SlideShare a Scribd company logo
1 of 26
Demolition Of
Building
By – Tushar Garg
INDEX
1. Introduction
2. Objective
3. Step before demolition
4. Method of demolition
5. Building implosion
6. Placing of explosive
7. conclusion
8. Reference
Introduction
 We know that every structure is designed for a life period.
 The existence of the structure after the service life period is very dangerous to its occupant and
surrounding building.
 Demolition is the process of tearing down or falling down of a building after its life period with the
help of some equipment or any other method.
 When explosive are used for this then demolition process are called as implosion.
objective
 Old and damaged building (due to earthquake and other various reasons) which are prone to fall
down completely or partially must be demolished before any fatal accident.
 When the important structural components like beams and columns become absolutely insufficient
for service then there is no option other than demolishing the building.
 When a new structure need to be constructed on the site, the old structure is demolished.
 For safety of neighbouring area, a deteriorated building is often demolished.
Step before demolition
1. Surveying
2. Removal of hazardous
materials
3. Preparation of plan
4. Safety measures
surveying
The building should cover the following :-
 The construction material.
 Adjoining pedestrians and vehicular traffic condition.
 The sensitivity of neighbourhood with respect to noise,
dust, vibration and traffic impact.
 Available site to demolition.
 Record drawing.
Removal of hazardous material
 Asbestos containing material – in case when asbestos containing material are discovered,
specialist contractor shall be employed to be removed such material. The asbestos waste should
be handled, stored and disposed off as a chemical waste.
 Soil contamination material – in case when soil contamination material is present, specialist shall
be employed to prepare soil contamination test proposal and submit such proposal to the
Environmental Protection Department.
Asbestos material soil contamination
Removal of hazardous material
Preparation of plan
 The Location of building to be demolished.
 A layout plan of all floors of the building to be demolished.
 The structural support system.
 A plan showing the procedure for the demolition of building.
 In the case when powered mechanical plants and equipment are used, a plan showing the route of
movement of powered mechanical plants and equipment.
Safety measure
 Training and communication - Demolition workers,
including plant or equipment operators, shall go through
proper job safety training and be informed of the
potential hazards by attending training sessions as well
as on-the-job training.
 Equipment maintenance - All equipment shall
be tested and examined before use. They shall
be properly stored and maintained. The
equipment shall be inspected daily and results
of the inspection shall be recorded
accordingly.
 Properly marked with exit signs.
Safety measure
 Fire - All flammable goods shall be removed from site
unless they are necessary for the works involved. Any
remaining flammable goods shall be stored in proper
storage facilities. All furniture, timber, doors, etc. shall be
removed before any welding work is performed. Fire
fighting appliances shall be provided and maintained in
working conditions
Safety measure
Method of demolition
PIECEMEAL
DEMOLITION
MECHANICAL
METHOD
EXPLOSIVE
DEMOLITION
Piecemeal demolition
A jackhammer is a pneumatic or electro-
mechanical tool that combines
a hammer directly with a chisel.
Jack hammer ->
Mechanical method
 Ball and crane - A crane uses a wrecking ball, weighing up to 6120 kg, which is either dropped
onto or swung into the element to be demolished.
Ball and crane
Mechanical method
Hydraulic breaker
 A hydraulic breaker is a powerful
percussion hammer fitted to an excavator for
demolishing concrete structures or rocks. It is
powered by an auxiliary hydraulic system.
Explosive demolition
 The basic idea of explosive demolition is quite simple.
 If we remove the support structure of a building at a certain point, the section of the building
above the point will fall down on the part of the building below that point.
Blasting machine blasting cap or electrical detonator
RDX-based explosive compounds expand at a
very high rate of
speed, up to 27,000 feet per second (8,230
meters per second)
Explosive demolition
Advantage of explosive demolition
Explosive demolition
 Less expensive.
 No ground vibrations.
 Quickest method.
 Suitable for multi-storey / high piers, cabins, distressed piers etc.
Building implosion
Building implosion
Concrete columns Steel columns
Process of implosion
Placing of explosive
conclusion
 It can be concluded that demolishing/imploding the building structure will prove very useful,
economical and quickest for reconstruction.
 Type of demolition method depends upon various factors such as site condition, type of structures,
age of building, height of building and economy.
 Explosive demolition is the preferred method for safely and efficiently demolishing the larger
structures.
 Development in techniques allows rapid demolition with no harm to the environment.
Reference
 www.google.com
 www.Wikipedia.com
 www.studymafia.org
 www.implosionworld.com
Thank you

More Related Content

What's hot

Introduction to demolition
Introduction to demolitionIntroduction to demolition
Introduction to demolitionDivyang Rathod
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of buildingvikas mishra
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of buildingAglaia Connect
 
Demolition of Structures.
Demolition of Structures.Demolition of Structures.
Demolition of Structures.Chintan Varia
 
DEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKDEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKKHUSHBU SHAH
 
Safety precautions during demolition
Safety precautions during demolitionSafety precautions during demolition
Safety precautions during demolitionManthan Vaghasiya
 
DEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUESDEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUESNirant Patel
 
Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequenceRanjith Kumar
 
Sub Structure Construction.pptx
Sub Structure Construction.pptxSub Structure Construction.pptx
Sub Structure Construction.pptxAnanthakumar75
 
Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundationsKHUSHBU SHAH
 
Demolition of building and blasting equipment
Demolition of building and blasting equipmentDemolition of building and blasting equipment
Demolition of building and blasting equipmentChetan Karwa
 
Chapter 1 repair stratergies
Chapter 1 repair stratergiesChapter 1 repair stratergies
Chapter 1 repair stratergiesAnkit Patel
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPTCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPTShankar Ramasamy
 

What's hot (20)

Introduction to demolition
Introduction to demolitionIntroduction to demolition
Introduction to demolition
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of building
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of building
 
Demolition of Structures.
Demolition of Structures.Demolition of Structures.
Demolition of Structures.
 
DEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKDEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORK
 
Safety precautions during demolition
Safety precautions during demolitionSafety precautions during demolition
Safety precautions during demolition
 
BCT Mod 4 demolition of structure
BCT Mod 4 demolition of structureBCT Mod 4 demolition of structure
BCT Mod 4 demolition of structure
 
Ila's ppt on demolition
Ila's ppt on demolitionIla's ppt on demolition
Ila's ppt on demolition
 
Formwork
FormworkFormwork
Formwork
 
Slipform
SlipformSlipform
Slipform
 
DEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUESDEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUES
 
Construction Equipment Management
Construction Equipment ManagementConstruction Equipment Management
Construction Equipment Management
 
Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequence
 
Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
 
Sub Structure Construction.pptx
Sub Structure Construction.pptxSub Structure Construction.pptx
Sub Structure Construction.pptx
 
Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundations
 
Shoring and underpinning
Shoring and underpinningShoring and underpinning
Shoring and underpinning
 
Demolition of building and blasting equipment
Demolition of building and blasting equipmentDemolition of building and blasting equipment
Demolition of building and blasting equipment
 
Chapter 1 repair stratergies
Chapter 1 repair stratergiesChapter 1 repair stratergies
Chapter 1 repair stratergies
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPTCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
 

Viewers also liked

DEMOLITION OF STRUCTURE BY ABHINAV RAWAT
DEMOLITION OF STRUCTURE BY ABHINAV RAWATDEMOLITION OF STRUCTURE BY ABHINAV RAWAT
DEMOLITION OF STRUCTURE BY ABHINAV RAWATAbhinav Rawat
 
Demolition Equipment/Technique Available
Demolition Equipment/Technique Available Demolition Equipment/Technique Available
Demolition Equipment/Technique Available Girish Singh
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsHamdija Velagic
 
Building demolition contractor delhi
Building demolition contractor delhiBuilding demolition contractor delhi
Building demolition contractor delhiFazil Khan
 
Demolition e2004
Demolition e2004Demolition e2004
Demolition e2004AMer PaisAn
 
CV - Andrea Forgó 2016
CV - Andrea Forgó 2016CV - Andrea Forgó 2016
CV - Andrea Forgó 2016Forgó Andrea
 
FORMWORK, SCAFFOLDING, CENTERING
FORMWORK, SCAFFOLDING, CENTERINGFORMWORK, SCAFFOLDING, CENTERING
FORMWORK, SCAFFOLDING, CENTERINGTANMAY SHETTY
 

Viewers also liked (13)

DEMOLITION OF STRUCTURE BY ABHINAV RAWAT
DEMOLITION OF STRUCTURE BY ABHINAV RAWATDEMOLITION OF STRUCTURE BY ABHINAV RAWAT
DEMOLITION OF STRUCTURE BY ABHINAV RAWAT
 
Demolition
 Demolition Demolition
Demolition
 
Demolition Equipment/Technique Available
Demolition Equipment/Technique Available Demolition Equipment/Technique Available
Demolition Equipment/Technique Available
 
Fully Demolition
Fully Demolition Fully Demolition
Fully Demolition
 
Presentation-Demolition-Yıkım
Presentation-Demolition-YıkımPresentation-Demolition-Yıkım
Presentation-Demolition-Yıkım
 
Pile foundation
Pile  foundation Pile  foundation
Pile foundation
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Pile Foundations
Pile FoundationsPile Foundations
Pile Foundations
 
Building demolition contractor delhi
Building demolition contractor delhiBuilding demolition contractor delhi
Building demolition contractor delhi
 
Demolition e2004
Demolition e2004Demolition e2004
Demolition e2004
 
CV - Andrea Forgó 2016
CV - Andrea Forgó 2016CV - Andrea Forgó 2016
CV - Andrea Forgó 2016
 
FORMWORK, SCAFFOLDING, CENTERING
FORMWORK, SCAFFOLDING, CENTERINGFORMWORK, SCAFFOLDING, CENTERING
FORMWORK, SCAFFOLDING, CENTERING
 

Similar to demolition of building

Techniques for Demolition of Structure
Techniques for Demolition of StructureTechniques for Demolition of Structure
Techniques for Demolition of StructureDinaker Dixit
 
Demolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS codeDemolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS codejaimin1702
 
Demolishing of concrete structures
Demolishing of concrete structuresDemolishing of concrete structures
Demolishing of concrete structuresTsegaye Arega
 
Building Construction Analysis Report
Building Construction Analysis ReportBuilding Construction Analysis Report
Building Construction Analysis ReportDaniel Yap
 
Demolition Hazards and Controls
Demolition Hazards and ControlsDemolition Hazards and Controls
Demolition Hazards and ControlsAbbas Tahir
 
Study of Safety in Demolition of Buildings
Study of Safety in Demolition of BuildingsStudy of Safety in Demolition of Buildings
Study of Safety in Demolition of BuildingsIRJET Journal
 
Construction Safety Training_Session 07_Construction Demolition, Hazards and ...
Construction Safety Training_Session 07_Construction Demolition, Hazards and ...Construction Safety Training_Session 07_Construction Demolition, Hazards and ...
Construction Safety Training_Session 07_Construction Demolition, Hazards and ...Muizz Anibire
 
Demolishing of concrete structures
Demolishing of concrete structuresDemolishing of concrete structures
Demolishing of concrete structuresTsegaye Arega
 
BUILDING CONSTRUCTION REPORT
BUILDING CONSTRUCTION REPORTBUILDING CONSTRUCTION REPORT
BUILDING CONSTRUCTION REPORTemily9199
 
Demolition of existing boiler house
Demolition of existing boiler houseDemolition of existing boiler house
Demolition of existing boiler houseAnatoliZ
 
Building Construction
Building ConstructionBuilding Construction
Building ConstructionWilden How
 
UNIT 3 Part A - Safety in Construction & Demolition Operation.pdf
UNIT 3 Part A - Safety in Construction & Demolition Operation.pdfUNIT 3 Part A - Safety in Construction & Demolition Operation.pdf
UNIT 3 Part A - Safety in Construction & Demolition Operation.pdfPinakRay1
 
UNIT 3 Part B - Safety in Special Construction Operations.pdf
UNIT 3 Part B - Safety in Special Construction Operations.pdfUNIT 3 Part B - Safety in Special Construction Operations.pdf
UNIT 3 Part B - Safety in Special Construction Operations.pdfPinakRay1
 

Similar to demolition of building (20)

Demolition pptx
Demolition pptxDemolition pptx
Demolition pptx
 
Techniques for Demolition of Structure
Techniques for Demolition of StructureTechniques for Demolition of Structure
Techniques for Demolition of Structure
 
Techniques behind demolition of structures
Techniques behind demolition of structuresTechniques behind demolition of structures
Techniques behind demolition of structures
 
DEMOLITION OF BUILDING 2.pptx
DEMOLITION OF BUILDING 2.pptxDEMOLITION OF BUILDING 2.pptx
DEMOLITION OF BUILDING 2.pptx
 
BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)
 
DOC pramod .pptx
DOC pramod .pptxDOC pramod .pptx
DOC pramod .pptx
 
Demolition of Structure ppt.pptx
Demolition of Structure ppt.pptxDemolition of Structure ppt.pptx
Demolition of Structure ppt.pptx
 
Demolition of BUILDING.pptx
Demolition of BUILDING.pptxDemolition of BUILDING.pptx
Demolition of BUILDING.pptx
 
Demolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS codeDemolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS code
 
Demolishing of concrete structures
Demolishing of concrete structuresDemolishing of concrete structures
Demolishing of concrete structures
 
Building Construction Analysis Report
Building Construction Analysis ReportBuilding Construction Analysis Report
Building Construction Analysis Report
 
Demolition Hazards and Controls
Demolition Hazards and ControlsDemolition Hazards and Controls
Demolition Hazards and Controls
 
Study of Safety in Demolition of Buildings
Study of Safety in Demolition of BuildingsStudy of Safety in Demolition of Buildings
Study of Safety in Demolition of Buildings
 
Construction Safety Training_Session 07_Construction Demolition, Hazards and ...
Construction Safety Training_Session 07_Construction Demolition, Hazards and ...Construction Safety Training_Session 07_Construction Demolition, Hazards and ...
Construction Safety Training_Session 07_Construction Demolition, Hazards and ...
 
Demolishing of concrete structures
Demolishing of concrete structuresDemolishing of concrete structures
Demolishing of concrete structures
 
BUILDING CONSTRUCTION REPORT
BUILDING CONSTRUCTION REPORTBUILDING CONSTRUCTION REPORT
BUILDING CONSTRUCTION REPORT
 
Demolition of existing boiler house
Demolition of existing boiler houseDemolition of existing boiler house
Demolition of existing boiler house
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 
UNIT 3 Part A - Safety in Construction & Demolition Operation.pdf
UNIT 3 Part A - Safety in Construction & Demolition Operation.pdfUNIT 3 Part A - Safety in Construction & Demolition Operation.pdf
UNIT 3 Part A - Safety in Construction & Demolition Operation.pdf
 
UNIT 3 Part B - Safety in Special Construction Operations.pdf
UNIT 3 Part B - Safety in Special Construction Operations.pdfUNIT 3 Part B - Safety in Special Construction Operations.pdf
UNIT 3 Part B - Safety in Special Construction Operations.pdf
 

More from tushar garg

Plum concrete (major project).pdf
Plum concrete (major project).pdfPlum concrete (major project).pdf
Plum concrete (major project).pdftushar garg
 
Rwss (rural water supply and sanitation)
Rwss (rural water supply and sanitation)Rwss (rural water supply and sanitation)
Rwss (rural water supply and sanitation)tushar garg
 
Plum concrete presentation
Plum concrete presentationPlum concrete presentation
Plum concrete presentationtushar garg
 
Training report on JMRC
Training report on JMRCTraining report on JMRC
Training report on JMRCtushar garg
 
jaipur metro rail presentation
jaipur metro rail presentationjaipur metro rail presentation
jaipur metro rail presentationtushar garg
 
Design of residential building
Design of residential buildingDesign of residential building
Design of residential buildingtushar garg
 
minor project report on design of residential building
minor project report on design of residential buildingminor project report on design of residential building
minor project report on design of residential buildingtushar garg
 

More from tushar garg (7)

Plum concrete (major project).pdf
Plum concrete (major project).pdfPlum concrete (major project).pdf
Plum concrete (major project).pdf
 
Rwss (rural water supply and sanitation)
Rwss (rural water supply and sanitation)Rwss (rural water supply and sanitation)
Rwss (rural water supply and sanitation)
 
Plum concrete presentation
Plum concrete presentationPlum concrete presentation
Plum concrete presentation
 
Training report on JMRC
Training report on JMRCTraining report on JMRC
Training report on JMRC
 
jaipur metro rail presentation
jaipur metro rail presentationjaipur metro rail presentation
jaipur metro rail presentation
 
Design of residential building
Design of residential buildingDesign of residential building
Design of residential building
 
minor project report on design of residential building
minor project report on design of residential buildingminor project report on design of residential building
minor project report on design of residential building
 

demolition of building

  • 2. INDEX 1. Introduction 2. Objective 3. Step before demolition 4. Method of demolition 5. Building implosion 6. Placing of explosive 7. conclusion 8. Reference
  • 3. Introduction  We know that every structure is designed for a life period.  The existence of the structure after the service life period is very dangerous to its occupant and surrounding building.  Demolition is the process of tearing down or falling down of a building after its life period with the help of some equipment or any other method.  When explosive are used for this then demolition process are called as implosion.
  • 4. objective  Old and damaged building (due to earthquake and other various reasons) which are prone to fall down completely or partially must be demolished before any fatal accident.  When the important structural components like beams and columns become absolutely insufficient for service then there is no option other than demolishing the building.  When a new structure need to be constructed on the site, the old structure is demolished.  For safety of neighbouring area, a deteriorated building is often demolished.
  • 5. Step before demolition 1. Surveying 2. Removal of hazardous materials 3. Preparation of plan 4. Safety measures
  • 6. surveying The building should cover the following :-  The construction material.  Adjoining pedestrians and vehicular traffic condition.  The sensitivity of neighbourhood with respect to noise, dust, vibration and traffic impact.  Available site to demolition.  Record drawing.
  • 7. Removal of hazardous material  Asbestos containing material – in case when asbestos containing material are discovered, specialist contractor shall be employed to be removed such material. The asbestos waste should be handled, stored and disposed off as a chemical waste.  Soil contamination material – in case when soil contamination material is present, specialist shall be employed to prepare soil contamination test proposal and submit such proposal to the Environmental Protection Department.
  • 8. Asbestos material soil contamination Removal of hazardous material
  • 9. Preparation of plan  The Location of building to be demolished.  A layout plan of all floors of the building to be demolished.  The structural support system.  A plan showing the procedure for the demolition of building.  In the case when powered mechanical plants and equipment are used, a plan showing the route of movement of powered mechanical plants and equipment.
  • 10. Safety measure  Training and communication - Demolition workers, including plant or equipment operators, shall go through proper job safety training and be informed of the potential hazards by attending training sessions as well as on-the-job training.
  • 11.  Equipment maintenance - All equipment shall be tested and examined before use. They shall be properly stored and maintained. The equipment shall be inspected daily and results of the inspection shall be recorded accordingly.  Properly marked with exit signs. Safety measure
  • 12.  Fire - All flammable goods shall be removed from site unless they are necessary for the works involved. Any remaining flammable goods shall be stored in proper storage facilities. All furniture, timber, doors, etc. shall be removed before any welding work is performed. Fire fighting appliances shall be provided and maintained in working conditions Safety measure
  • 14. Piecemeal demolition A jackhammer is a pneumatic or electro- mechanical tool that combines a hammer directly with a chisel. Jack hammer ->
  • 15. Mechanical method  Ball and crane - A crane uses a wrecking ball, weighing up to 6120 kg, which is either dropped onto or swung into the element to be demolished. Ball and crane
  • 16. Mechanical method Hydraulic breaker  A hydraulic breaker is a powerful percussion hammer fitted to an excavator for demolishing concrete structures or rocks. It is powered by an auxiliary hydraulic system.
  • 17. Explosive demolition  The basic idea of explosive demolition is quite simple.  If we remove the support structure of a building at a certain point, the section of the building above the point will fall down on the part of the building below that point.
  • 18. Blasting machine blasting cap or electrical detonator RDX-based explosive compounds expand at a very high rate of speed, up to 27,000 feet per second (8,230 meters per second) Explosive demolition
  • 19. Advantage of explosive demolition Explosive demolition  Less expensive.  No ground vibrations.  Quickest method.  Suitable for multi-storey / high piers, cabins, distressed piers etc.
  • 24. conclusion  It can be concluded that demolishing/imploding the building structure will prove very useful, economical and quickest for reconstruction.  Type of demolition method depends upon various factors such as site condition, type of structures, age of building, height of building and economy.  Explosive demolition is the preferred method for safely and efficiently demolishing the larger structures.  Development in techniques allows rapid demolition with no harm to the environment.
  • 25. Reference  www.google.com  www.Wikipedia.com  www.studymafia.org  www.implosionworld.com