➥🔝 7737669865 🔝▻ dharamshala Call-girls in Women Seeking Men 🔝dharamshala🔝 ...
Time & Schedule, Submittals, Site visits, Testing and Inspection
1. Time and Schedule
Lecture 7a
American University in Cairo School of Sciences and Engineering
Department of Architectural Engineering
AENG441 – Professional Practice, Design Management and Codes
1
4. Design Scheduling
• Phases of production from Conceptual Planning Start of
Construction.
• Efficient use of Manpower and Resources
• To achieve an economical, functional and harmonious
design
• Executed within a reasonable period of time
• With an efficient utilization of personnel.
• Experience and Judgment
4
5. Design Scheduling
• Phases (AIA standard owner-architect agreement)
• Schematic Design: Drawings + Cost Estimate
• Design Development: Drawings +Outline Specifications, + Cost
Estimate
• Construction Documents: Working Drawings +Final Specifications
+ Final Cost Estimate
• Bidding and Negotiation: Receipt and Evaluation of Bids +
Addenda
• Construction Administration: Services after bidding or negotiation
to assure that the structure is built in accordance with the
construction documents.
5
6. Design Scheduling
• Estimate time required for reach phase.
• Schematic Design phase is the most difficult to
estimate - Greatest amount of variability. (1-12
months!)
• Size and Complexity
• Quality and Completeness of the Program Information
• Decision Making Ability of the Client.(committees!)
• Nature of the Design Team.
6
7. Design Scheduling
• Design Development and Construction Documents:
• More predictable
• Project Architect and/or Job Captain
• From Schematic Design into Preliminary Design Drawings then
Working Drawings
• Complexity not Size determines scheduling and staffing
requirements.
• Coordination between consultants, client and designers is vital!
• From 2 - 4 months
• Construction Documents 3-7 months.
• Bidding or Negotiation 6 weeks.
7
8. Design Scheduling
• Project financing to convert design into reality.
• Client review and approval between phases depends on
the size and complexity of the project- usually between
one week. And one month.
• Approvals by building department and public agencies
varies considerably.
8
10. Contingencies
• Unexpected Problems:
• Building Department
• Consultants
• Staffing problems
• Client
• 10% average additional time
• Flexible and Responsive to changing conditions
10
11. Working with a Builder
• Working with contractor to Guarantee Maximum Project
Cost (GMP: Guaranteed Maximum Price)
• Time is generally shortened
• Risk that design is not fully developed
• Documents less specific
• No bidding and negotiation phase
11
13. Shortening the Schedule
• Optimum Use of staff effort and resources
• Work overtime - costly and inefficient
• Hire more people - Part time or freelance or subcontract to
another firm - costly and inefficient.
• Hire new staff - Not familiar with office procedures or projects -
Expensive
• Reduce man-hours - lower quality job, incomplete, unclear
,errors and inconsistencies.
• Higher cost, lower quality.
• Quality work requires time and staff.
13
15. Establishing a Schedule
• Construction Projects are Complicated
• They involve the work of numerous trades and
subcontractors
• Coordination
• Equipment and Materials
• Time schedules and Cost recording
15
16. Considerations
1. The construction documents - Well or Poorly prepared.
2. The architect-engineer -More or Less demanding
3. The subcontractors - coordination
4. The contractor’s organization - Project manager, field
superintendent, Office and Field staff, … workload
5. Material dealers - Reliability in meeting deliverability
6. Size and complexity of the project - Most critical.
7. Site conditions - Size and Accessibility
8. The Weather
9. The possibility of labor troubles
10. The possibility of material shortage.
16
18. CPM (Critical Path Method)
• Planning Phase - Diagram is drawn indicating the order in
which various operations are to be accomplished - Called
Activities.
• Activity Start and Finish referred to as “events” or “nodes”
• Event: That moment when a preceding activity has been
completed and the following activity may begin.
• Milestone Events - Important points in the construction process.
• No indication of time - arrows are not indicating time.
• No gaps of discontinuities
• CPM is known as a network diagram
18
23. Critical Path
• Critical Path is the longest path!
• Critical activities along the path must be monitored.
23
24. Float Path
• Paths that are not on the CP.
• The float is a measure of the extra time available for an
activity or group of activities.
24
25. Project Calendar
• Multiply by 7/5 (5 working days in each 7 days)
• 16 days x 7/5 = 22.4 or 23 calendar days.
• Starting date Completion date
• Project Calendar
• Critical Activities noted in color or boldface
• Most building construction projects require 9 - 18 months.
25
28. Bar Graphs
• Start and finish dates of major phases.
• They don’t indicate relationships nor dependencies!
• Inferior to CPM as a management tool but superior as a
means of visual communication.
• Continue to be widely used.
28
30. Shortening the Schedule
• Business demands.
• Minimize effect of inflation, weather, interest, …
• Reduce CP time.
• Critical activities 25-30% of all activities.
• Shorter time increases direct cost. Less efficiency in supervision
and coordination. Errors are more likely to occur.
• Less time - More direct cost!
• Less time - Less overhead!
• Analyze the effects and determine a balance.
30
31. Fast-Track Scheduling
• Fast-Track - Accelerated - Telescoped scheduling.
• Determine major building elements.
• Produce detailed working drawings for a portion of work on
which the contractor may begin construction
• Further details continue
• Requires close coordination:
Architect - Engineers - Client - Contractor
• Oversights expected, Correction of errors
• Staged bidding awarded to different contractors
• Cost and Time control by CM (Construction Manager)
31
33. Time Management
• Fabrication Time
• Erection Time
• Sequence of
Construction
Trades
• Scheduling of
Construction
Trades
33
34. Submittals - Site Visit,
Testing and Inspection
Lecture 7b
American University in Cairo School of Sciences and Engineering
Department of Architectural Engineering
AENG441 – Professional Practice, Design Management and Codes
34
36. Material and Equipment Submittals
• Shop Drawings, Product Data, and Samples
• Introduction
36
37. Material and Equipment Submittals
• Shop Drawings, Product Data, and Samples
• Introduction
37
38. Material and Equipment Submittals
• Shop Drawings, Product Data, and Samples
• Basic Concepts
38
39. Material and Equipment Submittals
• Shop Drawings, Product Data, and Samples
• Basic Concepts
39
40. Material and Equipment Submittals
• Shop Drawings, Product Data, and Samples
• Basic Concepts
40
41. Material and Equipment Submittals
• Shop Drawings, Product Data, and Samples
• Basic Concepts
• Shop drawings are not part of the contract documents.
41
45. Procedures
• Recordkeeping
• Dates received and returned
• Action taken: Approves, corrected, revised, resubmit
• Retain copies of all submittals
• Timeliness
• Within a reasonable time
• 10 working days or two weeks
• Changes and Revisions
• Change orders
• Standard Formats for processing submittals
45
51. Site Visits
• Contract Requirements
• Architect's Role
• Advise owner whether the contractor is performing the work in
accordance with the contract documents.
• Meeting Reports
• Pre-Bid Meetings
• Pre-Construction Meeting
• During Construction
51