14. Customer project
focused
Installation design
Project management
Installation works
Commissioning
Maintenance
Parts stockholding
Product quality
focused
Engine design
Engine development
Engine manufacture
Parts production
NB.
Tanzanian references installed by GE
South African references from Agaricus
Bangladesh references from Orient
1,393kWth @85C hot water
1,800 kg/h steam @9barg
Total fuel efficiency 75.5%
CHP Quality Index 128
£1m per year saving, 5,500tpa CO2
Output per engine 2MW
Heat recovery 1,864 kWth hot water at 95C
Total fuel efficiency 85%
CHP Quality Index 130
When complete will provide 100%of the thermal demand and 80% of the electrical demand for the 67 acrea site.