SlideShare a Scribd company logo
1 of 21
Download to read offline
1
A
PROJECT REPORT ON
“Boiler and its auxiliaries”
In accordance with
2-week Training
At C.S.T.P.S.
Submitted By:-
Uday Wankar Sainath Sorte
Anant D. Patil Shubham Asati
Sankalp Guremukhi Pratik Raut
Rohit Lonjekar Mangesh Jumnake
Surendra Butale Vivek Talande
Azhar Sheikh Atul Bhusari
Anup Mathankar Vivek Dhote
Rahul Chekbandalwar Ashish Dhande
Nikhil Shriramwar Gunjan Jaspal
Shivprasad Bhosale Bhushan Lode
Under the Guidance of
Er. A. G. Raut
2
INDEX
1. INTRODUCTION ……………………………………..………………………………..2
1.1 About C.S.T.P.S. …………..……………..……………………………...……2
2. THERMAL POWER STATION ……..………………..……………………………….. 3
2.1 An Overview ………………………..……..………………………………….…..3
3. PRICIPLE …………………………………………………..……………………….….. 4
3.1 Rankine Cycle ……………………………………………………………….……4
4. Design ………………………………………….………………………………………..6
4.1 Construction and Components …….……………………………………….……6
5. WORKING ………………………………………………….………………………..…8
6. BOILER AUXILERIES …………………………………….…………………………12
a) Fans …………………………………………………………………………….….12
1) I.D. Fans ………………………………………………………….12
2) F.D. Fans ……………………………………………………...….13
3) P.A. Fans ………………………………………………………….13
4) Seal air Fans …………………………..……………………….….14
5) Scanner Fan Fans …………………………..………………….….14
6) Ignitor Fans ……………………………………………………….14
b) Coal Feeder ……………………………………………………………………….15
c) Coal Mill ………………………………………………………………………….15
3
d) Air Pre-Heater …………………………………………………………………….15
e) Clinker Grinder ……………………………………………………………….….16
7. BOILER LIGHT-UP PROCEDURE …………………………………..………….…..17
4
INTRODUCTION: About CSTPS
MSEB was set up in 1960 to generate, transmit and distribute power to all consumers in
Maharashtra excluding Mumbai. MSEB was the largest SEB in the country. The generation
capacity of MSEB has grown from 760 MW in 1960-61 to 9771 MW in 2001-02. The customer
base has grown from 1,07,833 in 1960-61 to 1,40,09,089 in 2001-02.
C.S.T.P.S in contribution much in field of production of electricity. It is not only number
one thermal power station in Asia but also has occupied specific position on the international
map.
The first set was commission on August 1983 & was dedicated to nation by then PM
(late) Mrs. Indira Gandhi & second set commission on July 1984. The third & fourth units of
CSTPS under stage 2 were commissioned on the 3rd
May 1985 & 8th
March 1986 respectively.
The units 5 & 6 were commissioned on the 22nd
March 1991 & 11th
March 1992 respectively one
more units of 500MW was added to the CSTPS on making its generation to 2340 MW &
making “C.S.T.P.S.” as the giant in Power Generation of CSTPS.
 STAGE 1:- 2 * 210MW units
 STAGE2:- 2 * 210MW units
 STAGE3:- 3 * 500MW units
 Location of plant:-
Plant is situated about 7km away from Chandrapur Railway Station by the
side of Tadoba National Park road.
2. Climate condition:-
 Daily average ambient temp 40c
 Maximum ambient temp. 50c
 Minimum ambient temp. 5c
 Altitude for min sea level 192.3m
3. Total land area required:-
 Main plant including CHP & Railway sliding: 11256 hec
 Ash disposal area: 1117 Hec.
5
THERMAL POWER STATION: An Overview
The basic operation of any thermal power plant is based on the Rankin modified cycle.
Operation can be described as follows:
Coal is taken to coal storage from nearby mines. In CHP, the coal is converted into fine
powder called ‘pulverized coal’, because it gives complete combustion & hence better efficiency.
This fuel is fed to furnace of boiler for the sake of combustion. Boiler converts water into steam,
which is called saturated steam because it has some moisture content. This steam is further
heated in super heater at about 540 0
c so as to remove the last traces of moisture from the
steam before feeding it to the turbine. This superheated steam is passed over blades of turbine,
work done in the form of rotation of turbine & pressure drop is observed. It means high pressure
steam is converted into mechanical energy.
The turbine is mechanically coupled with rotor of three phase alternator & thereby acts as
prime mover to it. Hence as per faraday’s law of electromagnetic induction, the alternator
produces 3-phase electric power as its output terminal. The steam after doing its useful working
the steam is then condenses in condenser i.e. again converted into water, i.e. recirculated in the
cycle using boiler feed pump & economizer.
Fig.2 Energy conversion taking place in the thermal power plant
Chemical
Energy is
converted to
Heat Energy by
combustion of
fuel in boiler
Heat energy
converts water
to high
pressure, high
temperature
steam.
In Turbine, steam
expands as it is
passed through
number of
nozzles. Heat
energy is thus
converted to
kinetic energy.
Steam is
admitted
to
Turbine
through
pipes.
Steam is then passed
over blades, arranged on
shaft of Turbine. Shaft
rotates & Kinetic energy
is thus converted to
mechanical work
Steam exhausted
from turbine
condenses in
Condenser,
rejecting
unavailable heat
energy.
Pump delivers
condensed
water from
Condenser
back to
Boiler.
Generator is coupled to
Turbine, where mechanical
energy is converted to
electrical energy.
6
PRINCIPLE: Rankine cycle
Fig: Temperature verses Entropy Characteristics
There are four processes in the Rankine cycle. These states are identified by numbers (in
brown) in the above Ts diagram.
 Process 1-2: The working fluid is pumped from low to high pressure. As the fluid
is a liquid at this stage the pump requires little input energy.
 Process 2-3: The high pressure liquid enters a boiler where it is heated at constant
pressure by an external heat source to become a dry saturated vapor. The input energy required
can be easily calculated using mollier diagram or h-s chart or enthalpy-entropy chart also known
assteam tables.
 Process 3-4: The dry saturated vapor expands through a turbine, generating
power. This decreases the temperature and pressure of the vapor, and some condensation may
occur. The output in this process can be easily calculated using the Enthalpy-entropy chart or the
steam tables.
 Process 4-1: The wet vapor then enters a condenser where it is condensed at a
constant pressure to become a saturated liquid.
7
In an ideal Rankine cycle the pump and turbine would be isentropic, i.e., the pump and
turbine would generate no entropy and hence maximize the net work output. Processes 1-2 and
3-4 would be represented by vertical lines on the T-S diagram and more closely resemble that of
the Carnot cycle. The Rankine cycle shown here prevents the vapor ending up in the superheat
region after the expansion in the turbine, [1]
which reduces the energy removed by the
condensers.
8
DESIGN: Construction and Components
Boiler means any cleared vessel exceeding 22.75 LH in capacity used for steam.
Generation under pressure.The first Boiler developed in 1725 & working pressure was 6 to 10
kg/cal.
TYPES OF BOILERS: There are two types of Boilers:-
1) Fire tube boilers (Carnish & Lauchashine blrs.) developed in the year 1844
2) Water tube boilers developed in 1873 years.
We are having in Thermal Power stations water tube Boilers.
These are sub divided according to water circulation, as :-
1) Natural circulation: Drum to down comers to due ring main header to water wall
tubes & back to drum difference in density of water when cool & hot.
2) Forced circulation: Additional pumps are installed in down comers.
According to pressure the Boilers are called-
1) Drum type sub critical boiler: When boiler pressure is 130 kg/cm2 to 180 kg/cm2
2) Critical pressure Boilers : When boiler pressure is 221.2 kg/cm2
3) Super critical drum less once through boilers: When boiler pressure is 240 kg/cm2
All modern Boilers are top slung from steel structures from the Beams a series of slings
take up the boiler loads. Suspended weight of one 210 MW boiler is 3640 tonnes approx. eight of
Boiler is about 64 meters and Boiler drum is at a height of 52 meters from ground.
Boiler design:
1. Lowest capital cost, ease of construction, simplicity, ssafety, Good working condition
ease of maintenance
2. Efficient operation, effective baffling for heat transfer will insulate casings, ability to
deliver pure steam with effective drum internals, build steam ball capacity.
3. Availability of auxiliaries
9
The main parts of Boiler are:
 Boiler drum (Length: 15.7 meters, ID: 1976 mm, Thickness 132 mm) down comers (6
down comers of size 406x32 mm)
 Water walls (Made of SA 210 Gr A1 material, 63.5x6.3 mm, 76.1mm thick)
 Furnace (13.868 m width, 10.592 m depth, 5494m3 vol)
 Platen superheater (The size of tubes are 51x7.1 mm +51x8.6mm)
 Reheater (The size of tubes is 54x3.6 mm)
 Final superheater (size of tubes are 51x7.6 mm the materials are SA213 T22 alloy steel
and stands upto 5800
C (alloy steel)
 Primary superheater (The material used are SA209T, SA210 Gr. A, SA 213 T11.The
size of tubes are 44.5x4.5 mm & temperature range is 4500
C to 4800
C
 Economizer (The material used are carbon steel of SA 210 Gr. A1 stands upto 4500
C,
size of the tubes are 44.5x4.5 mm)
 Burners (The burners are situated at 3 elevations called AB,CD,EF)
 Ignitors (For every burner one ignitor is provided for igniting the burner for
combustion & cooling ignitor fan is provided. It is a centrifugal fan with backward
curved. Capacity 9000 m3/h, 75 mm WC, 1500 rpm.
10
WORKING:
In Boiler, Coal is stored in Bunkers. Size of coal in bunkers is 25 mm. The coal received
from coal mines has a size varying from 4 to 8 inches. In Coal Handling plant, it is first reduced
to 25-mm size and then fed to the bunkers through a series of conveyer belts. From bunkers, coal
is fed to the Coal Mill where it is pulverized. Coal particle average size, after pulverization, is 75
microns.(1 micron is 1000th
part of a millimeter) In 210 MW units, there are 6 coal mills and in
500 MW units, 8 coal mills are installed. For full load operation of the unit, 4 to 5 coal mills are
running. Other coal mills are stand by.
11
When boiler is to be started up from cold conditions, coal can not be fired, as there is no
ignition energy available. Hence first L.D.O. is fired for lighting up the boiler. After Boiler
pressure is built up to certain specified values, Heavy Furnace oil is fired. After achieving the
specified parameters with oil firing, coal is admitted.
Pulverized coal from the mills is continuously lifted with the help of air, called primary
air. Primary air fans are installed for this purpose. Coal-air mixture is fed to Boilers through coal
burners, arranged at various elevations. For complete and efficient combustion of coal, primary
air is not sufficient, and hence secondary air, obtained from Secondary Air fans, is also admitted
to the furnace in controlled quantity. Before admission in coal mills and boiler, primary air and
secondary air are first heated to a temperature of 325° C.
Heating of air is carried out in Air pre heaters, with the help of hot flue gas leaving the
boiler. When coal is burnt, it also produces ash. Small ash particles, which can flow with the flue
gas, is called fly ash. Flue gas , after leaving the Air pre heaters, is sent to Electrostatic
12
precipitators, where fly ash is separated from flue gas and collected in number of Ash Hopper,
arranged on Electrostatic precipitators. Ash hopper size is such that it can store all the fly ach
generated in 8 Hours continuous operation of Boiler. The flue gases from the boiler are sucked
by Induced draft fans, which are arranged after ESP. From there, flue gases are sent to Chimney,
which disposes off the flue gas to atmosphere. Ash hoppers are emptied after every 8 hours. For
disposing off the ash, it is mixed with water and no. of pumps then lift and transport the ash-
water mixture, called slurry, to pre determined place called ash bund.
Turbine is used to convert heat energy to mechanical work. Turbine consists of rotors, on
which a series of moving blades are arranged, and casing on which fixed blades are arranged.
Steam admitted to turbine, is guided by fixed blades to strikes on blades on Rotor, in the form of
jet, causing rotor to rotate thus converting heat energy to mechanical energy.
Heat energy released from the combustion of coal in the boiler is given to water
circulated in it. Water is thus converted to steam, pressure of which is 140 Kg/ cm² and
temperature is 537° C.. This steam, called live steam or main steam, is sent to High Pressure
Turbine, where it is made to strike on a series of rotor blades. When it reaches at the exhaust, its
temperature and pressure drops to 330° C and 30 Kg/ cm².
Exhaust steam from HPT is sent to Reheater, arranged in the boiler, where its temperature
is again raised to 537° C, and pressure remains 30 Kg/ cm². This steam is called Reheat steam,
which is sent to another turbine called Intermediate pressure turbine. From I.P.T, steam then is
sent to low-pressure turbine. At the exhaust of LPT, steam temperature and pressure is very low,
and further work can not be extracted from it. Hence it is condensed in the condenser, maintained
at a vaccume of 750 mm Hg. The condensed water is called condensate. Conedensate Extraction
Pumps, and Feed Water Pumps are used for pumping the condessate from Condenser to Boiler
through L. P. Heaters and H. P. Heaters. In these heaters, small quantity of steam, extracted from
intermediate stages of Turbine, heat the water. When water comes out of heaters, its temperature
is 250° C which is fed in to boiler. This is called regenerative feed heating cycle. The efficiency
of power plant increases due to regenerative feed heating.
Cooling water circulated in Condenser, at temperature of 30°C absorbs the heat energy
released in condensation due to which its temperature increases to 40° C. In cooling towers, this
hot water is again cooled to a temperature of 30° C for reuse in condenser.
13
. Generator consists of Copper conductors wound on Stator and a Rotor on which Electro
magnets are arranged. Rotors of all the three turbine and Generator are coupled with common
shaft. Rotation of shaft causes rotation of Generator rotor, causing the rotation of Electro
magnets. This sets up electrical voltage on stator conductors of the generator at 15 kV.
Transformer steps up this voltage to 400 kV or 220 kV or 132 kV depending on the Grid voltage
where it is connected. The electrical energy thus generated is sent to Power Grid, from where it
reaches to the consumer through Transmission and distribution system.
14
BOILER AUXILERIES
There are some important machines equipment for safe and efficient working of
Boiler. These machines are called Boiler auxiliaries. They are:
a) FANS:
1) Induced draft fan (I.D. Fan) 2 No. per Boiler. It induces gaseous products from furnace
and forces out through chimney. Type ND2V, Q= 230 m3
/s, Pressure = 405 mm WC, KW =
1300, Speed = 740 rpm, Radial fan.
Fig: Sectional assembly of ID Fan
15
2) F.D. Fan : Forced draft fan 2 Nos. per Boiler. It forces atmospheric air to furnace as
secondary air through air preheater and wind box for combustion of fuel. Type-API – 20/11,
Pressure = 408 mmWC, Q= 451m3
/s motor 900 KW, 1480 rpm, axial fan.
Fig: Sectional view of F.D. Fan
3) P.A. Fans: Primary air for Transport of coal from mill to furnace is provided by fan.
And one tap is provided to coal mill to maintain temperature at 40c. To facilitate drying of coal,
part of P.A. fan air is routed through. The P.A. fan air should maintain speed of 80 to 100 ft/sec
is fuel pipe to maintain coal is air born state to avoid chucking of coal pipes.
16
P.A. Fans have narrow section impellors, and 2 to 3 times higher speeds than I.D. or F.D.
high speed fans to give high heads required for fuel firing types blades are made of high tensile
alloy steels to resist abrasion.
Fig: P.A. Fan Sectional view
4) Seal Air Fan: Seal air pressure is higher than P.A. Fan pressure. It is required for
sealing purpose of coal mills bowl input shaft, journal assembly brgs, coal feeders shaft brgs,
sprockets otherwise dust enters above area and spoil brgs & oil.
5) Scanner fan : For sensing the flame scanners are provided at all elevations of all
corners in furnace. For cooling these scanners air is provided form these fans. Boiler will trip if
these fans fails. Capacity 1200 m3/h, Pressure = 320 mm WG, Motor 3 HP, 2970 rpm.
6) Igniter Fan : For every burner one igniter is provided for igniting the burner for
combustion & cooling igniter fan is provided. It is a centrifugal fan with backward curved.
Capacity 9000 m3/h, 75 mm WC, 1500 rpm.
17
b) COAL FEEDER:
Coal comes from CHP to bunkers and coal feeder feed to any coal mill is
regulated by a coal feeder by changing its speed. Coal feeder handles crushed coal of size 15 to
25 mm. There are two types of coal feeder:
1) Gravitic Feeder: can be to a large bunker outlet there by minimizing chokage
during rainy season. Type R600
2) Volumetric type is Rotary type 100, Capacity 7.4 to 43.6 T/hr., Speed 2.7 to 16
rpm. Coal can be measured by volume of sector rotating/min.
c) COAL MILLS: Coal from feeder comes to mill & coal is crushed in the mill to the
required fineness 75% by 200 mesh. There are classifier gate through which correct size
coal only passes other coal comes back for grinding again. Mill temp. to be maintained
below comes back for grinding again. Mill temp to be maintained below 900
C. the
required air flow is 50 T/h to lift the coal to furnace.
d) AIR PRE-HEATER: Air heater is unique among Boiler auxiliaries with principle purpose
of saving energy and an in come producing asset. It can have significant impact on plant
capacity and heat rate increases by 8 to 12%, saves fuel It provides heated air for drying
and conveying P.F. coal provides heated air to combustion of fuel & lower
emissionTrisector type Air heater is used in ktps. In this Flue gas flows through 180 of
portion;F.D. air flows through 128 of porsion;P.A. Fan air flows through 52 of poison
P.A. partial air is bypassed as cold air.
18
e) CLINKER GRINDER:
Capacity 60 T/hr. It reduces clinkers size upto 25 to 50 mm for early transmission
through pipes to ash yard/slurry pump house. Grinder made of manganese steel.
19
BOILER LIGHT-UP PROCEDURE
1. Line clear
Conform that thers is no work permit is pending and normalization of equipment after
cancellation of permit.
2. Starting of equipment
i. control& power supply made ready.
ii. Protection and interlocks are ok
iii. Normalization of equipment ( Ready to start position )
iv. Lubrication & cooling systems are in service.
Start equipment with no load & raise the load simultaneously
So as to avoid overloading the prime mover.
3. Filling up the Boiler
i. keep all the verts open & fill through all the circuits such as that no air pocket is
formed and water level in drum in the range of 40 to 50 %.
ii. To conform the level from direct gauge glass.
iii. Confirm their is sufficient water level in dearator.
4. Oil firing equipment
i. check that oil guns are insert in retracted position.
ii. Ensure that all manual valves opened and remote control valves are close.
iii. Gun tips are clean.
5. Pulverizer
i. pulverizedischange valve is open. Hot air & control damper is closed.
ii. Cold air gate is opened at 15%
6. Fans / air heater –
Normalize the damper position. Ignitorfan , scanner air fan & mill seal air fans are to be kept
on start up position.
7. Soot blowers :
check all soot blowers are in retracted position.
8. Valves in boiler
i. Keep vent valves open.
20
ii. Keep drain valves & open ( expect drum , water wall &economiser)
iii. Economiser recirculation valve open condition.
9. Start regenerative air heaters.
10. Start one air cycle ( ID& FD )and adjust draft to – 10 mmwc. Adjust the corresponding
dampers in air & gas circuit
a) place the steam coil air heater in sevice.
b) Start ignitor fan ,scanner fan and seal air fans.
c) put the secondary air damper control on auto.
d) The wind box to furnace differential pressure will be maintained to 40mmwG by
adjusting auxiliary air dampers.
e) Initiate furnace purge circuit.
f) Furnace purge will take 5 minutes
11. Intitate a light up sequence of the lower elevation of ignitors and warm oil guns. Check the
combustion and adjust the air dampers. If required.
12. Maintain furnace draft by controlling the ID fan loading place furnace draft system on auto.
13. Maintain the boiler drum level by opening blowdown. Initially water level will raise.
14. Increase firing rate . Firing rate should be controlled so that furnace exit gas temperature
does not exceed 5400
c, till sufficient steam flow through superheaters and reheaters are
established.
15. Soot blow the regerative air heater with steam /compressed air to avoid plugging and
possibility of fire.
16. Close drum vent when pressure reaches to 2 to 5 kg/cm2
close the drains and vents of
reheater, which are open to atmospher before pulling vacuum in condenser
17. Close drains and vents of superheater system.
18. Increase the firing rate as required to raise the pressure, when sufficient flow through
superheaters and rcheater is established ,with the help of HP-LP by pass. The firing rate need not
be restricted to furnace outlet temperature of 5400
c
19. As the drum pressure increase , progressively throttle superheat outlet header drain &
startup vents.
20. Steam to turbine rolling is permitted as soon as the minimum permissible pressure &
temperature for the corresponding turbine metal temp.
21
21. After synchronizing of T – G, close all drains & vents of boiler .
22. Increase firing rate and adjust air as per requirment.
23. Start coal firing as per requirement of loading of turbine.
24. When boiler reaches 30% of full load , the wind box to furnace differential is damped to
about 100 mmwG.
25. The oil support and igniters can be withdrawn when two adjutants coal elevation ,are in
service with atleast 50% of loading.
26. Take second air cycle in service & further load the coal firing
27. To control temperature desuperheters can be charged if required.

More Related Content

What's hot

6 weeks summer Training report on thermal power plant in DCPP
6 weeks summer Training report on thermal power plant in DCPP6 weeks summer Training report on thermal power plant in DCPP
6 weeks summer Training report on thermal power plant in DCPPAmit Bansal
 
rajwest thermal power plant
rajwest thermal power plantrajwest thermal power plant
rajwest thermal power plantRama Charan
 
Chandrapura thermal power station (CTPS)--DVC_Industrial Training
Chandrapura thermal power station (CTPS)--DVC_Industrial TrainingChandrapura thermal power station (CTPS)--DVC_Industrial Training
Chandrapura thermal power station (CTPS)--DVC_Industrial TrainingPragya wan
 
Combined Cycle Gas Turbine Power Plant Part 1
Combined Cycle Gas Turbine Power Plant Part 1Combined Cycle Gas Turbine Power Plant Part 1
Combined Cycle Gas Turbine Power Plant Part 1Anurak Atthasit
 
Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)abdul mohammad
 
Internship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plantInternship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plantAbhishek Kumar
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plantViren Patel
 
Thermal Power Plant - Manual
Thermal Power Plant - ManualThermal Power Plant - Manual
Thermal Power Plant - ManualSheel Shah
 
training report on thermal power plant & thermal power generation by sagar me...
training report on thermal power plant & thermal power generation by sagar me...training report on thermal power plant & thermal power generation by sagar me...
training report on thermal power plant & thermal power generation by sagar me...Sagar Mehta
 
Thermal Power Plant training Report
Thermal Power Plant training ReportThermal Power Plant training Report
Thermal Power Plant training ReportShani Kumar Singh
 
Coal Fired Thermal Power Plants
Coal Fired Thermal Power Plants Coal Fired Thermal Power Plants
Coal Fired Thermal Power Plants Arnab Nandi
 
Supercritical boiler ntpc sipat
Supercritical boiler ntpc sipatSupercritical boiler ntpc sipat
Supercritical boiler ntpc sipatpratikguptateddy
 
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSESSTUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSESMohammed Sameer
 
Presentation on Kota super Thermal Power Station
Presentation on Kota super Thermal Power StationPresentation on Kota super Thermal Power Station
Presentation on Kota super Thermal Power Stationpukhraj palariya
 
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)Rajan Kumar Choudhary
 

What's hot (20)

6 weeks summer Training report on thermal power plant in DCPP
6 weeks summer Training report on thermal power plant in DCPP6 weeks summer Training report on thermal power plant in DCPP
6 weeks summer Training report on thermal power plant in DCPP
 
rajwest thermal power plant
rajwest thermal power plantrajwest thermal power plant
rajwest thermal power plant
 
GSECL TPS SIKKA
GSECL TPS SIKKAGSECL TPS SIKKA
GSECL TPS SIKKA
 
Chandrapura thermal power station (CTPS)--DVC_Industrial Training
Chandrapura thermal power station (CTPS)--DVC_Industrial TrainingChandrapura thermal power station (CTPS)--DVC_Industrial Training
Chandrapura thermal power station (CTPS)--DVC_Industrial Training
 
Ntpc Report
Ntpc ReportNtpc Report
Ntpc Report
 
Combined Cycle Gas Turbine Power Plant Part 1
Combined Cycle Gas Turbine Power Plant Part 1Combined Cycle Gas Turbine Power Plant Part 1
Combined Cycle Gas Turbine Power Plant Part 1
 
Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)
 
Internship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plantInternship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plant
 
training report
training reporttraining report
training report
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Thermal Power Plant - Manual
Thermal Power Plant - ManualThermal Power Plant - Manual
Thermal Power Plant - Manual
 
training report on thermal power plant & thermal power generation by sagar me...
training report on thermal power plant & thermal power generation by sagar me...training report on thermal power plant & thermal power generation by sagar me...
training report on thermal power plant & thermal power generation by sagar me...
 
Thermal Power Plant training Report
Thermal Power Plant training ReportThermal Power Plant training Report
Thermal Power Plant training Report
 
Coal Fired Thermal Power Plants
Coal Fired Thermal Power Plants Coal Fired Thermal Power Plants
Coal Fired Thermal Power Plants
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Supercritical boiler ntpc sipat
Supercritical boiler ntpc sipatSupercritical boiler ntpc sipat
Supercritical boiler ntpc sipat
 
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSESSTUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
 
Thermal power point
Thermal power pointThermal power point
Thermal power point
 
Presentation on Kota super Thermal Power Station
Presentation on Kota super Thermal Power StationPresentation on Kota super Thermal Power Station
Presentation on Kota super Thermal Power Station
 
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
 

Viewers also liked

Training Report
Training Report Training Report
Training Report Pintu Khan
 
MAHAGENCO Recruitment 2017
MAHAGENCO Recruitment 2017MAHAGENCO Recruitment 2017
MAHAGENCO Recruitment 2017PrivateJobsHub
 
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...haxxo24
 
MB0038 – Management Process and Organization Behavior
 MB0038 – Management Process and Organization Behavior MB0038 – Management Process and Organization Behavior
MB0038 – Management Process and Organization Behaviorswejs
 
Improve Your Business Operations and Project Success with Gordon Tredgold
Improve Your Business Operations and Project Success with Gordon TredgoldImprove Your Business Operations and Project Success with Gordon Tredgold
Improve Your Business Operations and Project Success with Gordon TredgoldQuickBase, Inc.
 
GanttChart for ClearQuest 1.4 and 1.3.1
GanttChart for ClearQuest 1.4 and 1.3.1GanttChart for ClearQuest 1.4 and 1.3.1
GanttChart for ClearQuest 1.4 and 1.3.1Alexander Novichkov
 
Bus 606 operations analysis project - rip curl
Bus 606   operations analysis project - rip curlBus 606   operations analysis project - rip curl
Bus 606 operations analysis project - rip curlRipCurlTeamPhotos
 
Intern operations project
Intern operations projectIntern operations project
Intern operations projectKidd Khazini
 
Boiler MACT and Strategic Air Permitting
Boiler MACT and Strategic Air PermittingBoiler MACT and Strategic Air Permitting
Boiler MACT and Strategic Air PermittingAll4 Inc.
 
Energy Management by Food&Beverage Industry
Energy Management by Food&Beverage IndustryEnergy Management by Food&Beverage Industry
Energy Management by Food&Beverage IndustryAvanceon
 
Project work efficiency of boilers
Project work   efficiency of boilersProject work   efficiency of boilers
Project work efficiency of boilersRodrigo Barcelos
 
Microsoft project 2003
Microsoft project 2003Microsoft project 2003
Microsoft project 2003pparakh
 
Scheduling
SchedulingScheduling
Schedulingjaya_22
 
Project Report on Analysis of Boiler- Aditya
Project Report on Analysis of Boiler- AdityaProject Report on Analysis of Boiler- Aditya
Project Report on Analysis of Boiler- AdityaAditya Bhattacharjee
 
PRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROLPRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROLPriyanka Modugu
 
Royal dutch shell
Royal dutch shell Royal dutch shell
Royal dutch shell Bhavna Pant
 

Viewers also liked (20)

Year Book'15
Year Book'15Year Book'15
Year Book'15
 
Training Report
Training Report Training Report
Training Report
 
MAHAGENCO Recruitment 2017
MAHAGENCO Recruitment 2017MAHAGENCO Recruitment 2017
MAHAGENCO Recruitment 2017
 
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
 
MB0038 – Management Process and Organization Behavior
 MB0038 – Management Process and Organization Behavior MB0038 – Management Process and Organization Behavior
MB0038 – Management Process and Organization Behavior
 
Improve Your Business Operations and Project Success with Gordon Tredgold
Improve Your Business Operations and Project Success with Gordon TredgoldImprove Your Business Operations and Project Success with Gordon Tredgold
Improve Your Business Operations and Project Success with Gordon Tredgold
 
GanttChart for ClearQuest 1.4 and 1.3.1
GanttChart for ClearQuest 1.4 and 1.3.1GanttChart for ClearQuest 1.4 and 1.3.1
GanttChart for ClearQuest 1.4 and 1.3.1
 
BRASS MBA in a Day
BRASS MBA in a DayBRASS MBA in a Day
BRASS MBA in a Day
 
Commercial Condensing Boiler Optimizaiton
Commercial Condensing Boiler OptimizaitonCommercial Condensing Boiler Optimizaiton
Commercial Condensing Boiler Optimizaiton
 
Bus 606 operations analysis project - rip curl
Bus 606   operations analysis project - rip curlBus 606   operations analysis project - rip curl
Bus 606 operations analysis project - rip curl
 
Intern operations project
Intern operations projectIntern operations project
Intern operations project
 
Boiler MACT and Strategic Air Permitting
Boiler MACT and Strategic Air PermittingBoiler MACT and Strategic Air Permitting
Boiler MACT and Strategic Air Permitting
 
Energy Management by Food&Beverage Industry
Energy Management by Food&Beverage IndustryEnergy Management by Food&Beverage Industry
Energy Management by Food&Beverage Industry
 
Project work efficiency of boilers
Project work   efficiency of boilersProject work   efficiency of boilers
Project work efficiency of boilers
 
Boiler
BoilerBoiler
Boiler
 
Microsoft project 2003
Microsoft project 2003Microsoft project 2003
Microsoft project 2003
 
Scheduling
SchedulingScheduling
Scheduling
 
Project Report on Analysis of Boiler- Aditya
Project Report on Analysis of Boiler- AdityaProject Report on Analysis of Boiler- Aditya
Project Report on Analysis of Boiler- Aditya
 
PRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROLPRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROL
 
Royal dutch shell
Royal dutch shell Royal dutch shell
Royal dutch shell
 

Similar to CSTPS training REPORT

Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)Srikanta Sinha
 
vocational training at DVC andal
 vocational training at DVC andal vocational training at DVC andal
vocational training at DVC andalANIL kumar
 
Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Abhijeet Thakur
 
suratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadavsuratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadavmukesh yadav
 
BK T. P. P. Vocational Training Report
BK T. P. P. Vocational Training ReportBK T. P. P. Vocational Training Report
BK T. P. P. Vocational Training Reportavijit1996
 
National thermal power corporation
National thermal power corporationNational thermal power corporation
National thermal power corporationAbhishek Awasthi
 
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Shubham Thakur
 
Report on Boilers at NTPC Ramagunadam
Report on  Boilers at NTPC RamagunadamReport on  Boilers at NTPC Ramagunadam
Report on Boilers at NTPC RamagunadamAbhinay Angari
 
Ppt of internship at dccpp
Ppt of internship at dccppPpt of internship at dccpp
Ppt of internship at dccppDurgSingh
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant pptPrakash Jarotia
 
thermal training report
thermal training reportthermal training report
thermal training reportRakesh Kumar
 
Project Report on “WORKING MODEL OF POWER GRID/SMART GRID
Project Report on “WORKING MODEL OF POWER GRID/SMART GRIDProject Report on “WORKING MODEL OF POWER GRID/SMART GRID
Project Report on “WORKING MODEL OF POWER GRID/SMART GRIDPrasant Kumar
 

Similar to CSTPS training REPORT (20)

KTPS
KTPSKTPS
KTPS
 
Attachment.doc
Attachment.docAttachment.doc
Attachment.doc
 
Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)
 
vocational training at DVC andal
 vocational training at DVC andal vocational training at DVC andal
vocational training at DVC andal
 
Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT
 
suratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadavsuratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadav
 
kstps training report
kstps training reportkstps training report
kstps training report
 
BK T. P. P. Vocational Training Report
BK T. P. P. Vocational Training ReportBK T. P. P. Vocational Training Report
BK T. P. P. Vocational Training Report
 
National thermal power corporation
National thermal power corporationNational thermal power corporation
National thermal power corporation
 
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
 
Emam training
Emam training Emam training
Emam training
 
ppt of ntpc dadri by emam raza khan
ppt of ntpc dadri by emam raza khan  ppt of ntpc dadri by emam raza khan
ppt of ntpc dadri by emam raza khan
 
Report on Boilers at NTPC Ramagunadam
Report on  Boilers at NTPC RamagunadamReport on  Boilers at NTPC Ramagunadam
Report on Boilers at NTPC Ramagunadam
 
Ppt of internship at dccpp
Ppt of internship at dccppPpt of internship at dccpp
Ppt of internship at dccpp
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
 
thermal training report
thermal training reportthermal training report
thermal training report
 
Project Report on “WORKING MODEL OF POWER GRID/SMART GRID
Project Report on “WORKING MODEL OF POWER GRID/SMART GRIDProject Report on “WORKING MODEL OF POWER GRID/SMART GRID
Project Report on “WORKING MODEL OF POWER GRID/SMART GRID
 
Bandel training
Bandel trainingBandel training
Bandel training
 
POWER PLANT.pdf
POWER PLANT.pdfPOWER PLANT.pdf
POWER PLANT.pdf
 
Power Systems-I.pdf
Power Systems-I.pdfPower Systems-I.pdf
Power Systems-I.pdf
 

More from Uday Wankar

TEACHING AND LEARNING BASED OPTIMISATION
TEACHING AND LEARNING BASED OPTIMISATIONTEACHING AND LEARNING BASED OPTIMISATION
TEACHING AND LEARNING BASED OPTIMISATIONUday Wankar
 
Optimization Simulated Annealing
Optimization Simulated AnnealingOptimization Simulated Annealing
Optimization Simulated AnnealingUday Wankar
 
Optimization Shuffled Frog Leaping Algorithm
Optimization Shuffled Frog Leaping AlgorithmOptimization Shuffled Frog Leaping Algorithm
Optimization Shuffled Frog Leaping AlgorithmUday Wankar
 
Optimization technique genetic algorithm
Optimization technique genetic algorithmOptimization technique genetic algorithm
Optimization technique genetic algorithmUday Wankar
 
Optimization Technique Harmony Search
Optimization Technique Harmony Search Optimization Technique Harmony Search
Optimization Technique Harmony Search Uday Wankar
 
Optimization by Ant Colony Method
Optimization by Ant Colony MethodOptimization by Ant Colony Method
Optimization by Ant Colony MethodUday Wankar
 
Gas turbine engine
Gas turbine engineGas turbine engine
Gas turbine engineUday Wankar
 
Gas turbine engine
Gas turbine engineGas turbine engine
Gas turbine engineUday Wankar
 
Rewinding a brushless motor
Rewinding a brushless motorRewinding a brushless motor
Rewinding a brushless motorUday Wankar
 
Rewinding a bldc motor
Rewinding a bldc motorRewinding a bldc motor
Rewinding a bldc motorUday Wankar
 
Persistence of Vision Display
Persistence of Vision DisplayPersistence of Vision Display
Persistence of Vision DisplayUday Wankar
 
Arm cortex (lpc 2148) based motor speed
Arm cortex (lpc 2148) based motor speedArm cortex (lpc 2148) based motor speed
Arm cortex (lpc 2148) based motor speedUday Wankar
 
Arm Processor Based Speed Control Of BLDC Motor
Arm Processor Based Speed Control Of BLDC MotorArm Processor Based Speed Control Of BLDC Motor
Arm Processor Based Speed Control Of BLDC MotorUday Wankar
 
Arm cortex ( lpc 2148 ) based motor speed control
Arm cortex ( lpc 2148 ) based motor speed control Arm cortex ( lpc 2148 ) based motor speed control
Arm cortex ( lpc 2148 ) based motor speed control Uday Wankar
 
Arm cortex ( lpc 2148 ) based motor speed control
Arm cortex ( lpc 2148 ) based motor speed control Arm cortex ( lpc 2148 ) based motor speed control
Arm cortex ( lpc 2148 ) based motor speed control Uday Wankar
 
POWER QUALITY IMPROVEMENT
POWER QUALITY IMPROVEMENTPOWER QUALITY IMPROVEMENT
POWER QUALITY IMPROVEMENTUday Wankar
 
Hybrid power generation by solar –wind
Hybrid power generation by solar –windHybrid power generation by solar –wind
Hybrid power generation by solar –windUday Wankar
 
Hybrid power generation by and solar –wind
Hybrid power generation by and solar –windHybrid power generation by and solar –wind
Hybrid power generation by and solar –windUday Wankar
 
Grid solving robot
Grid solving robotGrid solving robot
Grid solving robotUday Wankar
 
A PROJECT REPORT ON BGPPL BALARPUR
A PROJECT REPORT ON BGPPL BALARPURA PROJECT REPORT ON BGPPL BALARPUR
A PROJECT REPORT ON BGPPL BALARPURUday Wankar
 

More from Uday Wankar (20)

TEACHING AND LEARNING BASED OPTIMISATION
TEACHING AND LEARNING BASED OPTIMISATIONTEACHING AND LEARNING BASED OPTIMISATION
TEACHING AND LEARNING BASED OPTIMISATION
 
Optimization Simulated Annealing
Optimization Simulated AnnealingOptimization Simulated Annealing
Optimization Simulated Annealing
 
Optimization Shuffled Frog Leaping Algorithm
Optimization Shuffled Frog Leaping AlgorithmOptimization Shuffled Frog Leaping Algorithm
Optimization Shuffled Frog Leaping Algorithm
 
Optimization technique genetic algorithm
Optimization technique genetic algorithmOptimization technique genetic algorithm
Optimization technique genetic algorithm
 
Optimization Technique Harmony Search
Optimization Technique Harmony Search Optimization Technique Harmony Search
Optimization Technique Harmony Search
 
Optimization by Ant Colony Method
Optimization by Ant Colony MethodOptimization by Ant Colony Method
Optimization by Ant Colony Method
 
Gas turbine engine
Gas turbine engineGas turbine engine
Gas turbine engine
 
Gas turbine engine
Gas turbine engineGas turbine engine
Gas turbine engine
 
Rewinding a brushless motor
Rewinding a brushless motorRewinding a brushless motor
Rewinding a brushless motor
 
Rewinding a bldc motor
Rewinding a bldc motorRewinding a bldc motor
Rewinding a bldc motor
 
Persistence of Vision Display
Persistence of Vision DisplayPersistence of Vision Display
Persistence of Vision Display
 
Arm cortex (lpc 2148) based motor speed
Arm cortex (lpc 2148) based motor speedArm cortex (lpc 2148) based motor speed
Arm cortex (lpc 2148) based motor speed
 
Arm Processor Based Speed Control Of BLDC Motor
Arm Processor Based Speed Control Of BLDC MotorArm Processor Based Speed Control Of BLDC Motor
Arm Processor Based Speed Control Of BLDC Motor
 
Arm cortex ( lpc 2148 ) based motor speed control
Arm cortex ( lpc 2148 ) based motor speed control Arm cortex ( lpc 2148 ) based motor speed control
Arm cortex ( lpc 2148 ) based motor speed control
 
Arm cortex ( lpc 2148 ) based motor speed control
Arm cortex ( lpc 2148 ) based motor speed control Arm cortex ( lpc 2148 ) based motor speed control
Arm cortex ( lpc 2148 ) based motor speed control
 
POWER QUALITY IMPROVEMENT
POWER QUALITY IMPROVEMENTPOWER QUALITY IMPROVEMENT
POWER QUALITY IMPROVEMENT
 
Hybrid power generation by solar –wind
Hybrid power generation by solar –windHybrid power generation by solar –wind
Hybrid power generation by solar –wind
 
Hybrid power generation by and solar –wind
Hybrid power generation by and solar –windHybrid power generation by and solar –wind
Hybrid power generation by and solar –wind
 
Grid solving robot
Grid solving robotGrid solving robot
Grid solving robot
 
A PROJECT REPORT ON BGPPL BALARPUR
A PROJECT REPORT ON BGPPL BALARPURA PROJECT REPORT ON BGPPL BALARPUR
A PROJECT REPORT ON BGPPL BALARPUR
 

Recently uploaded

Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdfsahilsajad201
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfisabel213075
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTSneha Padhiar
 
Theory of Machine Notes / Lecture Material .pdf
Theory of Machine Notes / Lecture Material .pdfTheory of Machine Notes / Lecture Material .pdf
Theory of Machine Notes / Lecture Material .pdfShreyas Pandit
 
Curve setting (Basic Mine Surveying)_MI10412MI.pptx
Curve setting (Basic Mine Surveying)_MI10412MI.pptxCurve setting (Basic Mine Surveying)_MI10412MI.pptx
Curve setting (Basic Mine Surveying)_MI10412MI.pptxRomil Mishra
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodManicka Mamallan Andavar
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdfHafizMudaserAhmad
 
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptJohnWilliam111370
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfComprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfalene1
 
Secure Key Crypto - Tech Paper JET Tech Labs
Secure Key Crypto - Tech Paper JET Tech LabsSecure Key Crypto - Tech Paper JET Tech Labs
Secure Key Crypto - Tech Paper JET Tech Labsamber724300
 
70 POWER PLANT IAE V2500 technical training
70 POWER PLANT IAE V2500 technical training70 POWER PLANT IAE V2500 technical training
70 POWER PLANT IAE V2500 technical trainingGladiatorsKasper
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxStephen Sitton
 
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESCME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESkarthi keyan
 
KCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitosKCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitosVictor Morales
 
Cost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionCost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionSneha Padhiar
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewsandhya757531
 

Recently uploaded (20)

Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdf
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdf
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
 
Theory of Machine Notes / Lecture Material .pdf
Theory of Machine Notes / Lecture Material .pdfTheory of Machine Notes / Lecture Material .pdf
Theory of Machine Notes / Lecture Material .pdf
 
Curve setting (Basic Mine Surveying)_MI10412MI.pptx
Curve setting (Basic Mine Surveying)_MI10412MI.pptxCurve setting (Basic Mine Surveying)_MI10412MI.pptx
Curve setting (Basic Mine Surveying)_MI10412MI.pptx
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument method
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf
 
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfComprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
 
Secure Key Crypto - Tech Paper JET Tech Labs
Secure Key Crypto - Tech Paper JET Tech LabsSecure Key Crypto - Tech Paper JET Tech Labs
Secure Key Crypto - Tech Paper JET Tech Labs
 
70 POWER PLANT IAE V2500 technical training
70 POWER PLANT IAE V2500 technical training70 POWER PLANT IAE V2500 technical training
70 POWER PLANT IAE V2500 technical training
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptx
 
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESCME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
 
KCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitosKCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitos
 
Cost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionCost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based question
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overview
 

CSTPS training REPORT

  • 1. 1 A PROJECT REPORT ON “Boiler and its auxiliaries” In accordance with 2-week Training At C.S.T.P.S. Submitted By:- Uday Wankar Sainath Sorte Anant D. Patil Shubham Asati Sankalp Guremukhi Pratik Raut Rohit Lonjekar Mangesh Jumnake Surendra Butale Vivek Talande Azhar Sheikh Atul Bhusari Anup Mathankar Vivek Dhote Rahul Chekbandalwar Ashish Dhande Nikhil Shriramwar Gunjan Jaspal Shivprasad Bhosale Bhushan Lode Under the Guidance of Er. A. G. Raut
  • 2. 2 INDEX 1. INTRODUCTION ……………………………………..………………………………..2 1.1 About C.S.T.P.S. …………..……………..……………………………...……2 2. THERMAL POWER STATION ……..………………..……………………………….. 3 2.1 An Overview ………………………..……..………………………………….…..3 3. PRICIPLE …………………………………………………..……………………….….. 4 3.1 Rankine Cycle ……………………………………………………………….……4 4. Design ………………………………………….………………………………………..6 4.1 Construction and Components …….……………………………………….……6 5. WORKING ………………………………………………….………………………..…8 6. BOILER AUXILERIES …………………………………….…………………………12 a) Fans …………………………………………………………………………….….12 1) I.D. Fans ………………………………………………………….12 2) F.D. Fans ……………………………………………………...….13 3) P.A. Fans ………………………………………………………….13 4) Seal air Fans …………………………..……………………….….14 5) Scanner Fan Fans …………………………..………………….….14 6) Ignitor Fans ……………………………………………………….14 b) Coal Feeder ……………………………………………………………………….15 c) Coal Mill ………………………………………………………………………….15
  • 3. 3 d) Air Pre-Heater …………………………………………………………………….15 e) Clinker Grinder ……………………………………………………………….….16 7. BOILER LIGHT-UP PROCEDURE …………………………………..………….…..17
  • 4. 4 INTRODUCTION: About CSTPS MSEB was set up in 1960 to generate, transmit and distribute power to all consumers in Maharashtra excluding Mumbai. MSEB was the largest SEB in the country. The generation capacity of MSEB has grown from 760 MW in 1960-61 to 9771 MW in 2001-02. The customer base has grown from 1,07,833 in 1960-61 to 1,40,09,089 in 2001-02. C.S.T.P.S in contribution much in field of production of electricity. It is not only number one thermal power station in Asia but also has occupied specific position on the international map. The first set was commission on August 1983 & was dedicated to nation by then PM (late) Mrs. Indira Gandhi & second set commission on July 1984. The third & fourth units of CSTPS under stage 2 were commissioned on the 3rd May 1985 & 8th March 1986 respectively. The units 5 & 6 were commissioned on the 22nd March 1991 & 11th March 1992 respectively one more units of 500MW was added to the CSTPS on making its generation to 2340 MW & making “C.S.T.P.S.” as the giant in Power Generation of CSTPS.  STAGE 1:- 2 * 210MW units  STAGE2:- 2 * 210MW units  STAGE3:- 3 * 500MW units  Location of plant:- Plant is situated about 7km away from Chandrapur Railway Station by the side of Tadoba National Park road. 2. Climate condition:-  Daily average ambient temp 40c  Maximum ambient temp. 50c  Minimum ambient temp. 5c  Altitude for min sea level 192.3m 3. Total land area required:-  Main plant including CHP & Railway sliding: 11256 hec  Ash disposal area: 1117 Hec.
  • 5. 5 THERMAL POWER STATION: An Overview The basic operation of any thermal power plant is based on the Rankin modified cycle. Operation can be described as follows: Coal is taken to coal storage from nearby mines. In CHP, the coal is converted into fine powder called ‘pulverized coal’, because it gives complete combustion & hence better efficiency. This fuel is fed to furnace of boiler for the sake of combustion. Boiler converts water into steam, which is called saturated steam because it has some moisture content. This steam is further heated in super heater at about 540 0 c so as to remove the last traces of moisture from the steam before feeding it to the turbine. This superheated steam is passed over blades of turbine, work done in the form of rotation of turbine & pressure drop is observed. It means high pressure steam is converted into mechanical energy. The turbine is mechanically coupled with rotor of three phase alternator & thereby acts as prime mover to it. Hence as per faraday’s law of electromagnetic induction, the alternator produces 3-phase electric power as its output terminal. The steam after doing its useful working the steam is then condenses in condenser i.e. again converted into water, i.e. recirculated in the cycle using boiler feed pump & economizer. Fig.2 Energy conversion taking place in the thermal power plant Chemical Energy is converted to Heat Energy by combustion of fuel in boiler Heat energy converts water to high pressure, high temperature steam. In Turbine, steam expands as it is passed through number of nozzles. Heat energy is thus converted to kinetic energy. Steam is admitted to Turbine through pipes. Steam is then passed over blades, arranged on shaft of Turbine. Shaft rotates & Kinetic energy is thus converted to mechanical work Steam exhausted from turbine condenses in Condenser, rejecting unavailable heat energy. Pump delivers condensed water from Condenser back to Boiler. Generator is coupled to Turbine, where mechanical energy is converted to electrical energy.
  • 6. 6 PRINCIPLE: Rankine cycle Fig: Temperature verses Entropy Characteristics There are four processes in the Rankine cycle. These states are identified by numbers (in brown) in the above Ts diagram.  Process 1-2: The working fluid is pumped from low to high pressure. As the fluid is a liquid at this stage the pump requires little input energy.  Process 2-3: The high pressure liquid enters a boiler where it is heated at constant pressure by an external heat source to become a dry saturated vapor. The input energy required can be easily calculated using mollier diagram or h-s chart or enthalpy-entropy chart also known assteam tables.  Process 3-4: The dry saturated vapor expands through a turbine, generating power. This decreases the temperature and pressure of the vapor, and some condensation may occur. The output in this process can be easily calculated using the Enthalpy-entropy chart or the steam tables.  Process 4-1: The wet vapor then enters a condenser where it is condensed at a constant pressure to become a saturated liquid.
  • 7. 7 In an ideal Rankine cycle the pump and turbine would be isentropic, i.e., the pump and turbine would generate no entropy and hence maximize the net work output. Processes 1-2 and 3-4 would be represented by vertical lines on the T-S diagram and more closely resemble that of the Carnot cycle. The Rankine cycle shown here prevents the vapor ending up in the superheat region after the expansion in the turbine, [1] which reduces the energy removed by the condensers.
  • 8. 8 DESIGN: Construction and Components Boiler means any cleared vessel exceeding 22.75 LH in capacity used for steam. Generation under pressure.The first Boiler developed in 1725 & working pressure was 6 to 10 kg/cal. TYPES OF BOILERS: There are two types of Boilers:- 1) Fire tube boilers (Carnish & Lauchashine blrs.) developed in the year 1844 2) Water tube boilers developed in 1873 years. We are having in Thermal Power stations water tube Boilers. These are sub divided according to water circulation, as :- 1) Natural circulation: Drum to down comers to due ring main header to water wall tubes & back to drum difference in density of water when cool & hot. 2) Forced circulation: Additional pumps are installed in down comers. According to pressure the Boilers are called- 1) Drum type sub critical boiler: When boiler pressure is 130 kg/cm2 to 180 kg/cm2 2) Critical pressure Boilers : When boiler pressure is 221.2 kg/cm2 3) Super critical drum less once through boilers: When boiler pressure is 240 kg/cm2 All modern Boilers are top slung from steel structures from the Beams a series of slings take up the boiler loads. Suspended weight of one 210 MW boiler is 3640 tonnes approx. eight of Boiler is about 64 meters and Boiler drum is at a height of 52 meters from ground. Boiler design: 1. Lowest capital cost, ease of construction, simplicity, ssafety, Good working condition ease of maintenance 2. Efficient operation, effective baffling for heat transfer will insulate casings, ability to deliver pure steam with effective drum internals, build steam ball capacity. 3. Availability of auxiliaries
  • 9. 9 The main parts of Boiler are:  Boiler drum (Length: 15.7 meters, ID: 1976 mm, Thickness 132 mm) down comers (6 down comers of size 406x32 mm)  Water walls (Made of SA 210 Gr A1 material, 63.5x6.3 mm, 76.1mm thick)  Furnace (13.868 m width, 10.592 m depth, 5494m3 vol)  Platen superheater (The size of tubes are 51x7.1 mm +51x8.6mm)  Reheater (The size of tubes is 54x3.6 mm)  Final superheater (size of tubes are 51x7.6 mm the materials are SA213 T22 alloy steel and stands upto 5800 C (alloy steel)  Primary superheater (The material used are SA209T, SA210 Gr. A, SA 213 T11.The size of tubes are 44.5x4.5 mm & temperature range is 4500 C to 4800 C  Economizer (The material used are carbon steel of SA 210 Gr. A1 stands upto 4500 C, size of the tubes are 44.5x4.5 mm)  Burners (The burners are situated at 3 elevations called AB,CD,EF)  Ignitors (For every burner one ignitor is provided for igniting the burner for combustion & cooling ignitor fan is provided. It is a centrifugal fan with backward curved. Capacity 9000 m3/h, 75 mm WC, 1500 rpm.
  • 10. 10 WORKING: In Boiler, Coal is stored in Bunkers. Size of coal in bunkers is 25 mm. The coal received from coal mines has a size varying from 4 to 8 inches. In Coal Handling plant, it is first reduced to 25-mm size and then fed to the bunkers through a series of conveyer belts. From bunkers, coal is fed to the Coal Mill where it is pulverized. Coal particle average size, after pulverization, is 75 microns.(1 micron is 1000th part of a millimeter) In 210 MW units, there are 6 coal mills and in 500 MW units, 8 coal mills are installed. For full load operation of the unit, 4 to 5 coal mills are running. Other coal mills are stand by.
  • 11. 11 When boiler is to be started up from cold conditions, coal can not be fired, as there is no ignition energy available. Hence first L.D.O. is fired for lighting up the boiler. After Boiler pressure is built up to certain specified values, Heavy Furnace oil is fired. After achieving the specified parameters with oil firing, coal is admitted. Pulverized coal from the mills is continuously lifted with the help of air, called primary air. Primary air fans are installed for this purpose. Coal-air mixture is fed to Boilers through coal burners, arranged at various elevations. For complete and efficient combustion of coal, primary air is not sufficient, and hence secondary air, obtained from Secondary Air fans, is also admitted to the furnace in controlled quantity. Before admission in coal mills and boiler, primary air and secondary air are first heated to a temperature of 325° C. Heating of air is carried out in Air pre heaters, with the help of hot flue gas leaving the boiler. When coal is burnt, it also produces ash. Small ash particles, which can flow with the flue gas, is called fly ash. Flue gas , after leaving the Air pre heaters, is sent to Electrostatic
  • 12. 12 precipitators, where fly ash is separated from flue gas and collected in number of Ash Hopper, arranged on Electrostatic precipitators. Ash hopper size is such that it can store all the fly ach generated in 8 Hours continuous operation of Boiler. The flue gases from the boiler are sucked by Induced draft fans, which are arranged after ESP. From there, flue gases are sent to Chimney, which disposes off the flue gas to atmosphere. Ash hoppers are emptied after every 8 hours. For disposing off the ash, it is mixed with water and no. of pumps then lift and transport the ash- water mixture, called slurry, to pre determined place called ash bund. Turbine is used to convert heat energy to mechanical work. Turbine consists of rotors, on which a series of moving blades are arranged, and casing on which fixed blades are arranged. Steam admitted to turbine, is guided by fixed blades to strikes on blades on Rotor, in the form of jet, causing rotor to rotate thus converting heat energy to mechanical energy. Heat energy released from the combustion of coal in the boiler is given to water circulated in it. Water is thus converted to steam, pressure of which is 140 Kg/ cm² and temperature is 537° C.. This steam, called live steam or main steam, is sent to High Pressure Turbine, where it is made to strike on a series of rotor blades. When it reaches at the exhaust, its temperature and pressure drops to 330° C and 30 Kg/ cm². Exhaust steam from HPT is sent to Reheater, arranged in the boiler, where its temperature is again raised to 537° C, and pressure remains 30 Kg/ cm². This steam is called Reheat steam, which is sent to another turbine called Intermediate pressure turbine. From I.P.T, steam then is sent to low-pressure turbine. At the exhaust of LPT, steam temperature and pressure is very low, and further work can not be extracted from it. Hence it is condensed in the condenser, maintained at a vaccume of 750 mm Hg. The condensed water is called condensate. Conedensate Extraction Pumps, and Feed Water Pumps are used for pumping the condessate from Condenser to Boiler through L. P. Heaters and H. P. Heaters. In these heaters, small quantity of steam, extracted from intermediate stages of Turbine, heat the water. When water comes out of heaters, its temperature is 250° C which is fed in to boiler. This is called regenerative feed heating cycle. The efficiency of power plant increases due to regenerative feed heating. Cooling water circulated in Condenser, at temperature of 30°C absorbs the heat energy released in condensation due to which its temperature increases to 40° C. In cooling towers, this hot water is again cooled to a temperature of 30° C for reuse in condenser.
  • 13. 13 . Generator consists of Copper conductors wound on Stator and a Rotor on which Electro magnets are arranged. Rotors of all the three turbine and Generator are coupled with common shaft. Rotation of shaft causes rotation of Generator rotor, causing the rotation of Electro magnets. This sets up electrical voltage on stator conductors of the generator at 15 kV. Transformer steps up this voltage to 400 kV or 220 kV or 132 kV depending on the Grid voltage where it is connected. The electrical energy thus generated is sent to Power Grid, from where it reaches to the consumer through Transmission and distribution system.
  • 14. 14 BOILER AUXILERIES There are some important machines equipment for safe and efficient working of Boiler. These machines are called Boiler auxiliaries. They are: a) FANS: 1) Induced draft fan (I.D. Fan) 2 No. per Boiler. It induces gaseous products from furnace and forces out through chimney. Type ND2V, Q= 230 m3 /s, Pressure = 405 mm WC, KW = 1300, Speed = 740 rpm, Radial fan. Fig: Sectional assembly of ID Fan
  • 15. 15 2) F.D. Fan : Forced draft fan 2 Nos. per Boiler. It forces atmospheric air to furnace as secondary air through air preheater and wind box for combustion of fuel. Type-API – 20/11, Pressure = 408 mmWC, Q= 451m3 /s motor 900 KW, 1480 rpm, axial fan. Fig: Sectional view of F.D. Fan 3) P.A. Fans: Primary air for Transport of coal from mill to furnace is provided by fan. And one tap is provided to coal mill to maintain temperature at 40c. To facilitate drying of coal, part of P.A. fan air is routed through. The P.A. fan air should maintain speed of 80 to 100 ft/sec is fuel pipe to maintain coal is air born state to avoid chucking of coal pipes.
  • 16. 16 P.A. Fans have narrow section impellors, and 2 to 3 times higher speeds than I.D. or F.D. high speed fans to give high heads required for fuel firing types blades are made of high tensile alloy steels to resist abrasion. Fig: P.A. Fan Sectional view 4) Seal Air Fan: Seal air pressure is higher than P.A. Fan pressure. It is required for sealing purpose of coal mills bowl input shaft, journal assembly brgs, coal feeders shaft brgs, sprockets otherwise dust enters above area and spoil brgs & oil. 5) Scanner fan : For sensing the flame scanners are provided at all elevations of all corners in furnace. For cooling these scanners air is provided form these fans. Boiler will trip if these fans fails. Capacity 1200 m3/h, Pressure = 320 mm WG, Motor 3 HP, 2970 rpm. 6) Igniter Fan : For every burner one igniter is provided for igniting the burner for combustion & cooling igniter fan is provided. It is a centrifugal fan with backward curved. Capacity 9000 m3/h, 75 mm WC, 1500 rpm.
  • 17. 17 b) COAL FEEDER: Coal comes from CHP to bunkers and coal feeder feed to any coal mill is regulated by a coal feeder by changing its speed. Coal feeder handles crushed coal of size 15 to 25 mm. There are two types of coal feeder: 1) Gravitic Feeder: can be to a large bunker outlet there by minimizing chokage during rainy season. Type R600 2) Volumetric type is Rotary type 100, Capacity 7.4 to 43.6 T/hr., Speed 2.7 to 16 rpm. Coal can be measured by volume of sector rotating/min. c) COAL MILLS: Coal from feeder comes to mill & coal is crushed in the mill to the required fineness 75% by 200 mesh. There are classifier gate through which correct size coal only passes other coal comes back for grinding again. Mill temp. to be maintained below comes back for grinding again. Mill temp to be maintained below 900 C. the required air flow is 50 T/h to lift the coal to furnace. d) AIR PRE-HEATER: Air heater is unique among Boiler auxiliaries with principle purpose of saving energy and an in come producing asset. It can have significant impact on plant capacity and heat rate increases by 8 to 12%, saves fuel It provides heated air for drying and conveying P.F. coal provides heated air to combustion of fuel & lower emissionTrisector type Air heater is used in ktps. In this Flue gas flows through 180 of portion;F.D. air flows through 128 of porsion;P.A. Fan air flows through 52 of poison P.A. partial air is bypassed as cold air.
  • 18. 18 e) CLINKER GRINDER: Capacity 60 T/hr. It reduces clinkers size upto 25 to 50 mm for early transmission through pipes to ash yard/slurry pump house. Grinder made of manganese steel.
  • 19. 19 BOILER LIGHT-UP PROCEDURE 1. Line clear Conform that thers is no work permit is pending and normalization of equipment after cancellation of permit. 2. Starting of equipment i. control& power supply made ready. ii. Protection and interlocks are ok iii. Normalization of equipment ( Ready to start position ) iv. Lubrication & cooling systems are in service. Start equipment with no load & raise the load simultaneously So as to avoid overloading the prime mover. 3. Filling up the Boiler i. keep all the verts open & fill through all the circuits such as that no air pocket is formed and water level in drum in the range of 40 to 50 %. ii. To conform the level from direct gauge glass. iii. Confirm their is sufficient water level in dearator. 4. Oil firing equipment i. check that oil guns are insert in retracted position. ii. Ensure that all manual valves opened and remote control valves are close. iii. Gun tips are clean. 5. Pulverizer i. pulverizedischange valve is open. Hot air & control damper is closed. ii. Cold air gate is opened at 15% 6. Fans / air heater – Normalize the damper position. Ignitorfan , scanner air fan & mill seal air fans are to be kept on start up position. 7. Soot blowers : check all soot blowers are in retracted position. 8. Valves in boiler i. Keep vent valves open.
  • 20. 20 ii. Keep drain valves & open ( expect drum , water wall &economiser) iii. Economiser recirculation valve open condition. 9. Start regenerative air heaters. 10. Start one air cycle ( ID& FD )and adjust draft to – 10 mmwc. Adjust the corresponding dampers in air & gas circuit a) place the steam coil air heater in sevice. b) Start ignitor fan ,scanner fan and seal air fans. c) put the secondary air damper control on auto. d) The wind box to furnace differential pressure will be maintained to 40mmwG by adjusting auxiliary air dampers. e) Initiate furnace purge circuit. f) Furnace purge will take 5 minutes 11. Intitate a light up sequence of the lower elevation of ignitors and warm oil guns. Check the combustion and adjust the air dampers. If required. 12. Maintain furnace draft by controlling the ID fan loading place furnace draft system on auto. 13. Maintain the boiler drum level by opening blowdown. Initially water level will raise. 14. Increase firing rate . Firing rate should be controlled so that furnace exit gas temperature does not exceed 5400 c, till sufficient steam flow through superheaters and reheaters are established. 15. Soot blow the regerative air heater with steam /compressed air to avoid plugging and possibility of fire. 16. Close drum vent when pressure reaches to 2 to 5 kg/cm2 close the drains and vents of reheater, which are open to atmospher before pulling vacuum in condenser 17. Close drains and vents of superheater system. 18. Increase the firing rate as required to raise the pressure, when sufficient flow through superheaters and rcheater is established ,with the help of HP-LP by pass. The firing rate need not be restricted to furnace outlet temperature of 5400 c 19. As the drum pressure increase , progressively throttle superheat outlet header drain & startup vents. 20. Steam to turbine rolling is permitted as soon as the minimum permissible pressure & temperature for the corresponding turbine metal temp.
  • 21. 21 21. After synchronizing of T – G, close all drains & vents of boiler . 22. Increase firing rate and adjust air as per requirment. 23. Start coal firing as per requirement of loading of turbine. 24. When boiler reaches 30% of full load , the wind box to furnace differential is damped to about 100 mmwG. 25. The oil support and igniters can be withdrawn when two adjutants coal elevation ,are in service with atleast 50% of loading. 26. Take second air cycle in service & further load the coal firing 27. To control temperature desuperheters can be charged if required.