SlideShare a Scribd company logo
1 of 4
Taher E. Hasanen
Personal
Information
 Full name: Taher Ibrahim Ali Mohamed Hasanen
 Nationality: Egyptian.
 Current Job: Senior Project Engineer at Seidco General contracting LLC,
AbuDhabi, A.UE.
Education Bachelor of Civil Engineering.
Faculty of Engineering, Elshrouk Acadmy
Graduation year: 2007.
Graduation project: V. Good 82.4%, Rank 3rd
.
Accumulative degree: V. Good 83.6%, Rank 3rd
.
Languages  Arabic "Mother Tongue".
 English "Fluent".
 Urdo "Beginner".
Computer Skills

 Proven ability to competently prepare, progress and daily reports,
corresponds & presentations.
 Proven ability to work under stressed situations & challenges.
 Building materials, Quantity surveying, Q.S.
 Handling and managing pouring concrete operations for complicated
structures.
 Handling all finishes works.

 Excellent English skills ( fluently speaking , listening & reading )

 Speaking Urdu, - Handling communication in work environment –

 Well-versed in using the following software Packages:

 Microsoft® Office (Word – Excel – PowerPoint), AutoCAD® Sap
Fields of
Experience
 Communicating and negotiating skills
 Execution of Steel Structures.
 Execution EFIS System and Cladding.
 Solar Tubes Lighting.
 Performing Concrete works / form works & reinforcements.
 Performing finishing works.
 Q.S. & QA/QC Works.
 Preparing Progress reports
Abudhabi, UAE.
E-mail eng_civil_egy@yahoo.com
Cell +971566167044
+971509219809
 Construction of transfer slab.
 Pouring concrete for complicated structures.
 Execution Concrete works / form works & reinforcements.
 Execution finishing works.
 Execution infra – structure works
 Preparing Progress reports.
 Coordination with M.E.P. departments.
Work experience 15/7/2007 to 5/6/2008 Egypt Cairo
Site Engineer
Participated in: Fouda Engineering consultancy.
7/1/2008 to 15/1/2009 UAE Dubai
Site Engineer.
Participated in:
 Project Construction of 3 villas G+1, UAE, A.I.C. General Contracting.
 Consultant: National Engineering Bureau.
 Location : El-BARCHA Dubai
 Project Value: 25 Million AED.
I had started work in this project in the excavation& foundation stage;
too many duties were handled to me such as following evocation and
foundation and column and slap, also handing over works to the
consultant. Block works, finishing works and other civil duties, in site
and office.
16/1/2009 to 30/1/2011 UAE Dubai
Site Engineer.
Participated in:
 Project Construction of Park Veuwe Hotel,-2B+G+7Typical Floors+Health
Club, UAE, A.I.C. General Contracting.
 Consultant : National Engineering Bureau.
 Location :Dubai
 Project Value:120 Million AED.
 Client : KHamas Group
I had started work in this project in the piles & raft foundation stage; too
many duties were handled to me such as following piles testing,
construction of pile caps and raft foundation, also Q.S. works, preparing
progress reports, handing over works to the consultant. Block works,
finishing works and other civil duties, in site and office.
Experience &skills gained:
 Performing Concrete works / form works & reinforcements.
 Performing finishing works.
 Q.S. & QA/QC Works.
 Preparing Progress reports
 Construction of transfer slab.
 Pouring concrete for complicated structures.
Page 3 of 5
1/02/2011 till 15/06/2012 UAE AbuDhabi
Site Engineer.
 Participated in project Development of Albateen Park 75 Residential Villa
G+1 & 12 Buildings B+ G+6,Abudhabi, UAE,Seideco General
Contracting.LLC.
 Consultant: DEWAN Architects & Engineers.
 Location :Abudhabi
 Project Value: 655 Million AED.
 Client : ALDAR Properties PJSC
My Career Development just received a very good deal of knowledge and
vast experience at this project, with horizontal construction works over an
area of 24000 m2 dealing with all aspects of construction works , ranging
from infra-structure to landscaping to ordinary construction works.
I was in charge of carrying out 3 Building, handling atop and A Right and A
Left, managing all construction works, & coordinating with all other parties
working at the project.
It was a stressful project, but I gained a lot of coordination and large
scale projects experience
Experience &skills gained:
 Execution Concrete works / form works & reinforcements.
 Execution finishing works.
 Execution infra – structure works
 Preparing Progress reports.
 Coordination with M.E.P. departments.
 Communicating and negotiating skills
16/06/2012 till 5/01/2014 UAE Abudhabi
Project Engineer.
 Participated in project Sheikh Omar Bin Zayed Al Nayhan 3B+G+2P+42,
UAE, Seideco General Contracting.LLC.
 Consultant: SEIR CONSULTANT.
 Location: Abudhabi, Elreem Island.
 Project Value: 230 Million AED.
 Client : Sheikh Omar Bin ZAYED Al-NYHAN
Another new project & much more experience and career development I
had received, due to being a member of the construction team at this
amazing tower, The tower contain 3B For car parking ,G For parking And 6
flat,2 Podium With Car Parking and each podium floor is typical each floor
have 7 flat ,20th floor is mechanical floor, ,41 floor is one flat with trace
and roof.
Experience &skills gained:
 Execution of Steel Structures.
 Execution EFIS System and Cladding.
 Solar Tubes Lighting.
06/01/2014 till 15/08/2015 Invensys UAE Abudhabi
Project Engineer.
Participated in project Residential Building 3B+G+M+17, UAE, Seideco
General Contracting.LLC.
 Consultant: SEREX.
 Location : Danet Abu Dhabi –SULTAN BIN ZAYED street
 Project Value: 105 Million AED.
 Client : H.E. Mohamed Saqer Al Falahi
This is my ongoing Project which is comprised of 3 Basements used as car
parks & services, Ground & Mezzanine used as Retail Complex, 17 typical
Floor used as residential apartments.
My role is to monitor all the site works, ordering material, dealing with
subcontractors, prepare payments; coordinate with MEP Departments,
Follow-up Site works Progress
16/08/2015 till Current UAE Abudhabi
Project Engineer.
Participated in project Office Building 4B+G+7, UAE, Seideco General
Contracting.LLC.
 Consultant : K EO.
 Location: Abudhabi, Elreem Island.
 Project Value: 200 Million AED.
 Client : WAFRA REAL ESTATE CO
This is my ongoing Project which is comprised of 4 Basements used as car
parks & services, Ground used as entrance and services & 7 typical Floor
used as residential apartments. This project 7500m2 give me more
experiences in horizontal and finishing of the office
My role is to monitor all the site works, ordering material, dealing with
subcontractors, prepare payments; coordinate with MEP Departments,
Follow-up Site works Progress
Awards received  A certificate of thanks from SEIDCO GENERAL CONTRACTING L.L.C,
year 2013.
Security Clearance
and Licenses
 United Arab Emirates Driving License
 International Driver License

More Related Content

What's hot (20)

Khaled Essam portfolio
Khaled Essam portfolioKhaled Essam portfolio
Khaled Essam portfolio
 
MOHAMED SALAH C.V 2016
MOHAMED SALAH C.V 2016MOHAMED SALAH C.V 2016
MOHAMED SALAH C.V 2016
 
DavidBarryCVSeptember2016
DavidBarryCVSeptember2016DavidBarryCVSeptember2016
DavidBarryCVSeptember2016
 
Mohamed Nabil Omar - CV
Mohamed Nabil Omar - CVMohamed Nabil Omar - CV
Mohamed Nabil Omar - CV
 
hatim marouf 4
hatim marouf 4hatim marouf 4
hatim marouf 4
 
Khaled essam portfolio
Khaled essam portfolioKhaled essam portfolio
Khaled essam portfolio
 
CV Ahmed Site
CV Ahmed SiteCV Ahmed Site
CV Ahmed Site
 
Curriculum vita mohamed nabil
Curriculum vita  mohamed nabilCurriculum vita  mohamed nabil
Curriculum vita mohamed nabil
 
Ayad Fakhery Karass2013
Ayad Fakhery Karass2013Ayad Fakhery Karass2013
Ayad Fakhery Karass2013
 
Resume new version 17
Resume new version 17Resume new version 17
Resume new version 17
 
Mohamed Barakat Updated CV
Mohamed Barakat Updated CVMohamed Barakat Updated CV
Mohamed Barakat Updated CV
 
amro cv last 8.2015
amro cv last 8.2015amro cv last 8.2015
amro cv last 8.2015
 
Asim Resume
Asim ResumeAsim Resume
Asim Resume
 
Draughtsman c v 2019 s.a mannan
Draughtsman c v 2019  s.a mannanDraughtsman c v 2019  s.a mannan
Draughtsman c v 2019 s.a mannan
 
my official cv
my official cvmy official cv
my official cv
 
Yousef Abu Alwafa Resume
Yousef Abu Alwafa ResumeYousef Abu Alwafa Resume
Yousef Abu Alwafa Resume
 
HENRY APPLEBY- CV_03.09.15
HENRY APPLEBY- CV_03.09.15HENRY APPLEBY- CV_03.09.15
HENRY APPLEBY- CV_03.09.15
 
engFahed C.V.
engFahed C.V.engFahed C.V.
engFahed C.V.
 
Application for the post of Project Engineer & Site Engineer
Application for the post of Project Engineer & Site  EngineerApplication for the post of Project Engineer & Site  Engineer
Application for the post of Project Engineer & Site Engineer
 
Curriculum Vitae
Curriculum VitaeCurriculum Vitae
Curriculum Vitae
 

Viewers also liked

Body Mass Supplements
Body Mass SupplementsBody Mass Supplements
Body Mass Supplements
sovaywqu
 
CompCloud2014_Process getting in the way of Profit_Breakout_OS_Xactly_BV_Brea...
CompCloud2014_Process getting in the way of Profit_Breakout_OS_Xactly_BV_Brea...CompCloud2014_Process getting in the way of Profit_Breakout_OS_Xactly_BV_Brea...
CompCloud2014_Process getting in the way of Profit_Breakout_OS_Xactly_BV_Brea...
Laura Roach
 
THE SYSTEM FOR ORGANIZATIONAL MANAGEMENT OF THE IMPLEMENTATION OF THE PROGRAM...
THE SYSTEM FOR ORGANIZATIONAL MANAGEMENT OF THE IMPLEMENTATION OF THE PROGRAM...THE SYSTEM FOR ORGANIZATIONAL MANAGEMENT OF THE IMPLEMENTATION OF THE PROGRAM...
THE SYSTEM FOR ORGANIZATIONAL MANAGEMENT OF THE IMPLEMENTATION OF THE PROGRAM...
Andrey Shabarov
 
Han vengut els patges power point
Han vengut els patges power pointHan vengut els patges power point
Han vengut els patges power point
ceipmolidenxema2n
 

Viewers also liked (18)

Body Mass Supplements
Body Mass SupplementsBody Mass Supplements
Body Mass Supplements
 
CompCloud2014_Process getting in the way of Profit_Breakout_OS_Xactly_BV_Brea...
CompCloud2014_Process getting in the way of Profit_Breakout_OS_Xactly_BV_Brea...CompCloud2014_Process getting in the way of Profit_Breakout_OS_Xactly_BV_Brea...
CompCloud2014_Process getting in the way of Profit_Breakout_OS_Xactly_BV_Brea...
 
Masjid postersize duas
Masjid postersize duasMasjid postersize duas
Masjid postersize duas
 
Presentación1
Presentación1Presentación1
Presentación1
 
Christmas 2013
Christmas 2013Christmas 2013
Christmas 2013
 
AoU CWEEN NEW ORLEANS Combined
AoU CWEEN NEW ORLEANS CombinedAoU CWEEN NEW ORLEANS Combined
AoU CWEEN NEW ORLEANS Combined
 
THE SYSTEM FOR ORGANIZATIONAL MANAGEMENT OF THE IMPLEMENTATION OF THE PROGRAM...
THE SYSTEM FOR ORGANIZATIONAL MANAGEMENT OF THE IMPLEMENTATION OF THE PROGRAM...THE SYSTEM FOR ORGANIZATIONAL MANAGEMENT OF THE IMPLEMENTATION OF THE PROGRAM...
THE SYSTEM FOR ORGANIZATIONAL MANAGEMENT OF THE IMPLEMENTATION OF THE PROGRAM...
 
Vision acerca de la enef
Vision acerca de la enefVision acerca de la enef
Vision acerca de la enef
 
sam resume draft 2
sam resume draft 2sam resume draft 2
sam resume draft 2
 
I 3 Profile
I 3 ProfileI 3 Profile
I 3 Profile
 
Тренинг по вопросам здорового образа жизни
Тренинг по вопросам здорового образа жизниТренинг по вопросам здорового образа жизни
Тренинг по вопросам здорового образа жизни
 
Marcus-final essay
Marcus-final essayMarcus-final essay
Marcus-final essay
 
Introducción al Hardware
Introducción al HardwareIntroducción al Hardware
Introducción al Hardware
 
Hukum Agama
Hukum AgamaHukum Agama
Hukum Agama
 
IRW Chapter 8
IRW Chapter 8IRW Chapter 8
IRW Chapter 8
 
Búsqueda y gestión de la información en la web
Búsqueda y gestión de la información en la webBúsqueda y gestión de la información en la web
Búsqueda y gestión de la información en la web
 
Statues
StatuesStatues
Statues
 
Han vengut els patges power point
Han vengut els patges power pointHan vengut els patges power point
Han vengut els patges power point
 

Similar to ENG Taher CV (20)

04-2016
04-201604-2016
04-2016
 
Abdelaziz Fawzy CV 1-11
Abdelaziz Fawzy CV 1-11Abdelaziz Fawzy CV 1-11
Abdelaziz Fawzy CV 1-11
 
Civil Site Engineer (2)
Civil Site Engineer (2)Civil Site Engineer (2)
Civil Site Engineer (2)
 
Hafez CV
Hafez CVHafez CV
Hafez CV
 
Hassans new cv 14-7-15
Hassans new cv 14-7-15Hassans new cv 14-7-15
Hassans new cv 14-7-15
 
Personal CV (Mohd) BM
Personal CV (Mohd) BMPersonal CV (Mohd) BM
Personal CV (Mohd) BM
 
Hanin qreis 2018 cv
Hanin qreis 2018 cvHanin qreis 2018 cv
Hanin qreis 2018 cv
 
CV GENDY 2016
CV GENDY 2016CV GENDY 2016
CV GENDY 2016
 
feras last resume
feras last resumeferas last resume
feras last resume
 
MAYAD_RAZOOK_CV__2022.pdf
MAYAD_RAZOOK_CV__2022.pdfMAYAD_RAZOOK_CV__2022.pdf
MAYAD_RAZOOK_CV__2022.pdf
 
modified cv khaled
modified  cv khaledmodified  cv khaled
modified cv khaled
 
MOHAMED CV - Civil Engineer
MOHAMED CV - Civil EngineerMOHAMED CV - Civil Engineer
MOHAMED CV - Civil Engineer
 
Land surveyor + site supervisor
Land surveyor + site  supervisorLand surveyor + site  supervisor
Land surveyor + site supervisor
 
Hamdy hussien cv resident engineer
Hamdy hussien cv resident engineerHamdy hussien cv resident engineer
Hamdy hussien cv resident engineer
 
Osama structure eng. cv
Osama structure eng. cvOsama structure eng. cv
Osama structure eng. cv
 
Samy Gaber CV sep18
Samy Gaber CV sep18Samy Gaber CV sep18
Samy Gaber CV sep18
 
Hussam mohammed el shetehy cv
Hussam mohammed el shetehy cvHussam mohammed el shetehy cv
Hussam mohammed el shetehy cv
 
Abdulrahman Shakboua15
Abdulrahman Shakboua15Abdulrahman Shakboua15
Abdulrahman Shakboua15
 
last c v 1-1-15
last c v 1-1-15last c v 1-1-15
last c v 1-1-15
 
السي في
السي فيالسي في
السي في
 

ENG Taher CV

  • 1. Taher E. Hasanen Personal Information  Full name: Taher Ibrahim Ali Mohamed Hasanen  Nationality: Egyptian.  Current Job: Senior Project Engineer at Seidco General contracting LLC, AbuDhabi, A.UE. Education Bachelor of Civil Engineering. Faculty of Engineering, Elshrouk Acadmy Graduation year: 2007. Graduation project: V. Good 82.4%, Rank 3rd . Accumulative degree: V. Good 83.6%, Rank 3rd . Languages  Arabic "Mother Tongue".  English "Fluent".  Urdo "Beginner". Computer Skills   Proven ability to competently prepare, progress and daily reports, corresponds & presentations.  Proven ability to work under stressed situations & challenges.  Building materials, Quantity surveying, Q.S.  Handling and managing pouring concrete operations for complicated structures.  Handling all finishes works.   Excellent English skills ( fluently speaking , listening & reading )   Speaking Urdu, - Handling communication in work environment –   Well-versed in using the following software Packages:   Microsoft® Office (Word – Excel – PowerPoint), AutoCAD® Sap Fields of Experience  Communicating and negotiating skills  Execution of Steel Structures.  Execution EFIS System and Cladding.  Solar Tubes Lighting.  Performing Concrete works / form works & reinforcements.  Performing finishing works.  Q.S. & QA/QC Works.  Preparing Progress reports Abudhabi, UAE. E-mail eng_civil_egy@yahoo.com Cell +971566167044 +971509219809
  • 2.  Construction of transfer slab.  Pouring concrete for complicated structures.  Execution Concrete works / form works & reinforcements.  Execution finishing works.  Execution infra – structure works  Preparing Progress reports.  Coordination with M.E.P. departments. Work experience 15/7/2007 to 5/6/2008 Egypt Cairo Site Engineer Participated in: Fouda Engineering consultancy. 7/1/2008 to 15/1/2009 UAE Dubai Site Engineer. Participated in:  Project Construction of 3 villas G+1, UAE, A.I.C. General Contracting.  Consultant: National Engineering Bureau.  Location : El-BARCHA Dubai  Project Value: 25 Million AED. I had started work in this project in the excavation& foundation stage; too many duties were handled to me such as following evocation and foundation and column and slap, also handing over works to the consultant. Block works, finishing works and other civil duties, in site and office. 16/1/2009 to 30/1/2011 UAE Dubai Site Engineer. Participated in:  Project Construction of Park Veuwe Hotel,-2B+G+7Typical Floors+Health Club, UAE, A.I.C. General Contracting.  Consultant : National Engineering Bureau.  Location :Dubai  Project Value:120 Million AED.  Client : KHamas Group I had started work in this project in the piles & raft foundation stage; too many duties were handled to me such as following piles testing, construction of pile caps and raft foundation, also Q.S. works, preparing progress reports, handing over works to the consultant. Block works, finishing works and other civil duties, in site and office. Experience &skills gained:  Performing Concrete works / form works & reinforcements.  Performing finishing works.  Q.S. & QA/QC Works.  Preparing Progress reports  Construction of transfer slab.  Pouring concrete for complicated structures. Page 3 of 5
  • 3. 1/02/2011 till 15/06/2012 UAE AbuDhabi Site Engineer.  Participated in project Development of Albateen Park 75 Residential Villa G+1 & 12 Buildings B+ G+6,Abudhabi, UAE,Seideco General Contracting.LLC.  Consultant: DEWAN Architects & Engineers.  Location :Abudhabi  Project Value: 655 Million AED.  Client : ALDAR Properties PJSC My Career Development just received a very good deal of knowledge and vast experience at this project, with horizontal construction works over an area of 24000 m2 dealing with all aspects of construction works , ranging from infra-structure to landscaping to ordinary construction works. I was in charge of carrying out 3 Building, handling atop and A Right and A Left, managing all construction works, & coordinating with all other parties working at the project. It was a stressful project, but I gained a lot of coordination and large scale projects experience Experience &skills gained:  Execution Concrete works / form works & reinforcements.  Execution finishing works.  Execution infra – structure works  Preparing Progress reports.  Coordination with M.E.P. departments.  Communicating and negotiating skills 16/06/2012 till 5/01/2014 UAE Abudhabi Project Engineer.  Participated in project Sheikh Omar Bin Zayed Al Nayhan 3B+G+2P+42, UAE, Seideco General Contracting.LLC.  Consultant: SEIR CONSULTANT.  Location: Abudhabi, Elreem Island.  Project Value: 230 Million AED.  Client : Sheikh Omar Bin ZAYED Al-NYHAN Another new project & much more experience and career development I had received, due to being a member of the construction team at this amazing tower, The tower contain 3B For car parking ,G For parking And 6 flat,2 Podium With Car Parking and each podium floor is typical each floor have 7 flat ,20th floor is mechanical floor, ,41 floor is one flat with trace and roof. Experience &skills gained:  Execution of Steel Structures.  Execution EFIS System and Cladding.  Solar Tubes Lighting.
  • 4. 06/01/2014 till 15/08/2015 Invensys UAE Abudhabi Project Engineer. Participated in project Residential Building 3B+G+M+17, UAE, Seideco General Contracting.LLC.  Consultant: SEREX.  Location : Danet Abu Dhabi –SULTAN BIN ZAYED street  Project Value: 105 Million AED.  Client : H.E. Mohamed Saqer Al Falahi This is my ongoing Project which is comprised of 3 Basements used as car parks & services, Ground & Mezzanine used as Retail Complex, 17 typical Floor used as residential apartments. My role is to monitor all the site works, ordering material, dealing with subcontractors, prepare payments; coordinate with MEP Departments, Follow-up Site works Progress 16/08/2015 till Current UAE Abudhabi Project Engineer. Participated in project Office Building 4B+G+7, UAE, Seideco General Contracting.LLC.  Consultant : K EO.  Location: Abudhabi, Elreem Island.  Project Value: 200 Million AED.  Client : WAFRA REAL ESTATE CO This is my ongoing Project which is comprised of 4 Basements used as car parks & services, Ground used as entrance and services & 7 typical Floor used as residential apartments. This project 7500m2 give me more experiences in horizontal and finishing of the office My role is to monitor all the site works, ordering material, dealing with subcontractors, prepare payments; coordinate with MEP Departments, Follow-up Site works Progress Awards received  A certificate of thanks from SEIDCO GENERAL CONTRACTING L.L.C, year 2013. Security Clearance and Licenses  United Arab Emirates Driving License  International Driver License