SlideShare a Scribd company logo
1 of 37
Download to read offline
Testing
of
Transformer
K.N.Srinivasan
Traceabllity
Accuracy
Precision
Probability
Std. deviation
Standards
Accreditation
Insulation tests
Short ckt test
Power rating
Other tests
Overview
A MODERN TRANSFORMER IS A
COMPLEX ELECTROMAGNETIC
APPARATUS
TRANSFORMERS SERVE FOR
TRANSMISSION AND DISTRIBUTION
OF ELECTRICAL ENERGY
TRANSFORMERS (DISTRIBUTION)
ARE THE LAST MAJOR LINK
BETWEEN UTILITY & CONSUMER
Introduction
TRANSFORMERS ARE STATIC
ALTERNATING CURRENT MACHINES
PRINCIPLE IS BASED ON MUTUAL
INDUCTION BETWEEN WINDINGS
THROUGH A COMMON CORE
OIL-IMMERSED AND DRY TYPES
POWER AND DISTRIBUTION TYPES
SPECIAL TYPES
Transformer on load
ϕ
V1
I0
E2
I1I’2
I2
E = - 4.44 φmf N
 Measurement of winding resistance
 Measurement of voltage ratio
 Polarity test
 Measurement of no-load loss & no-load current
 Measurement of load-loss & short-circuit impedance
 Measurement of insulation resistance
 Dielectric tests
Routine tests
 Measurement of winding resistance
 Measurement of voltage ratio
 Polarity test
 Measurement of no-load loss & no-load current
 Measurement of load-loss & short-circuit impedance
 Measurement of insulation resistance
 Dielectric tests
 Temperature-rise test
Type tests
 Dielectric test
 Short-circuit test
 Measurement of zero-sequence
impedance of three phase transformers
 Measurement of acoustic noise level
 Measurement of harmonics of the no-load
current
 Measurement of power taken by the fans
& oil pumps
Special tests
 Dielectric test
 Short-circuit test
 Measurement of zero-sequence
impedance of three phase transformers
 Measurement of acoustic noise level
 Measurement of harmonics of the no-load
current
 Measurement of power taken by the fans
& oil pumps
Special tests
• Separate source voltage withstand test
• Induced over voltage withstand test
• Impulse voltage withstand test
Dielectric test
Terminals of windings under test connected to HV terminal of the
source . All other windings, core, frame and tank are earthed.
Duration of test is 60 secs.
Highest system voltage(kV) Power frequency voltage(kV)
1.1 3
3.6 10
7.2 20
12 28
24 50
36 70
52 95
72.5 140
Separate source voltage withstand test
 This test is useful in determining
layer insulation and inter turn
insulation of windings.
 HV is kept open & twice the rated
voltage at twice the rated frequency
is applied to the LV for a duration of
60 secs.
Induced over voltage withstand test
Testing facilities
• Impulse generator
• Discharge circuit
• Recording system
• Voltage divider for measurement
Standard Impulse wave
Impulse withstand test
Wave shape
 Standard wave shape of impulse voltage is
1.2/50µsec.
 t1 is the rise time = 1.2µsecs.
 t2 is the tail time = 50 µ secs.
 Tolerance on t1 is ±30% & ±20% on t2.
Impulse generator
 Impulse wave is generated by discharge of
capacitors charged in parallel into a wave shaping
circuit.
Connection
Fig.7.3.1.Connection diagram
lmpulse Application : (Negative Polarity).
Oscillograms : 7.3.1 Reduced full wave 100 kV (Peak)
7.3.2. 100% full wave 170 kV (Peak)
7.3.3 Reduced Chopped wave 103 kV (Peak)
7.3.4. 100% chopped wave 170 kV (Peak)
7.3.5. 100% chopped wave 170 kV (Peak)
7.3.6. 100% full wave 170 kV (Peak)
7.2.7. 100% full wave 170 kV (Peak)
Oscilograms
Oscilograms contd.
Oscilograms contd.
Fig 7.3.3 Connection diagram
Generator capacitance 0.0625 uF
Series resistance 160 ohms
Tail resistance 1040 ohms
Voltage divider 1200 pF in parallel with 100 ohms
Impulse applications : (Negative Polarity)
Oscillogram No. 7.3.15. Reduced full wave 43 kV (Peak)
7.3.16. 100% full wave - 75 kV (Peak)
7.3.17. 100% full wave 75 kV (peak)
Comparison of oscillograms 15 & 16 indicates that the second voltage wave
oscillogram has collapsed and the corresponding point of the neutral current
there are high frequency oscillations. This indicates an arc over across major
portion of the transformer winding as a result of failure of the transformer
insulation.
Oscillograms 7.3.15 to 7.3.17
 MINOR INSULATION -conductor turns,
layers
●
enamel, paper
●
oil ducts, paper cylinders
 MAJOR INSULATION- winding, core
●
press board cylinders, oil ducts
BUSHINGS - porcelain , condenser
Power & distribution transformers must be constructed to
withstand mechanical stresses caused by external faults.
These stresses are produced due to electromagnetic forces
as a result of very high current in the windings during
short-circuits.
Short-circuit test
 Prior to the short-circuit, transformer
is subjected to routine tests.
Asymmetrical current
 The peak current that transformer is
required to withstand = Isc(peak)=K Isc
Dynamic ability to withstand short-circuit
Value of K :
x/r 1 1.5 2 3 4 5 6 8 10 >14
K 1.51 1.64 1.76 1.95 2.09 2.19 2.27 2.38 2.46 2.55
Short-circuit may be
a) Preset or
b) Post set
Duration of each test
being 0.5 sec. ( > 5 MVA 0.25 sec)
For 1φ Transformers
No. of tests = Three
one test with tap at highest voltage ratio, one test in principal taping &
one test in
lowest voltage ratio
Short-circuit testing procedure
3φ Transformers
 No. of tests = Nine
 Three tests with tap at highest voltage ratio, three
tests in principal taping & three tests in lowest voltage
ratio
Tolerances on
 Asymmetrical current = ±5 %
 Symmetrical current = ±10 %
 Test duration = ±10 %
Oscillogram of dynamic short-circuit test on
3Phase 11/0.433kV 500kVA Distribution
transformer
 All the routine tests shall be repeated
 Dielectric test shall be at 75%
 Transformer shall be untanked
 Reactance measured after s.c. test shall not
differ by more than 2% for circular coils & 7.5%
for non-circular coils.
Analysis of the results
SC Test contd.
This is to ascertain that transformer & its cooling arrangements
are effectively designed so that temp. rise of winding & cooling
medium does not exceed the permissible limits.
Temp. rise limits for Dry type transformers
Class of insulation Temp. rise °C
A 50
E 65
B 70
F 90
H 115
C 140
Temperature rise test
Temp. rise limits for oil immersed transformers
Part Temp. rise °C
External cooling medium
Air Water
Winding 55 60
(temp.rise by resistance method)
Top oil 50 55
(temp.rise by thermometer method)
a) Direct loading
b) Back-to-Back method
c) Short-circuit method
Loading methods
Duration of test
Top oil temperature-rise does not vary more than
10
C/hour during 4 consecutive hourly readings
Partial Discharge Tests
100pC
500pC
Sound pressure level 20 log10 d/0.00002 dB
d Newton per square meter
Noise Level
meter
Highest voltage
for equipment
Um
kV
(r.m.s. value)
Rated short duration
power frequency
withstand voltage
kV
(r.m.s. value)
Rated
lightning impulse
withstand voltage
kV
(peak value)
3.6 10 20
40
7.2 20 40
60
12 28 60
75
95
17.5 38 75
95
24 50 95
125
145
36 70 145
170
52 95 250
72.5 140 325
123 (185)
230
450
550
145 (185)
230
275
(450)
550
650
170 (230)
275
325
(550)
650
750
245 (275)
(325)
360
395
460
(650)
(750)
850
950
1050
Highest
voltage for
equipment
Um
kV
(r.m.s. value)
Standard switching impulse
withstand voltage
--------------------------------------
-------------------
Longitudinal Phase-to-earth
Phase-to-phase
Insulation
(ratio to the
(note 1)
phase-to-earth
kV kV
peak value)
(peak value) (peak value)
Standard
lightning impulse
withstand voltage
kV
(peak value)
300 750 750 1,50 850
950
750 850 1,50 950
1050
362 850 850 1,50 950
1050
850 950 1,50 1050
1175
420 850 850 1,60 1050
1175
950 950 1,50 1175
1300
950 1050 1,50 1300
1425
525 950 950 1,70 1175
1300
950 1050 1,60 1300
1425
950 1175 1,50 1425
1550
765 1175 1300 1,70 1675
1800
1175 1425 1,70 1800
1950
1175 1550 1,60 1950
2100

More Related Content

What's hot

Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentationKamal Mittal
 
Power system protection topic 1
Power system protection topic 1Power system protection topic 1
Power system protection topic 1Siswoyo Edo
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer ProtectionAng Sovann
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.Hemendra Kumar Rajput
 
Instrument transformer CT & PT
Instrument transformer CT & PTInstrument transformer CT & PT
Instrument transformer CT & PTChandan Singh
 
Transformers protection, an introduction
Transformers protection, an introductionTransformers protection, an introduction
Transformers protection, an introductionH. Kheir
 
Tan delta test for power transformers
Tan delta test for power transformersTan delta test for power transformers
Tan delta test for power transformersjibinjoy1988
 
Protection of transformer
Protection of transformerProtection of transformer
Protection of transformerSumeet Ratnawat
 
Generator protection calculations settings
Generator protection calculations settingsGenerator protection calculations settings
Generator protection calculations settingsmichaeljmack
 
Generator Protection
Generator ProtectionGenerator Protection
Generator ProtectionPriten Vasa
 
Substation Maintenance
Substation MaintenanceSubstation Maintenance
Substation Maintenancekarikalan123
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTCRohit Dave
 
Power Transformer Parts And Functions
Power Transformer Parts And FunctionsPower Transformer Parts And Functions
Power Transformer Parts And FunctionsNitendra Kumar Singh
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1Md Irshad Ahmad
 
Power transformer protection
Power transformer protectionPower transformer protection
Power transformer protectionmichaeljmack
 
Sample calculation-for-differential-relays
Sample calculation-for-differential-relaysSample calculation-for-differential-relays
Sample calculation-for-differential-relaysRoberto Costa
 
Frequency response analysis (FRA) of transformer
Frequency response analysis (FRA) of transformerFrequency response analysis (FRA) of transformer
Frequency response analysis (FRA) of transformerRaveendranath Macherla
 

What's hot (20)

Transformer basic
Transformer basicTransformer basic
Transformer basic
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
 
Power system protection topic 1
Power system protection topic 1Power system protection topic 1
Power system protection topic 1
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer Protection
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.
 
Instrument transformer CT & PT
Instrument transformer CT & PTInstrument transformer CT & PT
Instrument transformer CT & PT
 
Transformers protection, an introduction
Transformers protection, an introductionTransformers protection, an introduction
Transformers protection, an introduction
 
Tan delta test for power transformers
Tan delta test for power transformersTan delta test for power transformers
Tan delta test for power transformers
 
Protection of transformer
Protection of transformerProtection of transformer
Protection of transformer
 
Generator protection calculations settings
Generator protection calculations settingsGenerator protection calculations settings
Generator protection calculations settings
 
Generator Protection
Generator ProtectionGenerator Protection
Generator Protection
 
Substation Maintenance
Substation MaintenanceSubstation Maintenance
Substation Maintenance
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTC
 
Power Transformer Parts And Functions
Power Transformer Parts And FunctionsPower Transformer Parts And Functions
Power Transformer Parts And Functions
 
Tap changer
Tap changerTap changer
Tap changer
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1
 
Power transformer protection
Power transformer protectionPower transformer protection
Power transformer protection
 
Protection and Switchgear
Protection and SwitchgearProtection and Switchgear
Protection and Switchgear
 
Sample calculation-for-differential-relays
Sample calculation-for-differential-relaysSample calculation-for-differential-relays
Sample calculation-for-differential-relays
 
Frequency response analysis (FRA) of transformer
Frequency response analysis (FRA) of transformerFrequency response analysis (FRA) of transformer
Frequency response analysis (FRA) of transformer
 

Viewers also liked

EE201 -Chapter 4
EE201 -Chapter 4 EE201 -Chapter 4
EE201 -Chapter 4 ruhiyah
 
Sc and oc test on transformer
Sc and oc test on transformerSc and oc test on transformer
Sc and oc test on transformerPooja Dubey
 
open circuit and short circuit test on transformer
open circuit and short circuit test on transformeropen circuit and short circuit test on transformer
open circuit and short circuit test on transformerMILAN MANAVAR
 
EE201 -Chapter 6
EE201 -Chapter 6EE201 -Chapter 6
EE201 -Chapter 6ruhiyah
 
EE201 - Chapter 3 (BJT)
EE201 - Chapter 3 (BJT)EE201 - Chapter 3 (BJT)
EE201 - Chapter 3 (BJT)ruhiyah
 
TRANSISTORS
 TRANSISTORS TRANSISTORS
TRANSISTORSAJAL A J
 
3.bipolar junction transistor (bjt)
3.bipolar junction transistor (bjt)3.bipolar junction transistor (bjt)
3.bipolar junction transistor (bjt)firozamin
 
Transistors ppt by behin
Transistors ppt by behinTransistors ppt by behin
Transistors ppt by behinBehin anben
 

Viewers also liked (9)

EE201 -Chapter 4
EE201 -Chapter 4 EE201 -Chapter 4
EE201 -Chapter 4
 
Sc and oc test on transformer
Sc and oc test on transformerSc and oc test on transformer
Sc and oc test on transformer
 
open circuit and short circuit test on transformer
open circuit and short circuit test on transformeropen circuit and short circuit test on transformer
open circuit and short circuit test on transformer
 
EE201 -Chapter 6
EE201 -Chapter 6EE201 -Chapter 6
EE201 -Chapter 6
 
EE201 - Chapter 3 (BJT)
EE201 - Chapter 3 (BJT)EE201 - Chapter 3 (BJT)
EE201 - Chapter 3 (BJT)
 
Lecture 8 bjt_1
Lecture 8 bjt_1Lecture 8 bjt_1
Lecture 8 bjt_1
 
TRANSISTORS
 TRANSISTORS TRANSISTORS
TRANSISTORS
 
3.bipolar junction transistor (bjt)
3.bipolar junction transistor (bjt)3.bipolar junction transistor (bjt)
3.bipolar junction transistor (bjt)
 
Transistors ppt by behin
Transistors ppt by behinTransistors ppt by behin
Transistors ppt by behin
 

Similar to Transformer Testing Guide: Key Procedures and Standards

Introduction of transfromer
Introduction of transfromerIntroduction of transfromer
Introduction of transfromerpretty gurna
 
ct pt testing...........................................
ct pt testing...........................................ct pt testing...........................................
ct pt testing...........................................hiiarindam
 
Power-Transformer-Testing-Brochure-ENU.pdf
Power-Transformer-Testing-Brochure-ENU.pdfPower-Transformer-Testing-Brochure-ENU.pdf
Power-Transformer-Testing-Brochure-ENU.pdfNguyenXuanTung12
 
Lightning impulse test in precise
Lightning impulse test in  preciseLightning impulse test in  precise
Lightning impulse test in preciseMuthar Hussain
 
Power Transformer Differential protection
Power Transformer Differential protectionPower Transformer Differential protection
Power Transformer Differential protectionRishi Tandon
 
Differential protection
Differential protectionDifferential protection
Differential protectionRishi Tandon
 
Switchgear & Rectifier ppt
Switchgear & Rectifier pptSwitchgear & Rectifier ppt
Switchgear & Rectifier pptvikas kumar
 
Schneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment DesignersSchneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment DesignersThorne & Derrick International
 
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuitsModule 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuitsAsha Anu Kurian
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptChristinaBoyd12
 
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.pptsantubanga333
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptssuser1f60f6
 
Power transformers rating
Power transformers ratingPower transformers rating
Power transformers ratingLeonardo ENERGY
 
Ac Test Transformer
Ac Test TransformerAc Test Transformer
Ac Test Transformerkennypowerhv
 
Short circuit test in brief
Short circuit test in briefShort circuit test in brief
Short circuit test in briefMuthar Hussain
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushingNovia Putri
 
Insulation co cordination design
Insulation co cordination designInsulation co cordination design
Insulation co cordination designNaresh Surisetti
 

Similar to Transformer Testing Guide: Key Procedures and Standards (20)

Introduction of transfromer
Introduction of transfromerIntroduction of transfromer
Introduction of transfromer
 
ct pt testing...........................................
ct pt testing...........................................ct pt testing...........................................
ct pt testing...........................................
 
Power-Transformer-Testing-Brochure-ENU.pdf
Power-Transformer-Testing-Brochure-ENU.pdfPower-Transformer-Testing-Brochure-ENU.pdf
Power-Transformer-Testing-Brochure-ENU.pdf
 
Lightning impulse test in precise
Lightning impulse test in  preciseLightning impulse test in  precise
Lightning impulse test in precise
 
Transformer
TransformerTransformer
Transformer
 
Power Transformer Differential protection
Power Transformer Differential protectionPower Transformer Differential protection
Power Transformer Differential protection
 
Differential protection
Differential protectionDifferential protection
Differential protection
 
Switchgear & Rectifier ppt
Switchgear & Rectifier pptSwitchgear & Rectifier ppt
Switchgear & Rectifier ppt
 
Schneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment DesignersSchneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment Designers
 
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuitsModule 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
 
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
 
tcee-161003100321.pptx
tcee-161003100321.pptxtcee-161003100321.pptx
tcee-161003100321.pptx
 
Power transformers rating
Power transformers ratingPower transformers rating
Power transformers rating
 
Ac Test Transformer
Ac Test TransformerAc Test Transformer
Ac Test Transformer
 
Short circuit test in brief
Short circuit test in briefShort circuit test in brief
Short circuit test in brief
 
Testing
TestingTesting
Testing
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushing
 
Insulation co cordination design
Insulation co cordination designInsulation co cordination design
Insulation co cordination design
 

Recently uploaded

US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 

Recently uploaded (20)

US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 

Transformer Testing Guide: Key Procedures and Standards

  • 3. Insulation tests Short ckt test Power rating Other tests
  • 4. Overview A MODERN TRANSFORMER IS A COMPLEX ELECTROMAGNETIC APPARATUS TRANSFORMERS SERVE FOR TRANSMISSION AND DISTRIBUTION OF ELECTRICAL ENERGY TRANSFORMERS (DISTRIBUTION) ARE THE LAST MAJOR LINK BETWEEN UTILITY & CONSUMER
  • 5. Introduction TRANSFORMERS ARE STATIC ALTERNATING CURRENT MACHINES PRINCIPLE IS BASED ON MUTUAL INDUCTION BETWEEN WINDINGS THROUGH A COMMON CORE OIL-IMMERSED AND DRY TYPES POWER AND DISTRIBUTION TYPES SPECIAL TYPES
  • 7.  Measurement of winding resistance  Measurement of voltage ratio  Polarity test  Measurement of no-load loss & no-load current  Measurement of load-loss & short-circuit impedance  Measurement of insulation resistance  Dielectric tests Routine tests
  • 8.  Measurement of winding resistance  Measurement of voltage ratio  Polarity test  Measurement of no-load loss & no-load current  Measurement of load-loss & short-circuit impedance  Measurement of insulation resistance  Dielectric tests  Temperature-rise test Type tests
  • 9.  Dielectric test  Short-circuit test  Measurement of zero-sequence impedance of three phase transformers  Measurement of acoustic noise level  Measurement of harmonics of the no-load current  Measurement of power taken by the fans & oil pumps Special tests
  • 10.  Dielectric test  Short-circuit test  Measurement of zero-sequence impedance of three phase transformers  Measurement of acoustic noise level  Measurement of harmonics of the no-load current  Measurement of power taken by the fans & oil pumps Special tests
  • 11. • Separate source voltage withstand test • Induced over voltage withstand test • Impulse voltage withstand test Dielectric test
  • 12. Terminals of windings under test connected to HV terminal of the source . All other windings, core, frame and tank are earthed. Duration of test is 60 secs. Highest system voltage(kV) Power frequency voltage(kV) 1.1 3 3.6 10 7.2 20 12 28 24 50 36 70 52 95 72.5 140 Separate source voltage withstand test
  • 13.  This test is useful in determining layer insulation and inter turn insulation of windings.  HV is kept open & twice the rated voltage at twice the rated frequency is applied to the LV for a duration of 60 secs. Induced over voltage withstand test
  • 14. Testing facilities • Impulse generator • Discharge circuit • Recording system • Voltage divider for measurement Standard Impulse wave Impulse withstand test
  • 15. Wave shape  Standard wave shape of impulse voltage is 1.2/50µsec.  t1 is the rise time = 1.2µsecs.  t2 is the tail time = 50 µ secs.  Tolerance on t1 is ±30% & ±20% on t2. Impulse generator  Impulse wave is generated by discharge of capacitors charged in parallel into a wave shaping circuit.
  • 16. Connection Fig.7.3.1.Connection diagram lmpulse Application : (Negative Polarity). Oscillograms : 7.3.1 Reduced full wave 100 kV (Peak) 7.3.2. 100% full wave 170 kV (Peak) 7.3.3 Reduced Chopped wave 103 kV (Peak) 7.3.4. 100% chopped wave 170 kV (Peak) 7.3.5. 100% chopped wave 170 kV (Peak) 7.3.6. 100% full wave 170 kV (Peak) 7.2.7. 100% full wave 170 kV (Peak)
  • 19. Oscilograms contd. Fig 7.3.3 Connection diagram Generator capacitance 0.0625 uF Series resistance 160 ohms Tail resistance 1040 ohms Voltage divider 1200 pF in parallel with 100 ohms Impulse applications : (Negative Polarity) Oscillogram No. 7.3.15. Reduced full wave 43 kV (Peak) 7.3.16. 100% full wave - 75 kV (Peak) 7.3.17. 100% full wave 75 kV (peak) Comparison of oscillograms 15 & 16 indicates that the second voltage wave oscillogram has collapsed and the corresponding point of the neutral current there are high frequency oscillations. This indicates an arc over across major portion of the transformer winding as a result of failure of the transformer insulation.
  • 21.  MINOR INSULATION -conductor turns, layers ● enamel, paper ● oil ducts, paper cylinders  MAJOR INSULATION- winding, core ● press board cylinders, oil ducts BUSHINGS - porcelain , condenser
  • 22. Power & distribution transformers must be constructed to withstand mechanical stresses caused by external faults. These stresses are produced due to electromagnetic forces as a result of very high current in the windings during short-circuits. Short-circuit test
  • 23.  Prior to the short-circuit, transformer is subjected to routine tests. Asymmetrical current  The peak current that transformer is required to withstand = Isc(peak)=K Isc Dynamic ability to withstand short-circuit Value of K : x/r 1 1.5 2 3 4 5 6 8 10 >14 K 1.51 1.64 1.76 1.95 2.09 2.19 2.27 2.38 2.46 2.55
  • 24. Short-circuit may be a) Preset or b) Post set Duration of each test being 0.5 sec. ( > 5 MVA 0.25 sec) For 1φ Transformers No. of tests = Three one test with tap at highest voltage ratio, one test in principal taping & one test in lowest voltage ratio Short-circuit testing procedure
  • 25. 3φ Transformers  No. of tests = Nine  Three tests with tap at highest voltage ratio, three tests in principal taping & three tests in lowest voltage ratio Tolerances on  Asymmetrical current = ±5 %  Symmetrical current = ±10 %  Test duration = ±10 %
  • 26. Oscillogram of dynamic short-circuit test on 3Phase 11/0.433kV 500kVA Distribution transformer
  • 27.  All the routine tests shall be repeated  Dielectric test shall be at 75%  Transformer shall be untanked  Reactance measured after s.c. test shall not differ by more than 2% for circular coils & 7.5% for non-circular coils. Analysis of the results SC Test contd.
  • 28. This is to ascertain that transformer & its cooling arrangements are effectively designed so that temp. rise of winding & cooling medium does not exceed the permissible limits. Temp. rise limits for Dry type transformers Class of insulation Temp. rise °C A 50 E 65 B 70 F 90 H 115 C 140 Temperature rise test
  • 29. Temp. rise limits for oil immersed transformers Part Temp. rise °C External cooling medium Air Water Winding 55 60 (temp.rise by resistance method) Top oil 50 55 (temp.rise by thermometer method)
  • 30. a) Direct loading b) Back-to-Back method c) Short-circuit method Loading methods Duration of test Top oil temperature-rise does not vary more than 10 C/hour during 4 consecutive hourly readings
  • 32. Sound pressure level 20 log10 d/0.00002 dB d Newton per square meter Noise Level
  • 33.
  • 34.
  • 35. meter
  • 36. Highest voltage for equipment Um kV (r.m.s. value) Rated short duration power frequency withstand voltage kV (r.m.s. value) Rated lightning impulse withstand voltage kV (peak value) 3.6 10 20 40 7.2 20 40 60 12 28 60 75 95 17.5 38 75 95 24 50 95 125 145 36 70 145 170 52 95 250 72.5 140 325 123 (185) 230 450 550 145 (185) 230 275 (450) 550 650 170 (230) 275 325 (550) 650 750 245 (275) (325) 360 395 460 (650) (750) 850 950 1050
  • 37. Highest voltage for equipment Um kV (r.m.s. value) Standard switching impulse withstand voltage -------------------------------------- ------------------- Longitudinal Phase-to-earth Phase-to-phase Insulation (ratio to the (note 1) phase-to-earth kV kV peak value) (peak value) (peak value) Standard lightning impulse withstand voltage kV (peak value) 300 750 750 1,50 850 950 750 850 1,50 950 1050 362 850 850 1,50 950 1050 850 950 1,50 1050 1175 420 850 850 1,60 1050 1175 950 950 1,50 1175 1300 950 1050 1,50 1300 1425 525 950 950 1,70 1175 1300 950 1050 1,60 1300 1425 950 1175 1,50 1425 1550 765 1175 1300 1,70 1675 1800 1175 1425 1,70 1800 1950 1175 1550 1,60 1950 2100