi
 
SAP PM Training Manual - www.sapdocs.info
SAP PM Training Manual - www.sapdocs.infoSAP PM Training Manual - www.sapdocs.info
SAP PM Training Manual - www.sapdocs.infosapdocs. info
 
Lam config-131007234330-phpapp01
Lam config-131007234330-phpapp01Lam config-131007234330-phpapp01
Lam config-131007234330-phpapp01MaheshMamidi3
 
SAP EAM Maintenance organisation structure
SAP EAM Maintenance organisation structureSAP EAM Maintenance organisation structure
SAP EAM Maintenance organisation structureIITian Academy
 
Plant Maintenance user manual MTTR Report
Plant Maintenance user manual MTTR Report Plant Maintenance user manual MTTR Report
Plant Maintenance user manual MTTR Report Janaka Pathmendra
 
SAP Production Planning and Execution presentation
SAP Production Planning and Execution presentationSAP Production Planning and Execution presentation
SAP Production Planning and Execution presentationAnkur Aggarwal
 

What's hot (20)

Plant maintance module1
Plant maintance module1Plant maintance module1
Plant maintance module1
 
SAP PM Master Data Training Guide
SAP PM Master Data Training GuideSAP PM Master Data Training Guide
SAP PM Master Data Training Guide
 
SAP Plant Maintenance Training Material | www.sapdocs.info
SAP Plant Maintenance Training Material | www.sapdocs.infoSAP Plant Maintenance Training Material | www.sapdocs.info
SAP Plant Maintenance Training Material | www.sapdocs.info
 
SapPreventive Maintenance
SapPreventive Maintenance SapPreventive Maintenance
SapPreventive Maintenance
 
Sap S4 HANA PM Online training +918660816919
Sap S4 HANA PM Online training +918660816919Sap S4 HANA PM Online training +918660816919
Sap S4 HANA PM Online training +918660816919
 
Pm key user presentation- Harith senarath/Janaka Pathmendra
Pm   key user presentation- Harith senarath/Janaka PathmendraPm   key user presentation- Harith senarath/Janaka Pathmendra
Pm key user presentation- Harith senarath/Janaka Pathmendra
 
Pm overview comprehensive_1
Pm overview comprehensive_1Pm overview comprehensive_1
Pm overview comprehensive_1
 
SAP ECC 6.0 PM Configuration Manual - www.sapdocs.info
SAP ECC 6.0 PM Configuration Manual - www.sapdocs.infoSAP ECC 6.0 PM Configuration Manual - www.sapdocs.info
SAP ECC 6.0 PM Configuration Manual - www.sapdocs.info
 
Sap plant maintenance
Sap plant maintenanceSap plant maintenance
Sap plant maintenance
 
Sap plant-maintenance-pm-business-blueprint-bbp2
Sap plant-maintenance-pm-business-blueprint-bbp2Sap plant-maintenance-pm-business-blueprint-bbp2
Sap plant-maintenance-pm-business-blueprint-bbp2
 
Ps sap-pm maintenance-planning
Ps sap-pm maintenance-planningPs sap-pm maintenance-planning
Ps sap-pm maintenance-planning
 
SAP PM: Inspection Rounds & Operation Account Assignment
SAP PM: Inspection Rounds & Operation Account AssignmentSAP PM: Inspection Rounds & Operation Account Assignment
SAP PM: Inspection Rounds & Operation Account Assignment
 
using maintenance_strategy_plans
 using maintenance_strategy_plans using maintenance_strategy_plans
using maintenance_strategy_plans
 
SAP PM Training Manual - www.sapdocs.info
SAP PM Training Manual - www.sapdocs.infoSAP PM Training Manual - www.sapdocs.info
SAP PM Training Manual - www.sapdocs.info
 
Lam config-131007234330-phpapp01
Lam config-131007234330-phpapp01Lam config-131007234330-phpapp01
Lam config-131007234330-phpapp01
 
Caarcpm
CaarcpmCaarcpm
Caarcpm
 
SAP EAM Maintenance organisation structure
SAP EAM Maintenance organisation structureSAP EAM Maintenance organisation structure
SAP EAM Maintenance organisation structure
 
Plant Maintenance user manual MTTR Report
Plant Maintenance user manual MTTR Report Plant Maintenance user manual MTTR Report
Plant Maintenance user manual MTTR Report
 
SAP Production Planning and Execution presentation
SAP Production Planning and Execution presentationSAP Production Planning and Execution presentation
SAP Production Planning and Execution presentation
 
SAP CBM
SAP CBMSAP CBM
SAP CBM
 

Viewers also liked

Viewers also liked (7)

Bom in sap
Bom in sapBom in sap
Bom in sap
 
SAP Logistics - CS - Standard Process & Configuration document
SAP Logistics - CS - Standard Process & Configuration documentSAP Logistics - CS - Standard Process & Configuration document
SAP Logistics - CS - Standard Process & Configuration document
 
Maintenance types
Maintenance typesMaintenance types
Maintenance types
 
Maintenance management
Maintenance managementMaintenance management
Maintenance management
 
Types of maintenance
Types of maintenanceTypes of maintenance
Types of maintenance
 
Maintenence management
Maintenence managementMaintenence management
Maintenence management
 
Maintenance Management
Maintenance ManagementMaintenance Management
Maintenance Management
 

Similar to SAP Plant Maintenance Overview

The Business Value of Business Intelligence
The Business Value of Business IntelligenceThe Business Value of Business Intelligence
The Business Value of Business IntelligenceSenturus
 
BI the Agile Way
BI the Agile WayBI the Agile Way
BI the Agile Waynvvrajesh
 
sappresentation- By Prithwijit
sappresentation- By Prithwijit sappresentation- By Prithwijit
sappresentation- By Prithwijit PRITHWIJIT PAL
 
ERP OVERVIEW - Power point Presentation.ppt
ERP OVERVIEW - Power point Presentation.pptERP OVERVIEW - Power point Presentation.ppt
ERP OVERVIEW - Power point Presentation.pptsdeopknl
 
Enterprise resource-planning-erp-1218631405959212-8
Enterprise resource-planning-erp-1218631405959212-8Enterprise resource-planning-erp-1218631405959212-8
Enterprise resource-planning-erp-1218631405959212-8Pratik Van
 
Plugin ch11edited-ok
Plugin ch11edited-okPlugin ch11edited-ok
Plugin ch11edited-okdonasiilmu
 
SaaS PPM - How Do You Know When It's Right For You? EPM Live Webinar Presenta...
SaaS PPM - How Do You Know When It's Right For You? EPM Live Webinar Presenta...SaaS PPM - How Do You Know When It's Right For You? EPM Live Webinar Presenta...
SaaS PPM - How Do You Know When It's Right For You? EPM Live Webinar Presenta...EPM Live
 
Erp formanufacturingindustry
Erp formanufacturingindustryErp formanufacturingindustry
Erp formanufacturingindustryNeeraj Thakur
 
Automating user provisioning with SAP NW BPM
Automating user provisioning with SAP NW BPMAutomating user provisioning with SAP NW BPM
Automating user provisioning with SAP NW BPMBalakrishnan Bala B
 
MIS 18 Enterprise Management System
MIS 18 Enterprise Management SystemMIS 18 Enterprise Management System
MIS 18 Enterprise Management SystemTushar B Kute
 

Similar to SAP Plant Maintenance Overview (20)

Sap Presentation
Sap PresentationSap Presentation
Sap Presentation
 
The Business Value of Business Intelligence
The Business Value of Business IntelligenceThe Business Value of Business Intelligence
The Business Value of Business Intelligence
 
BI the Agile Way
BI the Agile WayBI the Agile Way
BI the Agile Way
 
Erp
ErpErp
Erp
 
Vitthal Day 1
Vitthal Day 1Vitthal Day 1
Vitthal Day 1
 
OpenERP for Hologram Industry
OpenERP for Hologram IndustryOpenERP for Hologram Industry
OpenERP for Hologram Industry
 
sappresentation- By Prithwijit
sappresentation- By Prithwijit sappresentation- By Prithwijit
sappresentation- By Prithwijit
 
ERP OVERVIEW - Power point Presentation.ppt
ERP OVERVIEW - Power point Presentation.pptERP OVERVIEW - Power point Presentation.ppt
ERP OVERVIEW - Power point Presentation.ppt
 
Enterprise resource-planning-erp-1218631405959212-8
Enterprise resource-planning-erp-1218631405959212-8Enterprise resource-planning-erp-1218631405959212-8
Enterprise resource-planning-erp-1218631405959212-8
 
Erp 2
Erp 2Erp 2
Erp 2
 
Plugin ch11edited-ok
Plugin ch11edited-okPlugin ch11edited-ok
Plugin ch11edited-ok
 
Erp
ErpErp
Erp
 
Ams Webinar 25 March 2010 Jf Final[1]
Ams Webinar 25 March 2010 Jf Final[1]Ams Webinar 25 March 2010 Jf Final[1]
Ams Webinar 25 March 2010 Jf Final[1]
 
ERP
ERPERP
ERP
 
SaaS PPM - How Do You Know When It's Right For You? EPM Live Webinar Presenta...
SaaS PPM - How Do You Know When It's Right For You? EPM Live Webinar Presenta...SaaS PPM - How Do You Know When It's Right For You? EPM Live Webinar Presenta...
SaaS PPM - How Do You Know When It's Right For You? EPM Live Webinar Presenta...
 
Product Costing
Product CostingProduct Costing
Product Costing
 
Erp formanufacturingindustry
Erp formanufacturingindustryErp formanufacturingindustry
Erp formanufacturingindustry
 
Automating user provisioning with SAP NW BPM
Automating user provisioning with SAP NW BPMAutomating user provisioning with SAP NW BPM
Automating user provisioning with SAP NW BPM
 
MIS 18 Enterprise Management System
MIS 18 Enterprise Management SystemMIS 18 Enterprise Management System
MIS 18 Enterprise Management System
 
Introduction to ERP
Introduction to ERPIntroduction to ERP
Introduction to ERP
 

Recently uploaded

Decarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityDecarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityIES VE
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxLoriGlavin3
 
Time Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsTime Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsNathaniel Shimoni
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxLoriGlavin3
 
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality AssuranceInflectra
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsRavi Sanghani
 
Zeshan Sattar- Assessing the skill requirements and industry expectations for...
Zeshan Sattar- Assessing the skill requirements and industry expectations for...Zeshan Sattar- Assessing the skill requirements and industry expectations for...
Zeshan Sattar- Assessing the skill requirements and industry expectations for...itnewsafrica
 
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxGenerative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxfnnc6jmgwh
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxLoriGlavin3
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Farhan Tariq
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersNicole Novielli
 
2024 April Patch Tuesday
2024 April Patch Tuesday2024 April Patch Tuesday
2024 April Patch TuesdayIvanti
 
Bridging Between CAD & GIS: 6 Ways to Automate Your Data Integration
Bridging Between CAD & GIS:  6 Ways to Automate Your Data IntegrationBridging Between CAD & GIS:  6 Ways to Automate Your Data Integration
Bridging Between CAD & GIS: 6 Ways to Automate Your Data Integrationmarketing932765
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...Wes McKinney
 
Scale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterScale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterMydbops
 
Top 10 Hubspot Development Companies in 2024
Top 10 Hubspot Development Companies in 2024Top 10 Hubspot Development Companies in 2024
Top 10 Hubspot Development Companies in 2024TopCSSGallery
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
QCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architecturesQCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architecturesBernd Ruecker
 
Connecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdfConnecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdfNeo4j
 
Glenn Lazarus- Why Your Observability Strategy Needs Security Observability
Glenn Lazarus- Why Your Observability Strategy Needs Security ObservabilityGlenn Lazarus- Why Your Observability Strategy Needs Security Observability
Glenn Lazarus- Why Your Observability Strategy Needs Security Observabilityitnewsafrica
 

Recently uploaded (20)

Decarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityDecarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a reality
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
 
Time Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsTime Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directions
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
 
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and Insights
 
Zeshan Sattar- Assessing the skill requirements and industry expectations for...
Zeshan Sattar- Assessing the skill requirements and industry expectations for...Zeshan Sattar- Assessing the skill requirements and industry expectations for...
Zeshan Sattar- Assessing the skill requirements and industry expectations for...
 
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxGenerative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software Developers
 
2024 April Patch Tuesday
2024 April Patch Tuesday2024 April Patch Tuesday
2024 April Patch Tuesday
 
Bridging Between CAD & GIS: 6 Ways to Automate Your Data Integration
Bridging Between CAD & GIS:  6 Ways to Automate Your Data IntegrationBridging Between CAD & GIS:  6 Ways to Automate Your Data Integration
Bridging Between CAD & GIS: 6 Ways to Automate Your Data Integration
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
 
Scale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterScale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL Router
 
Top 10 Hubspot Development Companies in 2024
Top 10 Hubspot Development Companies in 2024Top 10 Hubspot Development Companies in 2024
Top 10 Hubspot Development Companies in 2024
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
QCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architecturesQCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architectures
 
Connecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdfConnecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdf
 
Glenn Lazarus- Why Your Observability Strategy Needs Security Observability
Glenn Lazarus- Why Your Observability Strategy Needs Security ObservabilityGlenn Lazarus- Why Your Observability Strategy Needs Security Observability
Glenn Lazarus- Why Your Observability Strategy Needs Security Observability
 

SAP Plant Maintenance Overview

  • 1. SAP Plant Maintenance Presentation By: Mr. Subhrajyoti Bhattacharjee B.E., P.G.D.M., PMP®, Certified SAP PM Solution Consultant
  • 2. Brief Background of Presenter  Subhra works as SAP Systems Analyst at Iluka Resources Limited, Perth, Western Australia  He has a Net experience of around 7.8 years with around 6 years of SAP Consulting Experience in SAP PM & CS, MM modules. He has also has standard configuration knowledge of SAP PS, DMS and integration aspects of other SAP modules & applications  He has worked in multiple SAP Implementation, Upgrade, Support & Audit assignments in Australia, USA, India and Middle East and is an ex- employee of PwC India Ltd, T.C.S. Limited  He also possesses Core Industry experience of 1.8 years in Maintenance & Inbound Logistics
  • 3. ERP Systems: An Overview Plant Maintenance: An Overview Organizational Structure Master Data in SAP PM Maintenance Processing: Objects Maintenance Processing: Scenarios Advanced scenarios, Interfaces & Reports
  • 4. Government & Authorities Vendors Organization Customers Environment
  • 5. External Vendors Environment Organizational ERP System Finance & Controllin g Purchasin Projects g Productio n Planning HR & Payroll Sales & Distributio Maintena n nce Government & Customers Authorities
  • 6. ERP Systems: An Overview Plant Maintenance: An Overview Organizational Structure Master Data in SAP PM Maintenance Processing: Objects Maintenance Processing: Scenarios Advanced scenarios, Interfaces & Reports
  • 7.  Maintenance is a Support Function within an Organization and Maintenance costs generally constitute a part of Production overhead costs except when Maintenance is carried out on Customer Assets to earn revenue.  Primary Objective of Maintenance is to maintain a high level of Availability, preventing degeneration and maintaining optimal utilization life of an Organization’s Physical Assets.  Physical Assets primarily comprise:  Fixed assets such as Plant & Machinery, Buildings & Properties, Vehicles and so on. Usually such assets have a Long useful life (usually > 1 year) over which they are depreciated  Operating Assets which may not be treated as Assets in Financial Module nor depreciated, but having a long term utilization  High valued current assets such as High valued spares/operating supplies/machine parts which are subject to Refurbishments with their condition based values maintained accurately  Key Performance objectives in Maintenance include  Maintaining a high level of OEE (Overall Equipment Effectiveness) Maintaining and Optimal balance between Cost of Breakdown vs. Cost of Prevention Utilizing concepts such as TPM, RCM etc. to contribute in Lowering Operating costs and minimize adverse effects on Equipment ,Operating resources and
  • 8. ERP Systems: An Overview Plant Maintenance: An Overview Organizational Structure Master Data in SAP PM Maintenance Processing: Objects Maintenance Processing: Scenarios Advanced scenarios, Interfaces & Reports
  • 9. Company Centralized Code De-centralized Planning Planning Maintenance Maintenance Planning Planning Plant Plant Maintenance Maintenance Maintenance Plant Plant Plant
  • 10. ERP Systems: An Overview Plant Maintenance: An Overview Organizational Structure Master Data in SAP PM Maintenance Processing: Objects Maintenance Processing: Scenarios Advanced scenarios, Interfaces & Reports
  • 11. Technical Objects SAP Work PM: Planning Centres Master Objects Data Others
  • 12. Work Centre Work Centre Hierarchy is a Hierarch Grouping of Work centres y comprising Maintenance Task Force Work Capacity Centre Capacity information includes: PM Work Centre Category “0005” Comprises: Basic data, Default values, Capacity Unit of capacity view, Scheduling Start/End times view, HR Assignments, Costing Utilizations view Shift schedules etc.
  • 13.
  • 14. Load Monitoring Capacity Planning Capacity Leveling Capacity Functionalities
  • 15. Functional Locations Structured into Hierarchical Levels using Structure Indicators Equipment Serial Number Sub Equipment Material No Equipment Bill of Material Component material parts
  • 16.
  • 17. Plan Top Down Bottom up planning planning Task List Maintenance item
  • 18. • Single cycle Plans • Strategy Based Plans Plans • Counter Based Plans (Single/Multi Counter) • General Task Lists • Functional Location Task Lists Task Lists • Equipment Task Lists • Standard items • Strategy based items Items
  • 19. Other Master Data Measuring Points/Counters Class/ Characteristi cs Permits
  • 20. ERP Systems: An Overview Plant Maintenance: An Overview Organizational Structure Master Data in SAP PM Maintenance Processing: Objects Maintenance Processing: Scenarios Advanced scenarios, Interfaces & Reports
  • 21. Maintenance Notifications vs. Maintenance Orders  Maintenance  Maintenance Orders Notifications are are a complete record Reporting objects to of: record:  Operations performed  Maintenance requirement  Components used  Cause, Object (Stock/Non stock) Impacted, Tasks due &  Services hired Activities Performed  Time and costs posted  Types: Maintenance  Settlements executed Request, Malfunction (Breakdown)  Types: Breakdown Report, Activity Orders, Planned Report, Service Orders, Predictive Notifications Orders, Calibrations Orders, Refurbishment  Maintenance Notifications Orders, Capital Work
  • 22.
  • 23.
  • 24. ERP Systems: An Overview Plant Maintenance: An Overview Organizational Structure Master Data in SAP PM Maintenance Processing: Objects Maintenance Processing: Scenarios Advanced scenarios, Interfaces & Reports
  • 25.
  • 26. Master Data Functional Material Work center Equipment Location (Stock parts) (PM & PP) Production personnel Permits (If Activity Service follows up on work done against existing applicable) Type Master record Notification Yes Further work done is recorded in SAP Notification mail to Existing Notification Notification& initiator of work (Report IW29)? Notification Tasks Technically completed No No SAP Notification mail to Notification user PM Oredr Maintenance designated Person status changed to Planning done Equipment breaks Convert to PM Order (Type Notification (Type responsible in Yes ALWD and (Operation, down Order? PM01) created “M2”) created Notification header notification Components, released Service, Permits) Shop papers printed from PM order Goods receipt to Storage Issue stock part to Reservation No location assigned to PM Order Stock part Yes Approved purchase Purchase requisitions converted to requisition created Order user status Assigned permits if Is stock part Is Stock part Purchase order (MM side) No Yes changed to PLND any are issued by available? planned? and order released relevant personnel No Approved purchase Purchase Goods receipt against PO requisition requisitions Is Non – stock posts costs to associated converted to created within Yes part planned? PM order Purchase order PM order Y Order settled to relevant No Yes settlement receiver (Cost Center) Approved Service acceptance Purchase purchase throughService entry requisition Is Extenal Is further planning requisitions sheet against Service PO created within service required? converted to posts costs to associated PM order planned? Purchase order PM order No Production Settlement rule defined in User status of personnel to Time confirmation order & Order Technically Maintenance order confirm Order for Manhours with Is Maintenance completed with details of changed to MTCO – Yes No completion by suitable Activity work completed? Malfunction end date/time Completed by changing user Type status to PRCO Maintenance In SAP Outside SAP
  • 27. Master Data Functional Material Work center Service Equipment Location (Stock parts) (PM & PP) Master record Counter (For Permits (If Activity Maintenance Maintenance counter based applicable) Type Task List Plan plans) Measurement Planned Due document posting dates for order for Counter Based creation are set in plans system Orders generated Maintenance Plan Scheduling overview for the periodare Maintenance plan Is next call object – Preventive created (Single report generated by planned further Maintenance Task cycle/Strategy scheduled Maintenance Order Yes Maintenance order maintenance List created (Background job/ due? (Type”PM02") (Operation, based/Counter personnel on a Components, Manual) generated based) periodic basis Service, Permits) Shop papers printed from PM order Goods receipt to Storage Issue stock part to Reservation No location assigned to PM Order Stock part Yes Approved purchase Purchase requisitions converted to requisition created Order user status Assigned permits if Is stock part Is Stock part Purchase order (MM side) No Yes changed to PLND any are issued by available? planned? and order released relevant personnel No Approved Purchase purchase Goods receipt against PO requisition requisitions Is Non – stock posts costs to associated created within Yes converted to part planned? PM order PM order Purchase order Y Order settled to relevant No Yes settlement receiver (Cost Center) Approved Service acceptance purchase Purchase throughService entry requisitions requisition Is Extenal Is further planning sheet against Service PO converted to created within service required? posts costs to associated Purchase order PM order planned? PM order No Production Settlement rule defined in User status of personnel to Time confirmation order & Order Technically Maintenance order confirm Order for Manhours with Is Maintenance completed with details of changed to MTCO – Yes No completion by suitable Activity work completed? Start/end date/time Completed by changing user Type status to PRCO Maintenance In SAP Outside SAP
  • 28. Master Data Functional Material Work center Service Equipment Location (Stock parts) (PM & PP) Master record Counter (For Permits (If Activity Maintenance Maintenance counter based applicable) Type Task List Plan plans) Measurement Planned Due document posting dates for order for Counter Based creation are set in plans system Maintenance Task Maintenance Plan Scheduling overview Calibration Orders auto Maintenance plan Is next call object – Preventive List created created (Single report generated by generated and released (Inspection point cycle/Strategy scheduled Maintenance Order Yes Maintenance order maintenance (Operation, (Background job/ due? (Type”PM02") 300, MIC’s based/Counter personnel on a Components, Service, Manual) generated entered) based) periodic basis Permits) Goods receipt to Storage Issue stock part to Reservation No location assigned to PM Order Stock part Yes Shop papers printed from PM order Approved purchase Purchase requisitions converted to requisition created Quality Inspection Lot Is stock part Is Stock part Purchase order (MM side) No Yes Generated available? planned? Order settled to relevant No settlement receiver (Quality Cost Center) Approved Purchase purchase Goods receipt against PO requisition requisitions Is Non – stock posts costs to associated created within Yes converted to part planned? PM order PM order Purchase order Y No Yes Result recording done Approved against Inspection Lot, Order Service acceptance purchase Purchase Technically completed throughService entry requisitions requisition Is Extenal Is further planning sheet against Service PO converted to created within service required? posts costs to associated Purchase order PM order planned? PM order No Time confirmation for Internal Settlement rule set in Is Maintenance Manhours with Yes No Calibration order work completed? suitable Activity Type In SAP Outside SAP
  • 29. Master Data Functional Material Work center Equipment Location (Stock parts) (PM & PP) Permits (If Activity Service Requestor checks on work progress applicable) Type Master record Yes Work detailed in SAP Notification mail to Notification and Tasks Existing Notification initiator of work Technically completed (Report IW29)? No No Notification user PM Oredr Scope for correction/ Maintenance SAP Notification mail to status changed to Planning done predictive maintenance Notification (Type designated Person Convert to PM Order (Type Yes ALWD and (Operation, identified by Operator/ “M1” Maintenance responsible in Order? PM01) created notification Components, Maintenance person request) created Notification header released Service, Permits) Shop papers printed from PM order Goods receipt to Storage Issue stock part to Reservation No location assigned to PM Order Stock part Yes Approved purchase Purchase requisitions converted to requisition created Order user status Assigned permits if Is stock part Is Stock part Purchase order (MM side) No Yes changed to PLND any are issued by available? planned? and order released relevant personnel No Approved Purchase purchase Goods receipt against PO requisition requisitions Is Non – stock posts costs to associated created within Yes converted to part planned? PM order PM order Purchase order Y Order settled to relevant No Yes settlement receiver (Cost Center) Approved Service acceptance purchase Purchase throughService entry requisitions requisition Is Extenal Is further planning sheet against Service PO converted to created within service required? posts costs to associated Purchase order PM order planned? PM order No Production Settlement rule defined in User status of personnel to Time confirmation order & Order Technically Maintenance order confirm Order for Manhours with Is Maintenance completed with details of changed to MTCO – Yes No completion by suitable Activity work completed? Start/ end date/time Completed by changing user Type status to PRCO Maintenance In SAP Outside SAP
  • 30. Master Data Asset Master – Functional Material Work center AuC/FxA (As Location (Stock parts) (PM & PP) relevant) Permits (If Activity Service Equipment applicable) Type Master record (Associated to FxA) Asset under Maintenance Team Functional Location (for asset construction created intimated on the AuC build up created) as reference New Asset buildup by Business SAP Number Technical object Finance Team Capital work – New asset build up or Enhancement Order Planning Capital work Order (Type done (Operation, Existing Equipment No (with “PM06”) created – with Components, Asset Enhancement assigned Fixed asset) would relevant Maintenance Service, Permits), be identified Activity type assigned Settlement rule defined Shop papers printed from PM order Goods receipt to Storage Issue stock part to Reservation No location assigned to PM Order Yes Stock part Functional Location Structure Approved purchase Purchase requisitions converted to requisition created Is stock part Assigned permits if completed with assigned No Is Stock part Capital order Purchase order (MM side) available? Yes any are issued by Equipment tagged to FxA planned? released relevant personnel number No Approved Purchase purchase Maintenance Team Goods receipt against PO requisition intimated on the FxA requisitions Is Non – stock posts costs to associated created within Yes converted to part planned? Number PM order PM order Purchase order Y No Yes Approved Service acceptance Purchase In case of Asset buildup work, purchase throughService entry requisition Is Extenal Is further planning Finance finally settles AuC to requisitions sheet against Service PO created within Yes service required? a FxA ( created) converted to posts costs to associated PM order planned? Purchase order PM order No Time confirmation On completion of work Order Periodic settlement for Manhours with Is Maintenance Technically completed with executed to relevant Yes No suitable Activity work completed? necessary details receiver (AuC/FxA) Type In SAP Outside SAP
  • 31. Master Data Ref. Material (with PM Work center valuation types Serial Equipment (For Internal C1, C2, C3) Number Refurbishment) Batch Numbers for C1, Asset No Service Activity C2, C3 states of Ref (Tagged to material Master record Type Equipment ID) Refurbishment order type Order Planning done “PM04" created for Material (Operation – Internal or Need for Refurbishment No, to convert from C3 - External Services, Additional identified Damaged to C2 - Components if any), Refurbished state Settlement rule defined Shop papers printed from PM order Goods receipt to Storage Issue stock part to Reservation No location assigned to PM Order Stock part Yes Approved purchase Purchase Additional requisitions converted to requisition created Damaged Material part Available in Stock parts Order released Purchase order (MM side) No Yes (valuation type C3) issued to stock? required/ reservation no. in order planned? No Approved Purchase purchase Goods receipt against PO requisition requisitions Is Non – stock posts costs to associated created within Yes converted to part planned? PM order PM order Purchase order Y No Yes Approved Service acceptance Purchase Settlement executed to settle purchase Is Extenal throughService entry requisition Is further planning order costs (As per business requisitions Refurbishment sheet against Service PO created within required? requirement to FxA) converted to service posts costs to associated PM order Purchase order planned? PM order No Time confirmation for Manhours with On completion of work Order Goods receipt of suitable Activity Is Maintenance Technically completed with Refurbished part (val. Type Yes No Type – In case of work completed? necessary details “C2") to store internal manhour consumed In SAP Outside SAP
  • 32. ERP Systems: An Overview Plant Maintenance: An Overview Organizational Structure Master Data in SAP PM Maintenance Processing: Objects Maintenance Processing: Scenarios Integrations, Advanced scenarios, Interfaces & Reports
  • 33. Plant Maintenance Controlling QM Master Employe Equipments e Sender Cost Activity Functional Planned Notification PM Work Center Types Location Rates /hr Financial Center Accounting Receiver Cost Center Maintenance Order G/L Fixed Equipment Plan Header Account Asset Material Management Operation - Internal Shutdown Operation – Services Service Master PP Work BOM Spares Compone Center - nt Machine Material Master Costs
  • 34.  PM - Customer Service Scenarios  PM - Work Clearance Management  PM – Fleet Management  PM – Mobile Asset Management  ** PM – Project Oriented Maintenance ** PM – Linear Asset Management  ** PM – Rotables Subcontracting  ** PM – Inspection Rounds  ** PM – Take over- Hand over of Equipments ** Functionalities available only in ECC 6.0 and in specific EHP versions
  • 35. SCADA SAP BW SAP Plant Maintenance Others SAP MI
  • 36.
  • 37. Maintenance Cost Analysis Report Wave- I Wave- II
  • 38. Man hour Utilization Report Wave- I Wave- II
  • 39. Downtime Analysis Report Wave- I Wave- II
  • 40. MTTR/MTBF Report Wave- I Wave- II
  • 41. Cause and Effect Analysis Report Wave- I Wave- II
  • 42. Preventive Schedule Overview Report Wave- I Wave- II
  • 43. Material Goods Movement/Consumption Report Wave- I Wave- II