SlideShare a Scribd company logo
1 of 41
BASIC OF WORK STUDY,
JOB DESIGN &
WORK MEASUREMENT
BY
YASHESH MORKHIA

-> 816

KARTHIK NADAR

-> 818

AKSHAY PATIL

-> 819

SWAPNIL PRADHAN

-> 820

APEKSHA

->821
WORK STUDY
INTRODUCTION
 WITH INCREASING COMPLEXITIES OF THE TECHNOLOGICAL WORLD,
NEED TO SIMPLIFY THE WORK SYSTEM HAS BEEN INCREASING DAY
BY DAY.

 WORK STUDY IS AN AREA OF KNOWLEDGE THAT ADDRESSES THE
PROBLEM OF WORK SIMPLIFICATION WITH THE BASIC OBJECTIVES OF

PRODUCTIVITY ENHANCEMENT,
HUMAN COMFORT & SAFETY
EVOLUTION OF WORK STUDY
• F.W.TAYLOR: FOUNDER OF MODERN METHOD AND TIME STUDY.
• TAYLOR BEGAN HIS TIME STUDY WORK IN 1881.
• HE ESTABLISHED THAT EACH JOB SHOULD HAVE A STANDARD TIME, DETERMINED BY TIME STUDIES.

• IN THE TIMING PROCESS TAYLOR ADVOCATED DIVIDING THE WORK INTO SMALL DIVISIONS OF
•

EFFORT KNOWN AS ELEMENTS.

• TIME WAS OBTAINED FOR THESE ELEMENT INDIVIDUALLY AND THEIR COLLECTIVE VALUES WERE
USED TO DETERMINE THE ALLOWED TIME FOR THE TASK.
WORK OF GILBERTH
• GILBRETH IS CONSIDERED AS THE FOUNDER OF „MODERN MOTION STUDY
TECHNIQUE‟.
• WHICH IS DEFINED AS THE STUDY OF BODY MOTIONS USED IN PERFORMING AN
OPERATION FOR THE PURPOSE OF IMPROVING THE OPERATION BY

 ELIMINATING UNNECESSARY

:

MOTIONS

 SIMPLIFYING NECESSARY MOTIONS

 THEN ESTABLISHING THE MOST FAVORABLE MOTION SEQUENCE FOR MAXIMUM EFFICIENCY
IMPORTANCE:• ENHANCING THE PRODUCTION EFFICIENCY OF THE FIRM.
• TECHNIQUE TO IDENTIFY NON-VALUE OPERATIONS.

• ONLY

ACCURATE
TECHNIQUE.

AND

SYSTEMATIC

• HAS GOT UNIVERSAL APPLICATION.

PROCEDURE

ORIENTED
DEFINITION
“WORK STUDY IS DEFINED AS THAT BODY OF KNOWLEDGE CONCERNED
WITH THE ANALYSIS OF THE WORK METHODS AND THE EQUIPMENT USED
IN PERFORMING A JOB, THE DESIGN OF AN OPTIMUM WORK METHOD
AND THE STANDARDIZATION OF PROPOSED WORK METHODS.”

PREREQUISITES FOR CONDUCTING
WORK STUDY
STEPS INVOLVED IN WORK STUDY
1. SELECT
Job Or Process To Be Studied
2. RECORD
All the details concerning job using various Recording Techniques
3. EXAMINE
Recorded facts critically by asking questions like who, what, when, why
4. DEVELOP
Most economical method
5. MEASURE
The amount of work involved and set standard time to do that job
6. DEFINE
New method and standard time
7. INSTALL
The new method as a standard practice
8. MAINTAIN
New method as agreed standards
PRINCIPLES OF WORK STUDY
1. MUST COME FROM THE TOP LEVEL MANAGEMENT.
2. PEOPLE MADE AWARE OF THE OBJECTIVES AND THE NEED OF THE
EXERCISING SUCH STUDY.
3. METHOD STUDY MUST PRECEDE WORK MEASUREMENT .
OBJECTIVES
• TO

ANALYZE THE PRESENT METHOD OF DOING A JOB, SYSTEMATICALLY IN ORDER

TO DEVELOP A NEW AND BETTER METHOD.

• TO MEASURE THE WORK CONTENT OF A JOB BY MEASURING THE TIME REQUIRED TO
DO THE JOB FOR A QUALIFIED WORKER AND HENCE TO ESTABLISH STANDARD TIME.
• TO

INCREASE THE PRODUCTIVITY BY ENSURING THE BEST POSSIBLE USE OF HUMAN,

MACHINE

AND

MATERIAL

RESOURCES

AND

TO

ACHIEVE

BEST

QUALITY

PRODUCT/SERVICE AT MINIMUM POSSIBLE COST.

• TO IMPROVE OPERATIONAL EFFICIENCY.

• TO REDUCE WASTE THROUGH STANDARDIZATION
• TO IMPROVE LABOR EFFICIENCY.

OF WORK ELEMENTS OF A JOB.
COMPONENTS /
TECHNIQUES OF WORK STUDY

WORK STUDY

METHOD STUDY
• Motion Study : Examine the
job and finding more
efficient method to
perform it

WORK MEASUREMENT
• Time Study : Determine the
time necessary to perform
a job and its elements
BENEFITS OF WORK STUDY
 INCREASED PRODUCTIVITY AND OPERATIONAL EFFICIENCY
 REDUCED MANUFACTURING COSTS
 IMPROVED WORK PLACE LAYOUT

 BETTER MANPOWER PLANNING AND CAPACITY PLANNING
 FAIR WAGES TO EMPLOYEES
 BETTER WORKING CONDITIONS TO EMPLOYEES
 IMPROVED WORK FLOW

 REDUCED MATERIAL HANDLING COSTS
 PROVIDES A STANDARD OF PERFORMANCE TO MEASURE LABOUR EFFICIENCY
 BETTER INDUSTRIAL RELATIONS AND EMPLOYEE MORALE
 BASIS FOR SOUND INCENTIVE SCHEME
 PROVIDES BETTER JOB SATISFACTION TO EMPLOYEES
ADVANTAGES OF METHOD STUDY
•

WORK SIMPLIFICATION

•

IMPROVED WORKING METHOD ( CHEAPER METHOD)

•

BETTER PRODUCT QUALITY

•

IMPROVED WORK PLACE LAYOUT

•

IMPROVED EQUIPMENT DESIGN

•

BETTER WORKING CONDITIONS

DISADVANTAGES OF METHOD STUDY
• HIGH OPERATING COST
•

HIGH WASTAGE & SCRAP

•

EXCESSIVE MOVEMENT OF MATERIALS AND WORKMEN

•

EXCESSIVE PRODUCTION BOTTLENECKS

•

EXCESSIVE REJECTIONS AND REWORK

•

COMPLAINTS ABOUT QUALITY
WORK MEASUREMENT
DEFINATION :• “THE APPLICATION OF TECHNIQUES DESIGNED TO ESTABLISH THE
TIME FOR A QUALIFIED WORKER TO CARRY OUT A SPECIFIED JOB AT
A DEFINED LEVEL OF PERFORMANCE”
OBJECTIVES OF WORK MEASUREMENT :• 1. COMPARING ALTERNATIVE METHODS
• 2. ASSESSING THE CORRECT INITIAL MANNING (MANPOWER REQUIREMENT PLANNING)

• 3. PLANNING AND CONTROL
• 4. REALISTIC COSTING
• 5. DELIVERY DATE OF PLANNING

• 6. COST REDUCTION AND COST CONTROL
• 7. IDENTIFYING SUBSTANDARD WORKERS
• 8. TRAINING NEW EMPLOYEES.
TECHNIQUES OF WORK MEASUREMENT :• 1) REPETITIVE WORK:- THE TYPE OF WORK IN WHICH THE MAIN OPERATION OR GROUP OF OPERATIONS REPEAT
CONTINUOUSLY DURING THE TIME SPENT AT THE JOB. THESE APPLY TO WORK CYCLE OF EXTREMELY SHORT DURATION.
• 2) NON-REPETITIVE WORK:- IT INCLUDE SOME TYPE OF MAINTENANCE AND CONSTRUCTION WORK, WHERE CYCLE
ITSELF IS HARDLY EVER REPEATED IDENTICALLY.
VARIOUS TECHNIQUES:1)TIME STUDY
2) SYNTHESIS
3) WORK SAMPLING
4) ANALYTICAL ESTIMATION
5)PREDETERMINED MOTION AND TIME STUDY.
TIME STUDY
• TIME STUDY IS WORK MEASUREMENT TECHNIQUE FOR RECORDING THE TIMES AND
RATES OF WORKING FOR THE ELEMENTS OF A SPECIFIED JOB CARRIED OUT
UNDER SPECIFIED UNDER SPECIFIED CONDITIONS
STEPS IN MAKING TIME STUDY:1)SELECT (SELECTING

JOB FOR WORK STUDY)

2)OBTAIN & RECORD (DETAILS REGARDING METHODS,OPERATOR, JOB AND
WORKING CONDITION)
3)DEFINE (THE ELEMENT, BREAK THE JOB INTO CONVENIENT

FOR TIMING)

4)MEASURE (TIME DURATION FOR EACH ELEMENT AND ASSESS THE RATING)
5)EXTEND (OBSERVED

TIME INTO NORMAL TIME

{BASIC TIME})

6)DETERMINED (RELAXATION AND PERSONAL ALLOWANCES)
7) COMPUTE (STANDARD TIME FOR THE OPERATION FOR DEFINED JOB OR
OPERATION.)
TYPES OF ELEMENT

• A REPETITIVE ELEMENT – IS AN ELEMENT WHICH OCCURS IN EVERY WORK CYCLE OF THE JOB.
•

AN OCCASIONAL ELEMENT - DOES NOT OCCUR IN EACH WORK CYCLE OF THE JOB, BUT WHICH
MAY OCCUR AT REGULAR OR IRREGULAR INTERVALS. E.G. MACHINE SETTING.

• A CONSTANT ELEMENT - THE BASIC TIME REMAINS CONSTANT WHENEVER IT IS PERFORMED. E.G.
SWITCH THE MACHINE ON.

• A VARIABLE ELEMENT - IS AN ELEMENT FOR WHICH THE BASIC TIME VARIES IN RELATION TO SOME
CHARACTERISTICS OF THE PRODUCT, EQUIPMENT OR PROCESS, E.G. DIMENSIONS, WEIGHT, QUALITY
ETC. E.G. PUSH TROLLEY OF PARTS TO NEXT SHOP.
TYPES OF ELEMENT
• MANUAL ELEMENT - IS AN ELEMENT PERFORMED BY A WORKER.
•

MACHINE ELEMENT - IS AUTOMATICALLY PERFORMED BY A POWER-DRIVEN MACHINE (OR
PROCESS).

• GOVERNING ELEMENT

- OCCUPIES A LONGER TIME THAN ANY OF THE OTHER ELEMENTS
WHICH ARE BEING PERFORMED CONCURRENTLY. E.G. BOIL KETTLE OF WATER, WHILE SETTING OUT
TEAPOT AND CUPS.

•

FOREIGN ELEMENT - IS OBSERVED DURING A STUDY WHICH, AFTER ANALYSIS, IS NOT FOUND TO
BE NECESSARY PART OF THE JOB. E.G. DEGREASING A PART THAT HAS STILL TO BE MACHINED
FURTHER.
ALLOWANCES

• RELAXATION ALLOWANCES
• VARIABLE ALLOWANCES
• INTERFERENCE ALLOWANCES
• CONTINGENCY ALLOWANCES
• POLICY ALLOWANCES
Personal
Allowance

Constant
Fatigue
Allowance

Variable
Fatigue
Allowance

Relaxation
Allowance

Fatigue
Allowance

Normal Time

Contingence
Allowance

Total
Allowance

Policy
Allowance
If applicable

Standard Time

VARIOUS ALLOWANCES TO BUILD STANDARD TIME
EXAMPLE ON HOW TO CALCULATE STANDARD TIME:
WORK MEASUREMENT

• STANDARD TIME IS USED IN:
• COSTING THE LABOR COMPONENT OF PRODUCTS

• TRACKING EMPLOYEE PERFORMANCE
• SCHEDULING & PLANNING REQUIRED RESOURCES
SETTING STANDARD TIMES
• STEP 1: CHOOSE THE SPECIFIC JOB TO BE STUDIED
• STEP 2: TELL THE WORKER WHOSE JOB YOU WILL BE STUDYING

• STEP 3: BREAK THE JOB INTO EASILY RECOGNIZABLE UNITS
• STEP 4: CALCULATE THE NUMBER OF CYCLES YOU MUST OBSERVE
• STEP 5: TIME EACH ELEMENT, RECORD DATA & RATE THE
WORKER‟S PERFORMANCE

• STEP 6: COMPUTE THE NORMAL TIME
• STEP 7: COMPUTE THE STANDARD TIME
EXAMPLE :-
WORK SAMPLING:WORK SAMPLING WAS ORIGINALLY DEVELOPED BY L.H.C. TIPPETT IN BRITAIN IN 1934 FOR
THE BRITISH COTTON INDUSTRY RESEARCH BOARD.
DEFINATION:A TECHNIQUE IN WHICH A STATISTICALLY COMPETENT NUMBER OF INSTANTANEOUS
OBSERVATIONS ARE TAKEN, OVER A PERIOD TIME, OF A GROUP OF MACHINES,PROCESSES
OR WORKERS.
WORK SAMPLING HAS THREE MAIN APPLICATIONS:1) ACTIVITY AND DELAY SAMPLING:- TO MEASURE THE ACTIVITIES AND DELAYS OF WORKERS
AND MACHINES.
2) PERFORMANCE SAMPLING:- TO MEASURE

WORKING TIME AND NON WORKING TIME OF A
PERSON ON A MANUAL WORK AND TO ESTABLISH A PERFORMANCE INDEX OR
PERFORMANCE LEVEL FOR A PERSON DURING HIS WORKING TIME.

3) WORK MEASUREMENT:- UNDER CERTAIN CIRCUMSTANCES, TO MEASURE MANUAL TASK
THAT IS TO ESTABLISHED A TIME STANDARD FOR AN OPERATION.
WHAT IS JOB DESIGN
Job design – process by which managers decide
individual job tasks and authority
Job redesign – process by which managers reconsider
what employees are expected to do
The well-being of organizations and people relates to
how well management designs jobs
DEFINITION OF JOB DESIGN
Def: Job Design is the process of deciding on the content of a
job in terms of its duties and responsibilities; on the methods to
be used in carrying out the job, in terms of techniques, systems
and procedures and on the relationships that should exist
between the job holder and the superiors, subordinates and
colleagues.
GOALS OF JOB DESIGN
1.
2.
3.
4.

Major Concern
Purpose of Job Design
Affect on Employee
Impact
DESIGN FACTOR
• LAYOUT OF EQUIPMENT AND SEATING
• INSTRUMENT DISPLAY DESIGN
• COMPATIBILITY
• CONTROL DESIGN CHARACTERISTICS
ENVIRONMENTAL FACTORS

• TEMPERATURE AND HUMMIDITY
• VIBRATION
• NOISE
VISUAL ENVIRONMENT
• LIGHTING
• VENTILATION

• BEHAVIOURAL DIMENSIONS OF JOB DESIGN
• JOB ROTATION
• JOB ENLARGEMENT

• JOB ENRICHMENT
JOB ROTATION: JOB ENLARGEMENT
:JOB ENRICHMENT:
•

JOB ROTATION: REFERS TO THE MOVEMENT OF AN EMPLOYEE FROM ONE JOB TO ANOTHER.

•

PLEASE NOTE: JOBS THEMSELVES ARE NOT ACTUALLY CHANGED, ONLY EMPLOYEES ARE ROTATED AMONG VARIOUS
JOBS.

•
•

JOB ENLARGEMENT
WHEN A JOB IS ENLARGED THE TASKS BEING PERFORMED ARE EITHER ENLARGED OR SEVERAL SHORT TASKS ARE GIVEN
TO ON WORKER, THUS THE SCOPE OF THE JOB IS INCREASED BECAUSE THERE ARE MANY TASKS TO BE PERFORMED BY
THE SAME WORKER.

•
•

JOB ENRICHMENT:
JOB ENRICHMENT AS IS CURRENTLY PRACTICED ALL OVER THE WORK IS A DIRECT OUTGROWTH OF HERZBERG‟S TWO
FACTOR THEORY OF MOTIVATION.
APPROACHES TO JOB DESIGN

• ENGINEERING APPROACH:
• HUMAN APPROACH:
• JOB CHARACTERISTICS APPROACH:
ENGINEERING APPROACH:

• THE WORK OF EVERY WORKMAN IS FULLY PLANNED OUT BY THE

MANAGEMENT AT LEAST ON DAY IN ADVANCE AND EACH MAN
RECEIVES IN MOST CASES COMPLETE WRITTEN INSTRUCTIONS,
DESCRIBING IN DETAIL THE TASK WHICH HE/SHE HAS TO ACCOMPLISH-

FW TAYLOR.
• PROBLEM WITH THIS APPROACH: REPETITION-MECHANICAL PACING-NO
END PRODUCT-LITTLE SOCAL INTERACTION-NO INPUT
HUMAN APPROACH:
• THE HUMAN RELATIONS APPROACH RECOGNIZED THE NEED TO DESIGN JOBS WHICH ARE
INTERESTING AND REWARDING.
• HERZBERG‟S RESEARCH POPULARIZED THE NOTION OF ENHANCING NEED SATISFACTION
THROUGH WHAT IS CALLED JOB ENRICHMENT.
• FACTORS INVOLVED:
• MOTIVATORS LIKE ACHIEVEMENT, RECOGNITION, WORK
AND GROWTH AND HYGIENIC FACTORS.

ITSELF, RESPONSIBILITY, ADVANCEMENT

• ACCORDING TO HERZBERG. THE EMPLOYEE IS DISSATISFIED WITH THE JOB IF REQUIRED

MAINTENANCE FACTORS TO THE REQUIRED DEGREE ARE NOT INTRODUCED INTO THE JOB.
JOB CHARACTERISTICS APPROACH
•

THEORY BY HACKMAN AND OLDHAM STATES THAT EMPLOYEES WILL WORK HARD WHEN THEY
ARE REWARDED FOR THE WORK THEY DO AND WHEN THE WORK GIVES THEM SATISFACTION.

•

HENCE INTEGRATION OF MOTIVATION, SATISFACTION AND PERFORMANCE

•

ACCORDING TO THIS APPROACH JOB CAN BE DESCRIBED IN TERMS OF FIVE CORE JOB
DIMENSIONS:

1. SKILL VARIETY
2. TASK IDENTITY
3. TASK SIGNIFICANCE
4. AUTONOMY
5. FEEDBACK

WITH JOB DESIGN.
JOB DESIGN PROCESS:

• JOB DESIGN PROCESS HAS TO START FROM WHAT ACTIVITY NEEDS TO BE DONE
IN ORDER TO ACHIEVE ORGANIZATIONAL GOALS.
• IT REQUIRES USE OF TECHNIQUES LIKE WORK-STUDY, PROCESS PLANNING,
ORGANIZATIONAL METHODS AND ORGANIZATIONAL ANALYSIS AND ALSO
TECHNICAL ASPECTS
Basic of work study, work measurement & job design    om

More Related Content

What's hot (20)

1.1 Work study and method study -Industrial Engineering Basics
1.1 Work study and method study -Industrial Engineering Basics1.1 Work study and method study -Industrial Engineering Basics
1.1 Work study and method study -Industrial Engineering Basics
 
Method study
Method studyMethod study
Method study
 
Line balance
Line balanceLine balance
Line balance
 
Basic of work study
Basic of work studyBasic of work study
Basic of work study
 
Work Study: Method Study & Work Measurement
Work Study: Method Study & Work MeasurementWork Study: Method Study & Work Measurement
Work Study: Method Study & Work Measurement
 
UNIT 2 - WORK STUDY
UNIT 2 -  WORK STUDYUNIT 2 -  WORK STUDY
UNIT 2 - WORK STUDY
 
Work study method and time study-final - copy
Work study method and time study-final - copyWork study method and time study-final - copy
Work study method and time study-final - copy
 
Assembly line balancing
Assembly line balancingAssembly line balancing
Assembly line balancing
 
Overall Equipment Effectiveness
Overall Equipment EffectivenessOverall Equipment Effectiveness
Overall Equipment Effectiveness
 
Lecture 2 process charts work study
Lecture 2 process charts work studyLecture 2 process charts work study
Lecture 2 process charts work study
 
Assembly line balancing
Assembly line balancingAssembly line balancing
Assembly line balancing
 
Method Study
Method StudyMethod Study
Method Study
 
Principle 4 heijunka
Principle 4 heijunkaPrinciple 4 heijunka
Principle 4 heijunka
 
Work study
Work studyWork study
Work study
 
Work study method-and_time_study-final
Work study method-and_time_study-finalWork study method-and_time_study-final
Work study method-and_time_study-final
 
cycle time, normal time and standard allowance
cycle time, normal time and standard allowancecycle time, normal time and standard allowance
cycle time, normal time and standard allowance
 
Work methods
Work methodsWork methods
Work methods
 
Man and machine chart
Man and machine chartMan and machine chart
Man and machine chart
 
Me6703 cim systems
Me6703 cim systemsMe6703 cim systems
Me6703 cim systems
 
Work Study
Work StudyWork Study
Work Study
 

Viewers also liked

Strategic capacity planning for products and services
Strategic capacity planning for products and servicesStrategic capacity planning for products and services
Strategic capacity planning for products and servicesgerlyn bonus
 
Inventory Control Model
Inventory Control ModelInventory Control Model
Inventory Control Modelyashpal01
 
Job Design and Work Measurement
Job Design and Work Measurement Job Design and Work Measurement
Job Design and Work Measurement Joshua Miranda
 
Mps vs aggregate planning
Mps vs aggregate planningMps vs aggregate planning
Mps vs aggregate planningUmar Yazdani
 
Location Planning and Analysis
Location Planning and AnalysisLocation Planning and Analysis
Location Planning and AnalysisIza Marie
 
Inventory control & management
Inventory control & managementInventory control & management
Inventory control & managementGoa App
 
Inventory Control Final Ppt
Inventory Control Final PptInventory Control Final Ppt
Inventory Control Final Pptrajnikant
 
Operations strategy and competitiveness
Operations strategy and competitivenessOperations strategy and competitiveness
Operations strategy and competitivenessVaibhav Gupta
 
C5 process & layout
C5 process & layoutC5 process & layout
C5 process & layouthakimizaki
 
Product design and development ch3
Product design and development ch3Product design and development ch3
Product design and development ch3Kavindra Singh
 
Product design and development ch2
Product design and development ch2Product design and development ch2
Product design and development ch2Kavindra Singh
 
Learning Curves in Production Management
Learning Curves in Production ManagementLearning Curves in Production Management
Learning Curves in Production ManagementJoshua Miranda
 
Product design and development ch4
Product design and development ch4Product design and development ch4
Product design and development ch4Kavindra Singh
 
MARUTI SUZUKI PRODUCT ANALYSIS REPORT
MARUTI SUZUKI PRODUCT ANALYSIS REPORTMARUTI SUZUKI PRODUCT ANALYSIS REPORT
MARUTI SUZUKI PRODUCT ANALYSIS REPORTViʞaƨh ʞumar
 
Operation strategy at galanze
Operation strategy at galanzeOperation strategy at galanze
Operation strategy at galanzeNiilm-Cms
 
Aggregate planning and mps om
Aggregate planning and mps omAggregate planning and mps om
Aggregate planning and mps omfatuma ahmed
 

Viewers also liked (20)

Strategic capacity planning for products and services
Strategic capacity planning for products and servicesStrategic capacity planning for products and services
Strategic capacity planning for products and services
 
Inventory Control Model
Inventory Control ModelInventory Control Model
Inventory Control Model
 
Job Design and Work Measurement
Job Design and Work Measurement Job Design and Work Measurement
Job Design and Work Measurement
 
Mps vs aggregate planning
Mps vs aggregate planningMps vs aggregate planning
Mps vs aggregate planning
 
Location Planning and Analysis
Location Planning and AnalysisLocation Planning and Analysis
Location Planning and Analysis
 
Inventory control & management
Inventory control & managementInventory control & management
Inventory control & management
 
Inventory Control Final Ppt
Inventory Control Final PptInventory Control Final Ppt
Inventory Control Final Ppt
 
Operations strategy and competitiveness
Operations strategy and competitivenessOperations strategy and competitiveness
Operations strategy and competitiveness
 
C5 process & layout
C5 process & layoutC5 process & layout
C5 process & layout
 
Product design and development ch3
Product design and development ch3Product design and development ch3
Product design and development ch3
 
TIME STUDY
TIME STUDYTIME STUDY
TIME STUDY
 
Product design and development ch2
Product design and development ch2Product design and development ch2
Product design and development ch2
 
Learn curve
Learn curveLearn curve
Learn curve
 
Learning Curves in Production Management
Learning Curves in Production ManagementLearning Curves in Production Management
Learning Curves in Production Management
 
Product design and development ch4
Product design and development ch4Product design and development ch4
Product design and development ch4
 
Learning Curve Sample Problem
Learning Curve Sample ProblemLearning Curve Sample Problem
Learning Curve Sample Problem
 
MARUTI SUZUKI PRODUCT ANALYSIS REPORT
MARUTI SUZUKI PRODUCT ANALYSIS REPORTMARUTI SUZUKI PRODUCT ANALYSIS REPORT
MARUTI SUZUKI PRODUCT ANALYSIS REPORT
 
Operation strategy at galanze
Operation strategy at galanzeOperation strategy at galanze
Operation strategy at galanze
 
Product design
Product designProduct design
Product design
 
Aggregate planning and mps om
Aggregate planning and mps omAggregate planning and mps om
Aggregate planning and mps om
 

Similar to Basic of work study, work measurement & job design om

History of workstudy - Workmeasurement - Job design
History of workstudy - Workmeasurement - Job designHistory of workstudy - Workmeasurement - Job design
History of workstudy - Workmeasurement - Job designRajeswari Balakrishnan
 
work measurement_operation management
work measurement_operation managementwork measurement_operation management
work measurement_operation managementSaravanan Murugan
 
Unit 2 work measurement.pdf
Unit 2 work measurement.pdfUnit 2 work measurement.pdf
Unit 2 work measurement.pdfSaurabh Jain
 
Operations management takira motors
Operations management takira motorsOperations management takira motors
Operations management takira motorsShrey Agarwal
 
Production and material management
Production and material managementProduction and material management
Production and material managementsksbatish
 
Work study method study-work measurement
Work study method study-work measurementWork study method study-work measurement
Work study method study-work measurementEr. Vaibhav Agarwal
 
Introduction to Work Study .ppt
Introduction to Work Study  .pptIntroduction to Work Study  .ppt
Introduction to Work Study .pptAryaRukmana1
 
presentation group 5.pptx
presentation group 5.pptxpresentation group 5.pptx
presentation group 5.pptxDouglassRasuh1
 
Om lect 08(r0-june-08)_basics of work study_work measurement_mms_bharti_sies
Om lect 08(r0-june-08)_basics of work study_work measurement_mms_bharti_siesOm lect 08(r0-june-08)_basics of work study_work measurement_mms_bharti_sies
Om lect 08(r0-june-08)_basics of work study_work measurement_mms_bharti_siesvideoaakash15
 
Techniques of scientific management
Techniques of scientific managementTechniques of scientific management
Techniques of scientific managementFarheen Khilji
 
Time and Motion Study
Time and Motion StudyTime and Motion Study
Time and Motion StudyVivek Shelke
 

Similar to Basic of work study, work measurement & job design om (20)

History of workstudy - Workmeasurement - Job design
History of workstudy - Workmeasurement - Job designHistory of workstudy - Workmeasurement - Job design
History of workstudy - Workmeasurement - Job design
 
3...time study 07
3...time study 073...time study 07
3...time study 07
 
4th-IE-BSS.pptx.pptx
4th-IE-BSS.pptx.pptx4th-IE-BSS.pptx.pptx
4th-IE-BSS.pptx.pptx
 
work measurement_operation management
work measurement_operation managementwork measurement_operation management
work measurement_operation management
 
work-measurement-ppt.pptx
work-measurement-ppt.pptxwork-measurement-ppt.pptx
work-measurement-ppt.pptx
 
Unit 2 work measurement.pdf
Unit 2 work measurement.pdfUnit 2 work measurement.pdf
Unit 2 work measurement.pdf
 
Management tools
Management toolsManagement tools
Management tools
 
Operations management takira motors
Operations management takira motorsOperations management takira motors
Operations management takira motors
 
Time and motion study
Time and motion study Time and motion study
Time and motion study
 
Production and material management
Production and material managementProduction and material management
Production and material management
 
Work study method study-work measurement
Work study method study-work measurementWork study method study-work measurement
Work study method study-work measurement
 
Introduction to Work Study .ppt
Introduction to Work Study  .pptIntroduction to Work Study  .ppt
Introduction to Work Study .ppt
 
presentation group 5.pptx
presentation group 5.pptxpresentation group 5.pptx
presentation group 5.pptx
 
Work measurement
Work measurementWork measurement
Work measurement
 
Sanket work study-1
Sanket work study-1Sanket work study-1
Sanket work study-1
 
Om lect 08(r0-june-08)_basics of work study_work measurement_mms_bharti_sies
Om lect 08(r0-june-08)_basics of work study_work measurement_mms_bharti_siesOm lect 08(r0-june-08)_basics of work study_work measurement_mms_bharti_sies
Om lect 08(r0-june-08)_basics of work study_work measurement_mms_bharti_sies
 
Techniques of scientific management
Techniques of scientific managementTechniques of scientific management
Techniques of scientific management
 
WORK MEASUREMENT
WORK MEASUREMENTWORK MEASUREMENT
WORK MEASUREMENT
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and control
 
Time and Motion Study
Time and Motion StudyTime and Motion Study
Time and Motion Study
 

Recently uploaded

PB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal BrandPB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal BrandSharisaBethune
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Doge Mining Website
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxsaniyaimamuddin
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditNhtLNguyn9
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 

Recently uploaded (20)

No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
PB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal BrandPB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal Brand
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal audit
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 

Basic of work study, work measurement & job design om

  • 1. BASIC OF WORK STUDY, JOB DESIGN & WORK MEASUREMENT BY YASHESH MORKHIA -> 816 KARTHIK NADAR -> 818 AKSHAY PATIL -> 819 SWAPNIL PRADHAN -> 820 APEKSHA ->821
  • 3. INTRODUCTION  WITH INCREASING COMPLEXITIES OF THE TECHNOLOGICAL WORLD, NEED TO SIMPLIFY THE WORK SYSTEM HAS BEEN INCREASING DAY BY DAY.  WORK STUDY IS AN AREA OF KNOWLEDGE THAT ADDRESSES THE PROBLEM OF WORK SIMPLIFICATION WITH THE BASIC OBJECTIVES OF PRODUCTIVITY ENHANCEMENT, HUMAN COMFORT & SAFETY
  • 4. EVOLUTION OF WORK STUDY • F.W.TAYLOR: FOUNDER OF MODERN METHOD AND TIME STUDY. • TAYLOR BEGAN HIS TIME STUDY WORK IN 1881. • HE ESTABLISHED THAT EACH JOB SHOULD HAVE A STANDARD TIME, DETERMINED BY TIME STUDIES. • IN THE TIMING PROCESS TAYLOR ADVOCATED DIVIDING THE WORK INTO SMALL DIVISIONS OF • EFFORT KNOWN AS ELEMENTS. • TIME WAS OBTAINED FOR THESE ELEMENT INDIVIDUALLY AND THEIR COLLECTIVE VALUES WERE USED TO DETERMINE THE ALLOWED TIME FOR THE TASK.
  • 5. WORK OF GILBERTH • GILBRETH IS CONSIDERED AS THE FOUNDER OF „MODERN MOTION STUDY TECHNIQUE‟. • WHICH IS DEFINED AS THE STUDY OF BODY MOTIONS USED IN PERFORMING AN OPERATION FOR THE PURPOSE OF IMPROVING THE OPERATION BY  ELIMINATING UNNECESSARY : MOTIONS  SIMPLIFYING NECESSARY MOTIONS  THEN ESTABLISHING THE MOST FAVORABLE MOTION SEQUENCE FOR MAXIMUM EFFICIENCY
  • 6. IMPORTANCE:• ENHANCING THE PRODUCTION EFFICIENCY OF THE FIRM. • TECHNIQUE TO IDENTIFY NON-VALUE OPERATIONS. • ONLY ACCURATE TECHNIQUE. AND SYSTEMATIC • HAS GOT UNIVERSAL APPLICATION. PROCEDURE ORIENTED
  • 7. DEFINITION “WORK STUDY IS DEFINED AS THAT BODY OF KNOWLEDGE CONCERNED WITH THE ANALYSIS OF THE WORK METHODS AND THE EQUIPMENT USED IN PERFORMING A JOB, THE DESIGN OF AN OPTIMUM WORK METHOD AND THE STANDARDIZATION OF PROPOSED WORK METHODS.” PREREQUISITES FOR CONDUCTING WORK STUDY
  • 8. STEPS INVOLVED IN WORK STUDY 1. SELECT Job Or Process To Be Studied 2. RECORD All the details concerning job using various Recording Techniques 3. EXAMINE Recorded facts critically by asking questions like who, what, when, why 4. DEVELOP Most economical method 5. MEASURE The amount of work involved and set standard time to do that job 6. DEFINE New method and standard time 7. INSTALL The new method as a standard practice 8. MAINTAIN New method as agreed standards
  • 9. PRINCIPLES OF WORK STUDY 1. MUST COME FROM THE TOP LEVEL MANAGEMENT. 2. PEOPLE MADE AWARE OF THE OBJECTIVES AND THE NEED OF THE EXERCISING SUCH STUDY. 3. METHOD STUDY MUST PRECEDE WORK MEASUREMENT .
  • 10. OBJECTIVES • TO ANALYZE THE PRESENT METHOD OF DOING A JOB, SYSTEMATICALLY IN ORDER TO DEVELOP A NEW AND BETTER METHOD. • TO MEASURE THE WORK CONTENT OF A JOB BY MEASURING THE TIME REQUIRED TO DO THE JOB FOR A QUALIFIED WORKER AND HENCE TO ESTABLISH STANDARD TIME. • TO INCREASE THE PRODUCTIVITY BY ENSURING THE BEST POSSIBLE USE OF HUMAN, MACHINE AND MATERIAL RESOURCES AND TO ACHIEVE BEST QUALITY PRODUCT/SERVICE AT MINIMUM POSSIBLE COST. • TO IMPROVE OPERATIONAL EFFICIENCY. • TO REDUCE WASTE THROUGH STANDARDIZATION • TO IMPROVE LABOR EFFICIENCY. OF WORK ELEMENTS OF A JOB.
  • 11. COMPONENTS / TECHNIQUES OF WORK STUDY WORK STUDY METHOD STUDY • Motion Study : Examine the job and finding more efficient method to perform it WORK MEASUREMENT • Time Study : Determine the time necessary to perform a job and its elements
  • 12. BENEFITS OF WORK STUDY  INCREASED PRODUCTIVITY AND OPERATIONAL EFFICIENCY  REDUCED MANUFACTURING COSTS  IMPROVED WORK PLACE LAYOUT  BETTER MANPOWER PLANNING AND CAPACITY PLANNING  FAIR WAGES TO EMPLOYEES  BETTER WORKING CONDITIONS TO EMPLOYEES  IMPROVED WORK FLOW  REDUCED MATERIAL HANDLING COSTS  PROVIDES A STANDARD OF PERFORMANCE TO MEASURE LABOUR EFFICIENCY  BETTER INDUSTRIAL RELATIONS AND EMPLOYEE MORALE  BASIS FOR SOUND INCENTIVE SCHEME  PROVIDES BETTER JOB SATISFACTION TO EMPLOYEES
  • 13. ADVANTAGES OF METHOD STUDY • WORK SIMPLIFICATION • IMPROVED WORKING METHOD ( CHEAPER METHOD) • BETTER PRODUCT QUALITY • IMPROVED WORK PLACE LAYOUT • IMPROVED EQUIPMENT DESIGN • BETTER WORKING CONDITIONS DISADVANTAGES OF METHOD STUDY • HIGH OPERATING COST • HIGH WASTAGE & SCRAP • EXCESSIVE MOVEMENT OF MATERIALS AND WORKMEN • EXCESSIVE PRODUCTION BOTTLENECKS • EXCESSIVE REJECTIONS AND REWORK • COMPLAINTS ABOUT QUALITY
  • 15. DEFINATION :• “THE APPLICATION OF TECHNIQUES DESIGNED TO ESTABLISH THE TIME FOR A QUALIFIED WORKER TO CARRY OUT A SPECIFIED JOB AT A DEFINED LEVEL OF PERFORMANCE”
  • 16. OBJECTIVES OF WORK MEASUREMENT :• 1. COMPARING ALTERNATIVE METHODS • 2. ASSESSING THE CORRECT INITIAL MANNING (MANPOWER REQUIREMENT PLANNING) • 3. PLANNING AND CONTROL • 4. REALISTIC COSTING • 5. DELIVERY DATE OF PLANNING • 6. COST REDUCTION AND COST CONTROL • 7. IDENTIFYING SUBSTANDARD WORKERS • 8. TRAINING NEW EMPLOYEES.
  • 17. TECHNIQUES OF WORK MEASUREMENT :• 1) REPETITIVE WORK:- THE TYPE OF WORK IN WHICH THE MAIN OPERATION OR GROUP OF OPERATIONS REPEAT CONTINUOUSLY DURING THE TIME SPENT AT THE JOB. THESE APPLY TO WORK CYCLE OF EXTREMELY SHORT DURATION. • 2) NON-REPETITIVE WORK:- IT INCLUDE SOME TYPE OF MAINTENANCE AND CONSTRUCTION WORK, WHERE CYCLE ITSELF IS HARDLY EVER REPEATED IDENTICALLY. VARIOUS TECHNIQUES:1)TIME STUDY 2) SYNTHESIS 3) WORK SAMPLING 4) ANALYTICAL ESTIMATION 5)PREDETERMINED MOTION AND TIME STUDY.
  • 18. TIME STUDY • TIME STUDY IS WORK MEASUREMENT TECHNIQUE FOR RECORDING THE TIMES AND RATES OF WORKING FOR THE ELEMENTS OF A SPECIFIED JOB CARRIED OUT UNDER SPECIFIED UNDER SPECIFIED CONDITIONS
  • 19. STEPS IN MAKING TIME STUDY:1)SELECT (SELECTING JOB FOR WORK STUDY) 2)OBTAIN & RECORD (DETAILS REGARDING METHODS,OPERATOR, JOB AND WORKING CONDITION) 3)DEFINE (THE ELEMENT, BREAK THE JOB INTO CONVENIENT FOR TIMING) 4)MEASURE (TIME DURATION FOR EACH ELEMENT AND ASSESS THE RATING) 5)EXTEND (OBSERVED TIME INTO NORMAL TIME {BASIC TIME}) 6)DETERMINED (RELAXATION AND PERSONAL ALLOWANCES) 7) COMPUTE (STANDARD TIME FOR THE OPERATION FOR DEFINED JOB OR OPERATION.)
  • 20. TYPES OF ELEMENT • A REPETITIVE ELEMENT – IS AN ELEMENT WHICH OCCURS IN EVERY WORK CYCLE OF THE JOB. • AN OCCASIONAL ELEMENT - DOES NOT OCCUR IN EACH WORK CYCLE OF THE JOB, BUT WHICH MAY OCCUR AT REGULAR OR IRREGULAR INTERVALS. E.G. MACHINE SETTING. • A CONSTANT ELEMENT - THE BASIC TIME REMAINS CONSTANT WHENEVER IT IS PERFORMED. E.G. SWITCH THE MACHINE ON. • A VARIABLE ELEMENT - IS AN ELEMENT FOR WHICH THE BASIC TIME VARIES IN RELATION TO SOME CHARACTERISTICS OF THE PRODUCT, EQUIPMENT OR PROCESS, E.G. DIMENSIONS, WEIGHT, QUALITY ETC. E.G. PUSH TROLLEY OF PARTS TO NEXT SHOP.
  • 21. TYPES OF ELEMENT • MANUAL ELEMENT - IS AN ELEMENT PERFORMED BY A WORKER. • MACHINE ELEMENT - IS AUTOMATICALLY PERFORMED BY A POWER-DRIVEN MACHINE (OR PROCESS). • GOVERNING ELEMENT - OCCUPIES A LONGER TIME THAN ANY OF THE OTHER ELEMENTS WHICH ARE BEING PERFORMED CONCURRENTLY. E.G. BOIL KETTLE OF WATER, WHILE SETTING OUT TEAPOT AND CUPS. • FOREIGN ELEMENT - IS OBSERVED DURING A STUDY WHICH, AFTER ANALYSIS, IS NOT FOUND TO BE NECESSARY PART OF THE JOB. E.G. DEGREASING A PART THAT HAS STILL TO BE MACHINED FURTHER.
  • 22. ALLOWANCES • RELAXATION ALLOWANCES • VARIABLE ALLOWANCES • INTERFERENCE ALLOWANCES • CONTINGENCY ALLOWANCES • POLICY ALLOWANCES
  • 24. EXAMPLE ON HOW TO CALCULATE STANDARD TIME:
  • 25. WORK MEASUREMENT • STANDARD TIME IS USED IN: • COSTING THE LABOR COMPONENT OF PRODUCTS • TRACKING EMPLOYEE PERFORMANCE • SCHEDULING & PLANNING REQUIRED RESOURCES
  • 26. SETTING STANDARD TIMES • STEP 1: CHOOSE THE SPECIFIC JOB TO BE STUDIED • STEP 2: TELL THE WORKER WHOSE JOB YOU WILL BE STUDYING • STEP 3: BREAK THE JOB INTO EASILY RECOGNIZABLE UNITS • STEP 4: CALCULATE THE NUMBER OF CYCLES YOU MUST OBSERVE • STEP 5: TIME EACH ELEMENT, RECORD DATA & RATE THE WORKER‟S PERFORMANCE • STEP 6: COMPUTE THE NORMAL TIME • STEP 7: COMPUTE THE STANDARD TIME
  • 28. WORK SAMPLING:WORK SAMPLING WAS ORIGINALLY DEVELOPED BY L.H.C. TIPPETT IN BRITAIN IN 1934 FOR THE BRITISH COTTON INDUSTRY RESEARCH BOARD. DEFINATION:A TECHNIQUE IN WHICH A STATISTICALLY COMPETENT NUMBER OF INSTANTANEOUS OBSERVATIONS ARE TAKEN, OVER A PERIOD TIME, OF A GROUP OF MACHINES,PROCESSES OR WORKERS. WORK SAMPLING HAS THREE MAIN APPLICATIONS:1) ACTIVITY AND DELAY SAMPLING:- TO MEASURE THE ACTIVITIES AND DELAYS OF WORKERS AND MACHINES. 2) PERFORMANCE SAMPLING:- TO MEASURE WORKING TIME AND NON WORKING TIME OF A PERSON ON A MANUAL WORK AND TO ESTABLISH A PERFORMANCE INDEX OR PERFORMANCE LEVEL FOR A PERSON DURING HIS WORKING TIME. 3) WORK MEASUREMENT:- UNDER CERTAIN CIRCUMSTANCES, TO MEASURE MANUAL TASK THAT IS TO ESTABLISHED A TIME STANDARD FOR AN OPERATION.
  • 29. WHAT IS JOB DESIGN Job design – process by which managers decide individual job tasks and authority Job redesign – process by which managers reconsider what employees are expected to do The well-being of organizations and people relates to how well management designs jobs
  • 30. DEFINITION OF JOB DESIGN Def: Job Design is the process of deciding on the content of a job in terms of its duties and responsibilities; on the methods to be used in carrying out the job, in terms of techniques, systems and procedures and on the relationships that should exist between the job holder and the superiors, subordinates and colleagues.
  • 31. GOALS OF JOB DESIGN 1. 2. 3. 4. Major Concern Purpose of Job Design Affect on Employee Impact
  • 32. DESIGN FACTOR • LAYOUT OF EQUIPMENT AND SEATING • INSTRUMENT DISPLAY DESIGN • COMPATIBILITY • CONTROL DESIGN CHARACTERISTICS
  • 33. ENVIRONMENTAL FACTORS • TEMPERATURE AND HUMMIDITY • VIBRATION • NOISE
  • 34. VISUAL ENVIRONMENT • LIGHTING • VENTILATION • BEHAVIOURAL DIMENSIONS OF JOB DESIGN • JOB ROTATION • JOB ENLARGEMENT • JOB ENRICHMENT
  • 35. JOB ROTATION: JOB ENLARGEMENT :JOB ENRICHMENT: • JOB ROTATION: REFERS TO THE MOVEMENT OF AN EMPLOYEE FROM ONE JOB TO ANOTHER. • PLEASE NOTE: JOBS THEMSELVES ARE NOT ACTUALLY CHANGED, ONLY EMPLOYEES ARE ROTATED AMONG VARIOUS JOBS. • • JOB ENLARGEMENT WHEN A JOB IS ENLARGED THE TASKS BEING PERFORMED ARE EITHER ENLARGED OR SEVERAL SHORT TASKS ARE GIVEN TO ON WORKER, THUS THE SCOPE OF THE JOB IS INCREASED BECAUSE THERE ARE MANY TASKS TO BE PERFORMED BY THE SAME WORKER. • • JOB ENRICHMENT: JOB ENRICHMENT AS IS CURRENTLY PRACTICED ALL OVER THE WORK IS A DIRECT OUTGROWTH OF HERZBERG‟S TWO FACTOR THEORY OF MOTIVATION.
  • 36. APPROACHES TO JOB DESIGN • ENGINEERING APPROACH: • HUMAN APPROACH: • JOB CHARACTERISTICS APPROACH:
  • 37. ENGINEERING APPROACH: • THE WORK OF EVERY WORKMAN IS FULLY PLANNED OUT BY THE MANAGEMENT AT LEAST ON DAY IN ADVANCE AND EACH MAN RECEIVES IN MOST CASES COMPLETE WRITTEN INSTRUCTIONS, DESCRIBING IN DETAIL THE TASK WHICH HE/SHE HAS TO ACCOMPLISH- FW TAYLOR. • PROBLEM WITH THIS APPROACH: REPETITION-MECHANICAL PACING-NO END PRODUCT-LITTLE SOCAL INTERACTION-NO INPUT
  • 38. HUMAN APPROACH: • THE HUMAN RELATIONS APPROACH RECOGNIZED THE NEED TO DESIGN JOBS WHICH ARE INTERESTING AND REWARDING. • HERZBERG‟S RESEARCH POPULARIZED THE NOTION OF ENHANCING NEED SATISFACTION THROUGH WHAT IS CALLED JOB ENRICHMENT. • FACTORS INVOLVED: • MOTIVATORS LIKE ACHIEVEMENT, RECOGNITION, WORK AND GROWTH AND HYGIENIC FACTORS. ITSELF, RESPONSIBILITY, ADVANCEMENT • ACCORDING TO HERZBERG. THE EMPLOYEE IS DISSATISFIED WITH THE JOB IF REQUIRED MAINTENANCE FACTORS TO THE REQUIRED DEGREE ARE NOT INTRODUCED INTO THE JOB.
  • 39. JOB CHARACTERISTICS APPROACH • THEORY BY HACKMAN AND OLDHAM STATES THAT EMPLOYEES WILL WORK HARD WHEN THEY ARE REWARDED FOR THE WORK THEY DO AND WHEN THE WORK GIVES THEM SATISFACTION. • HENCE INTEGRATION OF MOTIVATION, SATISFACTION AND PERFORMANCE • ACCORDING TO THIS APPROACH JOB CAN BE DESCRIBED IN TERMS OF FIVE CORE JOB DIMENSIONS: 1. SKILL VARIETY 2. TASK IDENTITY 3. TASK SIGNIFICANCE 4. AUTONOMY 5. FEEDBACK WITH JOB DESIGN.
  • 40. JOB DESIGN PROCESS: • JOB DESIGN PROCESS HAS TO START FROM WHAT ACTIVITY NEEDS TO BE DONE IN ORDER TO ACHIEVE ORGANIZATIONAL GOALS. • IT REQUIRES USE OF TECHNIQUES LIKE WORK-STUDY, PROCESS PLANNING, ORGANIZATIONAL METHODS AND ORGANIZATIONAL ANALYSIS AND ALSO TECHNICAL ASPECTS